CN107060347A - A kind of big encorbelmented across metal decorates prefabricated roof and air translation splicing structure - Google Patents

A kind of big encorbelmented across metal decorates prefabricated roof and air translation splicing structure Download PDF

Info

Publication number
CN107060347A
CN107060347A CN201710356617.0A CN201710356617A CN107060347A CN 107060347 A CN107060347 A CN 107060347A CN 201710356617 A CN201710356617 A CN 201710356617A CN 107060347 A CN107060347 A CN 107060347A
Authority
CN
China
Prior art keywords
big
encorbelmented
prefabricated roof
splicing structure
metal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710356617.0A
Other languages
Chinese (zh)
Inventor
吕伟才
刘昌平
兰云睆
鲁少虎
孙常力
向伟
于金生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Original Assignee
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Engineering Co Ltd of China Construction Third Engineering Division filed Critical Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority to CN201710356617.0A priority Critical patent/CN107060347A/en
Publication of CN107060347A publication Critical patent/CN107060347A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/167Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to technical field of building construction, and in particular to a kind of big encorbelmented across metal decorates prefabricated roof and air translation splicing structure.It is this kind big to encorbelment decoration prefabricated roof across metal and air translation splicing structure includes lifting elements block, lift unit block, horizontal sliding cell block.It is this kind big to encorbelment that conceptual design is rationally, safe and efficient using preassembling form of construction work compared with prior art for decoration prefabricated roof and air translation splicing structure across metal, the duration can be shortened to greatest extent.The component being easily installed simultaneously using hoist engine and steel wire rope etc. constitutes constructing operation system, quick reliable during peace is torn open, cheap, with significant economic benefit.

Description

A kind of big encorbelmented across metal decorates prefabricated roof and air translation splicing structure
Technical field
The present invention relates to technical field of building construction, and in particular to a kind of big encorbelmented across metal decorates prefabricated roof and air translation Splicing structure.
Background technology
Fast development and the growing tension of urban land resource with building technology, multi-rise building quantity are just all with day Increase, wherein a large amount of Long-span Cantilever roof structure systems designed by practical performance or pursuit visual effect are occurred in that, because The particularity of this Long-span Cantilever roof structure system, its extraneous adornment often uses metal finishing roofing, so as to reach reality With and design effect, and the design of this Long-span Cantilever metal finishing roofing system often gives construction band huge challenge.
Mainly there are three kinds of forms of construction work currently for the construction of this Long-span Cantilever metal finishing roofing system, the first It is that, for tier building, using full hall scaffold form of construction work, that is, it is the scaffold of size of encorbelmenting to set up width, highly for from ground Face to the scope of operation height;Be for second for multi-rise building, using builder's jack form of construction work, i.e., the structure under the scope of operation Layer is using I-steel as primary structure member of encorbelmenting, and it is the scaffold of size of encorbelmenting to set up width, is highly plane of encorbelmenting to operation The height in face;The third is, for multi-rise building, using nacelle construction, i.e., hanging basket to be set immediately below construction location, by structure Part is placed on lifting in hanging basket and arrives operation surface construction.
Form of construction work of the prior art mainly has following deficiency:First, prior art is in situ assembled using high-altitude, component It is many, install complicated, easily cause component and fall, with great potential safety hazard.2nd, make when using full hall scaffold form of construction work Long in time limit, it is necessary to which substantial amounts of manpower sets up scaffold during industry, cost is big, and with the increase of support body height, security performance Also decrease.3rd, it is necessary to which substantial amounts of I-steel is used as suspension scaffold beaer when using builder's jack form of construction work operation System, required I-steel quantity is big, and cost is high, and I-steel handling is heavy, it is necessary to the longer duration, while there is also great peace Full hidden danger.4th, when using nacelle construction mode when because hanging basket can only vertically operation, it is necessary to hang a large amount of hanging baskets in dress of encorbelmenting Adorn on roof structure, so that larger construction loads is added, with great danger, while lifting rope position can not install dress Decoration panel, the amount of doing over again is big.
The content of the invention
Present invention aims at solve the above problems to decorate prefabricated roof and high-altitude cunning there is provided a kind of big encorbelment across metal Move splicing structure.
To achieve the above object, prefabricated roof and air translation assembly are decorated the invention provides a kind of big encorbelmented across metal Structure, it is characterised in that:Including lifting elements block, lift unit block, horizontal sliding cell block, lifting elements block includes decoration room Faceplate panels, light gauge steel structure, hoisting ring, dilatory ring and alignment connection sheet, light gauge steel structure are arranged on decoration roofing panel Back, hoisting ring, dilatory ring, alignment connection sheet are welded on light gauge steel structure, and lift unit block includes intelligence control and synchronously rolled up Machine, track cable, lifting hook, electric control box and circuit are raised, electric control box passes through circuit and intelligence control synchronous hoister It is connected, intelligence control synchronous hoister there are two, and two intelligence control synchronous hoisters are connected respectively at one end of a track cable, The other end of track cable, which is provided with bifurcated, bifurcated, is respectively arranged with lifting hook, and it is same that horizontal sliding cell block includes intelligence control Hoist engine, sliding guide rail, pulley, pull rope, the drawing suspension hook that hangs down, dilatory suspension hook, electric control box and circuit are walked, pulley is placed on cunning Move on guide rail, pulley lower end, which is connected with to hang down, draws suspension hook, and draught line is set in parallel in the middle of sliding guide rail, the two ends difference of draught line An intelligence control synchronous hoister is connected, intelligence control synchronous hoister is connected by circuit with electric control box, draw suspension hook and set On pull rope.
It is further described big to be connected on across the encorbelment dilatory boxing of decoration prefabricated roof and air translation splicing structure of metal The centre of light gauge steel structure.
Further described big have 4,4 across the encorbelment hoisting ring of decoration prefabricated roof and air translation splicing structure of metal Individual hoisting ring is centrosymmetric relative to dilatory ring.
Further big encorbelmented across metal decorates the alignment connection sheet of prefabricated roof and air translation splicing structure for L Type angle steel, length 5cm, while punching, another side is welded between the both sides of light gauge steel structure, each two alignment connection sheet Spacing is 1m.
It is further it is described it is big across the encorbelment sliding guide rail of decoration prefabricated roof and air translation splicing structure of metal be two The steel wire rope that root is horizontally mounted and is parallel to each other.
Beneficial effects of the present invention:It is this kind big across metal encorbelment decoration prefabricated roof and air translation splicing structure with it is existing Technology is compared to conceptual design rationally, safe and efficient using preassembling form of construction work, can shorten the duration to greatest extent.It is simultaneously sharp The component being easily installed with hoist engine and steel wire rope etc. constitutes constructing operation system, quick reliable during peace is torn open, low cost It is honest and clean, with significant economic benefit.
Brief description of the drawings
Fig. 1 is schematic diagram of the invention;
Fig. 2 is lifting elements block schematic diagram of the invention;
Fig. 3 is lifting elements block front view of the invention;
Fig. 4 is lifting elements block side view of the invention;
Fig. 5 is lift unit block schematic diagram of the invention;
Fig. 6 is horizontal sliding cell block schematic diagram of the invention;
Wherein:1st, roofing panel is decorated, 2, light gauge steel structure, 3, hoisting ring, 4, dilatory ring, 5, alignment connection sheet, 6, intelligence control Synchronous hoister, 7, track cable, 8, lifting hook, 9, sliding guide rail, 10, pulley, 11, pull rope, 12, hang down and draw suspension hook, 13rd, suspension hook is drawn, 14, electric control box, 15, circuit.
Embodiment
The present invention takes following technical scheme to realize:This kind big encorbelmented across metal decorates prefabricated roof and air translation spelling Assembling structure, including lifting elements block, lift unit block, horizontal sliding cell block.
As shown in Figures 2 to 4, the layout design size for decorating roofing of being encorbelmented according to metal is carried out to decorating roofing panel 1 Segmentation, is divided into a number of calibrated bolck and non-standard piece, then installs lightgage steel joist in calibrated bolck and the non-standard piece of back side Structure 2.In both sides, close to middle 1/4 position a hoisting ring 3 is respectively welded, in lightgage steel joist knot in long side light gauge steel structure 2 The middle part of structure 2, welds a dilatory ring 4, is welded on the long side lightweight steel construction material in the both sides of light gauge steel structure 2 at interval of 1m One alignment connection sheet 5.Decorate roofing panel 1, light gauge steel structure 2, hoisting ring 3, dilatory ring 4 and alignment connection sheet 5 common Constitute lifting elements block.
As shown in figure 5, lift unit block includes intelligence control synchronous hoister 6, track cable 7, lifting hook 8, electric-controlled Case 14 and circuit 15 processed, electric control box 14 are connected by circuit 15 with intelligence control synchronous hoister 6, intelligence control synchronous hoister 6 There are two, two intelligence control synchronous hoisters 6 are connected respectively at one end of a track cable 7, the other end of track cable 7 It is provided with bifurcated, bifurcated and is respectively arranged with lifting hook 8.Intelligence control synchronous hoister is fixed on decoration roof structure top of encorbelmenting.
As shown in fig. 6, horizontal sliding cell block includes intelligence control synchronous hoister 6, sliding guide rail 9, pulley 10, pull rope 11st, hang down and draw suspension hook 12, dilatory suspension hook 13, electric control box 14 and circuit 15, pulley 10 is placed on sliding guide rail 9, pulley 10 Lower end, which is connected with to hang down, draws suspension hook 12, and draught line 11 is set in parallel in the middle of sliding guide rail 9, and the two ends of draught line 11 connect one respectively Platform intelligence control synchronous hoister 6, intelligence control synchronous hoister 6 is connected by circuit 15 with electric control box 14, and dilatory suspension hook 13 is set Put on pull rope 11.Sliding guide rail is arranged on decoration roof structure bottom of encorbelmenting, and the two ends of sliding guide rail are connected to dress of encorbelmenting Adorn on roof structure.
As the preferred scheme of the present invention, encorbelmented the dilatory of decoration prefabricated roof and air translation splicing structure across metal greatly Ring 4 is welded on the centre of light gauge steel structure 2.
It is used as the preferred scheme of the present invention, the lifting of encorbelmented across metal greatly decoration prefabricated roof and air translation splicing structure Ring 3 has 4, and 4 hoisting rings 3 are centrosymmetric relative to dilatory ring 4.
It is used as the preferred scheme of the present invention, the alignment of encorbelmented across metal greatly decoration prefabricated roof and air translation splicing structure Connection sheet 5 is L-type angle steel, length 5cm, while punching, another side is welded on the both sides of light gauge steel structure 2, each two alignment Spacing between connection sheet 5 is 1m.
It is used as the preferred scheme of the present invention, the sliding of encorbelmented across metal greatly decoration prefabricated roof and air translation splicing structure Guide rail 9 is two steel wire ropes for being horizontally mounted and being parallel to each other.
4 hoisting rings 3 of the lifting hook 8 in lift unit block above lifting elements block are connected, pass through electricity Lifting elements block is promoted to horizontal sliding unit by two intelligence control synchronous hoisters 6 in the control lift unit block of gas control cabinet 14 Block sustained height, then connects vertical drawing suspension hook 12 respectively at 4 hoisting rings 3 on lifting elements block, while by dilatory suspension hook 13 are connected with dilatory ring 4, then control the intelligence control synchronous hoister 6 in lift unit block to invert by electric control box 14, Lifting elements block is declined certain altitude, draw the stress of suspension hook 12 so that it is guaranteed that hanging down, then untie lifting hook 8, pass through electric-controlled Intelligence control synchronous hoister 6 in the controlled level sliding element block of case 14 processed drives pull rope 11 to be lifted by the dilatory dragging of suspension hook 13 Cell block horizontal sliding is to construction location.Then lifting elements block is fixedly mounted on and encorbelmented by electric welding and bolt by operating personnel Decorate on roof structure, it is levelling that adjacent lifting elements are carried out fastening by last workman by bolt by connection sheet 5 of aliging.
Electric control box 14 is powered by external power supply.
This kind big encorbelmented across metal decorates prefabricated roof and air translation splicing structure conceptual design compared with prior art Rationally, it is safe and efficient using preassembling form of construction work, the duration can be shortened to greatest extent.Hoist engine and steel wire rope are utilized simultaneously Constructing operation system is constituted etc. the component being easily installed, it is quick reliable during peace is torn open, it is cheap, with significant economy Benefit.
Preferred embodiment of the invention described in detail above.It should be appreciated that one of ordinary skill in the art without Need creative work just can make many modifications and variations according to the design of the present invention.Therefore, all technologies in the art Personnel are available by logical analysis, reasoning, or a limited experiment on the basis of existing technology under this invention's idea Technical scheme, all should be in the protection domain being defined in the patent claims.

Claims (5)

1. a kind of big encorbelmented across metal decorates prefabricated roof and air translation splicing structure, it is characterised in that:Including lifting elements Block, lift unit block, horizontal sliding cell block, lifting elements block include decoration roofing panel, light gauge steel structure, hoisting ring, Dilatory ring and alignment connection sheet, light gauge steel structure are arranged on decoration roofing surface backboard portion, hoisting ring, dilatory ring, alignment connection Piece is welded on light gauge steel structure, and lift unit block includes intelligence control synchronous hoister, track cable, lifting hook, electricity Gas control cabinet and circuit, electric control box are connected by circuit with intelligence control synchronous hoister, and intelligence control synchronous hoister has two, Two intelligence control synchronous hoisters are connected respectively at one end of a track cable, and the other end of track cable is provided with bifurcated, Lifting hook is respectively arranged with bifurcated, horizontal sliding cell block includes intelligence control synchronous hoister, sliding guide rail, pulley, traction Rope, the drawing suspension hook that hangs down, dilatory suspension hook, electric control box and circuit, pulley are placed on sliding guide rail, and pulley lower end is connected with vertical drawing Suspension hook, draught line is set in parallel in the middle of sliding guide rail, and the two ends of draught line connect an intelligence control synchronous hoister, intelligence control respectively Synchronous hoister is connected by circuit with electric control box, and dilatory suspension hook is arranged on pull rope.
2. big encorbelmented across metal according to claim 1 decorates prefabricated roof and air translation splicing structure, its feature exists In:Dilatory boxing is connected on the centre of light gauge steel structure.
3. big encorbelmented across metal according to claim 1 decorates prefabricated roof and air translation splicing structure, its feature exists In:Hoisting ring has 4, and 4 hoisting rings are centrosymmetric relative to dilatory ring.
4. big encorbelmented across metal according to claim 1 decorates prefabricated roof and air translation splicing structure, its feature exists In:Alignment connection sheet be L-type angle steel, length 5cm, on one side punch, another side is welded on the both sides of light gauge steel structure, each two Spacing between connection sheet of aliging is 1m.
5. big encorbelmented across metal according to claim 1 decorates prefabricated roof and air translation splicing structure, its feature exists In:Sliding guide rail is two steel wire ropes for being horizontally mounted and being parallel to each other.
CN201710356617.0A 2017-05-19 2017-05-19 A kind of big encorbelmented across metal decorates prefabricated roof and air translation splicing structure Pending CN107060347A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710356617.0A CN107060347A (en) 2017-05-19 2017-05-19 A kind of big encorbelmented across metal decorates prefabricated roof and air translation splicing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710356617.0A CN107060347A (en) 2017-05-19 2017-05-19 A kind of big encorbelmented across metal decorates prefabricated roof and air translation splicing structure

Publications (1)

Publication Number Publication Date
CN107060347A true CN107060347A (en) 2017-08-18

Family

ID=59610287

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710356617.0A Pending CN107060347A (en) 2017-05-19 2017-05-19 A kind of big encorbelmented across metal decorates prefabricated roof and air translation splicing structure

Country Status (1)

Country Link
CN (1) CN107060347A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112942795A (en) * 2021-02-04 2021-06-11 广东世纪达建设集团有限公司 Flying wing curtain wall and roof steel structure decoration line construction method
CN114000635A (en) * 2021-11-12 2022-02-01 中铁建工集团有限公司 Assembly process based on metal roof framework sliding installation

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2355021A1 (en) * 1972-11-07 1974-05-16 Lely Nv C Van Der CONSTRUCTION CRANE, IN PARTICULAR CABLE CRANE, FOR THE ASSEMBLY OF A BUILDING MADE FROM PREFABRICATED ROOM BOXES
JPH0776932A (en) * 1993-09-07 1995-03-20 Kajima Corp Method of attaching wall member
JPH08170436A (en) * 1994-12-20 1996-07-02 Hitachi Ltd Method for constructing plant and construction facility
CN2727273Y (en) * 2004-08-27 2005-09-21 于国杰 Large-span hoisting beam structure
KR20090102047A (en) * 2008-03-25 2009-09-30 김지욱 Construction apparatus and installation method using it

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2355021A1 (en) * 1972-11-07 1974-05-16 Lely Nv C Van Der CONSTRUCTION CRANE, IN PARTICULAR CABLE CRANE, FOR THE ASSEMBLY OF A BUILDING MADE FROM PREFABRICATED ROOM BOXES
JPH0776932A (en) * 1993-09-07 1995-03-20 Kajima Corp Method of attaching wall member
JPH08170436A (en) * 1994-12-20 1996-07-02 Hitachi Ltd Method for constructing plant and construction facility
CN2727273Y (en) * 2004-08-27 2005-09-21 于国杰 Large-span hoisting beam structure
KR20090102047A (en) * 2008-03-25 2009-09-30 김지욱 Construction apparatus and installation method using it

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112942795A (en) * 2021-02-04 2021-06-11 广东世纪达建设集团有限公司 Flying wing curtain wall and roof steel structure decoration line construction method
CN114000635A (en) * 2021-11-12 2022-02-01 中铁建工集团有限公司 Assembly process based on metal roof framework sliding installation
CN114000635B (en) * 2021-11-12 2022-11-15 中铁建工集团有限公司 Assembly process based on metal roof framework sliding installation

Similar Documents

Publication Publication Date Title
CN106894342B (en) Pipe installing job platform and construction method
CN103603504B (en) The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction
CN204899184U (en) Hanging flower basket equipment
CN206784958U (en) A kind of encorbelmented across metal greatly decorates prefabricated roof and air translation splicing structure
CN109653484B (en) Roofing superelevation faces external hanging flower basket mounting structure of empty curtain engineering
CN106150057B (en) A kind of split blade type hydraulic pressure lift climbing frame
CN113137054A (en) Method for setting inverted hoisting power equipment in attached lifting scaffold
CN105256728A (en) Cable-stayed bridge warren steel truss cantilever erection method
CN107060347A (en) A kind of big encorbelmented across metal decorates prefabricated roof and air translation splicing structure
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN205637622U (en) Perpendicular unit glass curtain wall hoist and mount system
CN202658867U (en) Overhanging construction platform
CN109378767A (en) A kind of lifting engineering method of hoist engine to skyscraper electricity well inner cable
CN203475801U (en) Telescopic steel platform for elevator shaft
CN206720680U (en) A kind of roofing color corrugated sheet steel lifting device
CN205662256U (en) High rises pergola side and hangs a semi -portal bridge crane
CN105155427A (en) Construction method for laying suspension bridge catwalk
CN209397505U (en) One kind being used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device
CN210563326U (en) Overhead unit type overhead sliding splicing operation platform
CN208980193U (en) The curtain wall hanging apparatus of anticollision
CN103470057A (en) Method of hoisting high altitude components
CN203229334U (en) Lifting framework for lifting and translating single steel member
CN105155832A (en) Hanging basket device and moving method thereof
CN205604461U (en) Large tracts of land steel space frame single tube dead man crowd coordinated control synchronous lifting system
CN206088946U (en) A integrally lift up displacement device for unsettled steel gallery of large -span

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170818

RJ01 Rejection of invention patent application after publication