CN207048069U - A kind of pipe gallery segmental timbering - Google Patents

A kind of pipe gallery segmental timbering Download PDF

Info

Publication number
CN207048069U
CN207048069U CN201721042601.4U CN201721042601U CN207048069U CN 207048069 U CN207048069 U CN 207048069U CN 201721042601 U CN201721042601 U CN 201721042601U CN 207048069 U CN207048069 U CN 207048069U
Authority
CN
China
Prior art keywords
pipe gallery
channel flow
buried channel
buried
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721042601.4U
Other languages
Chinese (zh)
Inventor
何福江
夏维学
郭瑞
祁涛
张铎
李明星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 7 Co Ltd
Original Assignee
Sinohydro Bureau 7 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 7 Co Ltd filed Critical Sinohydro Bureau 7 Co Ltd
Priority to CN201721042601.4U priority Critical patent/CN207048069U/en
Application granted granted Critical
Publication of CN207048069U publication Critical patent/CN207048069U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model discloses a kind of pipe gallery segmental timbering.Including pre-buried structure and sectional shelf-unit, pre-buried structure includes pre-buried channel flow that is prefabricated and being fixedly arranged at pipe gallery concrete wall inner surface, and pre-buried channel flow back is welded with crab-bolt and is consolidated in concreting body;Sectional shelf-unit includes cradling piece, and the fixed plate that cradling piece is fixed by support bar and support bar one end vertical welding is formed, and fixed plate is connected by bolt and pre-buried channel flow;The head of bolt is T-shaped structure.The mounting structural mode combined using pre-buried channel flow and segmental timbering, can stationarity and mobility it is good, it is flexibly adjustable, line style is installed and installation accuracy is easy to control;The utility model supporting structure is stable, reliable, and installation only needs several steps to complete, and the instrument of use is few, and instrument is easily obtained, not only saved equipment cost, and improved efficiency of construction, it is thus also avoided that welding etc. the issuable pollution of technique, noise the problems such as.

Description

A kind of pipe gallery segmental timbering
Technical field
It the utility model is related to Urban Underground pipe gallery technical field of construction, and in particular to a kind of pipe gallery assembled Supporting structure.
Background technology
Pipe gallery is to build a tunnel space in Urban Underground, and electric power, communication, combustion gas, heat supply, plumbing etc. is each Kind utilities pipeline is integrated in one, and is a kind of modernization, intensive city provided with special access hole, dog-house and monitoring system City's infrastructure.According to pipe gallery layout feature, while to ensure pipeline performance safety, power cable, communication cable are general It is rack-mount.
For cast-in-place concrete structure, traditional support technology is the embedded iron parts in concrete structure, then pre-buried Welding support on ironware.Which installation effectiveness is relatively low, installation line style, the more difficult control of installation accuracy, and after support installation very Difficult carry out position adjustment, later maintenance difficulty are larger.
The content of the invention
The utility model discloses a kind of pipe gallery segmental timbering according to the deficiencies in the prior art, and the utility model will Solve the problems, such as to be to provide a kind of pipe gallery segmental timbering mounting structure, efficiency of construction can be effectively improved, be precisely controlled branch Frame installs line style, and support is detachable movable, can also increase and decrease number of holders according to the actual requirements in later stage adjustment and maintenance.
The utility model is achieved through the following technical solutions:
Pipe gallery segmental timbering, it is characterised in that:The segmental timbering includes pre-buried structure and sectional shelf-unit;
Pre-buried structure includes pre-buried channel flow that is prefabricated and being fixedly arranged at pipe gallery concrete wall inner surface, pre-buried channel flow back It is welded with crab-bolt and is consolidated in concreting body;
Sectional shelf-unit includes cradling piece, the fixed plate structure that cradling piece is fixed by support bar and support bar one end vertical welding Into fixed plate is connected by bolt and pre-buried channel flow.
The head of the bolt is T-shaped structure.
The pre-buried channel flow is the groove for having flanging, and pre-buried channel flow has multigroup and arranged vertically along pipe gallery wall.
The both ends of the bolt head T-shaped structure and the flanging tensioning of groove are fixed.
The pre-buried reinforcing bar for being consolidated with vertical and horizontal arrangement in the pipe gallery concrete wall.
The beneficial effects of the utility model:The mounting structural mode combined using pre-buried channel flow and segmental timbering, is had Preferably can stationarity and mobility, realize flexibly it is adjustable.In pipe gallery restricted clearance, with reference to using infrared rays survey Positioning, installs line style and installation accuracy is easy to control.The utility model supporting structure is stable, reliable, and installation only needs several steps It can complete, the instrument of use is few, and instrument is easily obtained, and has not only saved equipment cost, and improves efficiency of construction, also The problems such as avoiding the issuable pollution of technique, the noises such as welding.
Brief description of the drawings
Fig. 1 is the utility model segmental timbering structure schematic side view;
Fig. 2 is the utility model segmental timbering structure schematic top plan view.
Wherein, 1 is pre-buried channel flow, and 2 be crab-bolt, and 3 be reinforcing bar, and 4 be cradling piece, and 5 be bolt, and 6 be nut, and 7 be integrated pipe Corridor outer wall, 8 be pipe gallery inwall.
Embodiment
The utility model is specifically described below by embodiment, the present embodiment is served only for entering the utility model Row further instruction, but it is not intended that limitation to scope of protection of the utility model, those skilled in the art is according to upper State the scope that some nonessential modifications and adaptations that content of the present utility model is made fall within the utility model protection.
With reference to accompanying drawing.
Pipe gallery segmental timbering, segmental timbering include pre-buried structure and sectional shelf-unit;
Pre-buried structure includes pre-buried channel flow 1 that is prefabricated and being fixedly arranged at pipe gallery concrete wall inner surface, and pre-buried channel flow 1 is carried on the back Portion is welded with crab-bolt 2 and is consolidated in concreting body;
Sectional shelf-unit includes cradling piece 4, the fixed plate structure that cradling piece 4 is fixed by support bar and support bar one end vertical welding Into fixed plate is connected by bolt 5 and pre-buried channel flow 1.
The head of bolt 5 is T-shaped structure.
Pre-buried channel flow 1 is the groove for having flanging, and pre-buried channel flow 1 has multigroup and arranged vertically along pipe gallery wall.
The both ends of the head T-shaped structure of bolt 5 and the flanging tensioning of groove are fixed.
The pre-buried reinforcing bar 3 for being consolidated with vertical and horizontal arrangement in pipe gallery concrete wall.
Installation includes the installation and segmental timbering installation of pre-buried channel flow.
The installation of pre-buried channel flow comprises the following steps:
(1) surveying setting-out
Pipe gallery bottom slab concreting is completed, the positioning of pre-buried channel flow 1 is carried out after the completion of the system peace of side wall reinforcing bar 3, and both ends are pre-buried Conduit 1 should accurately be made apart from movement joint 25cm, the level interval 1.5m of pre-buried channel flow 1 using steel tape according to design spacing The horizontal level of pre-buried channel flow 1, and made marks on bottom plate, the bottom for then measuring pre-buried channel flow 1 with steel tape from bottom plate is erected Straight position, and made marks on reinforcing bar 3
(2) conduit is installed
Pre-buried channel flow 1 is temporarily fixed on design attitude with iron wire, and plumb line is set at top, adjusts pre-buried channel flow 1 ensures vertically, and the surface of pre-buried channel flow 1 is flushed with concrete surface on the inside of pipe gallery, then fixes pre-buried channel flow 1 The crab-bolt 2 carried carries out spot welding with agent structure reinforcing bar 3 and fixed, and welds the point of upper and lower part two.
(3) model sheetinstallat
After the installation of pre-buried channel flow 1, the installation of template is carried out, it is desirable to which pre-buried channel flow is close to inner wall form.To avoid mixing Pre-buried channel flow 1 misplaces when solidifying soil pours, and during model sheetinstallat, adds a reinforced bar support at the back side of pre-buried channel flow 1.
(4) concreting
Pipe gallery main body concrete is put in storage using automotive pump pumping, slow blanking, pours pump line close to storehouse face when putting in storage Vibrated in time using cable type vibrating spear when building, forbid to touch template and pre-buried channel flow 1, concreting to top when vibrating Behind face, the maintenance of receipts face is carried out.
(5) form removal, cleaning conduit
It is dismountable that template in concrete strength reaches design requirement rear.Form removable by first prop up tear open afterwards, rear branch is first torn open Order is carried out.It is artificial with pocket knife or small steel disc that the environmentally friendly low density polyethylene (LDPE) of the inside of pre-buried channel flow 1 filling is close after form removable Strip of paper used for sealing is rejected, and ensures cleaning, no-sundries in groove.
The installation of segmental timbering comprises the following steps:
(1) surveying setting-out
The line setting that support 4 is installed is carried out using infrared ray, steel tape, first with steel tape, measures this section of piping lane head and the tail The position of bottommost support 4 is held, infrared facility is placed on to the side of piping lane, the height and angle of infrared facility is adjusted, makes Infrared ray is through 2 points from beginning to end.
(2) support is installed
After the completion of measurement and positioning, manually installed bottom cradling piece 4., manually first will be with tooth according to the fixed position of infrared ray Tommyhead bolt 5 put into pre-buried channel flow 1, then cradling piece 4 is placed at design attitude, tommyhead bolt 5 is rotated by 90 °, made Bolt 5 is stuck in the flanging of pre-buried channel flow 1 and installs nut 6, then according to the position of infrared ray trimming rack bar 4, adjusts position Postpone, tightening nuts 6.After the installation of bottom bracket bar 4, the cradling piece 4 for carrying out upper strata with steel ruler according to design spacing positions, Installation method is identical.
(3) inspect for acceptance
After the installation of cradling piece 4, the height of infrared facility is adjusted, successively checks whether support installation site is accurate, If there is deviation, it is adjusted in time.
The mounting means that the present invention is combined using pre-buried channel flow and segmental timbering, having preferably can stationarity and removable Dynamic property, reach flexibly adjustable;In pipe gallery restricted clearance, support installation using infrared rays survey position, install line style and Installation accuracy is relatively easy to control;For the installation of support, it is only necessary to which several steps can be completed, and the instrument of use is few, and instrument is easy In acquisition, equipment cost is not only saved, and improve efficiency of construction, it is thus also avoided that the issuable dirt of technique such as welding The problems such as dye, noise.

Claims (5)

  1. A kind of 1. pipe gallery segmental timbering, it is characterised in that:The segmental timbering includes pre-buried structure and sectional shelf-unit;
    Pre-buried structure includes pre-buried channel flow that is prefabricated and being fixedly arranged at pipe gallery concrete wall inner surface, the welding of pre-buried channel flow back It is fixed with crab-bolt and is consolidated in concreting body;
    Sectional shelf-unit includes cradling piece, and the fixed plate that cradling piece is fixed by support bar and support bar one end vertical welding is formed, Gu Fixed board is connected by bolt and pre-buried channel flow.
  2. 2. pipe gallery segmental timbering according to claim 1, it is characterised in that:The head of the bolt is T-shaped knot Structure.
  3. 3. pipe gallery segmental timbering according to claim 2, it is characterised in that:The pre-buried channel flow is to have flanging Groove, pre-buried channel flow have multigroup and arranged vertically along pipe gallery wall.
  4. 4. pipe gallery segmental timbering according to claim 3, it is characterised in that:The bolt head T-shaped structure The tensioning of the flanging of both ends and groove is fixed.
  5. 5. according to the pipe gallery segmental timbering described in claim 1 or 2 or 3 or 4, it is characterised in that:The pipe gallery The pre-buried reinforcing bar for being consolidated with vertical and horizontal arrangement in concrete wall.
CN201721042601.4U 2017-08-20 2017-08-20 A kind of pipe gallery segmental timbering Active CN207048069U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721042601.4U CN207048069U (en) 2017-08-20 2017-08-20 A kind of pipe gallery segmental timbering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721042601.4U CN207048069U (en) 2017-08-20 2017-08-20 A kind of pipe gallery segmental timbering

Publications (1)

Publication Number Publication Date
CN207048069U true CN207048069U (en) 2018-02-27

Family

ID=61504104

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721042601.4U Active CN207048069U (en) 2017-08-20 2017-08-20 A kind of pipe gallery segmental timbering

Country Status (1)

Country Link
CN (1) CN207048069U (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108666960A (en) * 2018-06-12 2018-10-16 潘家红 A kind of electric power cable laying holder
CN109518719A (en) * 2018-12-27 2019-03-26 上海建工二建集团有限公司 Oversized-diameter pipeline steel support pipe frame applied to comprehensive pipe gallery and assembling method thereof
CN109826441A (en) * 2018-12-29 2019-05-31 济南城建集团有限公司 One kind breathing out fragrant slot laterally pre-buried installation method for concrete structure c-type
CN110578341A (en) * 2019-08-06 2019-12-17 苏州电力设计研究院有限公司 Power cable pipe arrangement working well and construction method thereof
CN110752572A (en) * 2019-11-01 2020-02-04 河北帕克轨道交通设备有限公司 Bracket with bracket arm easy to install
CN111501825A (en) * 2020-04-20 2020-08-07 中国一冶集团有限公司 Installation method of Hafen groove and cantilever support in cast-in-situ comprehensive pipe gallery
CN112510610A (en) * 2020-11-21 2021-03-16 江苏永联精筑建设集团有限公司 Assembled pipe gallery support and construction process thereof
CN112796189A (en) * 2021-01-29 2021-05-14 中国建筑第七工程局有限公司 Can have enough to meet need assembled road system
CN113482051A (en) * 2021-08-18 2021-10-08 中国十七冶集团有限公司 Comprehensive underground pipe gallery pipeline pre-buried support device and using method thereof
CN113585334A (en) * 2021-07-29 2021-11-02 中铁一局集团(广州)建设工程有限公司 Comprehensive pipe gallery support pre-buried channel and installation method thereof

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108666960A (en) * 2018-06-12 2018-10-16 潘家红 A kind of electric power cable laying holder
CN109518719A (en) * 2018-12-27 2019-03-26 上海建工二建集团有限公司 Oversized-diameter pipeline steel support pipe frame applied to comprehensive pipe gallery and assembling method thereof
CN109826441A (en) * 2018-12-29 2019-05-31 济南城建集团有限公司 One kind breathing out fragrant slot laterally pre-buried installation method for concrete structure c-type
CN110578341A (en) * 2019-08-06 2019-12-17 苏州电力设计研究院有限公司 Power cable pipe arrangement working well and construction method thereof
CN110752572A (en) * 2019-11-01 2020-02-04 河北帕克轨道交通设备有限公司 Bracket with bracket arm easy to install
CN110752572B (en) * 2019-11-01 2021-08-03 河北帕克轨道交通设备有限公司 Bracket with bracket arm easy to install
CN111501825A (en) * 2020-04-20 2020-08-07 中国一冶集团有限公司 Installation method of Hafen groove and cantilever support in cast-in-situ comprehensive pipe gallery
CN112510610A (en) * 2020-11-21 2021-03-16 江苏永联精筑建设集团有限公司 Assembled pipe gallery support and construction process thereof
CN112796189A (en) * 2021-01-29 2021-05-14 中国建筑第七工程局有限公司 Can have enough to meet need assembled road system
CN113585334A (en) * 2021-07-29 2021-11-02 中铁一局集团(广州)建设工程有限公司 Comprehensive pipe gallery support pre-buried channel and installation method thereof
CN113482051A (en) * 2021-08-18 2021-10-08 中国十七冶集团有限公司 Comprehensive underground pipe gallery pipeline pre-buried support device and using method thereof

Similar Documents

Publication Publication Date Title
CN207048069U (en) A kind of pipe gallery segmental timbering
CN102418530B (en) Roller guide rail station-passing construction method of whole shield machine
CN104060629B (en) The superimposed wall construction method in covered back-digging subway station and portable side wall formwork jumbo
CN102996143B (en) Construction method of fully pouring tunnel inverted arch
CN107489098B (en) Concrete prefabricated welding type guardrail and installation construction method
CN101929341B (en) Construction method for TBM synchronization lining
CN106223963B (en) A kind of shield machine air pushing passes through the construction method in subsurface excavation method tunnel
CN103643968B (en) Method for rapid construction of double-track tunnel ditch cable channel
CN103485549B (en) Based on the localization method to large-scale built-in fitting
CN109505613A (en) Originating method in the hole of earth pressure balanced shield, EPBS in small space
CN105951747B (en) A kind of construction method of the pre-buried lattice column of contrary sequence method
CN103334379B (en) A kind of construction method for anti-collision guard rail for highways overhanging portion
CN104532843B (en) A kind of steel column location straightening method of stand column pile
KR20140044172A (en) Method for constructing underground structure of railroad using steel pipe roof of two-side semicircle arch type and apparatus for pressing guidance pipe
CN209604084U (en) Karst area fault broken zone tunnel gushes water and administers structure
CN105672655A (en) Side wall self-propelled type triangular truss and construction method thereof
CN103088843B (en) Pipe gallery embedded iron parts construction method of installation
CN104675405A (en) Rectangular pipe jacking machine tunnel entering auxiliary structure and construction method
CN106836829B (en) A kind of mounting structure and its installation method of ring crane corbel
CN105370315A (en) Drainage construction technology for seasonally-frozen ground tunnel
CN103603503A (en) Anchor bolt installing method
CN204783045U (en) Big section tunnel support device
CN205742215U (en) A kind of reusable pipe gallery pattern foundation pit supporting structure and structure external mold combinative structure
CN213235079U (en) Concrete formwork supporting structure for underground excavation tunnel deformation joint post-cast strip
CN107476336A (en) A kind of steel pipe column positioning construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant