CN103088843B - Pipe gallery embedded iron parts construction method of installation - Google Patents

Pipe gallery embedded iron parts construction method of installation Download PDF

Info

Publication number
CN103088843B
CN103088843B CN201310066719.0A CN201310066719A CN103088843B CN 103088843 B CN103088843 B CN 103088843B CN 201310066719 A CN201310066719 A CN 201310066719A CN 103088843 B CN103088843 B CN 103088843B
Authority
CN
China
Prior art keywords
iron parts
embedded iron
template
installation
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310066719.0A
Other languages
Chinese (zh)
Other versions
CN103088843A (en
Inventor
陈斌
邵怀锋
王树伟
高瑞
孙丽丽
许茹
王佐雷
孙洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Urban Construction Group Co Ltd
Original Assignee
Jinan Urban Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Urban Construction Group Co Ltd filed Critical Jinan Urban Construction Group Co Ltd
Priority to CN201310066719.0A priority Critical patent/CN103088843B/en
Publication of CN103088843A publication Critical patent/CN103088843A/en
Application granted granted Critical
Publication of CN103088843B publication Critical patent/CN103088843B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The present invention relates to a kind of pipe gallery embedded iron parts construction method of installation, comprise the installation of horizontal embedded iron parts and the installation of vertical embedded iron parts, it is characterized in that: horizontal embedded iron parts is welded on reinforcing bar and reinforcing cage, be welded on reinforcing cage with reinforcing bar clout and determine horizontal embedded iron parts position, first the numbering of template and the setting of modulus is carried out before embedded iron parts is installed, the position of embedded iron parts is accurately located by template modulus, adopt screw to be fixed on by embedded iron parts on side wall inner formword, embedded iron parts is welded to support reinforcing bar.The invention has the beneficial effects as follows: reduce embedded iron parts constructed after repair rate, reduce cost, improve efficiency of construction, ensure that the installation accuracy of comprehensive pipeline, improve the application life of pipeline; Be applicable to the construction of reinforced concrete work embedded iron parts, in reinforced concrete work embedded iron parts is installed, have wide application space, have promotional value.

Description

Pipe gallery embedded iron parts construction method of installation
(1) technical field
The present invention relates to a kind of construction method of municipal engineering, particularly a kind of pipe gallery embedded iron parts construction method of installation.
(2) background technology
Along with the development in city, comprehensive pipeline entirety is laid in more and more general on the inherent newly-built road of reinforced concrete pipe gallery, the construction of integral cast-in-situ steel concrete pipe gallery can not only improve the using function of comprehensive pipeline, and can reduce the difficulty of pipeline maintenance.But the installation of integral cast-in-situ steel concrete pipe gallery comprehensive pipeline is comparatively large by embedded iron parts position influence in piping lane, embedded iron parts position is inaccurate cause to reprocess cost higher.
(3) summary of the invention
The present invention in order to make up the deficiencies in the prior art, provide a kind ofly improve embedded iron parts positional precision, reduce repair rate, improve efficiency of construction, improve pipeline application life, pipe gallery embedded iron parts construction method of installation that operating expenses is low.
The present invention is achieved through the following technical solutions:
A kind of pipe gallery embedded iron parts construction method of installation, comprise the installation of horizontal embedded iron parts and the installation of vertical embedded iron parts, it is characterized in that: horizontal embedded iron parts is welded on reinforcing bar and reinforcing cage, be welded on reinforcing cage with reinforcing bar clout and determine horizontal embedded iron parts position, first the numbering of template and the setting of modulus is carried out before embedded iron parts is installed, the position of embedded iron parts is accurately located by template modulus, adopt screw to be fixed on by embedded iron parts on side wall inner formword, embedded iron parts is welded to support reinforcing bar.
A kind of pipe gallery embedded iron parts construction method of installation, is characterized in that: the installation of horizontal embedded iron parts comprises the following steps:
(1), surveying setting-out: according to designing requirement in the position determining horizontal embedded iron parts, and carry out mark;
(2), reinforcing bar binding: the position considering embedded iron parts in process of binding;
(3), model sheetinstallat: support with double steel frame pipe during installation:
(4), bearing bar is welded: carry out unwrapping wire according to the design altitude of embedded iron parts, position, hang position and the elevation of bilinear con-trol embedded iron parts, construction line place elevation is that embedded iron parts is gone to the bottom absolute altitude, then operating personnel utilizes reinforcing bar clout, double bearing bar is welded according to the construction position of line and elevation, bearing bar upper flat consistent with line elevation of constructing, bearing bar is welded on bed course, will carry out horizontal welding simultaneously;
(5), embedded iron parts is installed: lifted to by embedded iron parts on bearing bar, then utilize crowbar mobile embedded iron parts on bearing bar, until after the position of embedded iron parts meets designing requirement, weld embedded iron parts;
(6), formwork reinforcement: be connected with template by steel wire after embedded iron parts has welded, closure should be triangularly arranged, and by steel wire bolt on the exhaust opening of embedded iron parts or the embedded bar of embedded iron parts, other end bolt is in template;
(7), concreting: will detect concrete slump before concreting, concrete vibrating adopts quincunx, and concreting bubble of no longer emerging is advisable, and concreting carries out receipts face after vibrating in time.
A kind of pipe gallery embedded iron parts construction method of installation, is characterized in that: the installation of vertical embedded iron parts comprises the following steps:
(1), surveying setting-out: the position determining embedded iron parts according to designing requirement in template, and play the line of ink marker and carry out mark;
(2), reinforcing bar binding: the position considering embedded iron parts in process of binding;
(3), embedded iron parts is installed: be installed in template by embedded iron parts according to line of ink marker position, and be screwed firmly;
(4), template assembly: the numbering according to template carries out the assembled of template, assembles during template assembly in strict accordance with the numbering of setting in advance and modulus;
(5), embedded iron parts welding: according to thickness of concrete cover, embedded iron parts is welded with skeleton reinforcing steel bar;
(6), formwork reinforcement: after having welded, adjust skeleton reinforcing steel bar position, and according to the reinforcing designing thickness of wall body, template is carried out in position, after formwork reinforcement completes, the stability of template is tested and concreting;
(7), concreting: when reducing in concreting process, reduce vibrating spear touching template;
(8), stripping: first fixing screw is turned on before dismounting, then pipe gallery template is removed according to assembled modulus block-by-block in advance.
(9), inspect for acceptance: often complete a procedure, carry out self-inspection, inspect for acceptance with spirit level and conjunction chi, recording error value, checks embedded iron parts position one by one, guarantees that each embedded iron parts is in place.
A kind of pipe gallery embedded iron parts construction method of installation, it is characterized in that: reinforce after the model sheetinstallat of horizontal embedded iron parts, reinforcing mode adopts little steel bar end to be welded in skeleton reinforcing steel bar.
A kind of pipe gallery embedded iron parts construction method of installation, it is characterized in that: the method being screwed template is: the edge in advance screw being welded to embedded iron parts, then embedded iron parts and template are fixed by screw hole reserved in template, screw adopts stainless steel electrode to be welded on the center on embedded iron parts four limits.
A kind of pipe gallery embedded iron parts construction method of installation, is characterized in that: the timely brushing release agent of the template after dismounting, and puts according to assembled order.
The invention has the beneficial effects as follows: strengthen the fixing of embedded iron parts, ensure that embedded iron parts position is accurate, this operation reduces the interference of concrete vibrating to embedded iron parts position, guarantees the accuracy of embedded iron parts.Therefore, this engineering method accurately can improve pipe gallery embedded iron parts positional precision, reduces reprocessing embedded iron parts when comprehensive pipeline is installed, improves efficiency of construction, can not cause the displacement of comprehensive pipeline, guarantee the requirement of pipeline safety around, reduce construction cost simultaneously.The advantage of the method also has: operating expenses is low, the long service life of pipeline, has good Social benefit and economic benefit, and installing in construction at municipal reinforced concrete work embedded iron parts has wide application space.
(4) accompanying drawing explanation
Below in conjunction with accompanying drawing, the present invention is further illustrated.
Accompanying drawing 1 is form assembly schematic diagram of the present invention;
(5) detailed description of the invention
Accompanying drawing is a kind of specific embodiment of the present invention.This embodiment comprises the installation of horizontal embedded iron parts and the installation of vertical embedded iron parts, is welded on reinforcing bar and reinforcing cage by horizontal embedded iron parts, prevents the lateral displacement of embedded iron parts; Be welded on reinforcing cage with reinforcing bar clout and determine horizontal embedded iron parts position, prevent the vertical displacement of embedded iron parts; Feature not concordant with surface of wall after having constructed for embedded iron parts, first the numbering of template and the setting of modulus is carried out before embedded iron parts is installed, the position of embedded iron parts is accurately located by template modulus, embedded iron parts is fixed on side wall inner formword by employing screw, makes template and embedded iron parts global displacement in the scope that specification allows.Embedded iron parts is welded to support reinforcing bar, ensures cage of reinforcement, template, embedded iron parts be linked to be an entirety, exempt from the generation of the inaccurate and phenomenon that do not leak outside in embedded iron parts position, thus guarantee the accurate of position relationship between three.
Adopt pipe gallery embedded iron parts construction method of installation of the present invention, the installation steps of horizontal embedded iron parts are:
1, preparation of construction
1) machine operation such as electric welding machine, internal vibration rod;
2) material such as embedded iron parts, template on deck, meets design, code requirement through on-the-spot retrial;
3) technical annotation in construction carried out to construction team and tell somebody what one's real intentions are safely, line correlation training of going forward side by side;
4) determine that embedded iron parts installs the control point of accuracy and foundation of inspecting for acceptance.
2, surveying setting-out
According to designing requirement in the position determining horizontal embedded iron parts, and carry out mark.
3, reinforcing bar binding
Carry out the colligation construction of reinforcing cage according to designing requirement, in process of binding, consider the position of embedded iron parts, avoid occurring occurring conflicting because of position between reinforcing bar with embedded iron parts anchor rib.
4, model sheetinstallat
First the template of embedded iron parts buttress carries out installing and reinforcing before installing by embedded iron parts.Horizontal embedded iron parts buttress is generally cuboid, and height is at about 50cm.Support with double steel frame pipe during installation, first row steel frame pipe position above 10cm at the bottom of embedded iron parts buttress, second row steel frame pipe is 10cm place below pre-buried buttress top.Simultaneously for preventing the global displacement of embedded iron parts buttress, reinforce after model sheetinstallat is complete, reinforcing mode adopts little steel bar end to be welded in skeleton reinforcing steel bar, stops the displacement of template.
5, bearing bar is welded
Survey crew carries out unwrapping wire according to the design altitude of embedded iron parts, position, hangs position and the elevation of bilinear con-trol embedded iron parts.Construction line place elevation should be embedded iron parts and to go to the bottom absolute altitude, and then operating personnel utilizes reinforcing bar clout, welds double bearing bar according to the position of construction line and elevation, bearing bar upper flat consistent with line elevation of constructing.Bearing bar should be welded on bed course, will carry out horizontal welding simultaneously, prevents the vertical of bearing bar and lateral displacement.Because embedded iron parts deadweight is comparatively large, during welding bearing bar, vertical supporting will meet support requirement, and General Requirements 50cm together, should select the reinforcing bar consistent with skeleton reinforcing steel bar diameter as bearing bar.
6, embedded iron parts is installed
Bearing bar has welded elevation and the straight cis degree of rear detection bearing bar.The upper flat elevation of bearing bar is the lower flat elevation (under plate flat) of embedded iron parts after testing, and after straight cis degree meets code requirement, can carry out the installation of embedded iron parts.Manually embedded iron parts is lifted on bearing bar when embedded iron parts is installed, then utilize crowbar mobile embedded iron parts on bearing bar, until after the position of embedded iron parts meets designing requirement, weld embedded iron parts.Embedded iron parts welds with bearing bar, prevents the skew of embedded iron parts.If skeleton reinforcing steel bar is closeer, the embedded bar of portion embedded iron parts may exist with skeleton reinforcing steel bar and conflicts, embedded iron parts will carry out planning before installing in advance, if really cannot dodge, need the skeleton reinforcing steel bar of conflict to be shifted, forbid to cut embedded iron parts embedded bar and skeleton reinforcing steel bar.
7, formwork reinforcement
Be connected with template by steel wire after embedded iron parts has welded, closure should be triangularly arranged.By steel wire bolt on the exhaust opening of embedded iron parts or the embedded bar of embedded iron parts, other end bolt is in template.
8, concreting
Embedded iron parts welds and checked and accepted rear carrying out in time concretely builds work.Will detect concrete slump before concreting, slump general control at 14-16cm, and is controlled well according to code requirement and is concretely built the time, and concrete vibrating adopts quincunx, and concreting bubble of no longer emerging is advisable.Concreting carries out receipts face after vibrating in time.
Adopt pipe gallery embedded iron parts construction method of installation of the present invention, the installation steps of vertical embedded iron parts are:
1, preparation of construction
1) machine operation such as electric welding machine, internal vibration rod;
2) material such as embedded iron parts, template on deck, meets design, code requirement through on-the-spot retrial;
3) the in advance numbering of setting template and modulus carry out mark;
4) technical annotation in construction carried out to construction team and tell somebody what one's real intentions are safely, line correlation training of going forward side by side;
5) determine that embedded iron parts installs the control point of accuracy and foundation of inspecting for acceptance.
2, surveying setting-out
In template, determine the position of embedded iron parts according to designing requirement, and play the line of ink marker and carry out mark.
3, reinforcing bar binding
Carry out the colligation construction of cage of reinforcement according to designing requirement, in process of binding, consider the position of embedded iron parts, avoid occurring occurring conflicting because of position between reinforcing bar with embedded iron parts anchor rib.
4, embedded iron parts is installed
Be installed in template by embedded iron parts according to line of ink marker position, and be screwed firmly, screw model (diameter) is selected according to the weight of embedded iron parts, and diameter is generally not less than selects 10mm.Fixing means is: the edge in advance screw being welded to embedded iron parts, then by screw hole reserved in template, embedded iron parts and template are fixed, screw adopts A309 stainless steel electrode to be welded on the center on embedded iron parts four limits, amounts to welding four screws.Bamboo slab rubber pad nut is adopted outside embedded iron parts template.Increase the number of turnover of template, reduce cost and drop into.
5, template assembly
Numbering according to template carries out the assembled of template, assembles, to avoid embedded iron parts prefabricated deviation during template assembly in strict accordance with the numbering of setting in advance and modulus.
6, embedded iron parts welding
After model sheetinstallat is in place, according to thickness of concrete cover, embedded iron parts is welded with skeleton reinforcing steel bar.
7, formwork reinforcement
After having welded, adjustment skeleton reinforcing steel bar position, and according to the reinforcing designing thickness of wall body, template is carried out in position.After formwork reinforcement completes, the stability of template is tested and concreting.
8, concreting
When reducing in concreting process, reduce vibrating spear touching template.
9, inspect for acceptance
Often complete a procedure, project management department carries out self-inspection.Inspect for acceptance with spirit level and conjunction chi, recording error value, checks embedded iron parts position one by one, guarantees that each embedded iron parts is in place.
Adopt pipe gallery embedded iron parts construction method of installation of the present invention, Specific construction step is as follows:
Horizontal embedded iron parts: preparation of construction → surveying setting-out → reinforcing bar binding → model sheetinstallat → welding bearing bar → embedded iron parts installation → formwork reinforcement → concreting → examination.
Vertical embedded iron parts: preparation of construction → surveying setting-out → reinforcing bar binding → embedded iron parts installation → template assembly → embedded iron parts welding → formwork reinforcement → concreting → stripping → examination.
Adopt pipe gallery embedded iron parts construction method of installation of the present invention, at Jinan City's tourism North Road road and comprehensive ditch engineering one bid section, Jinan City two ring West Road ground level road and environmental construction engineering three bid section, be applied in the first stage of the project of Long Ao North Road, Jinan City, embedded iron parts installation quality is subject to Construction unit and Quality Supervision Station favorable comment.

Claims (5)

1. a pipe gallery embedded iron parts construction method of installation, comprise the installation of horizontal embedded iron parts and the installation of vertical embedded iron parts, it is characterized in that: with reinforcing bar clout horizontal embedded iron parts is welded on bearing bar and determines horizontal embedded iron parts position, first the numbering of template and the setting of modulus is carried out before vertical embedded iron parts is installed, the position of vertical embedded iron parts is accurately located by template modulus, adopt screw to be fixed on side wall inner formword by vertical embedded iron parts, vertical embedded iron parts is welded to skeleton reinforcing steel bar.
2. pipe gallery embedded iron parts construction method of installation according to claim 1, is characterized in that: the installation of horizontal embedded iron parts comprises the following steps:
(1), surveying setting-out: according to designing requirement in the position determining horizontal embedded iron parts, and carry out mark;
(2), reinforcing bar binding: the position considering horizontal embedded iron parts in process of binding;
(3), model sheetinstallat: support with double steel frame pipe during installation;
(4), bearing bar is welded: carry out unwrapping wire according to the design altitude of horizontal embedded iron parts, position, hang position and the elevation of the horizontal embedded iron parts of bilinear con-trol, construction line place elevation is that horizontal embedded iron parts is gone to the bottom absolute altitude, then operating personnel utilizes reinforcing bar clout, double bearing bar is welded according to the construction position of line and elevation, bearing bar upper flat consistent with line elevation of constructing, bearing bar is welded on bed course, will carry out horizontal welding simultaneously;
(5), horizontal embedded iron parts is installed: lift on bearing bar by horizontal embedded iron parts, then utilize crowbar mobile and horizontal embedded iron parts on bearing bar, until after the position of horizontal embedded iron parts meets designing requirement, weld horizontal embedded iron parts;
(6), formwork reinforcement: be connected with template by steel wire after horizontal embedded iron parts has welded, closure should be triangularly arranged, by steel wire bolt on the exhaust opening of horizontal embedded iron parts or the embedded bar of horizontal embedded iron parts, other end bolt is in template;
(7), concreting: will detect concrete slump before concreting, concrete vibrating adopts quincunx, and concreting bubble of no longer emerging is advisable, and concreting carries out receipts face after vibrating in time.
3. pipe gallery embedded iron parts construction method of installation according to claim 1, is characterized in that: the installation of vertical embedded iron parts comprises the following steps:
(1), surveying setting-out: the position determining vertical embedded iron parts according to designing requirement in template, and play the line of ink marker and carry out mark;
(2), reinforcing bar binding: the position considering vertical embedded iron parts in process of binding;
(3), vertical embedded iron parts is installed: be installed in template by vertical embedded iron parts according to line of ink marker position, and be screwed firmly;
(4), template assembly: the numbering according to template carries out the assembled of template, assembles during template assembly in strict accordance with the numbering of setting in advance and modulus;
(5), vertical embedded iron parts welding: according to thickness of concrete cover, vertical embedded iron parts is welded with skeleton reinforcing steel bar;
(6), formwork reinforcement: after having welded, adjust skeleton reinforcing steel bar position, and according to the reinforcing designing thickness of wall body, template is carried out in position, after formwork reinforcement completes, the stability of template is tested and concreting;
(7), concreting: when reducing in concreting process, reduce vibrating spear touching template;
(8), stripping: first fixing screw is turned on before dismounting, then pipe gallery template is removed according to assembled modulus block-by-block in advance;
(9), inspect for acceptance: often complete a procedure, carry out self-inspection, inspect for acceptance with spirit level and conjunction chi, recording error value, checks vertical embedded iron parts position one by one, guarantees that each vertical embedded iron parts is in place.
4. pipe gallery embedded iron parts construction method of installation according to claim 3, it is characterized in that: the method being screwed template is: the edge in advance screw being welded to vertical embedded iron parts, then vertical embedded iron parts and template are fixed by screw hole reserved in template, screw adopts stainless steel electrode to be welded on the center on vertical embedded iron parts four limits.
5. pipe gallery embedded iron parts construction method of installation according to claim 3, is characterized in that: the timely brushing release agent of the template after dismounting, and puts according to assembled order.
CN201310066719.0A 2013-03-04 2013-03-04 Pipe gallery embedded iron parts construction method of installation Active CN103088843B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310066719.0A CN103088843B (en) 2013-03-04 2013-03-04 Pipe gallery embedded iron parts construction method of installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310066719.0A CN103088843B (en) 2013-03-04 2013-03-04 Pipe gallery embedded iron parts construction method of installation

Publications (2)

Publication Number Publication Date
CN103088843A CN103088843A (en) 2013-05-08
CN103088843B true CN103088843B (en) 2016-03-30

Family

ID=48201934

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310066719.0A Active CN103088843B (en) 2013-03-04 2013-03-04 Pipe gallery embedded iron parts construction method of installation

Country Status (1)

Country Link
CN (1) CN103088843B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104517550A (en) * 2013-09-30 2015-04-15 中铁六局集团有限公司 Subway passenger information system construction method
CN107503441B (en) * 2017-08-30 2019-09-10 五冶集团上海有限公司 The installation method of embedded iron parts
CN109487823A (en) * 2018-12-12 2019-03-19 中国十七冶集团有限公司 The accurate installation method of groove type embedded part in city integrated piping lane punching block system
CN111691458B (en) * 2020-06-22 2021-09-28 福建省华策建设集团有限公司 Construction method of comprehensive pipe rack support
CN112431219A (en) * 2020-11-24 2021-03-02 上海二十冶建设有限公司 Quick installation method for vertical continuous casting machine vertical surface foundation embedded iron part
CN114855779A (en) * 2022-06-20 2022-08-05 中国十九冶集团有限公司 Pile foundation reinforcement cage preparation method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85108069A (en) * 1984-11-08 1986-05-10 希斯莫国际公司 The improvement of prefabricated modules, and the application in construction industry
EP0585959A1 (en) * 1989-01-20 1994-03-09 Marcel Matière Method for realising an entrenched conduit
JP2000073339A (en) * 1998-06-15 2000-03-07 Natl Res Inst Of Agricultural Engineering Inspection gallery in fill-type dam and construction method of inspection gallery in fill-type dam
CN101649622A (en) * 2008-08-15 2010-02-17 天津万联管道工程有限公司 Method for manufacturing common ditch pipe gallery with ultra-large caliber in field
CN102535404A (en) * 2012-01-11 2012-07-04 中国建筑第二工程局有限公司 Construction device and construction method for steep segment of circulating pipe ditch

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85108069A (en) * 1984-11-08 1986-05-10 希斯莫国际公司 The improvement of prefabricated modules, and the application in construction industry
EP0585959A1 (en) * 1989-01-20 1994-03-09 Marcel Matière Method for realising an entrenched conduit
JP2000073339A (en) * 1998-06-15 2000-03-07 Natl Res Inst Of Agricultural Engineering Inspection gallery in fill-type dam and construction method of inspection gallery in fill-type dam
CN101649622A (en) * 2008-08-15 2010-02-17 天津万联管道工程有限公司 Method for manufacturing common ditch pipe gallery with ultra-large caliber in field
CN102535404A (en) * 2012-01-11 2012-07-04 中国建筑第二工程局有限公司 Construction device and construction method for steep segment of circulating pipe ditch

Also Published As

Publication number Publication date
CN103088843A (en) 2013-05-08

Similar Documents

Publication Publication Date Title
CN103088843B (en) Pipe gallery embedded iron parts construction method of installation
CN104141301B (en) Inverse construction method and the structure of making steel pipe column are installed revolving to dig in stake holes
CN102102444B (en) Assembling and positioning construction method of large steel casting members
CN207048069U (en) A kind of pipe gallery segmental timbering
CN101736698B (en) Accurate positioning method for cable-stayed bridge pylon cable guide pipe
CN104120656B (en) Method for automatically controlling bridge high pier construction perpendicularity
CN203891009U (en) Structure for installing reverse steel pipe column in rotary excavating pile hole
CN203891058U (en) Built-in foundation bolt positioning tool for fixed type tower crane foundation
CN104141318A (en) Installation and construction method of column base of large-diameter steel pipe column
CN204570711U (en) A kind of assembled steel reinforced concrete cofferdam
CN103669314B (en) High-efficiency rack mounting method and auxiliary adjustment device of gear rack climbing type vertical ship lift
CN103233482B (en) Cable trench pre-embedded bolt construction method of installation
CN204001428U (en) A kind of Large-diameter Steel tubing string suspension column is installed pre-buried location structure and suspension column structure thereof
CN201560398U (en) Inner steel mould for accurately positioning tower column cable sleeves of cable-stayed bridge
CN104074364A (en) Steel casting funnel-shaped structure pre-assembling positioning construction method
CN103523169A (en) Double-shell ship building method
CN103806426B (en) Earth pressure gauge adjustable position secure mounting arrangements
CN103938638A (en) Buoy type deepwater single-wall steel cofferdam construction method
CN103669634A (en) Construction method and structure with damping wall poured later
CN202866304U (en) Reverse-building-method steel pipe column bottom locating device
CN204326104U (en) A kind of well device of riding for jacking construction
CN105040992B (en) Reverse inverted-insertion type construction method for structural steel columns
CN204001429U (en) A kind of Large-diameter Steel tubing string suspension column structure and suspension column absolute altitude adjustment fixing structure thereof
CN103470036A (en) Overhanging structure construction method
CN102828533A (en) Vertical pressure resistance static load test pile head advanced processing node of cast-in-place pile and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Zhang Lianke

Inventor after: Shao Huaifeng

Inventor after: Wang Shuwei

Inventor after: Gao Rui

Inventor after: Cheng Guibao

Inventor before: Zhang Lianke

Inventor before: Shao Huaifeng

Inventor before: Wang Shuwei

Inventor before: Gao Rui

Inventor before: Cheng Guibao

C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Gao Rui

Inventor after: Shao Huaifeng

Inventor after: Zhang Lianke

Inventor after: Wang Shuwei

Inventor after: Sun Lili

Inventor before: Zhang Lianke

Inventor before: Shao Huaifeng

Inventor before: Wang Shuwei

Inventor before: Gao Rui

Inventor before: Cheng Guibao

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: ZHANG LIANKE SHAO HUAIFENG WANG SHUWEI GAO RUI CHENG GUIBAO TO: GAO RUI SHAO HUAIFENG ZHANG LIANKE WANG SHUWEI SUN LILI

C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Chen Bin

Inventor after: Shao Huaifeng

Inventor after: Wang Shuwei

Inventor after: Gao Rui

Inventor after: Sun Lili

Inventor after: Xu Ru

Inventor after: Wang Zuolei

Inventor after: Sun Jie

Inventor before: Gao Rui

Inventor before: Shao Huaifeng

Inventor before: Zhang Lianke

Inventor before: Wang Shuwei

Inventor before: Sun Lili

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: GAO RUI SHAO HUAIFENG ZHANG LIANKE WANG SHUWEI SUN LILI TO: CHEN BIN SHAO HUAIFENG WANG SHUWEI GAO RUI SUN LILI XU RU WANG ZUOLEI SUN JIE

CB03 Change of inventor or designer information

Inventor after: Chen Bin

Inventor after: Shao Huaifeng

Inventor after: Wang Shuwei

Inventor after: Gao Rui

Inventor after: Sun Lili

Inventor after: Xu Ru

Inventor after: Wang Zuolei

Inventor after: Sun Jie

Inventor before: Chen Bin

Inventor before: Shao Huaifeng

Inventor before: Wang Shuwei

Inventor before: Gao Rui

Inventor before: Sun Lili

Inventor before: Xu Ru

Inventor before: Wang Zuolei

Inventor before: Sun Jie

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant