CN209397505U - One kind being used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device - Google Patents

One kind being used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device Download PDF

Info

Publication number
CN209397505U
CN209397505U CN201822044388.1U CN201822044388U CN209397505U CN 209397505 U CN209397505 U CN 209397505U CN 201822044388 U CN201822044388 U CN 201822044388U CN 209397505 U CN209397505 U CN 209397505U
Authority
CN
China
Prior art keywords
truss
bailey beam
hanger
beam truss
bailey
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822044388.1U
Other languages
Chinese (zh)
Inventor
骆国建
徐建宁
曾凡福
卢池
马欣
陈慧
党宏斌
苏本林
赵恒�
白利勇
孙学帅
魏莹飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Engineering Group Co Ltd
Xiamen Construction Engineering Co Ltd of of China Railway First Engineering Group Co Ltd
Original Assignee
China Railway First Engineering Group Co Ltd
Xiamen Construction Engineering Co Ltd of of China Railway First Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Engineering Group Co Ltd, Xiamen Construction Engineering Co Ltd of of China Railway First Engineering Group Co Ltd filed Critical China Railway First Engineering Group Co Ltd
Priority to CN201822044388.1U priority Critical patent/CN209397505U/en
Application granted granted Critical
Publication of CN209397505U publication Critical patent/CN209397505U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses one kind to be used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device, including Bailey beam truss, hanger spandrel girder and lip block for carrying bridge floor beam, the Bailey beam truss is in the frame structure of rectangle, the Bailey beam truss is horizontally arranged and its top surface formation operation table top, the hanger spandrel girder is four and is evenly distributed on four corners of the Bailey beam truss, the hanger spandrel girder and the Bailey beam truss are interspersed together, the lip block is at least four and is uniformly arranged on the middle part of the operating table surface, the operating table surface is surrounded by protective fence.It is mounted using the cable of cable crane and the hanger spandrel girder of Bailey beam truss surrounding, Bailey beam truss and bridge floor beam are sling movement by cable crane, action is convenient, and in moving process, operator can install the hoist cable of bridge floor beam in the operating table surface of Bailey beam truss, save construction duration.

Description

One kind being used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device
Technical field
The utility model relates to one kind to be used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device.
Background technique
Bridge floor beam and hoist cable not only inefficiency are installed in high-altitude, but also security risk is high, therefore most construction party at present For case using hanger installation bridge floor beam and hoist cable, this just needs to be arranged on hoisting platform a hoisting of deck beam and hoist cable installation dress It sets.Since the length of each bridge floor girder segment and the installation site of hoist cable are not quite similar, traditional hanger is not able to satisfy bridge floor beam Stability problem and process quick joining problem during the installation process;Simultaneously because hoisting platform majority is arranged in main bridge steel arch The lower section of rib, is restricted by space factor, the hoisting platform narrow field of bridge floor beam, can only place a lifting segment every time. Therefore under construction condition, transhipment number in installation segment is more, and hanging apparatus cannot rest on steel girder erection position for a long time, And since hoist cable installation procedure is complex, need first to install hoist cable to the anchored end of bridge floor beam before girder steel lifts by crane, apply It is long between working hour, low efficiency.
Utility model content
The utility model provides one kind for loading test of half-through CFST arch bridge hoisting of deck beam mounting device, overcomes Deficiency present in background technique.The technical scheme adopted by the utility model to solve the technical problem is as follows:
One kind being used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device, including Bailey beam truss, hanger are held Weight beam and the lip block for carrying bridge floor beam, the Bailey beam truss are in the frame structure of rectangle, the Bailey beam truss Horizontal positioned and its top surface formation operation table top, the hanger spandrel girder are four and are evenly distributed on the Bailey beam truss Four corners, the hanger spandrel girder and the Bailey beam truss are interspersed together, and the lip block is at least four simultaneously It is uniformly arranged on the middle part of the operating table surface, the operating table surface is surrounded by protective fence, and the protective fence is connected to institute It states on Bailey beam truss.
Among one preferred embodiment: the left side of the Bailey beam truss includes three groups of parallel beret slices, the shellfish thunder The right edge of beam truss includes three groups of parallel beret slices, passes through beret slice between the left side and right edge of the thunder beam truss It links together.
Among one preferred embodiment: the lip block interlocking is on the Bailey beam truss.
Among one preferred embodiment: the both ends of the hanger spandrel girder extend through setting suspension shaft.
The technical program compared with the background art, it has the following advantages:
1. bridge floor beam is placed on lip block, held using the cable of cable crane and the hanger of Bailey beam truss surrounding Bailey beam truss and bridge floor beam are sling movement by weight beam mounting, cable crane, and action is convenient, and in moving process, behaviour The hoist cable of bridge floor beam can be installed in the operating table surface of Bailey beam truss by making personnel, save construction duration.Bridge floor beam Hoisting platform can be returned back to after being installed, is other processes slot milling, be especially suitable for narrow and small place and used.To sum up institute It states, the utility model simple structure and reasonable design meets lifting requirements, be especially suitable for narrow, it can be achieved that mounting device overall movement Small place uses the hoist cable, it can be achieved that preceding installation bridge floor beam anchored end, time saving and energy saving, easy to use and operate, practical, uses Effect is good, convenient for promoting the use of.
Detailed description of the invention
The utility model is described in further detail with reference to the accompanying drawings and examples.
Fig. 1 depicts the side view for loading test of half-through CFST arch bridge hoisting of deck beam mounting device.
Fig. 2 depicts the top view for loading test of half-through CFST arch bridge hoisting of deck beam mounting device.
Specific embodiment
Referring to Fig.1 and 2, being used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device, including Bailey beam Truss 10, hanger spandrel girder 20 and the lip block 30 for carrying bridge floor beam.The Bailey beam truss 10 is in the frame of rectangle Structure, the Bailey beam truss 10 is horizontally arranged and its top surface formation operation table top.The lip block 30 is at least four And it is uniformly arranged on the middle part of the operating table surface, the operating table surface is surrounded by protective fence 40, and the protective fence 40 connects It connects on the Bailey beam truss 10.The hanger spandrel girder 20 is four and is evenly distributed on the four of the Bailey beam truss 10 A corner, the hanger spandrel girder 20 are interspersed together with the Bailey beam truss 10.
When construction, bridge floor beam 001 is placed on lip block 30, and the cable of cable crane and four hanger spandrel girders 20 are hung It connects, during lifting, construction personnel can carry out installation operation to the hoist cable of bridge floor beam 001 simultaneously in operating table surface.
The both ends of the hanger spandrel girder 20 extend through setting suspension shaft 22, are mounted for convenient and cable.
The left side of the Bailey beam truss 10 includes three groups of parallel beret slices 11, the right edge of the Bailey beam truss Including three groups of parallel beret slices 12, one is connected to by beret slice 13 between the left side and right edge of the thunder beam truss It rises.
30 interlocking of lip block is on the Bailey beam truss 10.
The above, only the utility model preferred embodiment, therefore, it cannot be limited according to, and the utility model is implemented It is practical new to should still belong to this for range, i.e., equivalent changes and modifications made according to the scope of the patent of the utility model and the content of the manual In the range of type covers.

Claims (4)

1. one kind is used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device, it is characterised in that: including Bailey beam purlin Frame, hanger spandrel girder and the lip block for carrying bridge floor beam, the Bailey beam truss are in the frame structure of rectangle, the shellfish Thunder beam truss is horizontal positioned and its top surface formation operation table top, the hanger spandrel girder are four and are evenly distributed on the shellfish Four corners of thunder beam truss, the hanger spandrel girder and the Bailey beam truss are interspersed together, and the lip block is at least It is four and is uniformly arranged on the middle part of the operating table surface, the operating table surface is surrounded by protective fence, the protective fence It is connected on the Bailey beam truss.
2. hoisting of deck beam mounting device according to claim 1, it is characterised in that: the left side of the Bailey beam truss Including three groups of parallel beret slices, the right edge of the Bailey beam truss includes three groups of parallel beret slices, the thunder beam truss Left side and right edge between linked together by beret slice.
3. hoisting of deck beam mounting device according to claim 1, it is characterised in that: the lip block interlocking is described On Bailey beam truss.
4. hoisting of deck beam mounting device according to claim 1 or 2 or 3, it is characterised in that: the hanger spandrel girder Both ends extend through setting suspension shaft.
CN201822044388.1U 2018-12-06 2018-12-06 One kind being used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device Active CN209397505U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822044388.1U CN209397505U (en) 2018-12-06 2018-12-06 One kind being used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822044388.1U CN209397505U (en) 2018-12-06 2018-12-06 One kind being used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device

Publications (1)

Publication Number Publication Date
CN209397505U true CN209397505U (en) 2019-09-17

Family

ID=67881876

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822044388.1U Active CN209397505U (en) 2018-12-06 2018-12-06 One kind being used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device

Country Status (1)

Country Link
CN (1) CN209397505U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111254831A (en) * 2020-01-20 2020-06-09 中铁大桥局第七工程有限公司 Hoisting method of steel structure frame beam of through arch bridge

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111254831A (en) * 2020-01-20 2020-06-09 中铁大桥局第七工程有限公司 Hoisting method of steel structure frame beam of through arch bridge
CN111254831B (en) * 2020-01-20 2021-05-14 中铁大桥局第七工程有限公司 Hoisting method of steel structure frame beam of through arch bridge

Similar Documents

Publication Publication Date Title
CN105822072A (en) Hoisting construction structure and method for air corridor ceiling
CN203820281U (en) Hanger for prefabricating building component pulley block
CN206580442U (en) A kind of hanging apparatus suitable for Assembled Building gangboard prefabricated components
CN209397505U (en) One kind being used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device
CN106013453B (en) Long-span Cantilever transfinites structure construction engineering method
CN203794533U (en) Light portable mobile lifting equipment
CN207700708U (en) A kind of shellring shape ceiling mounted tracks of unit glass curtain wall
CN207890900U (en) Large-scale girder steel hoist and mount, stand up and use fixture
CN209353734U (en) For installing the double-track device of curtain wall
CN202441045U (en) Rail-type electric attached lifting scaffold
CN207277197U (en) A kind of operating platform suitable for the installation of high pier Wavelike steel webplate cantilever
CN206784958U (en) A kind of encorbelmented across metal greatly decorates prefabricated roof and air translation splicing structure
CN206720680U (en) A kind of roofing color corrugated sheet steel lifting device
CN107060347A (en) A kind of big encorbelmented across metal decorates prefabricated roof and air translation splicing structure
CN205662256U (en) High rises pergola side and hangs a semi -portal bridge crane
CN209723565U (en) Attached tower crane attachment construction operation platform outside a kind of steel-core wall structure
CN209583455U (en) A kind of outdoor handling machine for building
CN203499232U (en) Attached lifting scaffold
CN210239089U (en) Aluminum plate curtain wall superelevation furred ceiling work platform
CN208684250U (en) One kind being based on the quick detachable boom hoisting of major structure of construction
CN206751210U (en) The multi-thread boom hoisting of shiftable track
CN205857750U (en) A kind of lifter bearing for large-scale component Synchronous lifting sliding
CN205857749U (en) A kind of overall sliding and lifting device of the structure that transfinites for Long-span Cantilever
CN219217261U (en) Special scissors formula diagonal sling of prefabricated component
CN206088946U (en) A integrally lift up displacement device for unsettled steel gallery of large -span

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant