CN207144395U - The building waste vertical transit system of reconstruction of existing building - Google Patents
The building waste vertical transit system of reconstruction of existing building Download PDFInfo
- Publication number
- CN207144395U CN207144395U CN201720776050.8U CN201720776050U CN207144395U CN 207144395 U CN207144395 U CN 207144395U CN 201720776050 U CN201720776050 U CN 201720776050U CN 207144395 U CN207144395 U CN 207144395U
- Authority
- CN
- China
- Prior art keywords
- smoke evacuation
- side wall
- building
- building waste
- cinder notch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
A kind of building waste vertical transit system of reconstruction of existing building is the utility model is related to, including:The vertically communicated transport channel formed by the former smoke evacuation well in existing building;The side wall of former smoke evacuation well and the lower cinder notch of corresponding each storey setting are opened in, transport channel and floor are connected by lower cinder notch;Spray structure above lower cinder notch, sprayed water by spray structure into transport channel;And the side wall of former well of discharging fume and at least one elastic buffer structure below lower cinder notch are fixed on, for elastic buffer structure in transport channel, elastic buffer structure is provided with the inductive switch for being connected with spray structure, being sprayed water for control spray structure.The utility model is vertically transported the building waste on floor to bottom by original smoke evacuation well, and conevying efficiency is high, and elastic buffer structure reduces the acceleration of building waste, and spray system being capable of spray dust.
Description
Technical field
The realm of building construction is the utility model is related to, the building waste vertical transport system of espespecially a kind of reconstruction of existing building
System.
Background technology
During transforming existing building, the building waste quantity removed is more, it is difficult to convenient and swift
Transported from floor to ground on ground.In the prior art, typically vertical transport is carried out by original passenger elevators.
But when being transported with passenger elevators, rubbish is easily spilt, and influences hygienic conditions, cause cleaning difficult.Visitor
Elevator limited amount is transported, has a strong impact on conevying efficiency, efficiency of construction is low.
Utility model content
A kind of the defects of the purpose of this utility model is to overcome prior art, there is provided the building rubbish of reconstruction of existing building
Rubbish vertical transit system, solve the problems, such as that building waste is difficult to conveniently and efficiently transport from floor to ground in the prior art.
Realizing the technical scheme of above-mentioned purpose is:
The utility model provides a kind of building waste vertical transit system of reconstruction of existing building, including:
The vertically communicated transport channel formed by the former smoke evacuation well in existing building;
The side wall of former smoke evacuation well and the lower cinder notch of corresponding each storey setting are opened in, institute is connected by the lower cinder notch
State transport channel and the floor;
Spray structure above the lower cinder notch, sprayed water by the spray structure into the transport channel;With
And
The side wall of the former smoke evacuation well and at least one elastic buffer structure below the lower cinder notch are fixed on,
In the transport channel, the elastic buffer structure is provided with and is connected, supplies with the spray structure elastic buffer structure
Control the inductive switch of the spray structure water spray.
The beneficial effect of the building waste vertical transit system of the utility model reconstruction of existing building:
The building waste vertical transit system of the utility model reconstruction of existing building is formed by original smoke evacuation well and vertically passed through
Logical transport channel, the lower cinder notch of corresponding each storey setting is opened up in the side wall of former smoke evacuation well, so as to which building waste be passed through
Lower cinder notch is poured into former smoke evacuation well, is vertically transported the building waste on floor to bottom, conevying efficiency by original smoke evacuation well
Height, it is convenient and swift.Whereabouts is buffered using being fixed on former smoke evacuation well side wall and being located at the elastic buffer structure below lower cinder notch
Building waste, reduce the acceleration of building waste, prevent from coming under building waste excessively rapid and potential safety hazard be present.Work as building
The inductive switch that rubbish falls on triggering control spray system when on elastic buffer structure opens spray system, is sprayed into transport channel
Water, reach the effect of spray dust.
The utility model reconstruction of existing building building waste vertical transit system further improvement is that, in addition to
It is opened in the slag notch of the bottom of the side wall of the former smoke evacuation well.
The utility model reconstruction of existing building building waste vertical transit system further improvement is that, in addition to
Be layed in the hard protection structure of the bottom of the former smoke evacuation well, the hard protection it is structurally corresponding at the slag notch formed with
For the operating surface of excavator construction.
The utility model reconstruction of existing building building waste vertical transit system further improvement is that, in addition to
The oblique buffer board structure for being located at the hard protection structure and the former smoke evacuation well side wall, the buffer board structure are slagged tap with described
Mouth is oppositely arranged.
The utility model reconstruction of existing building building waste vertical transit system further improvement is that, the bullet
Property buffer structure includes:
The former smoke evacuation well side wall and the baffle plate below the lower cinder notch are fixed on, the baffle plate, which tilts down, to be set
Put and convexedly stretch in the transport channel, the bottom of the baffle plate is provided with the inductive switch;And
Flexible connecting rod, above the baffle plate and drawknot is between the baffle plate and the former smoke evacuation well side wall.
The utility model reconstruction of existing building building waste vertical transit system further improvement is that, the bullet
Property buffer structure also include being fixed in the former smoke evacuation well side wall positioned at the wall-connecting piece on indoor surface, the flexible connecting rod
The former smoke evacuation well side wall is arranged in be fixedly connected with the wall-connecting piece.
The utility model reconstruction of existing building building waste vertical transit system further improvement is that, the company
Wall part includes:
The L-type plate of the outside of the former smoke evacuation well side wall is fixed on by the first bolt;And
The connecting plate of the L-type plate, the connecting plate and the flexible connecting rod are fastened transversely to by the second bolt
End is fixedly connected.
The utility model reconstruction of existing building building waste vertical transit system further improvement is that, in addition to
Located at the former smoke evacuation well side wall and corresponding to the protective door structure of the lower cinder notch.
The utility model reconstruction of existing building building waste vertical transit system further improvement is that, it is described anti-
Shield door includes:
It is fixed on the stopper slot of the side wall of the former smoke evacuation well and the opposite sides positioned at the lower cinder notch;And
The door-plate being inserted in a pair of stopper slots, the door-plate set institute by moving down gear along the stopper slot
Lower cinder notch is stated, or the door-plate opens the lower cinder notch by being moved up along the stopper slot.
The utility model reconstruction of existing building building waste vertical transit system further improvement is that, it is described anti-
Shield door also includes:
The first fix bar being fastened transversely between the pair of stopper slot;And
The second fix bar of the door-plate is fastened transversely to, is fixed by connecting first fix bar and described second
Bar, so as to realize that the door-plate moves up the positioning after opening the lower cinder notch.
Brief description of the drawings
Fig. 1 is the structural representation of the building waste vertical transit system of the utility model reconstruction of existing building.
Fig. 2 is that the protective door structure of the building waste vertical transit system of the utility model reconstruction of existing building is in pass
The schematic diagram of closed state.
Fig. 3 is in for the protective door structure of the building waste vertical transit system of the utility model reconstruction of existing building and opened
Open the schematic diagram of state.
Fig. 4 is Fig. 3 A-A sectional view.
Fig. 5 is the structural representation of the bottom of the building waste vertical transit system of the utility model reconstruction of existing building
Figure.
Embodiment
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
Refering to Fig. 1, it is shown that the structure of the building waste vertical transit system of the utility model reconstruction of existing building is shown
It is intended to.As shown in figure 1, the building waste vertical transit system of the utility model reconstruction of existing building includes:Transport channel, under
Cinder notch 11, spray structure 20 and at least one elastic buffer structure 30, wherein, pass through the former smoke evacuation shape of well 10 in existing building
The transport channel vertically communicated into this;Lower cinder notch 11 is opened in the side wall of former smoke evacuation well 10 and corresponding each floor 40 is set, and leads to
Cross down cinder notch 11 and connect transport channel and floor 40;Spray structure 20 be located at lower cinder notch 11 top, by spray structure 20 to
Sprayed water in transport channel;At least one elastic buffer structure 30 is fixed on the side wall of former smoke evacuation well 10 and positioned at lower cinder notch 11
Lower section, in transport channel, elastic buffer structure 30 is provided with to be connected, is sprayed for control elastic buffer structure 30 with spray structure 20
Drench the inductive switch 50 that structure 20 is sprayed water.The building waste vertical transit system of the utility model reconstruction of existing building passes through original
Smoke evacuation well forms the vertically communicated transport channel, and the lower cinder notch of corresponding each storey setting is opened up in the side wall of former smoke evacuation well,
So as to which building waste is poured into former smoke evacuation well by lower cinder notch, the building waste on floor is vertically transported by original smoke evacuation well
Defeated to arrive bottom, conevying efficiency is high, convenient and swift.Delayed using the elasticity for being fixed on former smoke evacuation well side wall and being located at below lower cinder notch
Structure is rushed to buffer the building waste of whereabouts, reduces the acceleration of building waste, prevent from coming under building waste it is excessively rapid and
Potential safety hazard be present.When building waste is fallen on elastic buffer structure, the inductive switch of triggering control spray system opens spray
System, sprayed water into transport channel, reach the effect of spray dust.
In the present embodiment, by original smoke discharging pipe is successively torn open from top to bottom in hoistway in the floor 40 of existing building
Remove, so as to which former smoke evacuation well 10 is internally formed passage that is vertically communicated, being transported as vertical garbage.
In the present embodiment, lower cinder notch 11 is equipped with corresponding to each floor in the side wall of former smoke evacuation well 10, so as to be somebody's turn to do
The rubbish of floor can be poured into from lower cinder notch 11 in former smoke evacuation well 10.
As shown in figure 1, elastic buffer structure 30 includes:Baffle plate 31 and flexible connecting rod 32, wherein, baffle plate 31 is fixed on
Original smoke evacuation well 10 side wall and positioned at lower cinder notch 11 lower section, baffle plate 31 tilt down setting and convexedly stretch in transport channel,
Flexible connecting rod 32 is located at the top of baffle plate 31 and drawknot is between the side wall of baffle plate 31 and former smoke evacuation well 10.Baffle plate 31 is less than fortune
The sectional area of defeated passage, transport channel will not be blocked completely, so as to pour into the building waste of former smoke evacuation well 10 from lower cinder notch 11
It can down fall at baffle plate 31, baffle plate 31 is pressed downward, building waste slides from baffle plate 31 again, reduces building waste and falls
Acceleration, thus reduce the falling speed of building waste, because the drawknot of flexible connecting rod 32 connects, the and can of baffle plate 31 reaches
Set back, so as to which baffle plate 31 plays a part of certain deceleration buffer to the building waste to be fallen from high-altitude, reduce building rubbish
The whereabouts acceleration of rubbish, to reduce potential safety hazard.
The bottom of baffle plate 31 is provided with inductive switch 50, when rubbish touches baffle plate 31, causes the vibrations of baffle plate 31, then touches
Send out inductive switch 50 and open spray structure 20, spray system water spray dust into transport channel.
Elastic buffer structure 30 also includes being fixed in the former smoke evacuation side wall of well 10 positioned at the wall-connecting piece 33 on indoor surface, bullet
Property connecting rod 32 be arranged in the former smoke evacuation side wall of well 10 and be fixedly connected with wall-connecting piece 33, so as to flexible connecting rod 32 and former well 10 of discharging fume
Side wall be fastenedly connected, prevent the problem of flexible connecting rod 32 departs from former smoke evacuation 10 side wall of well.
In the present embodiment, wall-connecting piece 33 includes:L-type plate 330 and connecting plate 331, wherein, L-type plate 330 passes through first
Bolt is fixed on the outside of the side wall of former smoke evacuation well 10.Connecting plate 331 is fastened transversely to L-type plate 330 by the second bolt, connection
Plate 331 is fixedly connected with the end of flexible connecting rod 32.Flexible connecting rod 32 is made using spring housing outside steel pipe.Each
Three layers of storey setting, one elastic buffer structure 30, for carrying out buffer deceleration to the building waste of whereabouts.
Spray structure 20 is typically used for the top for the lower cinder notch 11 dumped rubbish on floor, so as to dump rubbish it
Afterwards, spray structure 20, which is triggered to open, carries out spray dust.Spray structure 20 includes shower nozzle and is communicated in the water-supply-pipe of shower nozzle, defeated
Water pipe is communicated in neighbouring water source, so as to the water delivery of spray structure 20.
Refering to Fig. 2, it is shown that the protective door of the building waste vertical transit system of the utility model reconstruction of existing building
The schematic diagram that structure is closed.Refering to Fig. 3, it is shown that the building waste of the utility model reconstruction of existing building is vertical
The protective door structure of transportation system is in the schematic diagram of opening.Refering to Fig. 4, it is shown that Fig. 3 A-A sectional view.With reference to
Shown in Fig. 1 to Fig. 4, in addition to it is located at the side wall of former smoke evacuation well 10 and corresponds to the protective door structure 90 of lower cinder notch 11.Protective door
Structure 90 includes:Stopper slot 91 and door-plate 92, wherein, stopper slot 91 is fixed on the side wall of former smoke evacuation well 10 and is located at slag
The opposite sides of mouth 11;Door-plate 92 is inserted in a pair of stopper slots 91, and door-plate 92 is set by moving down gear along stopper slot 91
Lower cinder notch 11, or door-plate 92 along stopper slot 91 by moving up the lower cinder notch 11 of opening.
Protective door structure 90 also includes:First fix bar 93 and the second fix bar 94, wherein, the first fix bar 93 is laterally
It is fixed between a pair of stopper slots 91;Second fix bar 94 is fastened transversely to door-plate 92, is bolted the first fix bar 93
With the second fix bar 94, so as to realize that door-plate 92 moves up the positioning after opening lower cinder notch 11, prevent door-plate 92 from gliding suddenly
Cause safety problem.
In the present embodiment, the side wall for former smoke evacuation well 10 being secured by bolts in using angle steel forms stopper slot 91.Door-plate
92 end is inserted in stopper slot 91, and door-plate 92 can move up and down along stopper slot 91.
Refering to Fig. 5, it is shown that the bottom of the building waste vertical transit system of the utility model reconstruction of existing building
Structural representation.With reference to shown in Fig. 1 and Fig. 5, the building waste vertical transit system of the utility model reconstruction of existing building is also
Including the slag notch 12 for the bottom for being opened in the former smoke evacuation side wall of well 10.The rubbish to bottom will be transported from floor 40 by slagging tap
Mouth 12 transfers out.
The building waste vertical transit system of the utility model reconstruction of existing building also includes:Hard protection structure 60 and
Buffer board structure 70, wherein, hard protection structure 60 is layed in the bottom of former smoke evacuation well 10, corresponds in hard protection structure 60 and slags tap
Formed with the operating surface constructed for excavator 80 at mouth 12.Buffer board structure 70 is oblique located at hard protection structure 60 and former smoke evacuation well
10 side wall, buffer board structure 70 are oppositely arranged with slag notch 12.
In the present embodiment, hard protection structure 60 can prevent the rubbish that the bottom ground of former smoke evacuation well 10 is fallen from eminence
Rubbish smashes.Buffer board structure 70 includes the steel plate 71 and pad between oblique fixed hard protection structure 60 and the side wall of former smoke evacuation well 10
In hard protection structure 60, the earthwork 72 of the lower section of steel plate 71, the angle between steel plate 71 and horizontal plane is 45 °, so as to from upper
The rubbish that sky falls to bottom is set by the gear of steel plate 71 and changes direction, assembles towards slag notch 12 direction relative with steel plate 71.
Excavator 80 is set at slag notch 12, coordinates the rubbish for excavating aggregation of falling at any time.
The building waste vertical transit system of the utility model reconstruction of existing building has the beneficial effect that:
The building waste vertical transit system of the utility model reconstruction of existing building is perpendicular by the way that former smoke evacuation well is formed
To the transport channel of insertion, the lower cinder notch of corresponding each storey setting is opened up in the side wall of former smoke evacuation well, so as to by building waste
Poured into former smoke evacuation well by lower cinder notch, vertically transported the building waste on floor to bottom, transport by original smoke evacuation well
Efficiency high, it is convenient and swift.Buffered down using being fixed on former smoke evacuation well side wall and being located at the elastic buffer structure below lower cinder notch
The building waste fallen, reduce the acceleration of building waste, prevent from coming under building waste excessively rapid and potential safety hazard be present.When
The inductive switch that building waste falls on triggering control spray system when on elastic buffer structure opens spray system, to transport channel
Interior water spray, reach the effect of spray dust.Hard protection structure can prevent what the bottom ground of former smoke evacuation well from being fallen from eminence
Rubbish smashes.When dumping rubbish, protective door structure, convenient construction, after this layer of rubbish, which is toppled over, to be finished, by protective door are opened
Structure is closed, and lower cinder notch can be protected, to ensure construction safety.
The utility model is described in detail above in association with accompanying drawing embodiment, those skilled in the art can root
Many variations example is made to the utility model according to described above.Thus, some details in embodiment should not be formed to this practicality
New restriction, the utility model will be used as the scope of protection of the utility model using the scope that appended claims define.
Claims (10)
- A kind of 1. building waste vertical transit system of reconstruction of existing building, it is characterised in that including:The vertically communicated transport channel formed by the former smoke evacuation well in existing building;The side wall of former smoke evacuation well and the lower cinder notch of corresponding each storey setting are opened in, the fortune is connected by the lower cinder notch Defeated passage and the floor;Spray structure above the lower cinder notch, sprayed water by the spray structure into the transport channel;AndThe side wall of the former smoke evacuation well and at least one elastic buffer structure below the lower cinder notch are fixed on, it is described In the transport channel, the elastic buffer structure is provided with to be connected, for control elastic buffer structure with the spray structure The inductive switch of the spray structure water spray.
- 2. the building waste vertical transit system of reconstruction of existing building as claimed in claim 1, it is characterised in that also include It is opened in the slag notch of the bottom of the side wall of the former smoke evacuation well.
- 3. the building waste vertical transit system of reconstruction of existing building as claimed in claim 2, it is characterised in that also include Be layed in the hard protection structure of the bottom of the former smoke evacuation well, the hard protection it is structurally corresponding at the slag notch formed with For the operating surface of excavator construction.
- 4. the building waste vertical transit system of reconstruction of existing building as claimed in claim 3, it is characterised in that also include The oblique buffer board structure for being located at the hard protection structure and the former smoke evacuation well side wall, the buffer board structure are slagged tap with described Mouth is oppositely arranged.
- 5. the building waste vertical transit system of reconstruction of existing building as claimed in claim 1, it is characterised in that the bullet Property buffer structure includes:Be fixed on the former smoke evacuation well side wall and the baffle plate below the lower cinder notch, the baffle plate tilt down setting and Convexedly stretch in the transport channel, the bottom of the baffle plate is provided with the inductive switch;AndFlexible connecting rod, above the baffle plate and drawknot is between the baffle plate and the former smoke evacuation well side wall.
- 6. the building waste vertical transit system of reconstruction of existing building as claimed in claim 5, it is characterised in that the bullet Property buffer structure also include being fixed in the former smoke evacuation well side wall positioned at the wall-connecting piece on indoor surface, the flexible connecting rod The former smoke evacuation well side wall is arranged in be fixedly connected with the wall-connecting piece.
- 7. the building waste vertical transit system of reconstruction of existing building as claimed in claim 6, it is characterised in that the company Wall part includes:The L-type plate of the outside of the former smoke evacuation well side wall is fixed on by the first bolt;AndThe connecting plate of the L-type plate, the end of the connecting plate and the flexible connecting rod are fastened transversely to by the second bolt It is fixedly connected.
- 8. the building waste vertical transit system of reconstruction of existing building as claimed in claim 1, it is characterised in that also include Located at the former smoke evacuation well side wall and corresponding to the protective door structure of the lower cinder notch.
- 9. the building waste vertical transit system of reconstruction of existing building as claimed in claim 8, it is characterised in that described anti- Shield door includes:It is fixed on the stopper slot of the side wall of the former smoke evacuation well and the opposite sides positioned at the lower cinder notch;AndThe door-plate being inserted in a pair of stopper slots, the door-plate by along the stopper slot move down gear set it is described under Cinder notch, or the door-plate open the lower cinder notch by being moved up along the stopper slot.
- 10. the building waste vertical transit system of reconstruction of existing building as claimed in claim 9, it is characterised in that described Protective door structure also includes:The first fix bar being fastened transversely between the pair of stopper slot;AndThe second fix bar of the door-plate is fastened transversely to, by connecting first fix bar and second fix bar, from And realize the door-plate and move up the positioning after opening the lower cinder notch.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720776050.8U CN207144395U (en) | 2017-06-29 | 2017-06-29 | The building waste vertical transit system of reconstruction of existing building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720776050.8U CN207144395U (en) | 2017-06-29 | 2017-06-29 | The building waste vertical transit system of reconstruction of existing building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207144395U true CN207144395U (en) | 2018-03-27 |
Family
ID=61671932
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720776050.8U Active CN207144395U (en) | 2017-06-29 | 2017-06-29 | The building waste vertical transit system of reconstruction of existing building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207144395U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108612287A (en) * | 2018-05-17 | 2018-10-02 | 江西联保工程咨询有限公司 | A kind of safety and environmental protection for work progress limits dirt system |
CN108824831A (en) * | 2018-06-20 | 2018-11-16 | 上海建工四建集团有限公司 | Existing skyscraper original position structure replacing reconstructs structure and method |
CN110304383A (en) * | 2019-07-31 | 2019-10-08 | 金陵科技学院 | A kind of high-rise building domestic refuse automatic transmission system |
CN113152843A (en) * | 2021-03-09 | 2021-07-23 | 中建二局第一建筑工程有限公司 | Flue combined type garbage channel and process flow thereof |
CN114775953A (en) * | 2022-04-13 | 2022-07-22 | 孙美玲 | Building body attached type high-rise building garbage vertical conveying pipeline |
-
2017
- 2017-06-29 CN CN201720776050.8U patent/CN207144395U/en active Active
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108612287A (en) * | 2018-05-17 | 2018-10-02 | 江西联保工程咨询有限公司 | A kind of safety and environmental protection for work progress limits dirt system |
CN108612287B (en) * | 2018-05-17 | 2019-04-26 | 江西联保工程咨询有限公司 | A kind of safety and environmental protection limit dirt system for work progress |
CN108824831A (en) * | 2018-06-20 | 2018-11-16 | 上海建工四建集团有限公司 | Existing skyscraper original position structure replacing reconstructs structure and method |
CN110304383A (en) * | 2019-07-31 | 2019-10-08 | 金陵科技学院 | A kind of high-rise building domestic refuse automatic transmission system |
CN113152843A (en) * | 2021-03-09 | 2021-07-23 | 中建二局第一建筑工程有限公司 | Flue combined type garbage channel and process flow thereof |
CN114775953A (en) * | 2022-04-13 | 2022-07-22 | 孙美玲 | Building body attached type high-rise building garbage vertical conveying pipeline |
CN114775953B (en) * | 2022-04-13 | 2024-04-19 | 中科斌港建设集团有限公司 | Vertical conveying pipeline for building body attached type high-rise building rubbish |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207144395U (en) | The building waste vertical transit system of reconstruction of existing building | |
CN208830666U (en) | A kind of skyscraper vertical garbage transportation system | |
CN104234388B (en) | Garbage chute for high-building construction | |
CN108286324A (en) | A kind of skyscraper intelligent garbage separate transport pipeline | |
CN205397580U (en) | Upset discharge apparatus | |
CN213293647U (en) | Super high-rise construction garbage disposal device | |
CN207776364U (en) | The conveyer of construction rubbish can be crushed | |
KR20070018496A (en) | A reclaimer for preventing dust dispersing | |
CN209506734U (en) | A kind of garbage collecting and transferring device | |
CN207934392U (en) | The quick conveying device of skyscraper rubbish | |
CN209509401U (en) | A kind of refuse collection structure for skyscraper | |
CN204184816U (en) | A kind of blanking device | |
CN212053623U (en) | Self-closing door system for high-rise building garbage channel | |
CN206752961U (en) | Rubbish storage case | |
CN204098438U (en) | A kind of refuse chute for high-building construction | |
CN214987836U (en) | Dustless collecting equipment of building waste residue | |
CN214402591U (en) | Vertical garbage transport channel for high-rise buildings | |
CN208642945U (en) | Ladder blanking type ore crusher | |
CN109353722A (en) | A kind of Construction of High-rise multipurpose body feed tank and its application method | |
CN207917764U (en) | Lane device for skyscraper rubbish quick drain | |
CN110629977B (en) | Vertical transport channel for construction waste and use method thereof | |
CN211418924U (en) | Ultra-clean transfer station | |
CN209618058U (en) | A kind of Construction of High-rise multipurpose body feed tank | |
CN209211840U (en) | A kind of building waste channel with novel buffering device | |
CN210853734U (en) | Buffer in funnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |