CN206751210U - The multi-thread boom hoisting of shiftable track - Google Patents
The multi-thread boom hoisting of shiftable track Download PDFInfo
- Publication number
- CN206751210U CN206751210U CN201621341444.2U CN201621341444U CN206751210U CN 206751210 U CN206751210 U CN 206751210U CN 201621341444 U CN201621341444 U CN 201621341444U CN 206751210 U CN206751210 U CN 206751210U
- Authority
- CN
- China
- Prior art keywords
- track
- shiftable track
- shiftable
- electric hoist
- hoisting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A kind of multi-thread boom hoisting of shiftable track it include shiftable track (1), shiftable track (2), shiftable track (3), fixed hoisting track (4), it is parallel between shiftable track (1) and shiftable track (2), and in same level, shiftable track (1) is vertical with fixed hoisting track (4), shiftable track (1) installation shiftable track suspension electric hoist (5), shiftable track (2) installation shiftable track suspension electric hoist (6), shiftable track (3) is installed on shiftable track suspension electric hoist (5) and shiftable track suspension electric hoist (6), shiftable track (3) is located in same level with fixed hoisting track (4), shiftable track (3) is provided with equipment lifting electric hoist (7).The advantages of the utility model has simple in construction, small investment, and utilization rate is high.
Description
Technical field
The utility model belongs to a kind of multi-thread boom hoisting of shiftable track.
Background technology
Industrial premises general device is relatively more, and is multi storied factory building, and overhaul of the equipments, which needs to be lifted by crane, to be moved to ground and enter
Row maintenance.It is middle to have structural column separation again because factory building span is big, it is impossible to solve the problems, such as lifting with a boom hoisting,
It can only be overhauled at every and a boom hoisting is respectively set on circuit, generally require to set more boom hoistings.What is so set lacks
Point is that boom hoisting investment is big, and utilization rate is low (boom hoisting can only be responsible for the equipment lifting on a circuit), itself
Maintenance cost it is also high.
The content of the invention
The utility model purpose is to provide a kind of simple in construction, small investment, the multi-thread lifting of the high shiftable track of utilization rate
Device.
The utility model is the mobility using track, realizes that a plurality of lifting circuit only needs a set of boom hoisting
Carry out the lifting of the equipment of each bar circuit.So, boom hoisting can be reduced, improve its utilization rate, the maintenance of itself into
This is also reduced.
The multi-thread boom hoisting of a kind of shiftable track of the present utility model, it includes the first shiftable track, and second is removable
Dynamic rail road, shiftable track, fixed hoisting track, the first shiftable track suspension electric hoist, the second shiftable track suspension electricity
Cucurbit, equipment lifting electric hoist, it is characterised in that it is parallel between the first shiftable track and the second shiftable track, and positioned at same
On one horizontal plane, the first shiftable track and the second shiftable track are vertical with fixed hoisting track, the first shiftable track peace
Electric hoist is hung equipped with the first shiftable track, the second shiftable track is provided with the second shiftable track suspension electric hoist,
First shiftable track hangs and is provided with shiftable track, removable dynamic rail on electric hoist and the second shiftable track suspension electric hoist
Road and fixed hoisting track be located in same level, and make the gap of shiftable track and fixed hoisting orbital docking be 2~
4mm, shiftable track are provided with equipment lifting electric hoist.
First shiftable track suspension electric hoist and the second shiftable track suspension electric hoist as described above is that interlocking exists
Together, it is synchronization-moving.
Fixed hoisting track as described above is fixedly installed at the top of the factory building of workspace, and fixed hoisting track can be
4a, 4b, 4c, 4d ..., more tracks of 4n are parallel between more fixed hoisting tracks.First shiftable track and second may move
Track is fixedly installed at the top of the factory building in maintenance area.
The multi-thread boom hoisting of the utility model shiftable track is installed in industrial premises and uses (such as accompanying drawing).Have in factory building
More industrial equipments, industrial equipment can be arranged on multistory frame, and the industrial equipment that need to be overhauled can be divided into a and play messenger wire
Road, b lifting circuit, c lifting circuit ..., n lifting circuit, it is therefore an objective to by equipment to be lifted from installation site lifting after be moved to
Overhauled on the ground of service area.
Shiftable track is risen by the mobile any one track alignment with fixed hoisting track (a, b, c ..., n), equipment
Electric hoist is hung to move on the line track with composition.
The course of work of the multi-thread boom hoisting of the utility model shiftable track is as follows:
When certain equipment of certain circuit or its part need lifting, such as the equipment on b lines, first pass through driving first
(the two electric hoists are to lock together, synchronous for shiftable track suspension electric hoist and the second shiftable track suspension electric hoist
It is mobile), lifting by crane electric hoist with the shiftable track and equipment being fixed thereon together can along the first shiftable track and second
Moving track moves, and shiftable track is moved to when being alignd with fixed hoisting track b, that is, stops movement.Driving equipment rises again
Hang electric hoist to move to workspace along shiftable track and the fixed hoisting track b line tracks formed, treat that equipment lifts by crane electric calabash
Lu Yidong causes to need the equipment surface lifted by crane, and stops movement, it would be desirable to which the hanging equipment of lifting is hung equipment lifting electric hoist
On hook and lift by crane, then driving equipment lifting electric hoist is moved to maintenance area, and equipment is put to ground and overhauled.Overhaul of the equipments
After the completion of, equipment is lifted by crane again, the installation site of equipment is returned to by reverse circuit, equipment lifting electric hoist returns to maintenance area
Treat slinging work next time.
The hoisting weight of the multi-thread boom hoisting of the utility model shiftable track is optional, and maximum is chosen as 20 tons;Play rise
Degree is optional according to factory building height, and optional scope is 10~60 meters.
The utility model has the following advantages:
(1) lifting track is divided into shiftable track and fixed hoisting track, realizes the mobility of track on demand.
(2) factory building for making to have a plurality of lifting circuit realizes the lifting for only needing a set of boom hoisting can to meet equipment
The function of maintenance, the utilization rate of boom hoisting is improved, reduce the maintenance quantity of boom hoisting.
Brief description of the drawings
Fig. 1 is the multi-thread boom hoisting top view of the utility model shiftable track;
Fig. 2 is the multi-thread boom hoisting A-A views of the utility model shiftable track;
Fig. 3 is figure a partial enlarged drawings;
Fig. 4 is figure b partial enlarged drawings.
As illustrated, the 1-the first shiftable track, the 2-the second shiftable track, 3-shiftable track, 4-fix
Hanger rail road, the 5-the first shiftable track suspension electric hoist, the 6-the second shiftable track suspension electric hoist, 7-equipment lifting electricity
Cucurbit, 8-workspace, 9-maintenance area, 10-mill construction post, 11-equipment to be lifted.
Embodiment
Embodiment 1:
The multi-thread boom hoisting of shiftable track, it includes the first shiftable track 1, the first shiftable track 2, removable dynamic rail
Road 3, fixed hoisting track 4, the first shiftable track suspension electric hoist 5, the second shiftable track suspension electric hoist 6, equipment rise
Hang electric hoist 7, it is characterised in that it is parallel between the first shiftable track 1 and the second shiftable track 2, and it is located at same level
On, the first shiftable track 1 and the second shiftable track 2 are vertical with fixed hoisting track 4, and the first shiftable track 1 is provided with
First shiftable track hangs electric hoist 5, and the second shiftable track 2 is provided with the second shiftable track suspension electric hoist 6, the
Shiftable track 3 is installed on one shiftable track suspension electric hoist 5 and second shiftable track suspension electric hoist 6, may move
Track 3 is located in same level with fixed hoisting track 4, and the gap for making shiftable track 3 be docked with fixed hoisting track 4
For 4mm, shiftable track 3 is provided with equipment lifting electric hoist 7.
Described the first shiftable track suspension electric hoist 5 and second shiftable track suspension electric hoist 6 is interlocking one
Rise, it is synchronization-moving.
Described fixed hoisting track 4 is fixedly installed at the top of the factory building of workspace, and fixed hoisting track 4 is 8 tracks,
Totally 8 lifting circuits, it is parallel between 8 fixed hoisting tracks 4.First shiftable track 1 and the second shiftable track 2 fix peace
At the top of factory building loaded on maintenance area.
4 tons of the equipment maximum part weight that need to be lifted by crane, equipment are supported on 2 layers, and support layer height is 6 meters, factory building heights of roofs
14 meters, every lifting circuit on need repair apparatus 6.
Equipment lifting electric hoist 7 is from the electric block that specified hoisting weight is 5 tons, shiftable track suspension electric hoist 5
Specified supporting power with 6 is 5 tons.The device lifting altitude is 10 meters.
The course of work of the multi-thread boom hoisting of the utility model shiftable track is as follows:
When certain equipment of certain circuit or its part need lifting, such as the equipment on b lines, first pass through driving first
(the two electric hoists are to lock together to shiftable track suspension electric hoist 5 and second shiftable track suspension electric hoist 6, together
Moved further), electric hoist 7 is lifted by crane together along the first shiftable track 1 and the with the shiftable track 3 and equipment that are fixed thereon
Two shiftable tracks 2 move, and shiftable track 3 are moved to when being alignd with fixed hoisting track 4b, that is, stop movement.Drive again
Equipment lifting electric hoist 7 moves along the shiftable track 3 and fixed hoisting track 4b line tracks formed to workspace, treats equipment
The lifting movement of electric hoist 7 causes to need the equipment surface lifted by crane, and stops movement, it would be desirable to which the hanging equipment of lifting lifts by crane electricity in equipment
On the suspension hook of cucurbit 7 and lift by crane, then driving equipment lifting electric hoist 7 is moved to maintenance area, and equipment is put to ground and examined
Repair.After the completion of overhaul of the equipments, equipment is lifted by crane again, the installation site of equipment, equipment lifting electric hoist 7 are returned to by reverse circuit
Return to maintenance area and treat slinging work next time.
Embodiment 2:
Described fixed hoisting track 4 is fixedly installed at the top of the factory building of workspace, and fixed hoisting track 4 is 4 tracks,
Totally 4 lifting circuits, it is parallel between 4 fixed hoisting tracks 4.
8 tons of the equipment maximum part weight that need to be lifted by crane, equipment are supported on 9 layers, and support layer height is 52 meters, factory building heights of roofs
63 meters, every lifting circuit on need repair apparatus 4.
Equipment lifting electric hoist 7 is from the electric block that specified hoisting weight is 10 tons, shiftable track suspension electric hoist 5
Specified supporting power with 6 is 10 tons.Shiftable track 3 is 3mm with the gap docked of fixed hoisting track 4.The device raising
Highly it is 60 meters.Remaining is the same as embodiment 1.
Embodiment 3:
Described fixed hoisting track 4 is fixedly installed at the top of the factory building of workspace, and fixed hoisting track 4 is 5 tracks,
Totally 5 lifting circuits, it is parallel between 5 fixed hoisting tracks 4.
16 tons of the equipment maximum part weight that need to be lifted by crane, equipment are supported on 5 layers, and support layer height is 30 meters, and factory building is risen
42 meters are spent, needs repair apparatus 3 on every lifting circuit.
Equipment lifting electric hoist 7 is from the electric block that specified hoisting weight is 20 tons, shiftable track suspension electric hoist 5
Specified supporting power with 6 is 20 tons.Shiftable track 3 is 2mm with the gap docked of fixed hoisting track 4.The device raising
Highly it is 38 meters.Remaining is the same as embodiment 1.
Claims (6)
1. a kind of multi-thread boom hoisting of shiftable track, it includes the first shiftable track (1), and the second shiftable track (2) can
Moving track (3), fixed hoisting track (4), the first shiftable track suspension electric hoist (5), the second shiftable track suspension electricity
Cucurbit (6), equipment lifting electric hoist (7), it is characterised in that between the first shiftable track (1) and the second shiftable track (2)
It is parallel, and in same level, the first shiftable track (1) and the second shiftable track (2) and fixed hoisting track (4)
Vertically, the first shiftable track (1) is provided with the first shiftable track suspension electric hoist (5), the second shiftable track (2) installation
There is the second shiftable track to hang electric hoist (6), hanged in the first shiftable track suspension electric hoist (5) and the second shiftable track
Hang and shiftable track (3) is installed on electric hoist (6), shiftable track (3) is located at same level with fixed hoisting track (4)
On, and the gap for making shiftable track (3) be docked with fixed hoisting track (4) is 2~4mm, shiftable track (3), which is provided with, to be set
Standby lifting electric hoist (7).
2. a kind of multi-thread boom hoisting of shiftable track as claimed in claim 1, it is characterised in that described first is removable
Track suspension electric hoist (5) and the second shiftable track suspension electric hoist (6) are to lock together, synchronization-moving.
A kind of 3. multi-thread boom hoisting of shiftable track as claimed in claim 1, it is characterised in that described fixed hoisting rail
Road (4) is fixedly installed at the top of the factory building of workspace, and fixed hoisting track (4) is 4a, 4b, 4c, 4d ..., and more tracks of 4n are more
It is parallel between root fixed hoisting track (4).
A kind of 4. multi-thread boom hoisting of shiftable track as claimed in claim 1, it is characterised in that the first removable dynamic rail
Road (2) and the second shiftable track (3) are fixedly installed at the top of the factory building in maintenance area.
5. a kind of multi-thread boom hoisting of shiftable track as claimed in claim 1, it is characterised in that hoisting weight is up to 20
Ton.
6. a kind of multi-thread boom hoisting of shiftable track as claimed in claim 1, it is characterised in that lift by crane the model of lifting altitude
Enclose for 10~60 meters.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621341444.2U CN206751210U (en) | 2016-12-07 | 2016-12-07 | The multi-thread boom hoisting of shiftable track |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621341444.2U CN206751210U (en) | 2016-12-07 | 2016-12-07 | The multi-thread boom hoisting of shiftable track |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206751210U true CN206751210U (en) | 2017-12-15 |
Family
ID=60606846
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621341444.2U Expired - Fee Related CN206751210U (en) | 2016-12-07 | 2016-12-07 | The multi-thread boom hoisting of shiftable track |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206751210U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113086841A (en) * | 2021-04-13 | 2021-07-09 | 索通发展股份有限公司 | Hanging basket device for repairing roasting furnace wall |
-
2016
- 2016-12-07 CN CN201621341444.2U patent/CN206751210U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113086841A (en) * | 2021-04-13 | 2021-07-09 | 索通发展股份有限公司 | Hanging basket device for repairing roasting furnace wall |
CN113086841B (en) * | 2021-04-13 | 2022-10-21 | 索通发展股份有限公司 | Be used for prosthetic hanging flower basket device of roasting furnace wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201268937Y (en) | Double-layer hanging cradle for working aloft | |
CN102786004B (en) | Integrally moving on-load hydraulic lifting system without mooring rope and lifting method | |
CN203143872U (en) | Mobile platform for elevator installation construction | |
CN206751210U (en) | The multi-thread boom hoisting of shiftable track | |
CN103967263A (en) | Novel hydraulic automatic climbing discharging platform | |
CN202542703U (en) | Electric signal beam crane | |
CN201460186U (en) | Adhesive lifting scaffold | |
CN204873491U (en) | Self -supporting does not have crossbeam hoist system | |
CN203878957U (en) | Protective screen module unit | |
CN205653077U (en) | Tower crane for building site of band shift dynamic formula scaffold frame | |
CN105253793B (en) | Construction method for traction transporting and hoisting of zinc pot in zinc plating workshop | |
CN204000632U (en) | A kind of sandbox prepressing device based on reaction frame | |
CN203594215U (en) | High-altitude large-area work platform semi-automatic lifting apparatus | |
CN203229334U (en) | Lifting framework for lifting and translating single steel member | |
CN209397505U (en) | One kind being used for loading test of half-through CFST arch bridge hoisting of deck beam mounting device | |
CN208666843U (en) | The anti-rope device of cant beam on machine room | |
CN201660377U (en) | Special gantry crane for overlength and large-tonnage parts | |
CN103225390B (en) | Hollow facade pulley guide attached-type lifting scaffold | |
CN107700854B (en) | Steel plate wall sliding installation device and installation method for super high-rise core tube | |
CN103058083B (en) | Bolt sphere truss gig | |
CN105060124A (en) | Intra-frame portal crane system and hoisting use method thereof | |
CN103626008A (en) | Elevator cable anti-deflection device | |
CN110748140A (en) | Track beam hanging basket special for stepped curtain wall | |
CN204549903U (en) | A kind of fixed point traction and slide rail displacement hoisting device | |
CN203602184U (en) | Arrangement structure of sightseeing elevator with no machine room |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |