CN106703072A - Scaffolding equipment foundation embedded part construction method - Google Patents

Scaffolding equipment foundation embedded part construction method Download PDF

Info

Publication number
CN106703072A
CN106703072A CN201611192563.0A CN201611192563A CN106703072A CN 106703072 A CN106703072 A CN 106703072A CN 201611192563 A CN201611192563 A CN 201611192563A CN 106703072 A CN106703072 A CN 106703072A
Authority
CN
China
Prior art keywords
steel pipe
steel tube
steel
embedded part
fitting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611192563.0A
Other languages
Chinese (zh)
Inventor
王丽梅
王安鑫
张振禹
郭建东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Engineering Bureau Civil Engineering Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Engineering Bureau Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, China Construction Sixth Engineering Bureau Civil Engineering Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201611192563.0A priority Critical patent/CN106703072A/en
Publication of CN106703072A publication Critical patent/CN106703072A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a scaffolding equipment foundation embedded part construction method. The scaffolding equipment foundation embedded part construction method comprises the following steps of excavating a foundation trench of an equipment foundation to a set depth; tamping plain soil at the bottom of the foundation trench of the equipment foundation; paving gravels on the plain soil, and tamping the paved gravels; binding transverse reinforcing bars and vertical reinforcing bars on the tamped gravels; vertically tamping multiple columns of steel tube stand pipes so that the steel tube stand pipes penetrate through the gravels and the plain soil; separately mounting one steel tube cross arm along the longitudinal direction on the corresponding one of the steel tube stand pipes which are located at the same transverse position in the columns of steel tube stand pipes; connecting the crossed positions of the steel tube cross arms and the corresponding steel tube stand pipes through cross-shaped buckles; mounting a left H-shaped steel embedded part and a right H-shaped steel embedded part on each steel tube cross arm; fixing two sides of the lower bottom of each H-shaped steel embedded part to the corresponding steel tube cross arm in a welding manner; and pouring concrete in the foundation trench of the equipment foundation, so that the top surface of the concrete is consistent with the ground level of a factory building. According to the method disclosed by the invention, each whole H-shaped steel beam can be well mounted by adopting a small number of the steel tube stand pipes and the steel tube cross bars.

Description

A kind of equipment basic pre-buried part construction method of Support Method
Technical field
The present invention relates to shaped steel built-in fitting construction method, more particularly to the equipment basic pre-buried part construction method of Support Method.
Background technology
Process with industrial production automation is constantly upgraded, and traditional operative will progressively by the big production institute of mechanization Substitute, increase equipment is the inexorable trend of development, and it is also inevitable to increase Equipment Foundations, as long as there are Equipment Foundations, is just had pre- The installation of embedded part.Installation of embedded parts Mass accuracy directly influences engineering construction quality, and the installation to follow-up equipment can be caused very Big influence, the Equipment Foundations particularly with gross ton position will more ensure installation quality.
1. application number:The Chinese patent of CN201110006166.0 discloses " ultralong device foundation platform embedded part embedding Accuracy control construction method ", comprises the following steps:First, built-in fitting and installation of embedded parts screw rod are processed;2nd, need to construct basic flat Platform middle and lower part reinforced concrete structure molding construction, many vertical reinforcements are from the middle and lower part reinforced concrete structure of construction molding Top is stretched out and in vertically to laying;3rd, installation of embedded parts screw rod is installed;4th, installation of embedded parts screw flight section bottom spiral shell Mother installs;5th, installation of embedded parts and positioning;6th, installation of embedded parts screw flight section top nut is installed;7th, need to construct basis Platform upper reinforced concrete structure molding construction;8th, subsequent construction treatment.It is pre- that the patent is applied to ultralong device foundation platform Embedded part, the equipment basic pre-buried part for not being suitable for gross ton position is installed.
2. application number:The Chinese patent of CN201320854312.X is disclosed " a kind of controllable embedded part ", including fixed seat And sliding seat, the fixed seat includes two lower floor's slotwares parallel to each other being embedded in building structure, lower floor's slotware It is the channel-section steel for being provided with the flanging for bending inwards of opening upwards, some earth anchors of bottom prewelding of lower floor's slotware, the slip Seat is respectively perpendicular the upper strata slotware being connected between two lower floor's slotwares including many, and upper strata slotware is provided with for opening upwards The channel-section steel of the flanging for bending inwards, connects the T-shaped spiral shell in the groove of head insertion lower floor slotware between upper strata slotware and lower floor's slotware Bolt, the T-bolt slided along groove in the groove that some head insertion upper strata slotwares are set in the groove of each upper strata slotware.The patent is applicable In controllable embedded part, the fixing equipment basis installation of embedded parts of installation accuracy it is not suitable for ensureing.
The content of the invention
It is an object of the invention to provide a kind of simple structure, construction cost is low, strong applicability Support Method Equipment Foundations Built-in fitting construction method.
A kind of equipment basic pre-buried part construction method of Support Method, comprises the following steps:
(1) Equipment Foundations foundation trench unwrapping wire is carried out in existing facility floor, using concrete cutting machine to Equipment Foundations foundation trench Cut in sideline;
(2), to set depth, then the element of tamping apparatus basis foundation trench bottom land is native for excavation equipment basis foundation trench, then in plain soil On pave and rubble and tamp, finally colligation transverse steel and longitudinal reinforcement in the horizontal direction on described rubble;
(3) multiple row steel pipe riser is vertically squeezed into through rubble and element soil, is located in multiple row steel pipe riser same Distinguish in the steel pipe riser of one lateral attitude and a steel pipe cross-arm is installed in the horizontal direction, steel pipe cross-arm described in each and right The intersection location of the steel pipe riser that should be set is connected by cruciform fastening for falsework;
(4) the sideline anchor point of the H profile steel embedded part of left and right two is thrown and surveys to steel pipe cross-arm, then bury two H profile steels On the steel pipe cross-arm that part is arranged on described in each along longitudinal bracing, H profile steel built-in fitting position is adjusted, make H profile steel built-in fitting side Line measures the point position on steel pipe cross-arm and overlaps with throwing, then carries out the adjustment of H profile steel built-in fitting upper surface absolute altitude, and thousand are used during adjustment Jin top sets sheet metal or adjustment cruciform fastening for falsework absolute altitude by the jack-up of H profile steel built-in fitting 1, then in H profile steel built-in fitting bottom pad, until H Shaped steel built-in fitting position and absolute altitude are met the requirements, and then H profile steel built-in fitting bottom both sides are welded and fixed with steel pipe cross-arm;
(5) casting concrete causes that top of concrete is consistent with facility floor absolute altitude in Equipment Foundations foundation trench.
The advantage of the invention is that:Construction cost is low, and simple structure, firm, position easy for installation are accurate.It is vertical using steel pipe The strutting system of pipe and steel pipe cross-arm, cross sectional moment of inertia is big, and bending resistance is strong, recycles the bending resistance of H profile steel itself, so that Whole H profile steel can be installed using a small amount of steel pipe riser and steel pipe cross-arm.Using cruciform fastening for falsework it is convenient to assemble and disassemble the characteristics of, Can controlled level cross-arm well absolute altitude, for fixing and finely tuning embedded part absolute altitude.Beaten through metalling and foundation trench bottom element soil Enter multiple row steel pipe riser, constrain the displacement of standpipe, H profile steel position deviation is controlled well.Steel pipe riser and steel pipe cross-arm The whole mounting structure system such as strutting system, adjustable cruciform fastening for falsework, armored concrete ensure that the precision of H profile steel, be follow-up Equipment install provide Reliable guarantee.
Brief description of the drawings
Fig. 1 is using a kind of equipment basic pre-buried part construction method elevational schematic view of Support Method of the invention.
Specific embodiment
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.
The equipment basic pre-buried part construction method of a kind of Support Method as shown in Figure 1, comprises the following steps:
(1) unwrapping wire of Equipment Foundations foundation trench 3 is carried out in existing facility floor 2, using concrete cutting machine to Equipment Foundations base Cut in the sideline of groove 3;
(2) excavation equipment basis foundation trench 3 is to set depth, then the element soil 4 of the tamping apparatus basis bottom land of foundation trench 3, then Paved on plain soil 4 and rubble and tamped, finally colligation transverse steel and longitudinal reinforcement in the horizontal direction on described rubble 5;
(3) multiple row steel pipe riser 6 is vertically squeezed into through rubble 5 and element soil 4, is located in multiple row steel pipe riser 6 With a steel pipe cross-arm 7 is installed in the horizontal direction respectively in the steel pipe riser 6 of lateral attitude one by one, the steel pipe described in each is horizontal The intersection location of load 7 and the steel pipe riser 6 being correspondingly arranged is connected by cruciform fastening for falsework 8.The absolute altitude of described steel pipe cross-arm according to The H profile steel built-in fitting bottom absolute altitude for intending installing determines.
(4) the sideline anchor point of the H profile steel embedded part 1 of left and right two is thrown and surveys to steel pipe cross-arm 7, then by two H profile steels On the steel pipe cross-arm 7 that embedded part 1 is arranged on described in each along longitudinal bracing, the position of adjustment H profile steel built-in fitting 1 makes H profile steel pre-buried The sideline of part 1 measures the point position on steel pipe cross-arm 7 and overlaps with throwing, then carries out the adjustment of the upper surface absolute altitude of H profile steel built-in fitting 1, adjusts Shi Caiyong jack set sheet metal or adjustment cruciform fastening for falsework mark by the jack-up of H profile steel built-in fitting 1, then in the bottom pad of H profile steel built-in fitting 1 Height, until the position of H profile steel built-in fitting 1 and absolute altitude meet the requirements, then welds the both sides of going to the bottom of H profile steel built-in fitting 1 with steel pipe cross-arm Connect fixation;
(5) casting concrete causes that top of concrete is consistent with the absolute altitude of facility floor 2 in Equipment Foundations foundation trench 3.

Claims (1)

1. the equipment basic pre-buried part construction method of a kind of Support Method, it is characterised in that comprise the following steps:
(1) Equipment Foundations foundation trench unwrapping wire is carried out in existing facility floor, using concrete cutting machine to Equipment Foundations foundation trench sideline Cut;
(2), to set depth, then the element of tamping apparatus basis foundation trench bottom land is native for excavation equipment basis foundation trench, then is spread out on plain soil Paving rubble is simultaneously tamped, finally colligation transverse steel and longitudinal reinforcement in the horizontal direction on described rubble;
(3) multiple row steel pipe riser is vertically squeezed into through rubble and element soil, same one is located in multiple row steel pipe riser horizontal A steel pipe cross-arm is installed in the horizontal direction to distinguishing in the steel pipe riser of position, steel pipe cross-arm and correspondence described in each set The intersection location of the steel pipe riser put is connected by cruciform fastening for falsework;
(4) the sideline anchor point of the H profile steel embedded part of left and right two is thrown and surveys to steel pipe cross-arm, then by two H profile steel embedded part edges Longitudinal bracing is arranged on the steel pipe cross-arm described in each, adjustment H profile steel built-in fitting position, make H profile steel built-in fitting sideline with The point position that throwing is measured on steel pipe cross-arm is overlapped, then carries out the adjustment of H profile steel built-in fitting upper surface absolute altitude, and jack is used during adjustment By the jack-up of H profile steel built-in fitting 1, then sheet metal or adjustment cruciform fastening for falsework absolute altitude are set in H profile steel built-in fitting bottom pad, until H profile steel Built-in fitting position and absolute altitude are met the requirements, and then H profile steel built-in fitting bottom both sides are welded and fixed with steel pipe cross-arm;
(5) casting concrete causes that top of concrete is consistent with facility floor absolute altitude in Equipment Foundations foundation trench.
CN201611192563.0A 2016-12-21 2016-12-21 Scaffolding equipment foundation embedded part construction method Pending CN106703072A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611192563.0A CN106703072A (en) 2016-12-21 2016-12-21 Scaffolding equipment foundation embedded part construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611192563.0A CN106703072A (en) 2016-12-21 2016-12-21 Scaffolding equipment foundation embedded part construction method

Publications (1)

Publication Number Publication Date
CN106703072A true CN106703072A (en) 2017-05-24

Family

ID=58938565

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611192563.0A Pending CN106703072A (en) 2016-12-21 2016-12-21 Scaffolding equipment foundation embedded part construction method

Country Status (1)

Country Link
CN (1) CN106703072A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108869874A (en) * 2018-06-15 2018-11-23 五冶集团上海有限公司 The production method and sliding support of jet chimney sliding support
CN110761319A (en) * 2019-11-27 2020-02-07 广东电网有限责任公司 Pre-buried positioning tool of concrete rag bolt
CN113718559A (en) * 2021-08-27 2021-11-30 中国二十二冶集团有限公司 Quick adjusting method for elevation of embedded part of track

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1861925A (en) * 2006-06-16 2006-11-15 崔成群 Anchor bolt preburied positioning device and using method thereof
JP2010156158A (en) * 2008-12-27 2010-07-15 Takacho Kensetsu:Kk Box drawing form supporting apparatus and method of installing the same
CN103669883A (en) * 2013-11-20 2014-03-26 中国建筑第二工程局有限公司 Installation and adjustment method of combined shock insulation support
CN103835308A (en) * 2012-11-23 2014-06-04 江西昌河航空工业有限公司 Method for installing embedded base plate of machine tool
CN105019470A (en) * 2015-08-03 2015-11-04 共享钢构有限责任公司 Method for pre-burying of large group of foundation bolts
CN105113799A (en) * 2015-08-07 2015-12-02 中建三局第二建设工程有限责任公司 Prearranged adjustable clamping fixture of large embedded part and construction method thereof
CN105544587A (en) * 2015-12-10 2016-05-04 上海建工一建集团有限公司 Combined tower crane foundation and construction method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1861925A (en) * 2006-06-16 2006-11-15 崔成群 Anchor bolt preburied positioning device and using method thereof
JP2010156158A (en) * 2008-12-27 2010-07-15 Takacho Kensetsu:Kk Box drawing form supporting apparatus and method of installing the same
CN103835308A (en) * 2012-11-23 2014-06-04 江西昌河航空工业有限公司 Method for installing embedded base plate of machine tool
CN103669883A (en) * 2013-11-20 2014-03-26 中国建筑第二工程局有限公司 Installation and adjustment method of combined shock insulation support
CN105019470A (en) * 2015-08-03 2015-11-04 共享钢构有限责任公司 Method for pre-burying of large group of foundation bolts
CN105113799A (en) * 2015-08-07 2015-12-02 中建三局第二建设工程有限责任公司 Prearranged adjustable clamping fixture of large embedded part and construction method thereof
CN105544587A (en) * 2015-12-10 2016-05-04 上海建工一建集团有限公司 Combined tower crane foundation and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108869874A (en) * 2018-06-15 2018-11-23 五冶集团上海有限公司 The production method and sliding support of jet chimney sliding support
CN110761319A (en) * 2019-11-27 2020-02-07 广东电网有限责任公司 Pre-buried positioning tool of concrete rag bolt
CN113718559A (en) * 2021-08-27 2021-11-30 中国二十二冶集团有限公司 Quick adjusting method for elevation of embedded part of track

Similar Documents

Publication Publication Date Title
CN104975622B (en) Correction and reinforcement method for precast pile foundation of high-rise building
CN104878835B (en) Strip footing increases basement structure behind house
CN108487256B (en) Reinforced structure and method for deepening and super-digging foundation pit
CN109322241A (en) Trestle work structure and construction method
CN106703072A (en) Scaffolding equipment foundation embedded part construction method
CN102071698B (en) Construction method of beddings of foundation downward overturn beam and pile cap
CN109931077B (en) Support system for tunnel repair and construction method thereof
CN106592990A (en) Prefabricated building foundation column bar precise positioning tool and positioning method
CN105696800A (en) Temporary fixed sleeve frame for preventing relative displacement generated during construction of steel-structured anchor bolts
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN106087991B (en) Stake top absolute altitude is in natural ground dug pile construction method below
KR101220256B1 (en) Retaining wall structure
CN110016919A (en) A kind of aging blocks install the minimally invasive foundation pit structure of elevator and construction method additional
CN108222046A (en) A kind of method of construction of prefabricated isolated footing
CN102296600B (en) Method for positioning middle pile of spread built subway station
CN206352308U (en) A kind of shaped steel part constructing structure
CN103866982B (en) A kind of petal art framework construction method
CN209412681U (en) Trestle work structure
JP7189001B2 (en) How to construct the foundation of a building
CN106677558A (en) Construction method for deep foundation pit assembling type stairway used for people
CN106193120A (en) Basement is encorbelmented, and base plate is inverse makees structure and construction method
CN109594577A (en) Prefabricated assembled bar shaped composite foundation mounting structure for soft soil foundation
CN108571014A (en) A kind of basement top-down method construction method of fixed lattice column
CN109577364A (en) A kind of stacker-reclaimer track foundation construction method
CN104695290A (en) Installation method of railway concrete protection fences

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170524