CN206784958U - A kind of encorbelmented across metal greatly decorates prefabricated roof and air translation splicing structure - Google Patents
A kind of encorbelmented across metal greatly decorates prefabricated roof and air translation splicing structure Download PDFInfo
- Publication number
- CN206784958U CN206784958U CN201720560861.4U CN201720560861U CN206784958U CN 206784958 U CN206784958 U CN 206784958U CN 201720560861 U CN201720560861 U CN 201720560861U CN 206784958 U CN206784958 U CN 206784958U
- Authority
- CN
- China
- Prior art keywords
- metal
- greatly
- prefabricated roof
- splicing structure
- dilatory
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
It the utility model is related to technical field of building construction, and in particular to a kind of encorbelmented across metal greatly decorates prefabricated roof and air translation splicing structure.This kind greatly across metal encorbelment decoration prefabricated roof and air translation splicing structure include lifting elements block, lift unit block, horizontal sliding cell block.This kind greatly across metal encorbelment decoration prefabricated roof and air translation splicing structure conceptual design is reasonable compared with prior art, it is safe and efficient using preassembling form of construction work, the duration can be shortened to greatest extent.The component being easily installed simultaneously using hoist engine and steel wire rope etc. forms constructing operation system, quick reliable during peace is torn open, cheap, has significant economic benefit.
Description
Technical field
The utility model is related to technical field of building construction, and in particular to it is a kind of greatly across metal encorbelment decoration prefabricated roof and
Air translation splicing structure.
Background technology
As the fast development of building technology and the growing tension of urban land resource, multi-rise building quantity are just all with day
Increase, wherein occur largely because of practical performance or the Long-span Cantilever roof structure system pursued visual effect and designed, because
The particularity of this Long-span Cantilever roof structure system, its extraneous adornment often use metal finishing roofing, real so as to reach
With and design effect, and the design of this Long-span Cantilever metal finishing roofing system often gives construction band huge challenge.
Mainly there are three kinds of forms of construction work currently for the construction of this Long-span Cantilever metal finishing roofing system, the first
It is for tier building, using full hall scaffold form of construction work, that is, it is the scaffold of size of encorbelmenting to set up width, highly for from ground
Face to the scope of operation height;Be for second for multi-rise building, using builder's jack form of construction work, i.e., the structure under the scope of operation
For layer using I-steel as encorbelmenting primary structure member, it is the scaffold of size of encorbelmenting to set up width, is highly plane of encorbelmenting to operation
The height in face;The third is for multi-rise building, using nacelle construction, i.e., hanging basket is set immediately below construction location, by structure
Part is placed on lifting in hanging basket and arrives operation surface construction.
Form of construction work of the prior art mainly has following deficiency:First, prior art is in situ assembled using high-altitude, component
More, installation is complicated, easily causes component and falls, has great potential safety hazard.2nd, make when using full hall scaffold form of construction work
, it is necessary to which substantial amounts of manpower sets up scaffold during industry, long in time limit, cost is big, and with the increase of support body height, security performance
Also decrease.3rd, it is necessary to which substantial amounts of I-steel is as suspension scaffold beaer when using builder's jack form of construction work operation
System, required I-steel quantity is big, and cost is high, and I-steel handling is heavy, it is necessary to the longer duration, while there is also great peace
Full hidden danger.4th, when using nacelle construction mode when because hanging basket can only vertically operation, it is necessary to hang a large amount of hanging baskets encorbelment fill
Adorn on roof structure, so as to add larger construction loads, there is greatly danger, while lifting rope position can not install dress
Decoration panel, the amount of doing over again are big.
Utility model content
The utility model purpose is to solve the above problems, there is provided a kind of encorbelmented across metal greatly decorates prefabricated roof and height
Empty slipping and assembling structure.
To achieve the above object, the utility model provides a kind of encorbelmented across metal greatly and decorates prefabricated roof and air translation
Splicing structure, it is characterised in that:Including lifting elements block, lift unit block, horizontal sliding cell block, lifting elements block includes dress
Roofing panel, light gauge steel structure, hoisting ring, dilatory ring and alignment connection sheet are adornd, light gauge steel structure is arranged on decoration roofing
Panel back, hoisting ring, dilatory ring, alignment connection sheet are welded on light gauge steel structure, and it is same that lift unit block includes intelligence control
Hoist engine, track cable, lifting hook, electric control box and circuit are walked, electric control box passes through circuit volume synchronous with intelligence control
The machine of raising is connected, and intelligence control synchronous hoister has two, and two intelligence control synchronous hoisters are respectively at one end of a track cable
It is connected, the other end of track cable is provided with bifurcated, and lifting hook is respectively arranged with bifurcated, and horizontal sliding cell block includes intelligence
Synchronous hoister, sliding guide rail, pulley, pull rope, the drawing suspension hook that hangs down, dilatory suspension hook, electric control box and circuit are controlled, pulley is placed
On sliding guide rail, pulley lower end, which is connected with to hang down, draws suspension hook, and draught line is set in parallel among sliding guide rail, the both ends of draught line
An intelligence control synchronous hoister is connected respectively, and intelligence control synchronous hoister is connected by circuit with electric control box, draws suspension hook
It is arranged on pull rope.
It is further described to be connected on across the encorbelment dilatory boxing of decoration prefabricated roof and air translation splicing structure of metal greatly
The centre of light gauge steel structure.
It is further it is described have 4 across the encorbelment hoisting ring of decoration prefabricated roof and air translation splicing structure of metal greatly, 4
Individual hoisting ring is centrosymmetric relative to dilatory ring.
It is further it is described greatly across the encorbelment alignment connection sheet of decoration prefabricated roof and air translation splicing structure of metal be L
Type angle steel, length 5cm, while punching, another side is welded on the both sides of light gauge steel structure, and each two is alignd between connection sheet
Spacing is 1m.
It is further it is described greatly across the encorbelment sliding guide rail of decoration prefabricated roof and air translation splicing structure of metal be two
The steel wire rope that root is horizontally mounted and is parallel to each other.
The beneficial effects of the utility model:This kind greatly across metal encorbelment decoration prefabricated roof and air translation splicing structure with
Prior art is reasonable compared to conceptual design, safe and efficient using preassembling form of construction work, can shorten the duration to greatest extent.Together
The component composition constructing operation system that Shi Liyong hoist engines and steel wire rope etc. are easily installed, it is quick reliable during peace is torn open, make
Valency is cheap, has significant economic benefit.
Brief description of the drawings
Fig. 1 is schematic diagram of the present utility model;
Fig. 2 is lifting elements block schematic diagram of the present utility model;
Fig. 3 is lifting elements block front view of the present utility model;
Fig. 4 is lifting elements block side view of the present utility model;
Fig. 5 is lift unit block schematic diagram of the present utility model;
Fig. 6 is horizontal sliding cell block schematic diagram of the present utility model;
Wherein:1st, roofing panel is decorated, 2, light gauge steel structure, 3, hoisting ring, 4, dilatory ring, 5, alignment connection sheet, 6,
Intelligence control synchronous hoister, 7, track cable, 8, lifting hook, 9, sliding guide rail, 10, pulley, 11, pull rope, 12, drawing of hanging down hangs
Hook, 13, dilatory suspension hook, 14, electric control box, 15, circuit.
Embodiment
The utility model takes following technical scheme to realize:This kind is encorbelmented greatly across metal decorates prefabricated roof and high-altitude cunning
Move splicing structure, including lifting elements block, lift unit block, horizontal sliding cell block.
As shown in Figures 2 to 4, the layout design size for decorating roofing of being encorbelmented according to metal is carried out to decorating roofing panel 1
Segmentation, is divided into a number of calibrated bolck and non-standard piece, then in calibrated bolck and non-standard piece of back side installation lightgage steel joist
Structure 2.In both sides, close to middle 1/4 position a hoisting ring 3 is respectively welded, in lightgage steel joist knot in long side light gauge steel structure 2
The middle part of structure 2, a dilatory ring 4 is welded, welded on the both sides long side lightweight steel construction material of light gauge steel structure 2 at interval of 1m
One alignment connection sheet 5.It is common to decorate roofing panel 1, light gauge steel structure 2, hoisting ring 3, dilatory ring 4 and alignment connection sheet 5
Constitute lifting elements block.
As shown in figure 5, lift unit block includes intelligence control synchronous hoister 6, track cable 7, lifting hook 8, electric-controlled
Case 14 and circuit 15 processed, electric control box 14 are connected by circuit 15 with intelligence control synchronous hoister 6, intelligence control synchronous hoister 6
There are two, two intelligence control synchronous hoisters 6 are connected respectively at one end of a track cable 7, the other end of track cable 7
Bifurcated is provided with, lifting hook 8 is respectively arranged with bifurcated.Intelligence control synchronous hoister is fixed on decoration roof structure top of encorbelmenting.
As shown in fig. 6, horizontal sliding cell block includes intelligence control synchronous hoister 6, sliding guide rail 9, pulley 10, pull rope
11st, hang down and draw suspension hook 12, dilatory suspension hook 13, electric control box 14 and circuit 15, pulley 10 is placed on sliding guide rail 9, pulley 10
Lower end, which is connected with to hang down, draws suspension hook 12, and draught line 11 is set in parallel among sliding guide rail 9, and the both ends of draught line 11 connect one respectively
Platform intelligence control synchronous hoister 6, intelligence control synchronous hoister 6 is connected by circuit 15 with electric control box 14, and dilatory suspension hook 13 is set
Put on pull rope 11.Sliding guide rail is arranged on decoration roof structure bottom of encorbelmenting, and the both ends for sliding guide rail are connected to dress of encorbelmenting
Adorn on roof structure.
As preferred scheme of the present utility model, encorbelmented decoration prefabricated roof and air translation splicing structure across metal greatly
Dilatory ring 4 is welded on the centre of light gauge steel structure 2.
As preferred scheme of the present utility model, encorbelmented decoration prefabricated roof and air translation splicing structure across metal greatly
Hoisting ring 3 has 4, and 4 hoisting rings 3 are centrosymmetric relative to dilatory ring 4.
As preferred scheme of the present utility model, encorbelmented decoration prefabricated roof and air translation splicing structure across metal greatly
Alignment connection sheet 5 is L-type angle steel, and length 5cm, while punching, another side is welded on the both sides of light gauge steel structure 2, each two
Spacing between connection sheet 5 of aliging is 1m.
As preferred scheme of the present utility model, encorbelmented decoration prefabricated roof and air translation splicing structure across metal greatly
Sliding guide rail 9 is two steel wire ropes for being horizontally mounted and being parallel to each other.
4 hoisting rings 3 of the lifting hook 8 in lift unit block above lifting elements block are connected, pass through electricity
Gas control cabinet 14 controls two intelligence control synchronous hoisters 6 in lift unit block that lifting elements block is promoted into horizontal sliding unit
Block sustained height, then vertical drawing suspension hook 12 is connected respectively at 4 hoisting rings 3 on lifting elements block, while by dilatory suspension hook
13 are connected with dilatory ring 4, then control the intelligence control synchronous hoister 6 in lift unit block to invert by electric control box 14,
Lifting elements block is declined certain altitude, draw the stress of suspension hook 12 so that it is guaranteed that hanging down, then untie lifting hook 8, pass through electric-controlled
Intelligence control synchronous hoister 6 in the controlled level sliding element block of case 14 processed drives pull rope 11 to pass through the dilatory dragging of suspension hook 13 lifting
Cell block horizontal sliding is to construction location.Then lifting elements block is fixedly mounted on and encorbelmented by electric welding and bolt by operating personnel
Decorate on roof structure, adjacent lifting elements by connection sheet 5 of aliging fasten levelling by last worker by bolt.
Electric control box 14 is powered by external power supply.
This kind is encorbelmented greatly across metal decorates prefabricated roof and air translation splicing structure conceptual design compared with prior art
Rationally, it is safe and efficient using preassembling form of construction work, the duration can be shortened to greatest extent.Utilize hoist engine and steel wire rope simultaneously
Constructing operation system is formed etc. the component being easily installed, it is quick reliable during peace is torn open, it is cheap, have significant economical
Benefit.
Preferred embodiment of the present utility model described in detail above.It should be appreciated that the ordinary skill people of this area
Member makes many modifications and variations without creative work can according to design of the present utility model.Therefore, all this technology necks
Technical staff passes through logic analysis, reasoning or limited reality on the basis of existing technology according to design of the present utility model in domain
Available technical scheme is tested, all should be in the protection domain being defined in the patent claims.
Claims (5)
1. a kind of encorbelmented across metal greatly decorates prefabricated roof and air translation splicing structure, it is characterised in that:Including lifting elements
Block, lift unit block, horizontal sliding cell block, lifting elements block include decoration roofing panel, light gauge steel structure, hoisting ring,
Dilatory ring and alignment connection sheet, light gauge steel structure are arranged on decoration roofing surface backboard portion, hoisting ring, dilatory ring, alignment connection
Piece is welded on light gauge steel structure, and lift unit block includes intelligence control synchronous hoister, track cable, lifting hook, electricity
Gas control cabinet and circuit, electric control box are connected by circuit with intelligence control synchronous hoister, and intelligence control synchronous hoister has two,
Two intelligence control synchronous hoisters are connected respectively at one end of a track cable, and the other end of track cable is provided with bifurcated,
Lifting hook is respectively arranged with bifurcated, horizontal sliding cell block includes intelligence control synchronous hoister, sliding guide rail, pulley, traction
Rope, hang down and draw suspension hook, dilatory suspension hook, electric control box and circuit, pulley is placed on sliding guide rail, and pulley lower end is connected with vertical drawing
Suspension hook, draught line are set in parallel among sliding guide rail, and the both ends of draught line connect an intelligence control synchronous hoister, intelligence control respectively
Synchronous hoister is connected by circuit with electric control box, and dilatory suspension hook is arranged on pull rope.
2. it is according to claim 1 greatly across metal encorbelment decoration prefabricated roof and air translation splicing structure, its feature exist
In:Dilatory boxing is connected on the centre of light gauge steel structure.
3. it is according to claim 1 greatly across metal encorbelment decoration prefabricated roof and air translation splicing structure, its feature exist
In:Hoisting ring has 4, and 4 hoisting rings are centrosymmetric relative to dilatory ring.
4. it is according to claim 1 greatly across metal encorbelment decoration prefabricated roof and air translation splicing structure, its feature exist
In:Alignment connection sheet is L-type angle steel, and length 5cm, while punching, another side is welded on the both sides of light gauge steel structure, each two
Spacing between connection sheet of aliging is 1m.
5. it is according to claim 1 greatly across metal encorbelment decoration prefabricated roof and air translation splicing structure, its feature exist
In:Sliding guide rail is two steel wire ropes for being horizontally mounted and being parallel to each other.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720560861.4U CN206784958U (en) | 2017-05-19 | 2017-05-19 | A kind of encorbelmented across metal greatly decorates prefabricated roof and air translation splicing structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720560861.4U CN206784958U (en) | 2017-05-19 | 2017-05-19 | A kind of encorbelmented across metal greatly decorates prefabricated roof and air translation splicing structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206784958U true CN206784958U (en) | 2017-12-22 |
Family
ID=60712768
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720560861.4U Active CN206784958U (en) | 2017-05-19 | 2017-05-19 | A kind of encorbelmented across metal greatly decorates prefabricated roof and air translation splicing structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206784958U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110284711A (en) * | 2019-05-21 | 2019-09-27 | 中国华冶科工集团有限公司 | The high vacant duct auxiliary positioning apparatus of heavy caliber and in-position installation method |
CN111593894A (en) * | 2019-02-21 | 2020-08-28 | 武汉凌云建筑装饰工程有限公司 | High altitude platform suspended ceiling system |
CN116427713A (en) * | 2023-05-20 | 2023-07-14 | 中建八局第四建设有限公司 | Horizontal movement lifting method |
-
2017
- 2017-05-19 CN CN201720560861.4U patent/CN206784958U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111593894A (en) * | 2019-02-21 | 2020-08-28 | 武汉凌云建筑装饰工程有限公司 | High altitude platform suspended ceiling system |
CN110284711A (en) * | 2019-05-21 | 2019-09-27 | 中国华冶科工集团有限公司 | The high vacant duct auxiliary positioning apparatus of heavy caliber and in-position installation method |
CN116427713A (en) * | 2023-05-20 | 2023-07-14 | 中建八局第四建设有限公司 | Horizontal movement lifting method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103086279B (en) | Vertical transportation construction method for building construction | |
CN206784958U (en) | A kind of encorbelmented across metal greatly decorates prefabricated roof and air translation splicing structure | |
CN103603504B (en) | The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction | |
CN109502480A (en) | The hoisting that high building turns over | |
CN105226560B (en) | A kind of crossing frame and its construction method | |
CN107700719A (en) | A kind of hanging method of high-rise building glass curtain wall | |
CN113137054A (en) | Method for setting inverted hoisting power equipment in attached lifting scaffold | |
CN106150057B (en) | A kind of split blade type hydraulic pressure lift climbing frame | |
CN205429566U (en) | Crossing structure | |
CN105256728A (en) | Cable-stayed bridge warren steel truss cantilever erection method | |
CN105464456A (en) | Method and lifting sling for assembling extra-high voltage transmission iron tower through helicopter | |
CN113335475B (en) | Deck bottom fixed pulley sliding platform dismantling process | |
CN107060347A (en) | A kind of big encorbelmented across metal decorates prefabricated roof and air translation splicing structure | |
CN201531111U (en) | Movable hanging basket for installing and decorating curtain walls | |
CN104153586A (en) | Construction method for installing purline through suspension cable cranes | |
CN201325826Y (en) | Rock anchor beam hoisting device for underground power house | |
CN202441045U (en) | Rail-type electric attached lifting scaffold | |
CN109378767A (en) | A kind of lifting engineering method of hoist engine to skyscraper electricity well inner cable | |
CN207553565U (en) | A kind of crosshead of truss | |
CN205662256U (en) | High rises pergola side and hangs a semi -portal bridge crane | |
CN105155427A (en) | Construction method for laying suspension bridge catwalk | |
CN106968371B (en) | A kind of construction method of the high wing articulated structure drifted by wind of curtain wall construction | |
CN211006334U (en) | Maintenance equipment for inner side surface of inverted Y-shaped tower column of three-way movable cable-stayed bridge | |
CN203499232U (en) | Attached lifting scaffold | |
CN208980193U (en) | The curtain wall hanging apparatus of anticollision |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||