CN105696800A - Temporary fixed sleeve frame for preventing relative displacement generated during construction of steel-structured anchor bolts - Google Patents

Temporary fixed sleeve frame for preventing relative displacement generated during construction of steel-structured anchor bolts Download PDF

Info

Publication number
CN105696800A
CN105696800A CN201610041360.5A CN201610041360A CN105696800A CN 105696800 A CN105696800 A CN 105696800A CN 201610041360 A CN201610041360 A CN 201610041360A CN 105696800 A CN105696800 A CN 105696800A
Authority
CN
China
Prior art keywords
crab
bolt
sleeve
relative displacement
cage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610041360.5A
Other languages
Chinese (zh)
Other versions
CN105696800B (en
Inventor
李卫华
杨斐
邵新宇
汪锋
龚光宁
王超
孙清华
李毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Steel Structure Engineering Co Ltd
Original Assignee
China Construction Steel Structure Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Steel Structure Corp Ltd filed Critical China Construction Steel Structure Corp Ltd
Priority to CN201610041360.5A priority Critical patent/CN105696800B/en
Publication of CN105696800A publication Critical patent/CN105696800A/en
Application granted granted Critical
Publication of CN105696800B publication Critical patent/CN105696800B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • E04G21/1841Means for positioning building parts or elements

Abstract

The invention discloses a temporary fixed sleeve frame for preventing the relative displacement generated during the construction process of steel-structured anchor bolts. The temporary fixed sleeve frame comprises two anchor bolt sleeve plates. The two anchor bolt sleeve plates are arranged up and down. Holes are drilled in the corresponding positions of the two anchor bolt sleeve plates. Anchor bolt sleeves are inserted in the holes, which are corresponding up and down, in the two anchor bolt sleeve plates and are welded and fixed. A plurality of fixed anchor bolts are fixed on a dedicated sleeve frame. The anchor bolt sleeves correspondingly sleeve the upper ends of the fixed anchor bolts. Anchor bolt sleeve caps cover the upper openings of the anchor bolt sleeves. During the construction process, especially in the concrete pouring stage, the anchor bolts does not move relatively; the temporary fixed sleeve frame can be applied before and after reinforcing steel bars are bound, so that the application range is wide; screw threads of the anchor bolts are protected, so that the finished product is protected; and the temporary fixed frame can be repeatedly used, so that the material using rate is improved.

Description

The construction of anti-steel construction sill anchor produces the interim fixed cage of relative displacement
Technical field
The present invention relates to the fixing utensil burying sill anchor under a kind of steel column underground, particularly relate to the construction of a kind of anti-steel construction sill anchor and produce the interim fixed cage of relative displacement。
Background technology
Steel construction project needs to bury sill anchor underground under steel column, is used for fixing steel column and uses。Sill anchor generally requires in the cast-in-place base plate being embedded in building, how ensure that being accurately positioned of sill anchor, buries underground, brings it about displacement because of concrete flowing when how to reduce cast in situs base plate, is the most important thing of steel construction early stage construction。Installing because relative displacement can affect follow-up steel column, may result in steel column time serious cannot install。
The main stream mode burying sill anchor at present underground has two kinds: crab-bolt is directly welded on the main muscle of building base plate by first kind of way。The second is the special stock in end making and being fixed on pile foundation, is welded on stock by crab-bolt, reduces concrete impact。
Prior art one:
As it is shown in figure 1, after civil engineering unit substrate reinforcing bar 2 colligation completes, by the post footing crab-bolt 1 needed for steel construction by measurement and positioning, preliminary fixing, correction, the accurate position adjusting crab-bolt 1 before casting concrete, and be finally fixed on baseplate reinforcing bar 2。
The shortcoming of prior art one is more apparent:
First: have plasticity and elasticity due to reinforcing bar itself, when burying underground, the weight of workman and construction machinery can make bar-mat reinforcement deform, and causes the change of crab-bolt absolute altitude and position;
Second: bar-mat reinforcement can offset when building underplate concrete, it is also secured to the sill anchor on reinforcing bar and also can ensue skew, cause change in location;The change in location of crab-bolt can seriously cause follow-up Steel Structure Installation precision and installation quality;
3rd: during casting concrete, lower end is subject to the impact of concrete flowing, and upper end can produce irregular displacement;
4th: relative displacement produced by crab-bolt can cause follow-up steel column installation difficulty。
Prior art two:
As shown in Fig. 2 a, Fig. 2 b, first, make special stock 3, in order to the position of fixing crab-bolt 1 system, strengthen its stability, crab-bolt is welded on stock, reduce the concreting impact on its position。
Before civil engineering unit completes reinforcing bar side bundle, the stock completed in advance and crab-bolt are measured by on-the-spot reality, is seated to and specifies position, and carry out reinforcement measure and finished product protection。
The shortcoming of prior art two:
First: when pouring into a mould concrete, due to the character of concrete construction technology and stock, being subject to concrete impulsive force bottom crab-bolt, relative displacement can occur in crab-bolt upper end;
Second: the adjustable space of steel column bottom bolts reserving hole is less, after crab-bolt top is subjected to displacement, it is more difficult to meet subsequent construction requirement;
3rd: can only bury underground before reinforcing bar binding on working procedure。If reinforcing bar binding completes, just cannot bury underground;
4th: the follow-up protection to crab-bolt screw thread is comparatively inconvenient。
Summary of the invention
It is an object of the invention to provide the anti-steel construction sill anchor construction generation interim fixed cage of relative displacement of a kind of safety height, good fixing effect, simple installation, good stability。
It is an object of the invention to be achieved through the following technical solutions:
The anti-steel construction sill anchor construction of the present invention produces the interim fixed cage of relative displacement, and including crab-bolt cage plate, described crab-bolt cage plate is provided with crab-bolt sleeve, and the suitable for reading of described crab-bolt sleeve is provided with crab-bolt upper shield。
As seen from the above technical solution provided by the invention; the anti-steel construction sill anchor construction that the embodiment of the present invention provides produces the interim fixed cage of relative displacement; crab-bolt relative displacement in work progress is fixed by fixation; and protect screw thread by crab-bolt sleeve; there is good safety; good fixing effect, simple installation, good stability。
Accompanying drawing explanation
Fig. 1 is that in prior art one, after reinforcing bar binding, crab-bolt is directly fixed on the structural representation of baseplate reinforcing bar;
The structural representation of special stock and application state thereof in Fig. 2 a and Fig. 2 b respectively prior art two;
Fig. 3 produces the structural representation of the interim fixed cage of relative displacement for the anti-steel construction sill anchor construction that the embodiment of the present invention provides;
Fig. 4 a to Fig. 4 d produces the application process schematic diagram of the interim fixed cage of relative displacement for the anti-steel construction sill anchor construction that the embodiment of the present invention provides。
Detailed description of the invention
The embodiment of the present invention will be described in further detail below。
The present invention anti-steel construction sill anchor construction produce the interim fixed cage of relative displacement, its preferably detailed description of the invention be:
Including crab-bolt cage plate, described crab-bolt cage plate is provided with crab-bolt sleeve, and the suitable for reading of described crab-bolt sleeve is provided with crab-bolt upper shield。
Including two pieces of crab-bolt cage plates, two pieces of crab-bolt cage plates are arranged up and down and hole in corresponding position, and described crab-bolt sleeve is inserted in the hole that two pieces of crab-bolt cage plates are corresponding up and down and is welded and fixed。
Described crab-bolt cage plate is arranged multiple crab-bolt sleeve, is arranged in the height of crab-bolt sleeve in described crab-bolt cage plate corner more than the height of the crab-bolt sleeve being arranged in the middle part of described crab-bolt cage plate。
Multiple fixing crab-bolts are fixed on special stock, after multiple crab-bolt sleeve correspondences are enclosed within the upper end of multiple fixing crab-bolt, and crab-bolt upper shield in the upper flap of each crab-bolt sleeve。
The anti-steel construction sill anchor construction of the present invention produces the interim fixed cage of relative displacement, can prevent in work progress, particularly the concreting stage, the relative movement of crab-bolt;Forward and backward all applicable at reinforcing bar binding, applicable surface is wider;The screw thread of protection crab-bolt, carries out finished product protection;The repeatable utilization of interim fixed cage, improves stock utilization。
Specific embodiment:
Increasingly can not meet the prescription of quickly construction rhythm and construction in traditional construction method, traditional construction technology has been improved by the present invention。
Interim fixed cage designs:
As it is shown on figure 3, interim fixed cage mainly includes crab-bolt cage plate 4, crab-bolt sleeve 5, crab-bolt upper shield 6 three part。
In interim fixed cage, crab-bolt cage plate 4 acts primarily as fixation; work progress controls the change of relative position of crab-bolt 1 in allowed band; crab-bolt sleeve 5, crab-bolt upper shield 6 act primarily as protection crab-bolt screw thread effect; four corner sleeves are longer and steel plate suitable for reading seals; by when putting interim stock, it is ensured that stock level。
Interim fixed cage makes:
First according to the diameter of crab-bolt and upper end exposed length, selecting round steel pipe, diameter of steel tube is preferably greater than crab-bolt 4mm and is advisable, and according to protruded length blanking。Corner sleeve and upper shield should exceed cage plate 10cm, and interim stock height (two cage plate spacing) is not preferably less than 15cm。Next according to pipe diameter and crab-bolt position, cage plate is accurately positioned, perforate。Finally that two pieces of cage plates are integral by sleeve weld, guarantee during welding that two edges of boards are in same vertical line。The concrete parameter that makes also to be determined by the size of sill anchor and distribution。
Interim fixed cage uses:
As shown in Fig. 4 a, 4b, 4c, 4d, bury underground after location completes at sill anchor stock, by fixed cage by being placed on its end, after in place, crab-bolt upper shield is covered the end in crab-bolt。
Building subregion and the order of floor casting concrete according to civil engineering, reach just can be pulled down after some strength until concrete, being arranged on next group needs in the crab-bolt of casting concrete。
Beneficial effects of the present invention:
1, owing to the application have employed interim fixed cage, this structure will make crab-bolt crab-bolt when concrete construction that relative displacement will not occur, substantially increase the work efficiency of subsequent construction, pressed crab-bolt short and buried the duration underground, improve the installation quality of first joint steel column。
2, before reinforcing bar binding, it is all suitable for after colligation, comparatively flexibly;
3, the repeatable utilization of interim fixed cage, improves stock utilization;
4 and crab-bolt screw thread is provided better protection, improve construction quality;
The present invention can also fix crab-bolt upper end or lower end by other forms and prevent the measure of its relative movement。By crab-bolt upper end screw thread being entangled the purpose other materials and measure reaching protection crab-bolt screw thread。
The present invention overlaps frame member temporarily, fixes crab-bolt relative displacement in work progress by fixation, and protect screw thread by crab-bolt sleeve, there is good safety, good fixing effect, simple installation, good stability。
The above; being only the present invention preferably detailed description of the invention, but protection scope of the present invention is not limited thereto, any those familiar with the art is in the technical scope of present disclosure; the change that can readily occur in or replacement, all should be encompassed within protection scope of the present invention。Therefore, protection scope of the present invention should be as the criterion with the protection domain of claims。

Claims (4)

1. an anti-steel construction sill anchor construction produces the interim fixed cage of relative displacement, it is characterised in that including crab-bolt cage plate, described crab-bolt cage plate is provided with crab-bolt sleeve, and the suitable for reading of described crab-bolt sleeve is provided with crab-bolt upper shield。
2. anti-steel construction sill anchor according to claim 1 construction produces the interim fixed cage of relative displacement, it is characterized in that, including two pieces of crab-bolt cage plates, two pieces of crab-bolt cage plates are arranged up and down and hole in corresponding position, and described crab-bolt sleeve is inserted in the hole that two pieces of crab-bolt cage plates are corresponding up and down and is welded and fixed。
3. anti-steel construction sill anchor according to claim 2 construction produces the interim fixed cage of relative displacement, it is characterized in that, described crab-bolt cage plate is arranged multiple crab-bolt sleeve, is arranged in the height of crab-bolt sleeve in described crab-bolt cage plate corner more than the height of the crab-bolt sleeve being arranged in the middle part of described crab-bolt cage plate。
4. anti-steel construction sill anchor according to claim 3 construction produces the interim fixed cage of relative displacement, it is characterized in that, multiple fixing crab-bolts are fixed on special stock, after multiple crab-bolt sleeve correspondences are enclosed within the upper end of multiple fixing crab-bolt, and crab-bolt upper shield in the upper flap of each crab-bolt sleeve。
CN201610041360.5A 2016-01-21 2016-01-21 Anti- steel construction sill anchor construction generates relative displacement and is fixed temporarily stock Active CN105696800B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610041360.5A CN105696800B (en) 2016-01-21 2016-01-21 Anti- steel construction sill anchor construction generates relative displacement and is fixed temporarily stock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610041360.5A CN105696800B (en) 2016-01-21 2016-01-21 Anti- steel construction sill anchor construction generates relative displacement and is fixed temporarily stock

Publications (2)

Publication Number Publication Date
CN105696800A true CN105696800A (en) 2016-06-22
CN105696800B CN105696800B (en) 2018-08-14

Family

ID=56228371

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610041360.5A Active CN105696800B (en) 2016-01-21 2016-01-21 Anti- steel construction sill anchor construction generates relative displacement and is fixed temporarily stock

Country Status (1)

Country Link
CN (1) CN105696800B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108360551A (en) * 2018-03-20 2018-08-03 南京兴华建筑设计研究院股份有限公司 The positioning device of scene binding foundation bolt in steel construction
CN108691423A (en) * 2017-04-05 2018-10-23 通州建总集团有限公司 A kind of foundation bolt assembling fixing device
CN109680974A (en) * 2018-12-20 2019-04-26 合肥巍华钢结构有限公司 A kind of Construction of Steel Structure anchor bolt screw thread shield
CN112695637A (en) * 2020-12-24 2021-04-23 云南交投公路建设第二工程有限公司 Tower beam temporary consolidation supporting structure easy to unload quickly and manufacturing and construction process
CN113605386A (en) * 2021-08-19 2021-11-05 中建钢构工程有限公司 Anchor bolt pre-embedding construction method
CN115434513A (en) * 2022-09-29 2022-12-06 上海宝冶冶金工程有限公司 Construction method for embedding anchor bolt
CN115506609A (en) * 2022-09-16 2022-12-23 太原重工工程技术有限公司 Foundation bolt positioning device and construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11237246A (en) * 1998-02-19 1999-08-31 Sekisui House Ltd Diagonal dimension checking tool of building foundation
US20030145475A1 (en) * 2001-05-17 2003-08-07 Sparkes David C. Framer's layout square
US20030209821A1 (en) * 2002-05-09 2003-11-13 Schmaltz Rodney J. Concrete jar step insert
CN201581650U (en) * 2009-12-04 2010-09-15 上海市第二建筑有限公司 Sleeve positioner
CN201991241U (en) * 2011-03-30 2011-09-28 宿迁市科路养护技术有限公司 Steel structural upright column foundation bolt positioning device
CN202266034U (en) * 2011-10-13 2012-06-06 武汉建工股份有限公司 Fixing device for anchor bolts of embedded type diamond combined steel and concrete column feet

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11237246A (en) * 1998-02-19 1999-08-31 Sekisui House Ltd Diagonal dimension checking tool of building foundation
US20030145475A1 (en) * 2001-05-17 2003-08-07 Sparkes David C. Framer's layout square
US20030209821A1 (en) * 2002-05-09 2003-11-13 Schmaltz Rodney J. Concrete jar step insert
CN201581650U (en) * 2009-12-04 2010-09-15 上海市第二建筑有限公司 Sleeve positioner
CN201991241U (en) * 2011-03-30 2011-09-28 宿迁市科路养护技术有限公司 Steel structural upright column foundation bolt positioning device
CN202266034U (en) * 2011-10-13 2012-06-06 武汉建工股份有限公司 Fixing device for anchor bolts of embedded type diamond combined steel and concrete column feet

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108691423A (en) * 2017-04-05 2018-10-23 通州建总集团有限公司 A kind of foundation bolt assembling fixing device
CN108360551A (en) * 2018-03-20 2018-08-03 南京兴华建筑设计研究院股份有限公司 The positioning device of scene binding foundation bolt in steel construction
CN109680974A (en) * 2018-12-20 2019-04-26 合肥巍华钢结构有限公司 A kind of Construction of Steel Structure anchor bolt screw thread shield
CN109680974B (en) * 2018-12-20 2020-10-09 合肥巍华钢结构有限公司 Anchor bolt thread protective cover for steel structure construction
CN112695637A (en) * 2020-12-24 2021-04-23 云南交投公路建设第二工程有限公司 Tower beam temporary consolidation supporting structure easy to unload quickly and manufacturing and construction process
CN112695637B (en) * 2020-12-24 2022-11-29 云南交投公路建设第二工程有限公司 Tower beam temporary consolidation supporting structure easy to unload quickly and manufacturing and construction process
CN113605386A (en) * 2021-08-19 2021-11-05 中建钢构工程有限公司 Anchor bolt pre-embedding construction method
CN115506609A (en) * 2022-09-16 2022-12-23 太原重工工程技术有限公司 Foundation bolt positioning device and construction method
CN115434513A (en) * 2022-09-29 2022-12-06 上海宝冶冶金工程有限公司 Construction method for embedding anchor bolt
CN115434513B (en) * 2022-09-29 2023-11-21 上海宝冶冶金工程有限公司 Construction method for embedding anchor bolts

Also Published As

Publication number Publication date
CN105696800B (en) 2018-08-14

Similar Documents

Publication Publication Date Title
CN105696800A (en) Temporary fixed sleeve frame for preventing relative displacement generated during construction of steel-structured anchor bolts
CN107268424B (en) Can fast leveling precast assembly bridge pier structure and its construction method
CN103669883B (en) A kind of installation adjusting method of combined isolation bearing
CN107130628A (en) The construction method of embedding anchor bolts flange and embedding anchor bolts
CN203247603U (en) High-position foundation bolt positioning device
CN112900450A (en) Rotary drilling and full-rotation combined back-inserting method positioning method for steel pipe structure pile by reverse construction method
CN109183812B (en) Construction method of combined deep foundation pit supporting structure
CN110685277A (en) Guide positioning device and method for permanent steel casing of large onshore pile foundation
CN108316290A (en) One pile for one column structure without cushion cap and its construction method
CN103161313A (en) Connection method of main reinforcement of constructional column of infilled wall and framed girder
CN108265725A (en) Drawknot stake supporting and the construction method of basement process
CN106087991A (en) The high dug pile construction method at natural below ground of stake top mark
CN106836198B (en) Positioning device combined steel formwork bored concrete pile and construction method
CN108149866A (en) PC stair cast-in-place node pre-cast bolt positioning devices and method
JP2011074632A (en) Unit structure of anchor bolt used for construction of foundation for equipment, and method of construction of foundation for equipment using the unit structure
CN116427622A (en) Semi-buried type steel pipe concrete column foot structure of underground garage and construction method thereof
CN207717504U (en) A kind of support construction for ultra-large type bifurcated pipe group's water pressure test
KR20120025945A (en) Reinforcement assembly of concrete file and building foundation
CN103397654B (en) Construction method for transforming reinforced concrete column into stiff column for connection
CN103352568A (en) Method for building constructional column on foundation pad
CN103205983B (en) Construction method of basement rear support system
CN206396782U (en) A kind of positioner for pre-embedded anchoring bolts of being constructed on isolated footing
CN207228104U (en) A kind of isolating and protecting device for preventing pile foundation steel bar cage deflection
CN206352308U (en) A kind of shaped steel part constructing structure
CN206752699U (en) A kind of concrete filled steel tube column connected node

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 3801, 38 / F, Zhongjian science and engineering building, No. 3331, Weilan Coast Community Center Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: China Construction Engineering Group Co.,Ltd.

Address before: 518040 Guangdong city of Shenzhen province Futian District Che Kung Temple tipping building 17 layer

Patentee before: China Construction Steel Structure Corp.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220921

Address after: Room 1908, Chengtou Xin Times Building, No. 2009, Pingshan Avenue, Liulian Community, Pingshan Street, Pingshan District, Shenzhen 518000

Patentee after: China Construction Steel Engineering Co.,Ltd.

Address before: 3801, 38 / F, China Construction Science and engineering building, No. 3331, Weilan Coast Community Central Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee before: China Construction Engineering Group Co.,Ltd.