CN205742215U - A kind of reusable pipe gallery pattern foundation pit supporting structure and structure external mold combinative structure - Google Patents
A kind of reusable pipe gallery pattern foundation pit supporting structure and structure external mold combinative structure Download PDFInfo
- Publication number
- CN205742215U CN205742215U CN201620425135.7U CN201620425135U CN205742215U CN 205742215 U CN205742215 U CN 205742215U CN 201620425135 U CN201620425135 U CN 201620425135U CN 205742215 U CN205742215 U CN 205742215U
- Authority
- CN
- China
- Prior art keywords
- shaped steel
- steel
- pipe gallery
- external mold
- foundation pit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 claims 26
- 239000010959 steel Substances 0.000 claims 26
- 239000004568 cement Substances 0.000 claims 4
- 230000003014 reinforcing effect Effects 0.000 claims 4
- 229920001903 high density polyethylene Polymers 0.000 claims 2
- 239000004700 high-density polyethylene Substances 0.000 claims 2
- 239000000463 material Substances 0.000 claims 2
- 238000005098 hot rolling Methods 0.000 claims 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
所属技术领域 Technical field
本实用新型涉及一种可重复使用的综合管廊基坑支护与结构外模组合结构,属于地下工程领域。 The utility model relates to a reusable comprehensive pipe gallery foundation pit support and structure outer mold combined structure, which belongs to the field of underground engineering.
背景技术 Background technique
目前地下各种管道之间是相互独立的立体结构,常常因各种管道的增容和维修,而造成马路“拉链”,严重影响城市交通和市容市貌。越来越多的城市开始筹划建设城市地下综合管廊来解决马路“拉链”的问题,但是城市地下综合管廊主要布设在市政道路下面,可提供的明挖开挖工作空间有限,无法为地下综合管廊结构外模提供足够的架设空间;另外在市政道路上施工地下综合管廊时应尽量减少开挖空间,避免施工时多占市政道路宽度,为城市交通保通提供条件,因此减少开挖空间的问题有着重大的技术价值和经济意义。 At present, various underground pipelines are three-dimensional structures independent of each other. The expansion and maintenance of various pipelines often cause road "zippers", seriously affecting urban traffic and city appearance. More and more cities are beginning to plan to build urban underground comprehensive utility corridors to solve the problem of road "zipper". However, urban underground comprehensive utility corridors are mainly laid out under municipal roads, and the available open-cut excavation work space is limited and cannot be used for underground construction. The external formwork of the comprehensive pipe gallery structure provides enough space for erection; in addition, when constructing the underground comprehensive pipe gallery on the municipal road, the excavation space should be minimized to avoid occupying the width of the municipal road during construction, and provide conditions for urban traffic flow, thus reducing the construction cost. The problem of digging space has great technical value and economic significance.
实用新型内容 Utility model content
为了更好的解决上述问题,本实用新型提出了一种可重复使用的综合管廊基坑支护与结构外模组合结构可减少开挖空间,解决了城市地下综合管廊明挖开挖时工作空间有限,无法为结构外模提供足够架设空间的问题。 In order to better solve the above problems, the utility model proposes a reusable combined structure of comprehensive pipe gallery foundation pit support and structural external formwork, which can reduce the excavation space and solve the problem of open excavation of urban underground comprehensive pipe gallery. The working space is limited, and it is impossible to provide enough erection space for the structural external formwork.
本实用新型采用的技术方案为:一种可重复使用的综合管廊基坑支护与结构外模组合结构,由综合管廊基坑两侧的基坑竖向支挡与结构外模组合单元9和水平支撑结构10构成。 The technical solution adopted by the utility model is: a reusable comprehensive pipe gallery foundation pit support and structural outer mold combination structure, which is composed of the vertical support of the foundation pit on both sides of the comprehensive pipe gallery foundation pit and the structural outer mold combined unit 9 and a horizontal support structure 10 constitute.
所述基坑竖向支挡与结构外模组合单元9包括一副三轴水泥土搅拌桩1、两块内插模板6、两个型钢单元8,所述型钢单元8包括内插型钢2、导槽型钢3、垫块5、扣件7,内插型钢2和导槽型钢3之间设有垫块5并通过螺栓4固定,导槽型钢3的上部通过扣件7与内插型钢2连接。 The combined unit 9 of the vertical support of the foundation pit and the external formwork of the structure includes a pair of three-axis cement-soil mixing piles 1, two interpolated templates 6, and two shaped steel units 8. The shaped steel units 8 include inserted shaped steel 2, Guide channel profile steel 3, spacer 5, fastener 7, spacer 5 is set between the insert profile steel 2 and guide channel profile steel 3 and fixed by bolt 4, the upper part of guide channel profile steel 3 is connected with the insert profile steel 2 through the fastener 7 connect.
所述水平支撑结构10包括冠梁和钢管支撑,冠梁通过对拉螺栓与内插型钢2固定,钢管支撑通过冠梁支撑在两端地下综合管廊基坑竖向支挡结构上。 The horizontal support structure 10 includes crown beams and steel pipe supports. The crown beams are fixed to the interpolated section steel 2 by pull bolts. The steel pipe supports are supported on the vertical support structures of the foundation pit of the underground comprehensive pipe gallery at both ends through the crown beams.
所述基坑竖向支挡与结构外模组合单元9和水平支撑结构10中除了三轴水泥土搅拌桩1外的其他部件均为可重复拼接与拆卸的标准构件。 Except for the three-axis cement-soil mixing pile 1, the combined unit 9 of the vertical support and external formwork of the foundation pit and the horizontal support structure 10 are all standard components that can be spliced and disassembled repeatedly.
所述三轴水泥土搅拌桩1直径为850mm,搭接250mm,长度根据地质条件和综合管廊的埋深来选取。 The diameter of the three-axis cement-soil mixing pile 1 is 850mm, the overlap is 250mm, and the length is selected according to the geological conditions and the buried depth of the integrated pipe gallery.
所述三轴水泥土搅拌桩1桩顶标高低于地面0.5m。 The pile top elevation of the three-axis cement-soil mixing pile 1 is 0.5m lower than the ground.
所述内插模板6采用高2000mm,宽1500mm,厚20mm的 HDPE材料或高2000mm,宽1500mm,厚8mm的钢材制成。 Described interpolation template 6 adopts high 2000mm, wide 1500mm, the HDPE material of thick 20mm or high 2000mm, wide 1500mm, the steel material of thick 8mm is made.
所述内插型钢2和扣件7之间通过方条卡紧。 The inserted section steel 2 and the fastener 7 are fastened by a square bar.
所述内插型钢2采用型号为HM400×300~600×300的H型钢。 The interpolation steel 2 adopts H-shaped steel with a model of HM400×300~600×300.
所述导槽型钢3采用型号为22的热轧普通槽钢,顶端距离内插型钢2的距离400mm,长度为3m~6m,根据地下结构的底板埋深和垫层厚度来选取。 The guide channel section steel 3 adopts the hot-rolled common channel steel of type 22, the distance from the top to the interpolation section steel 2 is 400mm, and the length is 3m~6m, which is selected according to the buried depth of the bottom plate of the underground structure and the thickness of the cushion layer.
所述扣件7由三根直径18~20mm的HRB335级钢筋组成,其中一根长260mm的钢筋穿过导槽型钢两边的翼缘,另外两根长280mm的钢筋一端弯折360度固定在穿过导槽型钢两端翼缘的钢筋上,另一端折成弯勾分别固定在内插型钢2的侧边翼缘。 The fastener 7 is composed of three HRB335 steel bars with a diameter of 18-20 mm, one of which is 260 mm long and passes through the flanges on both sides of the guide channel steel bar, and the other two 280 mm long steel bars are bent 360 degrees at one end and fixed to pass through On the reinforcing bars of the flanges at the two ends of the channel shaped steel, the other end is bent into a hook and fixed to the side flanges of the inserted shaped steel 2 respectively.
所述垫块5采用高150mm,宽260mm,厚35mm 的HDPE材料。 The spacer 5 is made of HDPE material with a height of 150mm, a width of 260mm, and a thickness of 35mm.
所述螺栓4的型号为M16。 The model of the bolt 4 is M16.
所述水平支撑结构10中的冠梁采用两条型号为28~40#的槽钢、H型钢或工字钢,钢管支撑采用型号为22~36#的工字钢双拼构成。 The crown beam in the horizontal support structure 10 adopts two channel steels, H-shaped steels or I-beams of 28-40#, and the steel pipe support adopts double I-beams of 22-36#.
本实用新型使用步骤如下: The utility model uses steps as follows:
地下综合管廊结构外边线各边扩宽50mm得到基坑开挖线;基坑两侧三轴水泥土搅拌桩1施工时中轴线距离基坑开挖线311mm;内插型钢2的内侧边线位于基坑开挖线上。 The outer side of the underground comprehensive pipe gallery structure is widened by 50mm on each side to obtain the excavation line of the foundation pit; the central axis of the three-axis cement-soil mixing pile 1 on both sides of the foundation pit is 311mm away from the excavation line of the foundation pit during construction; the inner sideline of the interpolated steel 2 is located at Foundation pit excavation line.
(1)将导槽型钢3通过垫块5用螺栓4安装在一根内插型钢2上形成一个型钢单元8; (1) Install the guide channel profiled steel 3 on an interpolated profiled steel 2 through the spacer 5 with bolts 4 to form a profiled steel unit 8;
(2)重复上述工序预先制作好所需的全部型钢单元8。 (2) Repeat the above process to prefabricate all required steel units 8 .
(3)测放现场平面控制网; (3) Plane control network at the surveying and launching site;
(4)轴线放样,开挖宽1.0m深0.55m的沟槽,桩位放样,桩机就位; (4) Stake out the axis, excavate a trench with a width of 1.0m and a depth of 0.55m, set out the pile position, and put the pile driver in place;
(5)采用插二跳一的布置方式在三轴水泥土搅拌桩1施工完成后先后插入型钢单元8; (5) Adopting the arrangement of inserting two jumps and one jumping, after the completion of the construction of the three-axis cement-soil mixing pile 1, insert the section steel unit 8 successively;
(6)当沉入至设计标高时,松开两个型钢单元8的顶部螺栓4,取出上部垫块5; (6) When sinking to the design elevation, loosen the top bolts 4 of the two steel units 8, and take out the upper pad 5;
(7)将第一块内插模板6插入导槽型钢3与内插型钢2之间,当其插入三轴水泥土搅拌桩中的适当位置时扣上导槽型钢和内插型钢的上部扣件7; (7) Insert the first insert template 6 between the guide channel profile steel 3 and the insert profile steel 2, and buckle the upper buckle of the guide channel profile steel and the insert profile steel when it is inserted into the appropriate position in the three-axis cement-soil mixing pile piece 7;
(8)第一块内插模板6沉入至设计标高后打开上部扣件7,插入第二块内插模板6,当其插入三轴水泥土搅拌桩的适当位置时再次扣上上部扣件7; (8) After the first interpolation formwork 6 sinks to the design elevation, open the upper fastener 7, insert the second interpolation formwork 6, and buckle the upper fastener again when it is inserted into the appropriate position of the three-axis cement-soil mixing pile 7;
(9)当第二块内插模板6沉入至设计标高时在一副三轴水泥土搅拌桩1中形成一个基坑竖向支挡与结构外模组合单元9; (9) When the second interpolation formwork 6 sinks to the design elevation, form a combination unit 9 of the vertical support of the foundation pit and the external formwork of the structure in a pair of triaxial cement-soil mixing pile 1;
(10)重复上述工序,依次完成综合管廊基坑两侧的基坑竖向支挡与结构外模组合单元9; (10) Repeat the above process to complete the foundation pit vertical support and structural external formwork combination unit 9 on both sides of the comprehensive pipe gallery foundation pit in sequence;
(11)待三轴水泥土搅拌桩1达到75%强度后,遵循“先撑后挖、限时支撑、分层开挖、严禁超挖”的原则开挖土方和施作水平支撑结构10; (11) After the triaxial cement-soil mixing pile 1 reaches 75% strength, excavate the earthwork and construct the horizontal support structure 10 in accordance with the principle of "supporting first, then digging, time-limited support, layered excavation, and over-excavation is strictly prohibited";
(12)开挖至导槽型钢3底即垫层11底的设计标高时,松开内插型钢2与导槽型钢3底部的高强螺栓4,使导槽型钢3和内插模板6脱落回收,取回底板垫块5,在三轴深搅桩1上得到光滑的地下结构外模; (12) When excavating to the design elevation of the bottom of the guide channel section steel 3, that is, the bottom of the cushion layer 11, loosen the high-strength bolts 4 at the bottom of the inserted section steel 2 and the guide channel section steel 3, so that the guide channel section steel 3 and the inserted formwork 6 fall off and recover , take back the floor cushion block 5, and obtain a smooth external mold of the underground structure on the three-axis deep stirring pile 1;
(13)人工凿除两组合单元9间多余的水泥土; (13) Manually remove the excess cement and soil between the 9 rooms of the two combined units;
(14)施作垫层11; (14) as a cushion layer 11;
(15)绑扎综合管廊12底板和侧墙的钢筋,并支设1/3侧墙高度的内内插模板,浇筑综合管廊11底板和侧墙1/3高度的混凝土; (15) Bind the steel bars of the bottom plate and side wall of the comprehensive pipe gallery 12, and support the interpolation formwork of 1/3 of the height of the side wall, and pour the concrete of the bottom plate and side wall of the comprehensive pipe gallery 11 of 1/3 height;
(16)待底板混凝土达到设计强度后,对已施工侧墙的顶部施工缝凿毛处理,支设顶板、剩余2/3侧墙高度的内插模板并绑扎顶板钢筋,浇筑顶板和侧墙剩余2/3高度的混凝土; (16) After the bottom slab concrete reaches the design strength, roughen the top construction joints of the constructed side walls, support the top slab, insert formwork for the remaining 2/3 of the side wall height and bind the top slab steel bars, and pour the rest of the top slab and side walls 2/3 height concrete;
(17)待混凝土达到设计强度后,分层回填土方至水平支撑以下20cm~50cm,拆除水平支撑结构10; (17) After the concrete reaches the design strength, backfill the earth in layers to 20cm~50cm below the horizontal support, and remove the horizontal support structure 10;
(18)采取跳拔的方式回收内插型钢2,并及时对空隙处注浆充填; (18) Recover the inserted section steel 2 by means of jumping, and fill the gap with grouting in time;
(19)最后恢复路面原有设施。 (19) Finally restore the original facilities on the road surface.
本实用新型的有益效果是:可重复使用的综合管廊基坑支护与结构外模组合结构可减少开挖空间,解决了城市地下综合管廊明挖开挖时工作空间有限,无法为结构外模提供足够架设空间的问题,而且该结构除三轴水泥土搅拌桩以外的全部构件可以制作成可拆卸式的标准件,方便安装和定位,使得内插模板能够准确插入三轴水泥土搅拌桩中,在三轴水泥土搅拌桩中很好地形成全部基坑竖向支挡与结构外模组合单元,减少了构件的损耗,达到全部标准构件可回收循环使用的目的,有经济、绿色环保、节能、对周围环境影响小的优点。 The beneficial effects of the utility model are: the combined structure of the reusable comprehensive pipe gallery foundation pit support and the structure outer mold can reduce the excavation space, and solve the problem that the working space of the urban underground comprehensive pipe gallery is limited and cannot be used for the structure. The external formwork provides enough space for erection, and all components of the structure except the triaxial cement-soil mixing pile can be made into detachable standard parts, which is convenient for installation and positioning, so that the inner formwork can be accurately inserted into the triaxial cement-soil mixing pile Among the piles, the combination unit of all the vertical supports of the foundation pit and the external formwork of the structure is well formed in the three-axis cement-soil mixing pile, which reduces the loss of components and achieves the purpose of recyclable recycling of all standard components, which is economical and green. The advantages of environmental protection, energy saving, and little impact on the surrounding environment.
附图说明 Description of drawings
图1本实用新型中型钢单元的正立面示意图; Fig. 1 is the schematic diagram of the front elevation of the medium-sized steel unit of the utility model;
图2本实用新型中型钢单元的平面示意图; Fig. 2 is the schematic plan view of the medium-sized steel unit of the utility model;
图3本实用新型中型钢单元的侧立面示意图; Fig. 3 is the side elevation schematic diagram of the medium-sized steel unit of the utility model;
图4本实用新型中开槽示意图; Slot schematic diagram in Fig. 4 the utility model;
图5本实用新型中型钢单元完成示意图; Fig. 5 completion schematic diagram of the medium-sized steel unit of the utility model;
图6本实用新型中基坑竖向支挡与结构外模组合单元形成剖面示意图; Fig. 6 is a schematic cross-sectional view of the formation of the vertical support block of the foundation pit and the combined unit of the structural outer mold in the utility model;
图7本实用新型中垫层施工完成示意图; Fig. 7 completion schematic diagram of cushion layer construction in the utility model;
图8本实用新型中施工1/3高的地下综合管廊示意图; Fig. 8 is a schematic diagram of the construction of 1/3 high underground comprehensive pipe gallery in the utility model;
图9本实用新型中地下综合管廊施工完成示意图; Figure 9 is a schematic diagram of the completion of the construction of the underground comprehensive pipe gallery in the utility model;
图10本实用新型中拔除内插型钢剖面示意图; Fig. 10 is a schematic cross-sectional view of removing the inserted section steel in the utility model;
图11本实用新型中施工完成的示意图; The schematic diagram that construction is completed in Fig. 11 the utility model;
图中各标号:1—三轴水泥土搅拌桩;2—内插型钢;3—导槽型钢;4—螺栓;5—垫块;6—内插模板;7—扣件;8—型钢单元;9—基坑竖向支挡与结构外模组合单元;10—水平支撑结构;11—垫层;12—综合管廊。 Each label in the figure: 1—three-axis cement-soil mixing pile; 2—interpolated steel; 3—guiding channel steel; 4—bolt; 5—pad; 6—interpolated formwork; 7—fastener; 8—shaped steel unit ; 9—combined unit of vertical support and external formwork of foundation pit; 10—horizontal support structure; 11—cushion layer; 12—comprehensive pipe gallery.
具体实施方式 detailed description
下面通过附图和实施例对本实用新型作进一步详细说明,但本实用新型的保护范围不局限于所述内容。 The utility model will be described in further detail below through the accompanying drawings and embodiments, but the protection scope of the utility model is not limited to the content described.
实施例1:如图1-11所示:根据周边建筑和周边道路情况,采用明挖法施工截面为高3800宽5000mm的综合管廊12,其底板埋深为7m,土质条件为黏土,设计采用抗渗等级为P8的C40钢筋混凝土,其中采用直径16mm的HRB400钢筋,且采用150mm厚的C20素混凝土垫层。首先导槽型钢3利用高150mm宽260mm厚35mm的HDPE垫块通过M16的螺栓4安装在内插型钢2上形成一个型钢单元8,重复上述工序预先制作好所需的全部型钢单元。内插型钢2采用H型钢,其中H型钢的型号为HM500×300,长12m;导槽型钢3型号为22的热轧普通槽钢,长6.75m;扣件7由三根直径18mm的HRB335级钢筋组成,其中一根长260mm的钢筋穿过导槽型钢3两边的翼缘;另外两根长280mm的钢筋一端弯折360度固定在穿过导槽型钢3两端翼缘的钢筋上,另一端折成弯勾分别固定在内插型钢2的侧边翼缘。测放现场平面控制网,轴线放样,开挖宽1.0m深0.55m的沟槽,桩位放样,桩机就位。当直径850mm搭接250mm的三轴水泥土搅拌桩施工完成后,采用插二跳一的布置方式在三轴水泥土搅拌桩1内先后插入型钢单元8。当沉入至设计标高时,松开两个型钢单元8的顶部螺栓4,取出上部垫块5;将第一块内插模板6插入导槽型钢3与内插型钢2之间,当其插入三轴水泥土搅拌1桩中适当位置时扣上导槽型钢3和内插型钢2的上部扣件7;第一块内插模板6沉入至设计标高后打开扣件7,插入第二块内插模板6,当其插入三轴水泥土搅拌桩1中适当位置时再次扣上扣件7;当第二块内插模板6沉入至设计路面以下时在一副三轴水泥土搅拌桩1中形成一个基坑竖向支挡与结构外模组合单元9。其中,每块内插模板6采用高2000mm宽1500mm厚20mm的HDPE板。重复上述工序,依次完成综合管廊基坑两侧的基坑竖向支挡与结构外模组合单元9;待三轴水泥土搅拌桩1强度达到1MPa后,遵循“先撑后挖、限时支撑、分层开挖、严禁超挖”的原则开挖土方和施作水平支撑结构10。开挖至导槽型钢3底即垫层11底的设计标高时,松开内插型钢2与导槽型钢3底部的螺栓4,使导槽型钢3和内插模板6脱落回收,取回底板垫块5,在三轴水泥土搅拌桩1上得到光滑的地下结构外模。为保证两个基坑竖向支挡与结构外模组合单元9之间的平整度,必须在拆除内插模板6后人工凿除两组合单元间多余的水泥土。然后施作垫层11,绑扎综合管廊12底板和侧墙的钢筋,并支设1/3侧墙高度的内模板,浇筑综合管廊12底板和侧墙1/3高度的混凝土。待底板混凝土达到设计强度后,对已施工侧墙顶部施工缝凿毛处理,支设顶板、剩余2/3侧墙高度的内模板并绑扎顶板钢筋,浇筑顶板和侧墙剩余2/3高度的混凝土。待混凝土达到设计强度后,分层回填土方至水平支撑结构10以下500mm处,拆除水平支撑结构10。采取跳拔的方式回收内插型钢2,并及时对空隙处注浆充填。最后恢复路面原有设施。 Example 1: As shown in Figure 1-11: According to the conditions of surrounding buildings and surrounding roads, an integrated pipe gallery 12 with a section height of 3,800 mm and a width of 5,000 mm was constructed using the open cut method. C40 reinforced concrete with an impermeability grade of P8 is used, of which HRB400 steel bars with a diameter of 16mm are used, and a 150mm thick C20 plain concrete cushion is used. Firstly, the guide channel section steel 3 utilizes HDPE spacers with a height of 150 mm, a width of 260 mm, and a thickness of 35 mm to be installed on the interpolated section steel 2 through M16 bolts 4 to form a section steel unit 8, and repeat the above process to prefabricate all required section steel units. The inserting section steel 2 adopts H-section steel, among which the type of H-section steel is HM500×300, and the length is 12m; the guide channel section steel 3 is hot-rolled ordinary channel steel, the type is 22, and the length is 6.75m; the fastener 7 is composed of three HRB335 steel bars with a diameter of 18mm One of the steel bars with a length of 260mm passes through the flanges on both sides of the channel steel 3; one end of the other two steel bars with a length of 280mm is bent 360 degrees and fixed on the steel bars passing through the flanges at both ends of the channel steel 3, and the other end The bent hooks are respectively fixed to the side flanges of the inserted section steel 2. Measure and lay out the site plane control network, stake out the axis, excavate a trench with a width of 1.0m and a depth of 0.55m, set out the pile position, and put the pile driver in place. After the construction of the three-axis cement-soil mixing pile with a diameter of 850 mm and an overlap of 250 mm is completed, the section steel unit 8 is successively inserted into the three-axis cement-soil mixing pile 1 in the arrangement of inserting two jumps and one jumping. When sinking to the design elevation, loosen the top bolts 4 of the two steel units 8, and take out the upper spacer 5; insert the first interpolation template 6 between the channel steel 3 and the interpolation steel 2, when it is inserted Fasten the upper fastener 7 of the guide channel section steel 3 and the insertion section steel 2 when the three-axis cement-soil mixing 1 pile is in an appropriate position; the first interpolation formwork 6 sinks to the design elevation and then opens the fastener 7 and inserts the second piece Insert the formwork 6, when it is inserted into the appropriate position of the three-axis cement-soil mixing pile 1, buckle the fastener 7 again; when the second interpolation formwork 6 sinks below the designed road surface 1 to form a combination unit 9 of the vertical support of the foundation pit and the external formwork of the structure. Wherein, each interpolation template 6 adopts a HDPE board with a height of 2000 mm, a width of 1500 mm and a thickness of 20 mm. Repeat the above process to complete the foundation pit vertical support and structural external form combination unit 9 on both sides of the foundation pit of the comprehensive pipe gallery in sequence; after the strength of the triaxial cement-soil mixing pile 1 reaches 1MPa, follow the "support first, then dig, and support within a limited time" Excavation of earthwork and construction of horizontal support structure 10 according to the principle of "excavation in layers, and prohibiting over-excavation". When excavating to the design elevation of the bottom of the guide channel section steel 3, that is, the bottom of the cushion layer 11, loosen the bolts 4 at the bottom of the insert section steel 2 and the guide channel section steel 3, so that the guide channel section steel 3 and the insert template 6 fall off and recover, and take back the bottom plate Pad block 5, a smooth underground structure outer mold is obtained on the triaxial cement-soil mixing pile 1. In order to ensure the flatness between the vertical supports of the two foundation pits and the combined unit 9 of the external formwork of the structure, it is necessary to manually chisel away the excess cement and soil between the two combined units after the interpolation formwork 6 is removed. Then apply the cushion 11, bind the reinforcement of the bottom plate and side wall of the comprehensive pipe gallery 12, and support the inner formwork of 1/3 side wall height, and pour the concrete of the bottom plate and side wall 1/3 height of the comprehensive pipe gallery 12. After the bottom slab concrete reaches the design strength, roughen the construction joints at the top of the constructed side wall, support the top slab and the inner formwork of the remaining 2/3 of the side wall height and bind the roof steel bars, and pour the remaining 2/3 of the height of the top slab and side wall concrete. After the concrete reaches the design strength, backfill the earth in layers to a place 500mm below the horizontal support structure 10, and remove the horizontal support structure 10. Recover the inserted section steel 2 by means of jumping, and fill the gap with grouting in time. Finally, restore the original facilities on the pavement.
实施例2:如图1-11所示:采用明挖法施工截面为高3800宽5000mm的综合管廊12,其底板埋深为5m,土质条件为粉土,设计采用抗渗等级为P8的C40钢筋混凝土,其中采用直径16mm的HRB400钢筋,且采用150mm厚的C20素混凝土垫层。首先将导槽型钢3利用高150mm宽260mm厚35mm的HDPE垫块5通过M16的螺栓4安装在内插型钢2上形成一个型钢单元8;重复上述工序预先制作好所需的全部型钢单元8。内插型钢2为H型钢,其中H型钢的型号为HM400×300,长9m;导槽型钢3的型号为22的普通槽钢,长4.75m;扣件7由三根直径18mm的HRB335级钢筋组成,其中一根长260mm的钢筋穿过导槽型钢3两边的翼缘;其他两根长280mm的钢筋一端弯折360度固定在穿过导槽型钢3两端翼缘的钢筋上,另一端折成弯勾分别固定在内插型钢2的侧边翼缘。测放现场平面控制网,轴线放样,开挖宽1.0m深0.55m的沟槽,桩位放样,桩机就位。当直径850mm搭接250mm的三轴水泥土搅拌桩1施工完成后,采用插二跳一的布置方式在三轴水泥土搅拌桩1内先后插入型钢单元8。当沉入至设计标高时,松开两个型钢单元8的顶部螺栓4,取出上部垫块5;将第一块内插模板6插入导槽型钢3与内插型钢2之间,当其插入三轴水泥土搅拌桩1中适当位置时扣上导槽型钢3和内插型钢2的扣件7;第一块内插模板6沉入至设计标高后打开扣件7,插入第二块内插模板6,当其插入三轴水泥土搅拌桩1中适当位置时再次扣上扣件7;当第二块内插模板6沉入至设计路面以下时在一副三轴水泥土搅拌桩1中形成一个基坑竖向支挡与结构外模组合单元9。其中,每块内插模板6采用高2000mm宽1500mm厚20mm的HDPE板。重复上述工序,依次完成综合管廊基坑两侧的基坑竖向支挡与结构外模组合单元9;待三轴水泥土搅拌桩1强度达到0.8MPa后,遵循“先撑后挖、限时支撑、分层开挖、严禁超挖”的原则开挖土方和施作水平支撑结构10。开挖至导槽型钢3底即垫层11底的设计标高时,松开内插型钢2与导槽型钢3底部的螺栓4,使导槽型钢3和内插模板6脱落回收,取回底板垫块5,在三轴水泥土搅拌桩1上得到光滑的地下结构外模。为保证两个基坑竖向支挡与结构外模组合单元9之间的平整度,必须在拆除内插模板后1人工凿除两组合单元间多余的水泥土。然后施作垫层11,绑扎综合管廊12底板和侧墙的钢筋,并支设1/3侧墙高度的内模板,浇筑综合管廊12底板和侧墙1/3高度的混凝土。待底板混凝土达到设计强度后,对已施工侧墙顶部施工缝凿毛处理,支设顶板、剩余2/3侧墙高度的内模板并绑扎顶板钢筋,浇筑顶板和侧墙剩余2/3高度的混凝土。待混凝土达到设计强度后,分层回填土方至水平支撑结构10以下500mm处,拆除水平支撑结构10。采取跳拔的方式回收内插型钢2,并及时对空隙处注浆充填。最后恢复路面原有设施。 Example 2: As shown in Figure 1-11: the comprehensive pipe gallery 12 with a section height of 3,800 mm and a width of 5,000 mm is constructed using the open cut method. C40 reinforced concrete, in which HRB400 steel bars with a diameter of 16mm are used, and a 150mm thick C20 plain concrete cushion is used. Firstly, the guide channel section steel 3 is installed on the insert section steel 2 by using the HDPE spacer 5 with a height of 150 mm, a width of 260 mm and a thickness of 35 mm through M16 bolts 4 to form a section steel unit 8; Inserted steel 2 is H-shaped steel, of which the type of H-shaped steel is HM400×300, and the length is 9m; the type of guide channel steel 3 is ordinary channel steel of 22, and the length is 4.75m; the fastener 7 is composed of three HRB335 steel bars with a diameter of 18mm , one of the steel bars with a length of 260mm passes through the flanges on both sides of the guide channel steel 3; Bending hooks are respectively fixed on the side flanges of the inserted section steel 2. Measure and lay out the site plane control network, stake out the axis, excavate a trench with a width of 1.0m and a depth of 0.55m, set out the pile position, and put the pile driver in place. After the construction of the three-axis cement-soil mixing pile 1 with a diameter of 850 mm and a lap joint of 250 mm is completed, the section steel unit 8 is successively inserted into the three-axis cement-soil mixing pile 1 by means of two insertions and one jump. When sinking to the design elevation, loosen the top bolts 4 of the two steel units 8, and take out the upper spacer 5; insert the first interpolation template 6 between the channel steel 3 and the interpolation steel 2, when it is inserted When the three-axis cement-soil mixing pile 1 is in the proper position, fasten the fastener 7 of the guide channel section steel 3 and the interpolation section steel 2; the first interpolation formwork 6 sinks to the design elevation and then opens the fastener 7 and inserts it into the second Insert the formwork 6, when it is inserted into the proper position of the three-axis cement-soil mixing pile 1, fasten the fastener 7 again; A combined unit 9 of the vertical support of the foundation pit and the external formwork of the structure is formed. Wherein, each interpolation template 6 adopts a HDPE board with a height of 2000 mm, a width of 1500 mm and a thickness of 20 mm. Repeat the above process to complete the foundation pit vertical support and structural external formwork combination unit 9 on both sides of the foundation pit of the comprehensive pipe gallery in sequence; Excavate earthwork and construct horizontal support structure 10 according to the principle of supporting, layered excavation, and strictly prohibiting over-excavation". When excavating to the design elevation of the bottom of the guide channel section steel 3, that is, the bottom of the cushion layer 11, loosen the bolts 4 at the bottom of the insert section steel 2 and the guide channel section steel 3, so that the guide channel section steel 3 and the insert template 6 fall off and recover, and take back the bottom plate Pad block 5, a smooth underground structure outer mold is obtained on the triaxial cement-soil mixing pile 1. In order to ensure the flatness between the vertical supports of the two foundation pits and the combined unit 9 of the external formwork of the structure, it is necessary to manually chisel away the excess cement and soil between the two combined units after the interpolation formwork is removed. Then apply the cushion 11, bind the reinforcement of the bottom plate and side wall of the comprehensive pipe gallery 12, and support the inner formwork of 1/3 side wall height, and pour the concrete of the bottom plate and side wall 1/3 height of the comprehensive pipe gallery 12. After the bottom slab concrete reaches the design strength, roughen the construction joints on the top of the constructed side wall, support the top slab and the inner formwork of the remaining 2/3 of the side wall height and bind the roof steel bars, and pour the remaining 2/3 of the height of the top slab and side wall concrete. After the concrete reaches the design strength, backfill the earth in layers to a place 500mm below the horizontal support structure 10, and remove the horizontal support structure 10. Recover the inserted section steel 2 by means of jumping, and fill the gap with grouting in time. Finally, restore the original facilities on the pavement.
Claims (12)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620425135.7U CN205742215U (en) | 2016-05-12 | 2016-05-12 | A kind of reusable pipe gallery pattern foundation pit supporting structure and structure external mold combinative structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620425135.7U CN205742215U (en) | 2016-05-12 | 2016-05-12 | A kind of reusable pipe gallery pattern foundation pit supporting structure and structure external mold combinative structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205742215U true CN205742215U (en) | 2016-11-30 |
Family
ID=57367540
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620425135.7U Expired - Fee Related CN205742215U (en) | 2016-05-12 | 2016-05-12 | A kind of reusable pipe gallery pattern foundation pit supporting structure and structure external mold combinative structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205742215U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109518722A (en) * | 2019-01-22 | 2019-03-26 | 云南省建设投资控股集团有限公司 | The short underpass structure and its construction method of newly-built basement and existing subway station |
CN110629791A (en) * | 2019-09-23 | 2019-12-31 | 海门市帕源路桥建设有限公司 | Built-in lateral telescopic supporting box type external mold |
-
2016
- 2016-05-12 CN CN201620425135.7U patent/CN205742215U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109518722A (en) * | 2019-01-22 | 2019-03-26 | 云南省建设投资控股集团有限公司 | The short underpass structure and its construction method of newly-built basement and existing subway station |
CN110629791A (en) * | 2019-09-23 | 2019-12-31 | 海门市帕源路桥建设有限公司 | Built-in lateral telescopic supporting box type external mold |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP7394252B1 (en) | Protruding type wind duct structure perpendicular to the vertical direction and construction method at deep subway station | |
CN109026064B (en) | Construction method for large-span multi-arch tunnel with semi-bright and semi-dark | |
CN102434717B (en) | Construction method of joist steel pipe-jacking work pit | |
CN202707075U (en) | Long-span subway station main structure constructed based on column and arch method | |
CN108343071A (en) | A kind of foundation pit supporting construction and construction method of steel sheet pile combined deposited pile | |
CN110761808B (en) | A large-section loess tunnel support system and support construction method | |
CN105201516B (en) | A kind of main structure of subway station and its tetrad arch PBA excavating construction methods | |
CN107905814B (en) | Large span loess tunnel top bar CD construction method | |
CN108678751B (en) | Assembly type construction method of shield cutter head manhole by jacking and excavating firstly | |
CN110593308B (en) | Open excavation back pressure construction method for foundation pit of overhead operation subway underground comprehensive pipe gallery | |
CN108560536A (en) | The continuous piling wall construction method of Soil-cement | |
CN106065628B (en) | Based on the major diameter running water pipe security protection construction method faced forever with reference to theory | |
CN112012762B (en) | Construction method of double-layer secondary lining multi-arch tunnel structure | |
CN108035379B (en) | Comprehensive pipe gallery and construction method thereof | |
CN105926642B (en) | A kind of Urban Underground pipe gallery pattern foundation pit supporting structure and underground structure external mold integral structure and construction method | |
CN105804117A (en) | Formwork tie bar structure of soil arch mould in cover-excavation method for mountain highway tunnel, and construction method thereof | |
CN205036380U (en) | Block of four encircles PBA and secretly digs subway station major structure | |
CN110985042A (en) | Combined support system and technology of urban comprehensive pipe gallery and underground shallow buried tunnel | |
CN205742215U (en) | A kind of reusable pipe gallery pattern foundation pit supporting structure and structure external mold combinative structure | |
CN213143117U (en) | Assembled keyway basis retaining wall structure | |
RU2032024C1 (en) | Method for reinforcing the footing of strip foundation during reconstruction of building or structure | |
CN111379273A (en) | Construction method of corrugated steel comprehensive pipe gallery | |
CN110939139B (en) | Pile plate wall structure based on rigid contact of post-pile special-shaped retaining wall and construction method thereof | |
CN115522963A (en) | Construction method of underground two-layer four-span underground excavation station structure | |
CN209704560U (en) | Build the scaffolding structure that an ultra shallow buries Large Underground space |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161130 Termination date: 20180512 |
|
CF01 | Termination of patent right due to non-payment of annual fee |