CN107476336A - A kind of steel pipe column positioning construction method - Google Patents
A kind of steel pipe column positioning construction method Download PDFInfo
- Publication number
- CN107476336A CN107476336A CN201710719024.6A CN201710719024A CN107476336A CN 107476336 A CN107476336 A CN 107476336A CN 201710719024 A CN201710719024 A CN 201710719024A CN 107476336 A CN107476336 A CN 107476336A
- Authority
- CN
- China
- Prior art keywords
- locator
- backing plate
- steel pipe
- construction
- pipe column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/04—Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Environmental & Geological Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A kind of construction steel tubing string locating mounting method belongs to subway station digging method construction steel pipe column technical field of construction.Whether steel pipe column positioning accurately determines whether lid excavation construction can be smoothed out.Present invention casting concrete first to locating cone and backing plate (1) below;Locating cone elevation and center are accurately positioned, is bored using Steel bar rack stationary positioned and backing plate (1);Casting concrete stationary positioned is bored and backing plate (1);Installation positioner, positioning hole (2) are inserted in locating cone and backing plate (1);Locator is supported using harness cord bolt (3);Locator flange respectively installs leveling nut (4) and is used for adjusting locator level up and down;Pour below locator to flange, fixed locator;Installation steel pipe column (6) simultaneously pours;The present invention reduces the construction procedure of conventional steel post construction, and positioning is more accurate, and precision is higher, and speed is faster.
Description
Technical field
The invention belongs to digging method construction steel pipe column technical field of construction, the installation how positioned more particularly to steel pipe column
Method.High construction method is required to steel pipe column positioning construction precision.
Background technology
Digging method construction is commonly used to busy section of town traffic main artery, when obstacles such as underground requirement of engineering highway crossing, buildings
Generally use cap excavation method during thing, to reduce the influence to traffic.It is after one kind is excavated to certain depth downwards by ground, by top
Closing, remaining bottom engineering are constructed under the top cover of closing.Horizontal displacement of its feature to structure is small, safety coefficient
Height, the influence to ground is small, only blocks traffic above-ground in a short time, constructing, it is small to be influenceed by outside climatic.
The support of digging method construction top cover is generally completed by steel pipe column, and steel pipe column often also needs to undertake beam, plate etc.
Structure, this requires that steel pipe column positions and elevation must be accurate, and otherwise beam, plate construction will be impacted.
The content of the invention
In order to solve the above problems, it is an object of the invention to provide a kind of steel pipe column positioning construction method.
In order to achieve the above object,
One kind lid digs station erection of steel pipe column positioning construction method, it is characterised in that comprises the following steps:
1) first casting concrete to locating cone and backing plate (1) below;
2) locating cone elevation and center are accurately positioned, is bored using Steel bar rack stationary positioned and backing plate (1);
3) casting concrete stationary positioned cone and backing plate (1);
4) installation positioner (5), positioning hole (2) are inserted in locating cone and backing plate (1);
5) using harness cord bolt (3) support locator (5);
6) locator (5) flange respectively installs leveling nut (4) and is used for adjusting locator (5) level up and down;
7) pour below locator (5) to flange, fixed locator (5);
8) steel pipe column (6) is installed and poured.
Steel pipe column construction method provided by the invention can reduce concreting number, save the concrete curing time,
Faster more accurately positioning steel tube post, ensures the smooth installation in beam slab.
Brief description of the drawings
Fig. 1 is steel pipe column positioning construction method schematic diagram.
Embodiment
Below in conjunction with the accompanying drawings and instantiation the present invention is described in detail.
Now illustrated by taking metro station cover and cut engineering as an example:The station end portion superstructure is busy highway,
To reduce the influence to highway, using digging method construction.After the completion of lid excavation construction, recover road travel, while use contrary sequence method
Work car station agent structure.
Station cover plate supports covering plate structure, agent structure beam, plate etc. to be installed in side wall and steel pipe using 12 steel pipe columns
On post bracket.
The construction method of the present invention includes carrying out the following steps in order:
1) first casting concrete to locating cone and backing plate (1) below;
2) after concrete final set, locating cone and backing plate (1) elevation and center is accurately positioned, is consolidated using Steel bar rack
Determine locating cone and backing plate (1);
3) casting concrete stationary positioned cone and backing plate (1);
4) installation positioner (5), positioning hole (2) are inserted in locating cone and backing plate (1);
5) locator (5) is supported using 3 harness cord bolts (3), bolt branch is stood on concrete surface;
6) locator (5) flange respectively installs leveling nut (4) and is used for adjusting locator (5) level up and down;
7) after measurement and positioning device (5) position, elevation are errorless, pour below locator (5) to flange, fixed locator (5);
8) steel pipe column (6) is installed and poured;Fine sand, stable steel pipe column are backfilled after the completion of pouring.
Claims (1)
1. a kind of erection of steel pipe column positioning construction method, it is characterised in that comprise the following steps:
1) first casting concrete to locating cone and backing plate (1) below;
2) locating cone elevation and center are accurately positioned, is bored using Steel bar rack stationary positioned and backing plate (1);
3) casting concrete stationary positioned cone and backing plate (1);
4) installation positioner (5), positioning hole (2) are inserted in locating cone and backing plate (1);
5) using harness cord bolt (3) support locator (5);
6) locator (5) flange respectively installs leveling nut (4) and is used for adjusting locator (5) level up and down;
7) pour below locator (5) to flange, fixed locator (5);
8) steel pipe column (6) is installed and poured.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710719024.6A CN107476336A (en) | 2017-08-21 | 2017-08-21 | A kind of steel pipe column positioning construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710719024.6A CN107476336A (en) | 2017-08-21 | 2017-08-21 | A kind of steel pipe column positioning construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107476336A true CN107476336A (en) | 2017-12-15 |
Family
ID=60601101
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710719024.6A Pending CN107476336A (en) | 2017-08-21 | 2017-08-21 | A kind of steel pipe column positioning construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107476336A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108265750A (en) * | 2018-02-02 | 2018-07-10 | 北京市政建设集团有限责任公司 | A kind of steel pipe column localization method |
CN108571008A (en) * | 2018-04-27 | 2018-09-25 | 中国电建市政建设集团有限公司 | Lid digs station steel pipe column positioning construction method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004162370A (en) * | 2002-11-13 | 2004-06-10 | Takenaka Komuten Co Ltd | Steel pipe structural permanent column erection method |
CN203594051U (en) * | 2013-12-11 | 2014-05-14 | 中铁九局集团第六工程有限公司 | Steel pipe pillar positioner supporting frame device used for cover and cut top-down method |
CN205062807U (en) * | 2015-09-19 | 2016-03-02 | 中铁二十二局集团第一工程有限公司 | Steel -pipe column construction installing the system |
CN105926672A (en) * | 2016-05-06 | 2016-09-07 | 中铁十六局集团地铁工程有限公司 | Mined metro station steel pipe column construction method |
-
2017
- 2017-08-21 CN CN201710719024.6A patent/CN107476336A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004162370A (en) * | 2002-11-13 | 2004-06-10 | Takenaka Komuten Co Ltd | Steel pipe structural permanent column erection method |
CN203594051U (en) * | 2013-12-11 | 2014-05-14 | 中铁九局集团第六工程有限公司 | Steel pipe pillar positioner supporting frame device used for cover and cut top-down method |
CN205062807U (en) * | 2015-09-19 | 2016-03-02 | 中铁二十二局集团第一工程有限公司 | Steel -pipe column construction installing the system |
CN105926672A (en) * | 2016-05-06 | 2016-09-07 | 中铁十六局集团地铁工程有限公司 | Mined metro station steel pipe column construction method |
Non-Patent Citations (2)
Title |
---|
张昊等: "北京地铁菜市口站盖挖逆筑法施工技术", 《市政技术》 * |
郝广成: "盖挖逆作法地铁车站钢管柱安装定位施工技术", 《施工技术》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108265750A (en) * | 2018-02-02 | 2018-07-10 | 北京市政建设集团有限责任公司 | A kind of steel pipe column localization method |
CN108571008A (en) * | 2018-04-27 | 2018-09-25 | 中国电建市政建设集团有限公司 | Lid digs station steel pipe column positioning construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102146672B (en) | Method for constructing pile foundation in karst area | |
CN207048069U (en) | A kind of pipe gallery segmental timbering | |
CN105926672B (en) | A kind of Underground Subway Station steel pipe column construction method | |
KR101401934B1 (en) | Method for constructing underground structure of railroad using steel pipe roof of two-side semicircle arch type and apparatus for pressing guidance pipe | |
KR20090100867A (en) | The method construction work and unit metal tubing constructing system for the road underground driveway | |
CN109778992A (en) | A kind of ride well device and its construction method for pipeline construction | |
CN105951747A (en) | Construction method for embedding latticed column through reverse building method | |
CN103334379A (en) | Construction method for hanging part of anti-collision guardrail on expressway | |
KR20190022132A (en) | Top-down method using precast-concrete colum | |
CN107476336A (en) | A kind of steel pipe column positioning construction method | |
CN106285040B (en) | The method that building moving steering is realized using track height difference | |
CN202866304U (en) | Reverse-building-method steel pipe column bottom locating device | |
CN102587386A (en) | Reverse HPE (hydraulic perpendicular embedding) construction method for steel pipe columns in basement | |
KR101401057B1 (en) | Method to build underground structures using the pillars and the stigma and steel beam and slab structures are formed | |
CN102296600B (en) | Method for positioning middle pile of spread built subway station | |
CN204282399U (en) | A kind of subway space enclosing structure | |
CN110185390B (en) | Miniature pile group pile drilling positioning and guiding device and use method | |
KR101165451B1 (en) | Pillar foundation structure of street facility and construction method thereof | |
CN203891060U (en) | Permanent steel pipe column positioning system of major structure of cover and excavation top-down station | |
CN106703072A (en) | Scaffolding equipment foundation embedded part construction method | |
CN103669347B (en) | Underwater anchor rod construction method | |
CN207538090U (en) | A kind of externally reinforced structure of Urban underground Tunnel | |
CN110273435A (en) | A kind of construction of city open trench tunnel | |
CN109235453B (en) | Deep foundation pit PRC pipe pile assembled supporting method | |
CN111579039B (en) | Anti-settling seamless construction method for flat plate type dynamic weighing equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20171215 |