CN103590603B - Large span multi-curvature shell structure of reinforced concrete method - Google Patents

Large span multi-curvature shell structure of reinforced concrete method Download PDF

Info

Publication number
CN103590603B
CN103590603B CN201310564950.2A CN201310564950A CN103590603B CN 103590603 B CN103590603 B CN 103590603B CN 201310564950 A CN201310564950 A CN 201310564950A CN 103590603 B CN103590603 B CN 103590603B
Authority
CN
China
Prior art keywords
formwork
curvature
concrete
template
shell
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310564950.2A
Other languages
Chinese (zh)
Other versions
CN103590603A (en
Inventor
张谦
韩立江
田利坤
马泽琛
卢晓佳
季鹏
郑小川
李军
李�瑞
徐小烈
候丽霞
范贵元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Original Assignee
Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd filed Critical Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority to CN201310564950.2A priority Critical patent/CN103590603B/en
Publication of CN103590603A publication Critical patent/CN103590603A/en
Application granted granted Critical
Publication of CN103590603B publication Critical patent/CN103590603B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

一种大跨度多曲率薄壳钢筋混凝土结构施工方法,该施工具体步骤包括绘制图纸、制作构建玻璃钢、施工场地清理、根据既定的曲率与等高线数据进行放线定位、搭设支撑架、搭设薄壳结构支撑架、制作薄壳结构模板、绑扎壳体钢筋、浇注混凝土和拆除模板支撑架等,本发明采用等高线法配合控制线对模板进行分解确定构件玻璃钢的规格,实现了快速搭设,节约了施工时间;壳体靠近底部部分采用双侧玻璃钢模板,并用间隔的钢丝网进行封模,保证了竖向承载力的同时,解决了大坡度混凝土施工的难题,有效的解决了结构对架体的斜向推力;此外,本发明中采用混凝土分段对称浇注,使支撑体系受力均衡,解决了由于壳体面积大、坡度陡带来的施工困难。

A construction method for a large-span multi-curvature thin-shell reinforced concrete structure. The specific construction steps include drawing drawings, making and constructing glass fiber reinforced plastics, cleaning the construction site, performing setting-out positioning according to predetermined curvature and contour line data, erecting support frames, and erecting thin-shell reinforced concrete structures. Shell structure support frame, making thin shell structure formwork, binding shell steel bars, pouring concrete and removing formwork support frame, etc., the present invention adopts the contour line method and control line to decompose the formwork to determine the specifications of the component glass fiber reinforced plastics, and realizes rapid erection. The construction time is saved; the part near the bottom of the shell adopts double-sided glass fiber reinforced plastic formwork, and the mold is sealed with spaced steel wire mesh, which ensures the vertical bearing capacity and solves the problem of large-slope concrete construction, effectively solving the problem of structural alignment The oblique thrust of the body; in addition, in the present invention, the concrete is poured symmetrically in sections to balance the force on the support system and solve the construction difficulties caused by the large shell area and steep slope.

Description

大跨度多曲率薄壳钢筋混凝土结构施工方法Construction method of long-span multi-curvature thin-shell reinforced concrete structure

技术领域 technical field

本发明涉及一种大跨度多曲率的薄壳结构的钢筋混凝土施工方法,特别涉及一种蛋壳形的钢筋混凝土结构的施工方法。 The invention relates to a reinforced concrete construction method of a large-span multi-curvature thin shell structure, in particular to a construction method of an eggshell-shaped reinforced concrete structure.

背景技术 Background technique

随着我国经济实力的增强,人们对于建筑的造型、空间提出了越来越高的要求。建筑结构理论的不断发展和大型工程实践的积累使混凝土结构形式由平面规则、空间平直向空间异型、造型美观、高净空发展。对于空间异型结构,选用合理、安全模板支撑设计方式和先进的施工工艺是保证结构质量效果的关键。大跨度、多曲率、形体复杂的空间结构即美观又大气,越来越受到投资者们的青睐,但目前,尽管高层建筑的施工工艺已达到了比较高的水平,但对于这种大跨度、多曲率、形体复杂的空间结构,特别是现浇钢筋混凝土结构,现有技术的实践还比较少,与之相配套的施工方法、工艺也很不完善、成熟,目前多选用玻璃钢作为多曲率结构的模板材料,但由于曲率变化多,支撑架搭设过程中立杆的位置定位及高度控制都面临难题,由于跨度比较大,一般玻璃钢模板的承重能力达不到要求,壳体边缘曲率较大,混凝土浇注时易出现混凝土下滑问题,因此,目前亟需一种成本合理、操作简单、可行性高的大跨度多曲率薄壳钢筋混凝土结构施工方法。 With the strengthening of my country's economic strength, people have put forward higher and higher requirements for the shape and space of buildings. The continuous development of architectural structure theory and the accumulation of large-scale engineering practice have led to the development of concrete structure forms from regular planes and straight spaces to special-shaped spaces, beautiful shapes, and high headroom. For space-shaped structures, choosing a reasonable and safe formwork support design method and advanced construction technology is the key to ensuring the quality and effect of the structure. Large-span, multi-curvature, and complex spatial structures are beautiful and majestic, and are increasingly favored by investors. However, at present, although the construction technology of high-rise buildings has reached a relatively high level, for such large-span, For space structures with multiple curvatures and complex shapes, especially cast-in-place reinforced concrete structures, there is still relatively little practice in the prior art, and the corresponding construction methods and processes are also very imperfect and mature. At present, glass fiber reinforced plastics are mostly used as multi-curvature structures. However, due to the many changes in curvature, the position positioning and height control of the vertical poles during the erection of the support frame are facing difficulties. Due to the relatively large span, the load-bearing capacity of the general FRP formwork cannot meet the requirements, and the curvature of the shell edge is large. Concrete Concrete slides easily during pouring. Therefore, there is an urgent need for a construction method for large-span multi-curvature thin-shell reinforced concrete structures with reasonable cost, simple operation, and high feasibility.

发明内容 Contents of the invention

本发明目的在于提供一种大跨度多曲率薄壳钢筋混凝土结构施工方法,解决现有技术中对于大跨度多曲率薄壳钢筋混凝土结构施工中的难题,如构建玻璃钢规格确定问题、由于曲率变化多支撑架搭设过程中立杆的位置定位及高度控制都面临难题、由于跨度较大一般玻璃钢模板的承重能力达不到要求的问题以及由壳体边缘曲率较大带来的混凝土浇注时易出现混凝土下滑问题等。 The purpose of the present invention is to provide a construction method for large-span multi-curvature thin-shell reinforced concrete structures, which solves the difficult problems in the construction of large-span multi-curvature thin-shell reinforced concrete structures in the prior art, such as the problem of determining the specifications of glass fiber reinforced plastics, and the large curvature changes. In the process of erecting the support frame, the position positioning and height control of the vertical pole are facing difficulties. Due to the large span, the load-bearing capacity of the general FRP formwork cannot meet the requirements, and the concrete is prone to slide when pouring the concrete due to the large curvature of the shell edge. question etc.

为实现上述目的,本发明采用的具体实施方案是: To achieve the above object, the specific implementation scheme adopted by the present invention is:

一种大跨度多曲率薄壳钢筋混凝土结构施工方法,其特征在于: A construction method for a large-span multi-curvature thin-shell reinforced concrete structure, characterized in that:

其施工具体步骤包括: Its construction specific steps include:

步骤一、绘制CAD施工图纸,并通过犀牛软件绘制成3D模型图,同时绘制满堂支撑架立杆平面布置图和壳体等高线投影示意图; Step 1. Draw CAD construction drawings, and draw 3D model drawings through rhino software, and at the same time draw the floor plan layout of the support frame and the contour projection diagram of the shell;

步骤二、制作特定曲率的构件玻璃钢:在所述3D模型图上找到待施工结构的长向中心轴线,以长向中心轴线为基线向两侧做一系列间距1~3米的平行线作为控制线,将相邻两条控制线和相邻两条等高线围成部分的规格和曲率数据作为分解后的玻璃钢的规格和曲率数据,模板厂家根据已得的数据制作构件玻璃钢; Step 2. Make the component glass fiber reinforced plastics with specific curvature: Find the longitudinal central axis of the structure to be constructed on the 3D model diagram, and use the longitudinal central axis as the baseline to make a series of parallel lines with an interval of 1 to 3 meters on both sides as a control Line, the specifications and curvature data of the part surrounded by two adjacent control lines and two adjacent contour lines are used as the specifications and curvature data of the decomposed FRP, and the formwork manufacturer makes the component FRP according to the obtained data;

步骤三、施工场地清理; Step 3: Clean up the construction site;

步骤四、放线定位:根据满堂支撑架立杆平面布置图和壳体等高线投影示意图对施工现场进行测量并放线定位,标记等高线及立杆的位置; Step 4, setting out positioning: measure the construction site and set out the positioning according to the plan layout of the vertical pole of the full house support frame and the contour line projection diagram of the shell, and mark the position of the contour line and the vertical pole;

步骤五、搭设满堂支撑架:在拟建薄壳结构的下方搭设满堂支撑架,采用扣件将立杆和横杆连接成架体,支撑架的立杆的顶部连接U托,U托之上连接与薄壳曲率相同的钢管龙骨,所述U托与钢管龙骨之间加木楔塞紧钢管与U托之间的缝隙; Step 5. Set up the full support frame: set up the full support frame under the proposed thin shell structure, use fasteners to connect the vertical bar and the horizontal bar to form a frame body, the top of the vertical bar of the support frame is connected to the U bracket, and the U bracket is on top Connect the steel pipe keel with the same curvature as the thin shell, and add a wooden wedge between the U bracket and the steel pipe keel to plug the gap between the steel pipe and the U bracket;

步骤六、制作薄壳结构模板:首先标高为1~2米高的模板分界线,模板分界线以下的部分采用双侧玻璃钢模板,即同时设立底模板和顶模板;模板分界线以上的部分采用单侧玻璃钢模板,即只有底模板;薄壳结构的双侧玻璃钢模板的底模板和顶模板之间采用对拉止水螺栓连接; Step 6. Make the thin-shell structure formwork: first, the formwork boundary line with an elevation of 1 to 2 meters is used. The part below the formwork boundary line adopts double-sided FRP formwork, that is, the bottom formwork and the top formwork are set up at the same time; the part above the formwork boundary line adopts Single-sided FRP formwork, that is, only the bottom formwork; the bottom formwork and top formwork of the double-sided FRP formwork of the thin shell structure are connected by anti-sealing bolts;

步骤七、模板安装完成后直接在模板中间绑扎钢筋,包括根据已定曲率弯折钢筋、绑扎壳体暗梁钢筋和绑扎壳体板钢筋,在壳体钢筋之间间隔设立拦截钢丝网,混凝土浇注时拦截混凝土下落; Step 7. After the formwork is installed, directly bind the steel bars in the middle of the formwork, including bending the steel bars according to the predetermined curvature, binding the steel bars of the hidden beams of the shell and binding the steel bars of the shell plates, and setting up intercepting steel wire meshes at intervals between the shell steel bars, and pouring concrete When intercepting the concrete drop;

步骤八、浇注混凝土: 采用连续分层浇注方法,每层浇注厚度控制在450mm以内,上下层的间隔时间不要超过混凝土的初凝时间,在混凝土浇注前先在底部均匀浇注50mm厚与壳体混凝土砂浆成份相同的水泥砂浆;在浇注底部双侧玻璃钢模板部分时,采用两侧对称下料方式;最后进行人工振捣并压光抹面,壳体成型; Step 8. Concrete pouring: Use continuous layer pouring method, control the pouring thickness of each layer within 450mm, the interval between the upper and lower layers should not exceed the initial setting time of the concrete, and pour 50mm thick shell concrete evenly at the bottom before pouring concrete Cement mortar with the same mortar composition; when pouring the double-sided glass fiber reinforced plastic formwork part at the bottom, adopt the symmetrical cutting method on both sides; finally, manually vibrate and calender the surface, and the shell is formed;

步骤九、对混凝土浇注成的壳体进行养护; Step 9, maintaining the shell formed by pouring concrete;

步骤十、拆除薄壳结构支撑架。 Step 10. Remove the support frame of the thin shell structure.

所述步骤五中搭设薄壳结构支撑架的具体操作为: The specific operation of setting up the thin shell structure support frame in the step 5 is:

步骤1、在满堂支撑架立杆平面布置图上标记皮数杆布置位点; Step 1. Mark the location of the number rod layout on the floor plan of the vertical rod of the support frame in the whole hall;

步骤2、根据皮数杆布置图布置皮数杆; Step 2. Arrange the number rods according to the layout diagram of the number rods;

步骤3、通过相邻皮数杆拉线方式确定中间立杆的标高,对立杆钢管进行锯切,使其高度符合要求; Step 3. Determine the elevation of the middle vertical pole by means of pulling wires of adjacent scale rods, and saw the steel pipe of the vertical pole to make the height meet the requirements;

步骤4、由左右两侧往中间逐步搭设立杆; Step 4. Set up poles gradually from the left and right sides to the middle;

步骤5、在立杆顶部安装U托; Step 5. Install the U bracket on the top of the pole;

步骤6、对立杆高度进行检验并校准; Step 6. Check and calibrate the height of the pole;

步骤7、搭设横杆; Step 7, set up the cross bar;

步骤8、将钢管沿薄壳结构的曲率进行弯曲,制成钢管龙骨,同时制作相应的木楔; Step 8, bending the steel pipe along the curvature of the thin shell structure to make a steel pipe keel, and making corresponding wooden wedges at the same time;

步骤9、将钢管龙骨放在架顶,用铁丝与U托绑扎牢固,并与横杆7用铁丝绑扎连结, U托与钢管龙骨之间塞木楔,支撑架完成。 Step 9. Put the steel pipe keel on the top of the frame, tie it firmly with the U bracket with iron wire, and tie it with the crossbar 7 with iron wire, plug the wooden wedge between the U bracket and the steel pipe keel, and the support frame is completed.

其中,所述步骤3中皮数杆不承重,只进行立杆的标高控制,随搭随拆,操作中以每4~8列立杆为一组,当第一组的立杆搭设完成后,拆除用于控制标高的皮数杆,然后开始布置下一组皮数杆,搭设下一组立杆。 Wherein, in the step 3, the number pole is not load-bearing, only the elevation control of the pole is carried out, and it is dismantled as it is erected. During the operation, every 4 to 8 columns of poles are used as a group. When the erection of the first group of poles is completed , remove the number rod used to control the elevation, and then start to arrange the next group of number rods, and set up the next group of vertical poles.

在大跨度多曲率薄壳钢筋混凝土结构施工方法操作步骤中,所述步骤六中制作薄壳结构模板的具体操作步骤为: In the operation steps of the construction method of the large-span multi-curvature thin-shell reinforced concrete structure, the specific operation steps for making the thin-shell structure formwork in the step six are:

步骤1、对所有不同曲率的待安装模板依据待安装位置进行编号; Step 1. Number all the templates to be installed with different curvatures according to the positions to be installed;

步骤2、在壳体高度为1~2米的地方标注模板分界线,即标注一条特定高度的等高线为模板分界线; Step 2. Mark the template boundary line at the place where the height of the shell is 1-2 meters, that is, mark a contour line of a specific height as the template boundary line;

步骤3、对整个壳体吊装玻璃钢底模板:底模从顶部向两侧根据编号进行安装,必须保证拼缝严密,模板拼缝处粘贴海绵条,模板之间的拼缝用专用材料涂抹密封,以防止漏浆; Step 3. Hoist the glass fiber reinforced plastic bottom formwork for the entire shell: install the bottom formwork from the top to both sides according to the number. It is necessary to ensure that the joints are tight. The joints of the formwork are pasted with sponge strips. The joints between the formworks are sealed with special materials. To prevent slurry leakage;

步骤4、对模板分界线以下部分制备壳体玻璃钢顶模板:在模板分界线以下部分,在已完成的单侧玻璃钢外侧面再加设一层玻璃钢,成为双侧玻璃钢模板,双侧玻璃钢模板的底模板和顶模板之间采用对拉止水螺栓连接; Step 4. Prepare the shell glass fiber reinforced plastic top formwork for the part below the formwork boundary line: in the part below the formwork boundary line, add a layer of glass fiber reinforced plastic on the outer surface of the completed single-side glass fiber reinforced plastic to become a double-sided glass fiber reinforced plastic formwork, and the double-sided glass fiber reinforced plastic formwork The bottom formwork and the top formwork are connected by pull water stop bolts;

步骤5、对模板进行校正:模板施工完毕后必须进行复核工作,达到要求方可浇注混凝土。 Step 5. Calibrate the formwork: After the formwork construction is completed, the review work must be carried out, and the concrete can only be poured when the requirements are met.

作为大跨度多曲率薄壳钢筋混凝土结构施工方法操作步骤中的优选方案,所述步骤六中对拉止水螺栓的两侧加焊钢筋头作为顶撑。 As an optimal scheme in the operation steps of the construction method of the large-span multi-curvature thin-shell reinforced concrete structure, in the sixth step, welded steel bar heads are added to both sides of the pulling water-stop bolts as top supports.

作为大跨度多曲率薄壳钢筋混凝土结构施工方法操作步骤中的优选方案,所述步骤六中对拉止水螺栓的两端穿有防浆作用的圆台形的胶塞,两个胶塞的净间距为壳厚减去两倍胶塞的厚度,待混凝土浇注完后取出胶塞,墙上将留下弧形凹坑,凹坑用标号高一级的防水砂浆填塞。 As an optimal scheme in the operation steps of the construction method of the large-span multi-curvature thin-shell reinforced concrete structure, in the sixth step, the two ends of the anti-slip bolts are worn with frustum-shaped rubber plugs with anti-slurry effect, and the net of the two rubber plugs is The spacing is the thickness of the shell minus twice the thickness of the rubber plug. After the concrete is poured, the rubber plug will be removed, and an arc-shaped pit will be left on the wall. The pit will be filled with waterproof mortar with a higher grade.

作为大跨度多曲率薄壳钢筋混凝土结构施工方法操作步骤中的优选方案,在步骤六中所述底模板的前后向的边缘设置翻边,翻边高度同壳体的厚度相同。 As an optimal solution in the operation steps of the construction method of the large-span multi-curvature thin-shell reinforced concrete structure, in step 6, the front and rear edges of the bottom formwork are provided with flanging, and the height of the flanging is the same as the thickness of the shell.

与现有技术相比,本发明的优势在于:本发明采用等高线法配合控制线对模板进行分解确定构件玻璃钢的规格,同时快速实现支撑架中立杆位置与高度的统一从而进行快速搭设,节约了施工时间;在壳体靠近底部部分采用双侧封闭式模板,保证了竖向承载力;在钢筋捆绑时用间隔的钢丝网进行封模,解决了大坡度混凝土施工的难题,有效的解决了结构对架体的斜向推力,很好的解决了现有技术施工中的冷缝问题;此外,本发明中采用混凝土分段对称浇注,使支撑体系受力均衡,解决了由于壳体面积大、坡度陡带来的施工困难。 Compared with the prior art, the advantage of the present invention is that: the present invention uses the contour line method with the control line to decompose the formwork to determine the specifications of the component glass fiber reinforced plastics, and at the same time quickly realizes the unification of the position and height of the vertical pole in the support frame so as to perform rapid erection. The construction time is saved; the double-sided closed formwork is used near the bottom of the shell to ensure the vertical bearing capacity; the spaced steel wire mesh is used to seal the formwork when the steel bars are bound, which solves the problem of large-slope concrete construction and effectively solves the problem. The oblique thrust of the structure on the frame is solved, and the problem of cold joints in the construction of the prior art is well solved; in addition, in the present invention, the concrete is poured symmetrically in sections, so that the force of the support system is balanced, and it solves the problem caused by the area of the shell. Construction difficulties caused by large and steep slopes.

附图说明 Description of drawings

图1是本发明大跨度多曲率薄壳钢筋混凝土结构施工方法的施工流程图; Fig. 1 is the construction flowchart of the large-span multi-curvature thin-shell reinforced concrete structure construction method of the present invention;

图2是本发明实施例蛋壳形钢筋混凝土结构施工中的立杆和等高线布置示意图; Fig. 2 is a schematic diagram of vertical poles and contour lines in the construction of an eggshell-shaped reinforced concrete structure according to an embodiment of the present invention;

图3是本发明实施例蛋壳形的钢筋混凝土结构施工中模板结构示意图; Fig. 3 is the schematic diagram of formwork structure in the construction of eggshell-shaped reinforced concrete structure of the embodiment of the present invention;

图4是本发明实施例蛋壳形的钢筋混凝土结构的结构示意图。 Fig. 4 is a structural schematic diagram of an eggshell-shaped reinforced concrete structure according to an embodiment of the present invention.

附图标记: 1-双侧玻璃钢模板、2-对拉止水螺栓、3-止水片、4-钢管龙骨、5-木楔、6-U托、7-横杆、8-立杆、9-壳体、10-模板分界线、11-等高线、12-单侧玻璃钢模板、13-底部筋、14-顶部筋、15-底模板、16-顶模板、17-拦截钢丝网。 Reference signs: 1-double-sided glass fiber reinforced plastic formwork, 2-pull water stop bolts, 3-water stop sheet, 4-steel pipe keel, 5-wooden wedge, 6-U bracket, 7-horizontal bar, 8-vertical bar, 9-shell, 10-formwork boundary, 11-contour line, 12-one-sided FRP formwork, 13-bottom reinforcement, 14-top reinforcement, 15-bottom formwork, 16-top formwork, 17-interception wire mesh.

具体实施方式 Detailed ways

本发明实施例所涉及蛋壳形的钢筋混凝土结构为大门的外饰结构,该蛋壳形外饰结构的四围均接地,前后侧开有对应的拱形门洞,本蛋壳形的钢筋混凝土结构按照合理使用年限50年进行设计,建筑结构的安全等级为二级,抗震设防烈度为8度,如图4所示,本发明蛋壳形的钢筋混凝土结构的结构示意图的壳顶标高为4.45m,壳体跨度达42m,比较大,结构表面曲率变化繁多且不规则,使得模板设计与施工存在较大困难。 The eggshell-shaped reinforced concrete structure involved in the embodiment of the present invention is the exterior decoration structure of the gate. Design according to the reasonable service life of 50 years, the safety grade of the building structure is two grades, and the seismic fortification intensity is 8 degrees, as shown in Figure 4, the shell top elevation of the structure schematic diagram of the eggshell-shaped reinforced concrete structure of the present invention is 4.45m , the shell has a span of 42m, which is relatively large, and the surface curvature of the structure varies widely and irregularly, which makes the design and construction of the formwork difficult.

图1是本发明大跨度多曲率薄壳钢筋混凝土结构施工方法的施工流程图,具体施工方法如下: Fig. 1 is the construction flowchart of the large-span multi-curvature thin-shell reinforced concrete structure construction method of the present invention, and concrete construction method is as follows:

1 绘制施工图纸 1 Draw construction drawings

通过犀牛软件绘制3D模型图,同时绘制满堂支撑架立杆8平面布置图和壳体等高线投影示意图; Draw the 3D model diagram through the Rhino software, and at the same time draw the floor plan of the support frame pole 8 and the schematic diagram of the contour projection of the shell;

2 制作特定曲率的构件玻璃钢 2 Make the component FRP with specific curvature

具体步骤如下: Specific steps are as follows:

1)找出结构长向中心轴线和等高线; 1) Find out the longitudinal central axis and contour line of the structure;

2)以中心轴线为基线向两侧间距2m做平行线,作为控制线; 2) Take the central axis as the baseline and make parallel lines with a distance of 2m to both sides as the control line;

3)以控制线为基准对结构模型做垂直剖切面,剖切面与结构相交的两条弧线即为结构的底线与顶线; 3) Take the control line as the benchmark to make a vertical cut plane on the structural model, and the two arcs where the cut plane intersects with the structure are the bottom line and the top line of the structure;

4)两条相邻控制线和两条相邻等高线所夹区域即为分解的模板模型,四线的交点数据即为模板的四个角的数据; 4) The area between two adjacent control lines and two adjacent contour lines is the decomposed template model, and the intersection data of the four lines is the data of the four corners of the template;

5)根据等高线和控制线的特性可以确定每块模板的具体数据。 5) According to the characteristics of contour lines and control lines, the specific data of each template can be determined.

6)根据已得的数据,模板厂家制作出定型玻璃钢模板 6) According to the obtained data, the formwork manufacturer produces the finalized FRP formwork

3 施工场地清理 3 Construction site cleanup

在施工前,要把欲搭设支撑架的地面清理干净,应保证支撑架垫板下平整以使其受力均匀。 Before construction, the ground where the support frame is to be erected should be cleaned up, and the underplate of the support frame should be ensured to be evenly stressed.

4 根据既定的曲率与等高线11数据并放线定位 4 According to the established curvature and contour line 11 data and lay out the positioning

图2是本发明实施例蛋壳形的钢筋混凝土结构施工方法中的立杆和等高线布置示意图;图3是本发明实施例蛋壳形的钢筋混凝土结构施工方法中的模板的结构示意图;本实施例中在工程前期已经通过计算机模型施工模拟技术,获得曲率与等高线的具体数据并两者相结合取得模板的设计数值,施工中首先绘制满堂支撑架立杆8平面布置图和等高线平面示意图,据图对施工现场进行测量并放线定位,标记等高线11及立杆8的位置。 Fig. 2 is a schematic diagram of vertical rod and contour layout in the eggshell-shaped reinforced concrete structure construction method of the embodiment of the present invention; Fig. 3 is a structural schematic diagram of the formwork in the eggshell-shaped reinforced concrete structure construction method of the embodiment of the present invention; In this embodiment, the computer model construction simulation technology has been used in the early stage of the project to obtain the specific data of the curvature and the contour line and combine the two to obtain the design value of the formwork. Schematic diagram of the plane of the high line, measure the construction site according to the diagram, set out the line and position, mark the position of the contour line 11 and the pole 8.

5 搭设支撑架 5 Set up the support frame

搭设支撑架:在地下室顶板上搭设防护操作架,操作架沿大门周围设置,立杆8纵距1500mm,排距1000mm,步距1200mm,加设安全兜网、密目安全网和踢脚板。防护栏杆采用三道栏杆形式,扫地杆距作业面高度50mm,中道栏杆离地500mm,上道栏杆离地1500,高度超出操作面不小于1500mm。 Set up a support frame: set up a protective operating frame on the roof of the basement, and the operating frame is set up around the gate. The vertical distance of the vertical poles is 1500mm, the row distance is 1000mm, and the step distance is 1200mm. Safety nets, dense mesh safety nets and skirting boards are added. The protective railing adopts the form of three railings. The sweeping pole is 50mm from the working surface, the middle railing is 500mm from the ground, and the upper railing is 1500 from the ground. The height exceeds the operating surface by no less than 1500mm.

6 搭设薄壳结构支撑架 6 Set up the support frame of the thin shell structure

支撑架的技术参数:支撑架采用扣件式钢管支撑架体系,立杆8纵横间距均应不大于950mm,步距为1200mm,横杆第一道离地300mm,所有支撑顶部采用U托6,钢管龙骨4在U托6之上,两者中间有木楔塞紧,所有立杆8底部可采用50×100mm的短木方作垫木,长度不小于400mm,垫木统一为与钢管龙骨4同向。顶部支撑点到最上一道横杆7的间距不大于300mm。支撑架的横杆应顶紧在后续安装的两侧模板上,以防止水平位移。 The technical parameters of the support frame: the support frame adopts the fastener type steel pipe support frame system, the vertical and horizontal spacing of the vertical poles 8 should not be greater than 950mm, the step distance is 1200mm, the first horizontal bar is 300mm from the ground, and all support tops use U brackets 6, The steel pipe keel 4 is on the U bracket 6, and there is a wooden wedge between the two. The bottom of all the vertical poles 8 can be used as a short wooden square of 50×100mm as a skid, and the length is not less than 400mm. The skid is unified with the steel pipe keel 4 In the same direction. The spacing from the top support point to the last cross bar 7 is no more than 300mm. The crossbar of the support frame should be pressed tightly against the templates on both sides of the subsequent installation to prevent horizontal displacement.

支撑架的具体搭设步骤:在满堂支撑架立杆平面布置图上标记皮数杆布置位点→通过相邻皮数杆拉线方式确定中间立杆8的标高,对立杆钢管进行锯切,使其高度符合要求→由左右两侧往中间逐步搭设立杆8→在立杆8顶部设置U托6→对立杆8高度进行检验并校准→搭设横杆7→将钢管沿薄壳结构的曲率进行弯曲,制成钢管龙骨4,同时制作相应的木楔5→安装沿钢管龙骨4用铁丝与U托绑扎牢固,并与横杆7用铁丝绑扎连结, U托与钢管龙骨4之间塞木楔5,支撑架完成。 The specific erection steps of the support frame: mark the arrangement position of the vertical pole on the floor plan of the support frame in the whole hall → determine the elevation of the middle pole 8 through the drawing of the adjacent vertical pole, and saw the steel pipe of the vertical pole to make it The height meets the requirements→set up the vertical pole 8 step by step from the left and right sides to the middle→set the U bracket 6 on the top of the vertical pole 8→inspect and calibrate the height of the vertical pole 8→set up the cross bar 7→bend the steel pipe along the curvature of the thin shell structure , make the steel pipe keel 4, and make the corresponding wooden wedge 5 at the same time → install along the steel pipe keel 4 and tie it firmly with the U bracket with iron wire, and tie it with the cross bar 7 with iron wire, and plug the wooden wedge 5 between the U bracket and the steel pipe keel 4 , the support frame is completed.

大门结构跨度较大,且为不规则蛋壳型壳体9,结构表面曲率变化繁多且不规则,因此大门的定位测量放线工作是保证整个工程施工质量的重中之重;大门等高线11投影线属于不规则弧线,测量员只能逐点进行放线,再进行连线,大门壳体结构跨度达42米,需要测量放线的等高线11投影点较多,工作量极大,需大量测量人员进行配合作业;测量员需要在结构顶板上放出模板支撑体系的平面布置网,所有支撑架立杆8均需在结构顶板进行定位标记,工作量较大,需要大量测量人员配合作业;架子工根据横杆7步距搭设横杆7,立杆8搭设至设计要求的高度范围时,通过相邻皮数杆拉线控制,在立杆8顶端套一可调U托6,并调整至设计标高;支撑架由大门左右两侧往中间搭设,皮数杆不承重,应随立杆8标高控制随搭随拆;以每五列立杆8为一组,当第一组的五列立杆8搭设至设计标高时,拆除用于控制标高的皮数杆,然后开始布置第二组皮数杆,搭设第二组立杆8,依此类推;由于结构跨度,结构曲率较小,且钢筋长度为9-12m,因此可沿模板曲面采用人工弯曲即可绑扎。 The gate structure has a large span and is an irregular eggshell shell 9, and the surface curvature of the structure varies widely and is irregular. Therefore, the positioning, measurement and setting out of the gate is the most important thing to ensure the construction quality of the entire project; the contour line of the gate The 11 projection line is an irregular arc, and the surveyor can only set out the line point by point, and then connect the line. The structure span of the gate shell is 42 meters. There are many projection points of the contour line 11 that need to be measured and set out, and the workload is extremely high. Large, requiring a large number of surveyors to cooperate; surveyors need to release the plane layout net of the formwork support system on the structural roof, and all support frame poles 8 need to be positioned on the structural roof. The workload is large and a large number of surveyors are required Cooperate with the operation; the shelf worker erects the crossbar 7 according to the step distance of the crossbar 7, and when the vertical pole 8 is erected to the height range required by the design, an adjustable U bracket 6 is placed on the top of the vertical pole 8 through the control of the pull wire of the adjacent leather number rod. And adjust to the design elevation; the support frame is set up from the left and right sides of the gate to the middle, and the number poles are not load-bearing, and should be controlled with the height of the poles 8 to be erected and dismantled; every five columns of poles 8 are a group, and when the first group When the five rows of vertical poles 8 are erected to the design elevation, remove the scale poles used to control the elevation, then start to arrange the second set of scale poles, set up the second set of poles 8, and so on; due to the structural span, the structural curvature Smaller, and the length of the steel bar is 9-12m, so it can be bound by manual bending along the surface of the formwork.

7 制作薄壳结构模板 7 Make a thin shell structure template

薄壳结构模板的顶模板16和底模板15均采用预制玻璃钢模板,首先标高为1.350米高的模板分界线10,模板分界线10以下的部分设置底模板15和顶模板16,模板分界线10以上的部分只设置底模板15,顶模板16和底模板15之间采用A14对拉止水螺栓,对拉止水螺栓的竖向间距350mm,横向间距为600mm,螺栓要加焊止水片3,止水螺杆两侧加焊50mm A14钢筋头作为顶撑,封模时在螺杆的两端穿上25mm厚圆台形胶塞作为防浆帽。混凝土浇注完后取出胶塞,墙上将留下弧形凹坑,凹坑用标号高一级的防水砂浆填塞。 Both the top formwork 16 and the bottom formwork 15 of the thin-shell structure formwork adopt prefabricated glass fiber reinforced plastic formwork. First, the elevation is 1.350 meters high. For the above part, only the bottom formwork 15 is provided, and A14 paired waterstop bolts are used between the top formwork 16 and the bottom formwork 15. The vertical spacing of the paired waterstop bolts is 350mm, and the horizontal spacing is 600mm. The bolts need to be welded with waterstops 3 , welded 50mm A14 steel bar heads on both sides of the waterstop screw as a top support, and put 25mm thick conical rubber plugs on both ends of the screw as anti-sludge caps when sealing the mold. After the concrete is poured, take out the rubber plug, and an arc-shaped pit will be left on the wall, and the pit will be filled with waterproof mortar with a higher grade.

具体施工步骤为:首先对所有不同曲率的待安装模板依据待安装位置进行编号;在壳体9高度为1.35米的地方标注模板分界线10,即标注一条特定高度的等高线为模板分界线10;对整个壳体9吊装底模板15:模板从顶部向两侧根据编号进行安装,必须保证拼缝严密,模板拼缝处粘贴海绵条,模板之间的拼缝用专用材料涂抹密封,以防止漏浆;对模板分界线10以下部分搭设壳体9顶模板16;对模板进行校正:模板施工完毕后必须进行复核工作,达到要求方可浇注混凝土。壳体9前后边缘的底模在结构边缘一侧应设置翻边,翻边高度同结构板厚度。 The specific construction steps are: first, number all the templates to be installed with different curvatures according to the location to be installed; mark the template boundary line 10 at the place where the height of the shell 9 is 1.35 meters, that is, mark a contour line of a specific height as the template boundary line 10. Hoist the bottom formwork for the entire shell 9. 15: The formwork is installed from the top to both sides according to the number. It is necessary to ensure that the joints are tight. The joints of the formwork are pasted with sponge strips. The joints between the formworks are coated and sealed with special materials. Prevent grout leakage; set up the shell 9 top formwork 16 for the part below the formwork boundary 10; correct the formwork: after the formwork construction is completed, the review work must be carried out, and the concrete can only be poured when the requirements are met. The bottom mold of the front and rear edges of the housing 9 should be provided with flanging on one side of the structural edge, and the flanging height is the same as the thickness of the structural plate.

模板专业厂家和技术人员进行模板及支撑系统的配置设计,绘出模板排列图,对所有模板进行编号加工安装;有关模板支撑、排列、施工顺序和拆装方法,工长必须向班组人员进行详细交底;对运到现场的模板及配件应按规格、数量逐次清点及检查,不符合质量要求的不得使用;模板在现场按编号分类并平行堆放,上下块模板之间应用木块垫开,防止模板受压变形;壳体9的根部外侧模板必须在钢筋验收以后才能合模,合模前对砼结构施工缝进行处理,清除所有碎渣,防止烂根;模板拼接保证拼缝严密,模板拼缝处粘贴海绵条,以防止漏浆,模板施工完毕后必须进行复核工作,达到要求方可浇注混凝土。 Formwork professional manufacturers and technicians design formwork and support system configurations, draw formwork arrangement diagrams, and number, process and install all formworks; for formwork support, arrangement, construction sequence and disassembly methods, the foreman must explain to the team members in detail Disclosure; the templates and accessories transported to the site should be counted and inspected one by one according to the specifications and quantities, and those that do not meet the quality requirements should not be used; the templates are sorted by number on the site and stacked in parallel, and the upper and lower templates should be placed between the upper and lower templates. The formwork is compressed and deformed; the outer formwork of the root of the shell 9 must be closed after the acceptance of the steel bars. Paste sponge strips on the seams to prevent grout leakage. After the formwork is completed, it must be reviewed and the concrete can only be poured when the requirements are met.

8 壳体钢筋的绑扎 8 Binding of shell reinforcement

8.1壳体基础梁钢筋除锈 8.1 Rust removal of shell foundation beam reinforcement

施工现场钢筋由于长期外露,其表面产生不同程度浮锈,为满足设计与施工规范要求,需对此部分钢筋进行除锈处理,以保证工程项目的施工质量。 Due to the long-term exposure of the steel bars on the construction site, the surface has different degrees of floating rust. In order to meet the requirements of the design and construction specifications, this part of the steel bars needs to be derusted to ensure the construction quality of the project.

根据钢筋浮锈情况的不同,主要采取以下两种方案: According to the different floating rust conditions of steel bars, the following two methods are mainly adopted:

1)对浮锈多的钢筋,采取除锈剂进行清除的方法; 1) For steel bars with a lot of floating rust, use a rust remover to remove them;

2)对浮锈少的钢筋,采取钢刷进行清除的方法。 2) For steel bars with little floating rust, use steel brush to remove them.

8.2钢筋加工 8.2 Steel bar processing

钢筋由施工队配筋员负责翻样,在施工现场搭设钢筋加工棚,所有钢筋在施工现场加工弯制。 Reinforcement staff of the construction team is responsible for flipping the steel bars. A steel bar processing shed is set up at the construction site, and all steel bars are processed and bent at the construction site.

8.3壳体边缘暗梁和底边暗梁钢筋的绑扎 8.3 Binding of hidden beams at the edge of the shell and hidden beams at the bottom

熟悉图纸,清理料单→整理所用钢筋→清理操作面→钢筋倒运到位→划梁箍筋间距→放梁箍筋→穿梁底层纵筋→穿梁顶层纵筋→调整钢筋保护层厚度及间距→检查钢筋保护层、钢筋位置是否符合要求→清理现场机具及废料。 Familiar with the drawings, clean up the bill of materials→sort out the steel bars used→clean up the operation surface→transport the steel bars in place→draw the spacing of the beam stirrups→place the beam stirrups→through the bottom longitudinal reinforcement of the beam→through the top longitudinal reinforcement of the beam→adjust the thickness and spacing of the reinforcement cover→ Check whether the protective layer of steel bars and the position of steel bars meet the requirements → clean up the on-site equipment and waste.

8.4壳体板钢筋绑扎 8.4 Binding of steel bars for shell plates

熟悉图纸,清查料单→整理所用钢筋→清理模板→在模板上划线→钢筋倒运到位→绑底部筋13→绑顶部筋14→调整钢筋保护层厚度及间距→检查钢筋保护层、钢筋位置是否符合要求→清理现场机具及废料。在绑扎钢筋前,模板面必须图刷隔离剂,准备工作中重点控制钢筋的规格尺寸、混凝土垫块的厚度、马凳铁尺寸、墙柱钢筋定位筋、预埋铁件等。 Familiar with the drawings, check the bill of materials → sort out the steel bars used → clean the formwork → mark the line on the formwork → ship the steel bars in place → tie the bottom reinforcement 13 → tie the top reinforcement 14 → adjust the thickness and spacing of the reinforcement protection layer → check whether the reinforcement protection layer and the location of the reinforcement are correct Meet the requirements → clean up on-site equipment and waste. Before tying the steel bars, the surface of the formwork must be brushed with a release agent. During the preparation work, focus on controlling the specifications and sizes of the steel bars, the thickness of the concrete pad, the size of the horse stool iron, the positioning bar of the wall column reinforcement, and the embedded iron parts, etc.

9混凝土的浇注 9 pouring of concrete

此壳体结构混凝土的强度等级为C30,混凝土骨料的颗粒直径不得大于最小保护层厚度。浇注时,由一台汽车泵从大门左右两侧向中间进行浇注。 The strength grade of the concrete for this shell structure is C30, and the particle diameter of the concrete aggregate shall not be greater than the minimum thickness of the protective layer. When pouring, a car pump pours from the left and right sides of the gate to the middle.

预先安排好混凝土下料点位置和振捣器操作人员数量。混凝土浇注前先在底部均匀浇注50mm厚与壳体的混凝土砂浆成份相同的水泥砂浆。混凝土要连续分层浇注,每层浇注厚度控制在450mm以内,振捣密实后,从先下料处重新布料,上下层的间隔时间不要超过混凝土的初凝时间,应根据现场混凝土坍落度、天气情况、混凝土缓凝时间等情况确定,一般控制不宜大于1.5h,采用人工振捣,用B20钢筋反复插捣,再用人工分两次拍实,最后人工压光抹面。由于壳体9是蛋壳形倾斜屋面,在浇注单侧模板范围内,即标高为1.35m以上部分,壳体9混凝土时,为防止混凝土向低处倾倒,此范围内的混凝土的坍落度严格控制在140±10mm,同时在壳体9钢筋上,每3m设一道钢丝网以拦截混凝土下落。底部封闭式模板部分采用A50振捣棒浇捣,两侧对称下料。 Pre-arrange the location of the concrete feeding point and the number of vibrator operators. Before concrete pouring, pour 50mm thick cement mortar with the same composition as the concrete mortar of the shell evenly at the bottom. Concrete should be continuously poured in layers, and the pouring thickness of each layer should be controlled within 450mm. After vibrating and compacting, the material should be redistributed from the place where the material was cut first. The interval between the upper and lower layers should not exceed the initial setting time of the concrete. The weather conditions, concrete retarding time and other conditions are determined, and the general control should not be greater than 1.5h. Manual vibration is used, and B20 steel bars are repeatedly inserted and tamped. Since the shell 9 is an eggshell-shaped inclined roof, within the scope of pouring one-sided formwork, that is, the part with an elevation above 1.35m, when the shell 9 is concreted, in order to prevent the concrete from falling to a low place, the slump of the concrete within this range It is strictly controlled at 140±10mm, and at the same time, on the 9 steel bars of the shell, a steel wire mesh is set every 3m to stop the concrete from falling. The bottom closed formwork part is poured with A50 vibrating rod, and the material is symmetrically cut on both sides.

为控制壳体9结构表面标高,浇注混凝土前,在单侧模板的结构范围内,沿等高线11每隔2m焊接一根钢筋头,在受力筋上不可施焊,钢筋头的标高与壳体9结构面的标高相同。在混凝土浇注过程中派专人看护模板,随时检查模板的支撑情况。在梁板混凝土浇注过程中不能集中于一点下料,也不得在一个地方堆积大量的混凝土,应采用对称跳仓的方式浇注混凝土,要保持均匀下料,避免使大量荷载集中一点,造成局部失稳。 In order to control the structural surface elevation of the shell 9, before pouring concrete, within the structural scope of the one-sided formwork, a steel bar head is welded every 2m along the contour line 11, and welding is not allowed on the stress bars. The elevations of the structural surfaces of the casing 9 are the same. During the concrete pouring process, special personnel are assigned to take care of the formwork and check the support of the formwork at any time. In the process of concrete pouring for beams and slabs, it is not allowed to concentrate on one point of blanking, and it is not allowed to accumulate a large amount of concrete in one place. The concrete should be poured in a symmetrical way, and the uniform blanking should be maintained to avoid concentrating a large amount of load on one point and causing local failure. stable.

10进行混凝土养护后拆除薄壳结构支撑架 10 Remove the support frame of the thin shell structure after concrete curing

在混凝土强度达到100%设计强度时方可开始拆模。应自上而下按编号、逐块拆除,严禁上下两侧同时拆除。拆除顺序:拆除顶模板16玻璃钢→下调U托6→拆除底模板15玻璃钢→拆除支撑体系支撑架。 Formwork removal can only be started when the concrete strength reaches 100% of the design strength. It should be dismantled by number and block by block from top to bottom, and it is strictly forbidden to dismantle the upper and lower sides at the same time. Removal sequence: remove the top formwork 16 FRP → lower the U bracket 6 → remove the bottom formwork 15 FRP → remove the support system support frame.

(1)钢筋绑扎前,工长应对施工队进行书面技术交底,并对作业班组进行进一步的详细交底后,方可安排施工。明确现场具体要求:弹线、钢筋控制线板边第一根钢筋距梁边混凝土50mm等、钢筋马凳间距、钢筋绑扎方法、钢筋绑扎顺序、不同部位垫块厚度、钢筋绑扎得允许偏差等。 (1) Before the steel bars are bound, the foreman should make a written technical disclosure to the construction team, and make further detailed disclosures to the operation team before the construction can be arranged. Clarify the specific requirements of the site: elastic line, the first steel bar on the side of the steel control line board is 50mm away from the concrete beside the beam, etc., the distance between the steel bar stool, the method of steel bar binding, the order of steel bar binding, the thickness of pads in different parts, the allowable deviation of steel bar binding, etc.

(2)在绑扎钢筋前,模板面必须图刷隔离剂,必须把一些必要的准备工作做到位,重点控制钢筋的直径、规格尺寸,混凝土垫块的厚度、马凳铁尺寸、墙柱钢筋定位筋、预埋铁件等。 (2) Before binding the steel bars, the surface of the formwork must be brushed with a release agent, and some necessary preparations must be done in place, focusing on controlling the diameter and size of the steel bars, the thickness of the concrete pad, the size of the horse stool iron, and the positioning of the wall column steel bars Ribs, pre-embedded iron parts, etc.

(3)施工期间不得在结构上超负荷堆放建材和施工垃圾。 (3) Construction materials and construction waste shall not be overloaded on the structure during the construction period.

11 大跨度多曲率薄壳钢筋混凝土的工程质量控制 11 Engineering quality control of long-span multi-curvature thin-shell reinforced concrete

模板安装必须保证位置准确无误,模板拼缝严密,支撑系统牢固可靠,不发生变形和位移。模板安装完毕后,测量人员应对模板位置、垂直度、标高、预埋及预留洞的位置等进行检查。薄壳结构模板的允许偏差应符合以下表1规定;钢筋安装时,受力钢筋的品种、级别、规格和数量必须符合设计要求,检查时通过观察或钢尺检查进行全数检查,检查预埋件中心线位置时,应沿纵横两个方向量测,并取其中的较大值,梁类、板类构件上部纵向受力钢筋保护层厚度的合格点率应达到90%以上,且不得有超过表2或表3数值1.5倍的尺寸偏差,表4是混凝土浇注的工程质量要求。 The formwork installation must ensure that the position is accurate, the formwork joints are tight, the support system is firm and reliable, and no deformation or displacement occurs. After the formwork is installed, surveyors should check the formwork position, verticality, elevation, pre-buried and reserved hole positions, etc. The allowable deviation of the thin-shell structure formwork shall comply with the provisions in Table 1 below; when the steel bars are installed, the type, grade, specification and quantity of the stressed steel bars must meet the design requirements. For the position of the center line, it should be measured along the vertical and horizontal directions, and the larger value should be taken. The qualified point rate of the protective layer thickness of the longitudinally stressed reinforcement on the upper part of beams and slabs should reach more than 90%, and no more than The size deviation of 1.5 times the value in Table 2 or Table 3, Table 4 is the engineering quality requirements for concrete pouring.

Claims (7)

1. a large span multi-curvature shell structure of reinforced concrete method, is characterized in that:
Its Specific construction step comprises:
Step one, drafting construction drawing: draw construction drawing, and become 3D illustraton of model by rhinoceros Software on Drawing, draw full hall bracing frame vertical rod (8) layout plan and housing isohypse perspective view simultaneously;
The component glass fiber reinforced plastic of step 2, making specific curvature: find the length of structure to be onstructed to central axis on described 3D illustraton of model, using length to central axis for baseline does the parallel lines of a series of spacing 1 ~ 3 meter as control line to both sides, adjacent two control lines and adjacent two isohypses (11) are surrounded the specification of part and curvature data as the specification of glass fiber reinforced plastic after decomposing and curvature data, template producer according to must data creating component glass fiber reinforced plastic;
Step 3, construction plant cleaning;
Step 4, unwrapping wire are located: carry out measurement and unwrapping wire location to job site, the position of mark isohypse (11) and vertical rod (8) according to full hall bracing frame vertical rod (8) layout plan and housing isohypse perspective view;
Step 5, set up full hall bracing frame: set up full hall bracing frame in the below of planning to build thin shell structures, adopt fastener that vertical rod (8) and cross bar (7) are connected into support body, the top of the vertical rod (8) of bracing frame connects U holder (6), connect the steel tube framework (4) identical with shell curvature on U holder (6), described U hold in the palm to add between (6) and steel tube framework (4) timber wedge (5) jam-pack steel pipe and U hold in the palm between gap;
Step 6, making thin shell structures template: first absolute altitude is the template line of demarcation (10) of 1 ~ 2 meter high, and template line of demarcation (10) part below adopts bilateral glass steel form (1), namely sets up soffit formwork (15) and top template (16) simultaneously; Part more than template line of demarcation (10) adopts one-sided glass steel formwork (12), namely only has soffit formwork (15); Adopt drawing water-proof bolt (2) to connect between the soffit formwork (15) of the bilateral glass steel form (1) of thin shell structures and top template (16);
After step 7, model sheetinstallat complete directly in a template between assembling reinforcement, comprise according to determining curvature bending reinforcing steel bar, the dark beam steel of colligation housing and colligation shell plates reinforcing bar, between housing reinforcing bar, interception gauze wire cloth (17) is set up at interval, tackles concrete and fall during pouring concrete;
Step 8, fluid concrete: adopt continuous stratification pouring procedure, every layer of cast THICKNESS CONTROL is within 450mm, the interval time of levels does not exceed the concrete initial setting time, first in the thick cement mortar identical with housing concrete mortar composition of bottom even cast 50mm before pouring concrete; When pouring into a mould bottom bilateral glass steel form (1) part, adopt bilateral symmetry cutting mode; Also press polish of finally manually vibrating is wiped one's face, and housing (9) is shaping;
Step 9, maintenance is carried out to the housing (9) that concrete casting forms;
Step 10, dismounting thin shell structures bracing frame.
2. a kind of large span multi-curvature shell structure of reinforced concrete method according to claim 1, is characterized in that: the concrete operations of setting up thin shell structures bracing frame in described step 5 are:
Step 1, on full hall bracing frame vertical rod (8) layout plan, mark marked rod cloth set-point;
Step 2, according to marked rod arrangement diagram arrange marked rod;
Step 3, absolute altitude by adjacent marked rod span wire system determination intermediate uprights, carry out sawing to pole steel tube, make it highly meet the requirements;
Step 4, progressively set up vertical rod (8) from the left and right sides toward centre;
Step 5, vertical rod (8) top install U holder (6);
Step 6, vertical rod (8) is highly tested and calibrated;
Step 7, set up cross bar (7);
Step 8, the curvature of steel pipe along thin shell structures to be bent, make steel tube framework (4), make corresponding timber wedge (5) simultaneously;
Step 9, steel tube framework (4) is placed on frame top, asks (6) colligation firm with iron wire and U, and links with cross bar 7 iron wire colligation, U holds in the palm between (6) and steel tube framework (4) and fills in timber wedge (5), and bracing frame completes.
3. a kind of large span multi-curvature shell structure of reinforced concrete method according to claim 2, it is characterized in that: marked rod not load-bearing in described step 3, the absolute altitude only carrying out vertical rod (8) controls, with taking with tearing open, be one group with every 4 ~ 8 row vertical rods in operation, after the vertical rod of first group has been set up, remove the marked rod being used for elevation control, then start to arrange next group marked rod, set up next group vertical rod (8).
4. a kind of large span multi-curvature shell structure of reinforced concrete method according to claim 1, is characterized in that: the concrete operation step making thin shell structures template in described step 6 is:
Step 1, the template to be installed of all different curvature to be numbered according to position to be installed;
Step 2, be highly place mark template line of demarcation (10) of 1 ~ 2 meter at housing (9), namely marking the isohypse of a certain height is template line of demarcation (10);
Step 3, to whole housing (9) lifting glass fiber reinforced plastic bottom template (15): bed die is installed according to numbering from top to both sides, must ensure that piece is tight, sponge strip is pasted at formwork edge joint place, and the piece proprietary material between template smears sealing, with mortar leakage prevention;
Step 4, with lower part prepared by housing (9) glass fiber reinforced plastic top template (16) to template line of demarcation (10): in template line of demarcation (10) with lower part, one deck glass fiber reinforced plastic is added again at completed one-sided glass fiber reinforced plastic lateral surface, becoming bilateral glass steel form (1), adopting drawing water-proof bolt (2) to connect between the soffit formwork (15) of bilateral glass steel form and top template (16);
Step 5, template to be corrected: must check work after template construction, reaching requirement can fluid concrete.
5. a kind of large span multi-curvature shell structure of reinforced concrete method according to claim 1, is characterized in that: to drawing the both sides of water-proof bolt (2) to be welded with steel bar end as shoring in described step 6.
6. a kind of large span multi-curvature shell structure of reinforced concrete method according to claim 1, it is characterized in that: to the plug drawing the two ends of water-proof bolt (2) to be installed with the truncated cone-shaped of anti-slurry effect in described step 6, the clear spacing of two plugs is the thick thickness deducting twice plug of housing, plug is taken out after pouring concrete is complete, housing will leave arc pit, the higher leveled waterproofing mortar filling of pit label.
7. a kind of large span multi-curvature shell structure of reinforced concrete method according to claim 1, it is characterized in that: described in step 6, the sagittal edge of soffit formwork (15) arranges flange, the thickness of the same housing of flange height (9) is identical.
CN201310564950.2A 2013-11-14 2013-11-14 Large span multi-curvature shell structure of reinforced concrete method Expired - Fee Related CN103590603B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310564950.2A CN103590603B (en) 2013-11-14 2013-11-14 Large span multi-curvature shell structure of reinforced concrete method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310564950.2A CN103590603B (en) 2013-11-14 2013-11-14 Large span multi-curvature shell structure of reinforced concrete method

Publications (2)

Publication Number Publication Date
CN103590603A CN103590603A (en) 2014-02-19
CN103590603B true CN103590603B (en) 2015-08-26

Family

ID=50080903

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310564950.2A Expired - Fee Related CN103590603B (en) 2013-11-14 2013-11-14 Large span multi-curvature shell structure of reinforced concrete method

Country Status (1)

Country Link
CN (1) CN103590603B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105544873B (en) * 2015-12-16 2017-12-26 中国建筑第二工程局有限公司 Construction method of wave-shaped hollow roof
CN107869249B (en) * 2017-11-17 2019-10-11 成都建工第四建筑工程有限公司 Arcuate structure high-formwork construction method
CN107939094B (en) * 2017-11-25 2020-04-24 二十二冶集团天津建设有限公司 Conical concrete funnel construction method
CN108762171B (en) * 2018-08-21 2024-05-14 陕西建工第三建设集团有限公司 Template support system safety monitoring system and monitoring method
CN110080517A (en) * 2019-04-04 2019-08-02 上海建工二建集团有限公司 Formwork system of concrete thin-shell dome structure and construction method thereof
CN110778108B (en) * 2019-10-30 2021-09-21 中国建筑第八工程局有限公司 Construction method of complex space multi-curved surface double-layer oblique crossing concrete grid structure
CN110685434B (en) * 2019-10-30 2023-11-21 中国建筑第八工程局有限公司 Cast-in-situ multi-curved surface double-layer oblique-crossing concrete grid structure formwork system and construction method
CN112031400B (en) * 2020-09-03 2021-06-11 北京市第三建筑工程有限公司 Construction method of concrete dome structure template
CN114892524A (en) * 2022-03-18 2022-08-12 中国建筑第四工程局有限公司 Construction method of large-span variable-cross-section cantilever oblique beam
CN116717073A (en) * 2023-06-27 2023-09-08 中建八局第三建设有限公司 A construction method for high formwork for large-span special-shaped and multi-curved concrete components

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7162844B2 (en) * 2003-01-09 2007-01-16 Chicago Bridge & Iron Company Use of partial precast panels for construction of concrete walls and shells
CN102061803B (en) * 2010-11-26 2012-05-23 清华大学建筑设计研究院 Shear wall structure building based on cross-hole prefabricated reinforced concrete template and construction method thereof
CN102359208B (en) * 2011-08-01 2013-09-11 中建二局第三建筑工程有限公司 Oblique curtain wall system and installation method thereof
CN202509754U (en) * 2012-04-18 2012-10-31 中建二局第三建筑工程有限公司 High-altitude steel structure node construction working platform
CN103046746B (en) * 2012-12-03 2014-01-29 江苏通州四建集团有限公司 Construction method of conversion beam reinforcing bars for tall building structure

Also Published As

Publication number Publication date
CN103590603A (en) 2014-02-19

Similar Documents

Publication Publication Date Title
CN103590603B (en) Large span multi-curvature shell structure of reinforced concrete method
CN112049143B (en) Large-sized concrete bearing platform construction method for large-sized low-temperature storage tank
CN105345926B (en) The precast construction method of prestressed concrete box girder
CN113202222A (en) Construction method for assembled type superposed beam slab
CN114412182B (en) Construction method of ultrahigh large-section stiffness inclined column hanging template
CN107882321A (en) Diameter Silo slding form operation engineering method
CN115030064A (en) A kind of construction method of moving beam for reconstruction of high-speed railway elevated station
CN110939051A (en) Subway hidden cover beam construction method
CN117306861B (en) Construction method of prefabricated canopy at tunnel entrance based on BIM technology
CN103243912B (en) Multilayer is without plate framework construction method
CN111576878A (en) Construction process for quick-release system of aluminum alloy template
CN104894954A (en) Overall mounting and constructing method of pier stud reinforcing steel bars of urban bridge
CN103174095B (en) Box girder concrete pouring structure with rear-expanding flanges and construction method thereof
CN103758348A (en) Profile steel framework structure concrete floor slab suspension mould pouring construction method
CN113152262A (en) Bridge single-column pier reinforcement construction method
CN116910854A (en) Large-span arch concrete structure construction method based on digital construction
CN103806659B (en) Super thick prestressing force change-over panel individual layer comprehensively supports and splits temperature control construction technology with control
CN108005255A (en) A method of building a wall
CN118601373A (en) Construction method for reinforcing reinforced concrete inner frame of old multi-story brick-concrete structure buildings
CN107905609A (en) Underground people's air defense construction method
CN109112903A (en) Solid concrete roabed trackless construction technology is cheated in a kind of phase library inner column formula inspection
CN110258890B (en) Construction method of concrete structure with connected broken line type outer wall and roof
CN114277672B (en) Large-span prestressed concrete bent cap structure and construction method thereof
CN110593477A (en) A Construction Method of Cast-in-situ Reinforced Concrete Special-shaped Inclined Slab
CN105544832B (en) Shell roof and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150826