CN206784389U - Quick block up fabricated construction system and erecting device - Google Patents

Quick block up fabricated construction system and erecting device Download PDF

Info

Publication number
CN206784389U
CN206784389U CN201720432121.2U CN201720432121U CN206784389U CN 206784389 U CN206784389 U CN 206784389U CN 201720432121 U CN201720432121 U CN 201720432121U CN 206784389 U CN206784389 U CN 206784389U
Authority
CN
China
Prior art keywords
firm banking
soldier piles
guide rail
sliding block
mobile base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201720432121.2U
Other languages
Chinese (zh)
Inventor
汪滨
臧德记
胡良浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Original Assignee
Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources filed Critical Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Priority to CN201720432121.2U priority Critical patent/CN206784389U/en
Application granted granted Critical
Publication of CN206784389U publication Critical patent/CN206784389U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

Assembled is the utility model is related to block up rapid installation device, including base, base includes firm banking and mobile base, and firm banking, the bottom of mobile base have track respectively, with merging, composition sliding is secondary, and guide rail is in outside construct with corresponding guide rail respectively for track;Firm banking has makes firm banking be fixed on the locking device on guide rail by track and after locking;Retractor device is provided between firm banking and mobile base, the receipts mechanism driving that pushes away that controlled end and the firm banking of retractor device have is connected;Mobile base is provided with soldier piles clamping device, and the controlling organization of putting that controlled end and the firm banking of soldier piles clamping device have is connected.The utility model further relates to fabricated construction system of quickly blocking up accordingly.The utility model quickly and safely can block up to the place's of inrushing implementation.

Description

Quick block up fabricated construction system and erecting device
Technical field
A kind of quick block up fabricated construction system and erecting device are the utility model is related to, belongs to hydraulic engineering dash and blocks up Mouth equipment technology field.
Background technology
According to the inventors knowledge, in hydraulic engineering dash blocks up technology, current existing multiple technologies means.
Earth and rockfill dam dike method in an opposite direction of blocking up is a kind of traditional conventional method, is specially directly jettisoninged native stone to breach direction Material, forms nature by the earth and stone material settled out in torrent and clashes dike.Based on this method, to reduce the amount of washing away of earth and stone material, also adopt Jettisoninged and blocked up with gabion stone string, bamboo cage, steel reinforcement cage, galvanized wire cage.
In recent decades, technological means of blocking up has further development, has occurred at present:Combined dam of steel, wood, soil and stone blocks Breach method, Screw Anchor are quickly blocked up method, and rubber dam is blocked up method, and shipwreck, caisson are blocked up method, the steel sheet pile dyke side of blocking up Method, etc..
Wherein, combined dam of steel, wood, soil and stone closure breach method is that the steel pipe for squeezing into ground links together in length and breadth, with wood Stake is reinforced, and formation can receive certain pressure and the steel wooden frame of impulsive force, and inwardly clog packed metaling, then with geotextiles, modeling Expect the covering of the materials such as cloth, and inwardly clog packed metaling, then covered with materials such as geotextiles, plastic clothes, being formed has synthesis The water-stopping dam of drag and impermeable ability.
Screw Anchor quickly block up method using machinery cast anchor instead of piling, in general stake is replaced using Screw Anchor, utilizes anchor The Screw Anchor entered is knitted a net frame, and then throwing is blocked up.Special lower windlass and unique construction technology are combined, and Screw Anchor makes the anti-of stake Pull out force, horizontal bearing capacity significantly improve, and can greatly improve the stability for rack of blocking up.
The rubber dam method of blocking up makes full use of the advantages that fast rubber dam inflation speed, conveniently moving, in the upper of breach mouth door Trip sets rubber dam cofferdam, and stifled to mouth door creates favorable conditions again, realizes that flood season quickly blocks up referendum mouth.
The steel sheet pile dyke method of blocking up is:First, skirt piles are beaten to the dike head at breach Kou Men both ends, does U-shaped steel sheet pile and wrap up in head Protective treatment, anti-current scour expand breach mouth door;Secondly, pier pontoon bridge is set up between breach mouth door, as waterborne Piling platform and the traffic aisle for transporting steel sheet pile;3rd, bordered on the river in breach Kou Men upstreams and build spur dike, chosen and slip outer shifting, subtract Flow and washed away at few breach;4th, implement steel sheet pile closure and hold one's breath, one layer of I-steel is used in the form of purlin at the top of cofferdam Supporting, middle longitudinal supporting use H steel, are arranged by 5m spacing, and sand backfill is taken out in cofferdam after closure.
, following disadvantage more or less be present in the method however, of the prior art these are blocked up:(1) due to the epoch Reason, former equipment of blocking up are to gather materials on the spot as main technological route, and the stake of carrying uses ferrous materials, and weight is big;Add Close shelves soil timber measurement is big.(2) construction technology of building of framework is the process that building on land scaffold is built, near water Operating mode, speed are slow, it has not been convenient to, work also has certain danger.(3) it is single that stake, which enters water, is held in the case of high water head It is flexible.(4) mainly gather materials on the spot on technical method and be combined with tactics of human sea, with the development in epoch, the requisition of manpower Difficulty increases, cost more and more higher.
Find, patent No. CN99126056.2, Authorization Notice No. CN1077941C Chinese invention patent, be related to through retrieval It is a kind of to be used to block the fast-assembling bracket of dike breach, by framves, I-shaped support are closed in multiple exhibitions, the support of string rope, string, string stake, block water the wing Formed with base etc..When dykes and dams burst, burst and front upper place, said elements are assembled into and breach width rapidly The adaptable bow-shaped support of the depth and after loading onto multiple rubber boats or air bag, makes support float to breach by manipulating drag rope Place, after placing, multiple staking outs are first laid at more people stations on support in support back, then insert size flashboard one by one in front, Followed by sandstone soil is inserted in support back, you can block breach.
The patent No. 99233465.9, Authorization Notice No. CN2391910Y Chinese utility model patent, it is related to one kind and blocks up Truss, it is the Truss for blocking break of a dike of the trapezium structure made of shaped steel, when flood breach occurs, Truss for blocking break of a dike is placed in group in breach Into a framework, water blockoff wall then is established by support of this framework again, can prevent that set stifled goods and materials is not washed away by current.
The patent No. 2009100747782.2, Authorization Notice No. CN101586335B Chinese invention patent, it is related to a kind of burst Mouthful cut-off equipment and closure method, crevasse cut-off equipment are one or more rope and the water suction leak stoppage bag of company, in leak stoppage bag Equipped with high hydroscopic resin, leak stoppage bag connecting rope both ends are connected with the hollow piling bar being fixed on dykes and dams.Closure method includes:A、 Four open circles piling bars are separately fixed at crevasse both ends, often hold two;B, by and even crevasse leak stoppage bag on the crevasse water surface Side is set up, and is hung on the link of the four open circles piling bars in both ends, is tensed, is driven into steel column in crevasse water;C, next group Crevasse leak stoppage bag is entered in water with same method, until last group of crevasse leak stoppage bag exceeds the water surface;By crevasse cut-off equipment Water swelling, crevasse is blocked.
Application number CN201610656081.X, application publication number CN106245584A Chinese invention patent application, is related to A kind of to be used to build dykes and dams or the double jaw rack blocked up that dams, some frames join as framework two-by-two, every two neighbouring The side end of frame is stretched out at interface point as cross one another double jaw;Attaching twine turns into double jaw net in framework Frame;The frame of several double jaw racks is connected with each other two-by-two to turn into cage body, and cage body summit turns into trident crown point, and cage body turns into Three jaw cage bodies.During implementation, double jaw rack is made into semifinished part, in the quick assembling positive tetrahedron three in flood-fighting scene Jaw steel reinforcement cage, stone, soil or sandbag are put into steel reinforcement cage during assembling, turns into effective flood-fighting goods and materials;Three jaws There are three jaws in each direction of steel reinforcement cage, it is easy to is inserted under the bottom or in dykes and dams, then other jaws can hook again Other steel reinforcement cage or water blockoff dam weight, and raising is speedily carried out rescue work effect;There is jaw at each interface point of rack, handle can be used as, It is easy to carry.
Techniques described above scheme is the prior art of representative, on the one hand the disadvantage referred to before more or less be present, On the other hand be difficult to ensuring quickly and safely to build the system of blocking up at the breach center, need badly develop can solve it is above-mentioned The technological means of problem.
Utility model content
Technical problem to be solved in the utility model is:A kind of the problem of overcoming prior art to exist, there is provided assembled Block up rapid installation device, quickly and easily the module of blocking up assembled can be put into and inrush intraoral, be easy to quickly and safely real Apply and block up.Quick fabricated construction system of blocking up using the erecting device is also provided.
The technical scheme in the invention for solving the technical problem is as follows:
Assembled is blocked up rapid installation device, including base, it is characterized in that, the base includes firm banking and dump bottom Seat, the firm banking, the bottom of mobile base have track respectively, and the track is formed with corresponding guide rail with merging respectively Sliding is secondary, and the guide rail is in outside construct;The firm banking, which has, to be located at by track and makes firm banking after locking The locking device being fixed on guide rail;Retractor device is provided between the firm banking and mobile base, the retractor device Controlled end is connected with the receipts mechanism driving that pushes away that firm banking has;The mobile base is provided with soldier piles clamping device, the soldier piles The controlled end of clamping device is connected with the controlling organization of putting that firm banking has;
The erecting device has the first state that soldier piles gripping apparatus grips have soldier piles;Push away and receive mechanism controls retractor device The second state for promoting mobile base to be slided along guide rail to the direction away from firm banking;Put a controlling organization control soldier piles clamping Device decontrols the third state of soldier piles;Push away and receive mechanism controls retractor device pulling mobile base along guide rail to close to firm banking The 4th state that direction is slided.
Using the erecting device, can implement to put an operation on the basis of safety is ensured, it is fast beneficial to safely and fast building Speed is blocked up fabricated construction system, and implementation is blocked up method.
Preferably, the retractor device includes expansion bracket, main drive and from drive device;
The expansion bracket has close to the active free end of firm banking and close to the driven free end of mobile base;
The main drive corresponds with active free end;The main drive includes being supported in firm banking First slide bar, it is sheathed on the first slide bar circumferential the first sliding block, bearing block and the screw rod parallel with the first slide bar;The spiral shell One end of bar is supported in bearing block and the other end and the output end of Tui Shou mechanisms are connected;First sliding block also has The screw being connected with screw flight;First sliding block forms screw pair with screw rod, and first sliding block and the first slide bar are formed Sliding is secondary;First sliding block is hinged with corresponding expansion bracket active free end;
It is described to be corresponded from drive device and driven free end;It is described to include being supported in mobile base from drive device Second slide bar and the second sliding block for being sheathed on the second slide bar circumference;It is secondary that second slide bar and the second sliding block form sliding;Institute The second sliding block is stated to be hinged with the driven free end of corresponding expansion bracket;
There is the retractor device Tui Shou mechanisms to drive screw rod rotation, and screw rod drives the first sliding block sliding on the first slide bar Dynamic, the first sliding block passes through the driven freedom of expansion bracket by driving expansion bracket active free end expansion bracket is stretched out or is retracted End drives the motion state that the second sliding block slides on the second slide bar.
It is highly preferred that the expansion bracket by two intersection rod-like elements intersect it is point articulated form, the rod-like element has Two close to the active free end of firm banking and two close to the driven free end of mobile base;The active free end, Driven free end is respectively symmetrically distributed in the both sides in crosspoint;The main drive, there are two sets respectively from drive device, and divide The both sides in crosspoint are not symmetrically distributed in.
Using the preferred scheme, it can rapidly be disposed along guide rail and put a position, beneficial to raising operating efficiency.
Preferably, the Tui Shou mechanisms are commutation driver;The commutation driver has the crank handle of drive connection And output shaft;The output shaft of the commutation driver is connected through the other end of shaft coupling and screw rod.
Using the preferred scheme, the position deployment to retractor device can be simply and effectively realized.
Preferably, the soldier piles clamping device has at least one;The soldier piles clamping device includes grip folder, tightening system And top opening mechanism;
The grip folder is made up of support base and two symmetrically placed single armeds, and the support base is fixed with mobile base to be connected Connect;The clamping plate and the other end that one end of the single armed is provided with towards soldier piles are provided with spacing elongated hole, the be hinged branch in middle part of the single armed Support in support base;The clamping plate of two single armeds is toward each other and space is held in formation between the two;Two single armed other ends it is spacing Elongated hole is stacked up and down;
The tightening system includes pedestal, guide pillar, elastic component and push rod;The guide pillar is fixed on support base;The base Cover for seat is located at guide pillar circumference and forms prismatic pair;The elastic component is sheathed on guide pillar circumference, and one end and the support base of elastic component support Connect and the other end abuts with pedestal;The push rod is fixed on pedestal, and push rod inserts the spacing elongated hole of two single armeds;
The top opening mechanism be middle part hinged support in the lever of mobile base, one end of the lever and put a control machine The control terminal drive connection of structure, the other end of the lever are provided with ejection part part;
The grip fixture puts a controlling organization control terminal makes ejection part part promote push rod by lever, and push rod drives base Seat is moved along guide pillar and compression elastic piece, while push rod makes the clamping plate of two single armeds respectively towards remote by acting on spacing elongated hole The open mode of mutual direction motion;And put a controlling organization control terminal makes ejection part part depart from push rod, bullet by lever Property part diastole and promote pedestal to be moved along guide pillar, pedestal drives push rod movement, and push rod makes two lists by acting on spacing elongated hole The clamping plate of arm is respectively towards the tightening state close to the motion of mutual direction.
It is highly preferred that the ejection part part is in shaft-like or spherical component;A controlling organization of putting is included with soft The brake cable and rim brake of pipe, one end of the brake cable are fixedly connected with one end of top opening mechanism lever, the brake cable The other end is fixedly connected with rim brake.
Using the preferred scheme, i.e., realized with simple structure and put stake across water, safely and fast.
Preferably, the locking device includes fixed plate, portable plate, bolt and nut;The fixed plate and portable plate It is located at the both sides of guide rail respectively;The fixed plate is fixedly connected with firm banking and is in contact with guide rail, the portable plate support In firm banking and form prismatic pair;One end of the bolt be connected with fixed plate and the other end through portable plate and with nut spiral shell Line connects, or, one end of the bolt is connected with portable plate and the other end passes through fixed plate and is connected with nut thread;
There is the locking device tightening nut to make portable plate mobile towards fixed plate and the clamping guide-rail together with fixed plate, Firm banking is set to be fixed on the locking state on guide rail.
Using the preferred scheme, it can be ensured that firm banking can lock when needed, improve operational reliability.
The utility model also provides:
Quick fabricated construction system of blocking up, it is characterized in that, including the erecting device addressed above;Also include parallel the One guide rail and the second guide rail, one group of module of blocking up, one group of crossbeam, one group of workbench and one group of block;Described first, second leads Rail is on outside structures;The module of blocking up includes the first soldier piles, the second soldier piles, end wall bracket and X-shaped reinforcing member, described The top of first soldier piles is connected with the first guide rail, and top and the second guide rail of second soldier piles are connected, the X-shaped reinforcing member One side end is connected with the first soldier piles and end side is connected with the second soldier piles;The end wall bracket includes brace, cross bar and erected Bar, one end and the montant top of the brace are connected, and the other end of the brace and one end of cross bar are connected, the cross bar it is another One end is connected with montant bottom, and the montant is connected with the first soldier piles;First soldier piles of the block located at adjacent module of blocking up Between;The crossbeam, workbench are fixed on first, second guide rail at each interval.
Using the fabricated construction system of quickly blocking up, module of blocking up can be first assembled, recycles erecting device will be each stifled Mouth mold block is thrown to precalculated position, then can put up total system, safely and fast.
Preferably, first, second soldier piles are formed by stake bar and pile top grafting respectively, and the pile top forms first or the The bottom of two soldier piles;The stake bar has the hollow material of chute using rectangular and four sides;One end of the end wall bracket cross bar Provided with anchor directed downwardly point, the end wall bracket montant has the sliding block to match with the first soldier piles chute;The both sides difference of the block It is connected with strip sliding block, the strip sliding block is respectively in the chute of corresponding first soldier piles.
Using the preferred scheme, operating efficiency can further improve.
The utility model blocked up rapid installation device using the assembled of unique design, will quickly and easily can be assembled Module of blocking up, which is put into, to inrush intraoral, is easy to quickly and safely implement to block up;Build it is quick block up fabricated construction system when, adopt It is quick, efficient with assembly flow shop, it is adapted to emergency repair;The overall weight of quick fabricated construction system of blocking up is light, carry, Easy for construction, labor intensity is low;Connected, enhanced caused by resistance flood impact by X-shaped reinforcing member between first, second soldier piles Moment of flexure ability;End wall bracket is easy for installation, support is reasonable, improves the stability of total system;Jettisoninged thing with interception of blocking, It is easy for installation quick and small volume, in light weight;When implementing to block up method, native stone is substituted to jettisoning thing using high percentage of water rapid solidifying material, Simple to operate, mechanization degree is high, speed of application is fast.
Brief description of the drawings
Fig. 1 is the structural representation of the erecting device of the utility model embodiment 1.
Fig. 2, Fig. 3 be respectively in the soldier piles clamping device of the utility model embodiment 1 grip folder in tighten up, open mode when Schematic diagram.
Fig. 4 is the schematic diagram of the locking device of the utility model embodiment 1.
Fig. 5 is the schematic diagram of the structural system of the utility model embodiment 2.
Fig. 6 is the schematic diagram of the guide rail of the utility model embodiment 2.
Fig. 7 is the schematic diagram of the soldier piles of the utility model embodiment 2 first, second.
Fig. 8 is the schematic cross-section of 2 bars of the utility model embodiment.
Fig. 9 is the schematic diagram of end wall bracket.
Figure 10 is Fig. 9 top cross sectional view.
Embodiment
The utility model is described in further detail with reference to the accompanying drawings and in conjunction with the embodiments.But the utility model is not It is limited to given example.
Embodiment 1
Rapid installation device, including base as shown in figure 1, the assembled of the present embodiment is blocked up, base include firm banking 01 and mobile base 02, firm banking 01, the bottom of mobile base 02 have a track respectively, track respectively with corresponding guide rail 03 Sliding pair is formed with merging, guide rail 03 is in outside construct;Firm banking 01, which has, to be located at by track and makes after locking solid Determine the locking device 04 that base 01 is fixed on guide rail 03;Retractor device 05 is provided between firm banking 01 and mobile base 02, The Tui Shou mechanisms 06 that the controlled end of retractor device 05 has with firm banking 01 are connected;Mobile base 02 clamps provided with soldier piles Device 07, the controlling organization 08 of putting that controlled end and the firm banking 01 of soldier piles clamping device 07 have are connected;
Erecting device has the first state that soldier piles clamping device 07 is clamped with soldier piles 09;The control of Tui Shou mechanisms 06 is flexible Device 05 promotes the second state that mobile base 02 is slided along guide rail 03 to the direction away from firm banking 01;Put a controlling organization 08 control soldier piles clamping device 07 decontrols the third state of soldier piles 09;Tui Shou mechanisms 06 control retractor device 05 to pull mobile base 02 along guide rail 03 to the 4th state close to the slip of the direction of firm banking 01.
As shown in figure 1, retractor device 05 includes expansion bracket 10, main drive and from drive device;Expansion bracket 10 has There is the active free end 11 of close firm banking 01 and close to the driven free end 12 of mobile base 02;
Main drive corresponds with active free end 11;Main drive includes being supported in the of firm banking 01 One slide bar 13, it is sheathed on the first slide bar 13 circumferential the first sliding block 14, bearing block 15 and the screw rod parallel with the first slide bar 13 16;One end of screw rod 16 is supported in bearing block 15 and the other end and the output end of Tui Shou mechanisms 06 are connected;First sliding block 14 also have the screw being threadedly coupled with screw rod 16;First sliding block 14 forms screw pair, the first sliding block 14 and first with screw rod 16 It is secondary that slide bar 13 forms sliding;First sliding block 14 is be hinged with corresponding expansion bracket active free end 11;
Corresponded from drive device and driven free end 12;Include being supported in the of mobile base 02 from drive device Two slide bars 17 and the second sliding block 18 for being sheathed on the circumference of the second slide bar 17;Second slide bar 17 and the second sliding block 18, which are formed, to be slid It is secondary;Second sliding block 18 free end 12 driven with corresponding expansion bracket is be hinged;
There is retractor device 05 Tui Shou mechanisms 06 to drive screw rod 16 to rotate, and screw rod 16 drives the first sliding block 14 to be slided first Slided on bar 13, the first sliding block 14 is passed through by driving expansion bracket active free end 11 expansion bracket 10 is stretched out or is retracted The driven free end 12 of expansion bracket drives the motion state that the second sliding block 18 slides on the second slide bar 17.
Specifically, expansion bracket 10 by two intersection rod-like elements intersect it is point articulated form, rod-like element have two lean on The active free end 11 of nearly firm banking 01 and the driven free end 12 of two close mobile bases 02;Active free end 11, Driven free end 12 is respectively symmetrically distributed in the both sides in crosspoint;Main drive, there are two sets respectively from drive device, and respectively It is symmetrically distributed in the both sides in crosspoint.
Tui Shou mechanisms 06 are commutation driver;The driver that commutates has crank handle 20 and the output shaft 21 of drive connection; The other end of the output shaft 21 of driver through shaft coupling 22 and screw rod 16 that commutate is connected.
As shown in Figure 1 to Figure 3, soldier piles clamping device 07 has at least one;Soldier piles clamping device 07 includes grip folder, tightened up Mechanism and top opening mechanism;Grip folder is made up of the symmetrically placed single armed 24 of support base 23 and two, support base 23 and dump bottom Seat 02 is fixedly connected;The clamping plate 25 and the other end that one end of single armed 24 is provided with towards soldier piles 09 are provided with spacing elongated hole 26, single armed 24 middle part hinged support is in support base 23;The clamping plate 25 of two single armeds 24 is toward each other and space is held in formation between the two; The spacing elongated hole of two other ends of single armed 24 is stacked about 26;
Tightening system includes pedestal 27, guide pillar 28, elastic component 29 and push rod 30;Guide pillar 28 is fixed on support base 23;Base Seat 27 is sheathed on the circumference of guide pillar 28 and forms prismatic pair;Elastic component 29 is sheathed on guide pillar 28 circumferentially, one end of elastic component 29 and branch Support seat 23 abuts and the other end abuts with pedestal 27;Push rod 30 is fixed on pedestal 27, and two single armeds 24 of insertion of push rod 30 Spacing elongated hole 26;
Top opening mechanism be middle part hinged support in the lever 31 of mobile base 02, one end of lever 31 and put a controlling organization 08 control terminal drive connection, the other end of lever 31 are provided with ejection part part 32;
Grip fixture puts the control terminal of a controlling organization 08 makes ejection part part 32 promote push rod 30, push rod 30 by lever 31 Band moving base 27 is moved along guide pillar 28 and compression elastic piece 29, while push rod 30 makes two single armeds by acting on spacing elongated hole 26 24 clamping plate 25 is respectively towards the open mode of direction motion away from each other;And put the control terminal of a controlling organization 08 and pass through thick stick Bar 31 makes ejection part part 32 depart from push rod 30, and the diastole of elastic component 29 simultaneously promotes pedestal 27 to be moved along guide pillar 28, and pedestal 27 drives and pushed away Bar 30 moves, and push rod 30 makes the clamping plate 25 of two single armeds 24 be transported respectively towards close to mutual direction by acting on spacing elongated hole 26 Dynamic tightening state.
Specifically, ejection part part 32 is in shaft-like or spherical component;Putting a controlling organization 08 is included with flexible pipe Brake cable 33 and rim brake (not shown), one end of brake cable 33 are fixedly connected with one end of top opening mechanism lever 31, brake The other end of line 33 is fixedly connected with rim brake.
As shown in figure 4, locking device 04 includes fixed plate 34, portable plate 35, bolt 36 and nut 37;Fixed plate 34 It is located at the both sides of guide rail 03 respectively with portable plate 35;Fixed plate 34 is fixedly connected with firm banking 01 and is in contact with guide rail 03, Portable plate 35 is supported in firm banking 01 and forms prismatic pair;One end of bolt 36 is connected with fixed plate 34 and the other end is passed through and lived Move plate 35 and be threadedly coupled with nut 37 and (also can optionally be used:One end of bolt 36 is connected with portable plate 35 and the other end is worn Cross fixed plate 34 and be threadedly coupled with nut 37);
There is locking device 04 tightening nut 37 portable plate 35 is moved towards fixed plate 34 and is pressed from both sides together with fixed plate 34 Tight guide rail 03, the locking state for making firm banking 01 be fixed on guide rail 03.
Embodiment 2
As shown in Fig. 5 to Figure 10, the quick fabricated construction system of blocking up of the present embodiment, the installation for including embodiment 1 fills Put;Also include 39, one groups of modules of blocking up of the first parallel guide rail 38 and the second guide rail, one group of crossbeam, 40, one groups of workbench (in figure Do not show) and one group of block 41;First, second guide rail 38,39 is on outside structures;Module of blocking up includes the first soldier piles 42nd, the second soldier piles 43, end wall bracket 44 and X-shaped reinforcing member 45, the top of the first soldier piles 42 are connected with the first guide rail 38, and second The top of soldier piles 43 is connected with the second guide rail 39, and a side end of X-shaped reinforcing member 45 is connected with the first soldier piles 42 and another side Portion is connected with the second soldier piles 43;End wall bracket 44 includes brace, cross bar and montant, and one end and the montant top of brace are connected, brace The other end and one end of cross bar be connected, the other end and the montant bottom of cross bar are connected, and montant is connected with the first soldier piles 42;Block 41 between the first soldier piles 42 of adjacent module of blocking up;Crossbeam 40, workbench are fixed on first, second guide rail at each interval 38th, on 39.
Specifically, first, second soldier piles 42,43 are formed by stake bar 46 and the grafting of pile top 47 respectively, and pile top 47 forms the One or second soldier piles bottom;Stake bar 46 has the hollow material of chute using rectangular and four sides;One end of end wall bracket cross bar Provided with anchor point 48 directed downwardly, end wall bracket montant has the sliding block to match with the chute of the first soldier piles 42;Block 41 both sides respectively with Strip sliding block is connected, and strip sliding block is respectively in the chute of corresponding first soldier piles 42.
The detailed process blocked up using the present embodiment is as follows:
The first step, the dike head that inrushes is carried out to wrap up in head processing;The end of first, second guide rail 38,39 is individually fixed in dike On, and make first, second guide rail 38,39 across breach of inrushing;Assemble one group of module of blocking up;
Second step, set up erecting device on guide rail 03:By firm banking 01, mobile base 02 track respectively with guide rail 03 is fastened, and firm banking 01 is moved into leading edge near water, and firm banking 01 is fixed on guide rail 03 by locking device 04; Putting a controlling organization 08 controls soldier piles clamping device 07 to open, and then puts first, second soldier piles 42,43 of module of blocking up respectively In soldier piles clamping device 07 corresponding to entering, put a controlling organization 08 control soldier piles clamping device 07 clamp first, second soldier piles 42, 43;Tui Shou mechanisms 06 control retractor device 05 to promote mobile base 02 to be moved to precalculated position along guide rail 03;Put a controlling organization 08 control soldier piles clamping device 07 is opened, and puts down first, second soldier piles 42,43, and drive piles and bury (i.e. by pile top 47 and anchor point 48 Squeeze into soil);
3rd step, remove assembled and block up rapid installation device;Lay at workbench to the module of blocking up driven piles;Will be stifled The top of the soldier piles 42,43 of mouth mold block first, second is connected (as pressed from both sides using Hough) with corresponding rails 03 respectively;In workbench front end The crossbeam 40 that installation is connected with guide rail 03;
4th step, judge whether to continue placement and block up module, if then going to second step, if otherwise going to the 5th step;
5th step, between the first soldier piles 42 of adjacent module of blocking up, by block 41 both sides strip sliding block be put into correspondingly In the chute of first soldier piles 42, and block 41 is set to slide into precalculated position;
6th step, in the side that meets water of block 41 filling bag is placed respectively, the material of high percentage of water rapid solidifying material is filled with into filling bag Slurry, obturation to be formed and after reaching predetermined strength are completed to block up.
In addition to the implementation, the utility model can also have other embodiment.It is all to use equivalent substitution or equivalent change The technical scheme to be formed is changed, all falls within the protection domain of the requires of the utility model.

Claims (9)

  1. The rapid installation device 1. assembled is blocked up, including base, it is characterized in that, the base includes firm banking and dump bottom Seat, the firm banking, the bottom of mobile base have track respectively, and the track is formed with corresponding guide rail with merging respectively Sliding is secondary, and the guide rail is in outside construct;The firm banking, which has, to be located at by track and makes firm banking after locking The locking device being fixed on guide rail;Retractor device is provided between the firm banking and mobile base, the retractor device Controlled end is connected with the receipts mechanism driving that pushes away that firm banking has;The mobile base is provided with soldier piles clamping device, the soldier piles The controlled end of clamping device is connected with the controlling organization of putting that firm banking has;
    The erecting device has the first state that soldier piles gripping apparatus grips have soldier piles;Push away and receive the promotion of mechanism controls retractor device The second state that mobile base is slided along guide rail to the direction away from firm banking;Put a controlling organization control soldier piles clamping device Decontrol the third state of soldier piles;Push away and receive mechanism controls retractor device pulling mobile base along guide rail to close to the direction of firm banking The 4th state slided.
  2. 2. erecting device according to claim 1, it is characterized in that, the retractor device includes expansion bracket, main drive And from drive device;
    The expansion bracket has close to the active free end of firm banking and close to the driven free end of mobile base;
    The main drive corresponds with active free end;The main drive includes being supported in the first of firm banking Slide bar, it is sheathed on the first slide bar circumferential the first sliding block, bearing block and the screw rod parallel with the first slide bar;The screw rod One end is supported in bearing block and the other end and the output end of Tui Shou mechanisms are connected;First sliding block also has and spiral shell The screw of bar threaded connection;First sliding block forms screw pair with screw rod, and first sliding block and the first slide bar form sliding It is secondary;First sliding block is hinged with corresponding expansion bracket active free end;
    It is described to be corresponded from drive device and driven free end;It is described to include being supported in the second of mobile base from drive device Slide bar and the second sliding block for being sheathed on the second slide bar circumference;It is secondary that second slide bar and the second sliding block form sliding;Described Two sliding blocks are hinged with the driven free end of corresponding expansion bracket;
    There is the retractor device Tui Shou mechanisms to drive screw rod rotation, and screw rod drives the first sliding block to be slided on the first slide bar, the One sliding block drives by driving expansion bracket active free end expansion bracket is stretched out or is retracted, and then by the driven free end of expansion bracket The motion state that second sliding block slides on the second slide bar.
  3. 3. erecting device according to claim 2, it is characterized in that, the expansion bracket is being intersected by the rod-like element of two intersections It is point articulated to form, the rod-like element have two close to the active free end of firm banking and two close to mobile base Driven free end;The active free end, driven free end are respectively symmetrically distributed in the both sides in crosspoint;The main driving dress Put, there are two sets respectively from drive device, and be respectively symmetrically distributed in the both sides in crosspoint.
  4. 4. erecting device according to claim 2, it is characterized in that, the Tui Shou mechanisms are commutation driver;The commutation Driver has crank handle and the output shaft of drive connection;The output shaft of the commutation driver is another through shaft coupling and screw rod One end is connected.
  5. 5. erecting device according to claim 1, it is characterized in that, the soldier piles clamping device has at least one;It is described perpendicular Holder for pile device includes grip folder, tightening system and top opening mechanism;
    The grip folder is made up of support base and two symmetrically placed single armeds, and the support base is fixedly connected with mobile base; The clamping plate and the other end that one end of the single armed is provided with towards soldier piles are provided with spacing elongated hole, the middle part hinged support of the single armed In support base;The clamping plate of two single armeds is toward each other and space is held in formation between the two;The spacing length of two single armed other ends Hole is stacked up and down;
    The tightening system includes pedestal, guide pillar, elastic component and push rod;The guide pillar is fixed on support base;The base sleeve Located at guide pillar circumference and form prismatic pair;The elastic component be sheathed on guide pillar circumference, one end of elastic component abutted with support base and The other end abuts with pedestal;The push rod is fixed on pedestal, and push rod inserts the spacing elongated hole of two single armeds;
    The top opening mechanism be middle part hinged support in the lever of mobile base, one end of the lever and put a controlling organization Control terminal is connected, and the other end of the lever is provided with ejection part part;
    The grip fixture puts a controlling organization control terminal makes ejection part part promote push rod, push rod band moving base edge by lever Guide pillar movement and compression elastic piece, while push rod makes the clamping plate of two single armeds respectively towards away from each other by acting on spacing elongated hole Direction motion open mode;And put a controlling organization control terminal makes ejection part part depart from push rod, elastic component by lever Diastole simultaneously promotes pedestal to be moved along guide pillar, and pedestal drives push rod movement, and push rod makes two single armeds by acting on spacing elongated hole Clamping plate is respectively towards the tightening state close to the motion of mutual direction.
  6. 6. erecting device according to claim 5, it is characterized in that, the ejection part part is in shaft-like or spherical component; A controlling organization of putting includes brake cable and rim brake with flexible pipe, one end and the top opening mechanism lever of the brake cable One end is fixedly connected, and the other end of the brake cable is fixedly connected with rim brake.
  7. 7. erecting device according to claim 1, it is characterized in that, the locking device includes fixed plate, portable plate, bolt And nut;The fixed plate and portable plate are located at the both sides of guide rail respectively;The fixed plate is fixedly connected simultaneously with firm banking It is in contact with guide rail, the portable plate is supported in firm banking and forms prismatic pair;One end of the bolt is connected with fixed plate And the other end is with nut thread through portable plate and be connected, or, one end of the bolt and portable plate is connected and the other end is worn Cross fixed plate and be connected with nut thread;
    There is the locking device tightening nut portable plate is made solid towards fixed plate movement and the clamping guide-rail together with fixed plate Determine the locking state that base is fixed on guide rail.
  8. 8. quick fabricated construction system of blocking up, it is characterized in that, including the erecting device described in any one of claim 1 to 7;Also Including parallel the first guide rail and the second guide rail, one group of module of blocking up, one group of crossbeam, one group of workbench and one group of block;Institute First, second guide rail is stated on outside structures;The module of blocking up includes the first soldier piles, the second soldier piles, end wall bracket and X Shape reinforcing member, top and the first guide rail of first soldier piles are connected, and top and the second guide rail of second soldier piles are connected, institute State a side end of X-shaped reinforcing member and the first soldier piles are connected and end side is connected with the second soldier piles;The end wall bracket includes Brace, cross bar and montant, one end and the montant top of the brace are connected, and the other end of the brace and one end of cross bar are consolidated Even, the other end and the montant bottom of the cross bar are connected, and the montant is connected with the first soldier piles;The block is blocked up located at adjacent Between first soldier piles of module;The crossbeam, workbench are fixed on first, second guide rail at each interval.
  9. 9. structural system according to claim 8, it is characterized in that, first, second soldier piles are respectively by stake bar and pile top Grafting forms, and the pile top forms the bottom of the first or second soldier piles;The stake bar has chute using rectangular and four sides Hollow material;One end of the end wall bracket cross bar is provided with anchor directed downwardly point, and the end wall bracket montant has and the first soldier piles chute The sliding block of matching;The both sides of the block are connected with strip sliding block respectively, and the strip sliding block is respectively positioned at corresponding first soldier piles Chute in.
CN201720432121.2U 2017-04-21 2017-04-21 Quick block up fabricated construction system and erecting device Withdrawn - After Issue CN206784389U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720432121.2U CN206784389U (en) 2017-04-21 2017-04-21 Quick block up fabricated construction system and erecting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720432121.2U CN206784389U (en) 2017-04-21 2017-04-21 Quick block up fabricated construction system and erecting device

Publications (1)

Publication Number Publication Date
CN206784389U true CN206784389U (en) 2017-12-22

Family

ID=60708797

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720432121.2U Withdrawn - After Issue CN206784389U (en) 2017-04-21 2017-04-21 Quick block up fabricated construction system and erecting device

Country Status (1)

Country Link
CN (1) CN206784389U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106948349A (en) * 2017-04-21 2017-07-14 水利部交通运输部国家能源局南京水利科学研究院 Quick block up fabricated construction system, erecting device and method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106948349A (en) * 2017-04-21 2017-07-14 水利部交通运输部国家能源局南京水利科学研究院 Quick block up fabricated construction system, erecting device and method

Similar Documents

Publication Publication Date Title
CN106948349A (en) Quick block up fabricated construction system, erecting device and method
US8287209B2 (en) Protective flood barrier system
CN206428653U (en) A kind of flood control small dike
CN206784389U (en) Quick block up fabricated construction system and erecting device
CN101586335B (en) Breach cut-off device and cut-off method
CN108104058A (en) A kind of dykes and dams flood crevasse plugging device and its method for blocking
CN107059786A (en) A kind of movable embankment protection floats wall
NO300648B1 (en) Duvet-shaped tablecloths comprising a sleeve of a flexible and stretch-resistant cloth material
CN108035319A (en) The fixed telescopic breach plugging device of one kind, method
CN107054572A (en) A kind of flood disaster prevention and reduction ship
CN206581217U (en) Flood control checkdam monomer and flood control checkdam
CN206554018U (en) A kind of ecological flood control wall construction
DE202009005592U1 (en) On the bank standing dam-like flood protection system
CN114150618A (en) Emergency side slope protection gabion and matched parts thereof
CN207714256U (en) A kind of dykes and dams flood crevasse plugging device
CN105714740A (en) Rapid dike leaking stoppage equipment
CN1651658A (en) Flood proof leak proof drought proof bag and matched reinforcing bar cage, steal girder net structure
CN107130605A (en) Rivers and lakes breach a dyke fast blockage ship and blocking method
CN109972588A (en) Quick-assembling dike breach plugging device
CN206873458U (en) Rivers and lakes breach a dyke fast blockage ship
CN110424329A (en) A kind of dyke is quickly blocked up specific stub net anti-impact equipment and the application method of speedily carrying out rescue work
CN108203969A (en) The flexible board-like breach plugging device of one kind, method
CN108118665A (en) A kind of breach plugging device and method using fixed tower
CN212612293U (en) Framework-detachable anti-floating water-blocking infiltration blocking blanket
CN108750031A (en) Wind wave prevention marine devices and its working method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20171222

Effective date of abandoning: 20220819

AV01 Patent right actively abandoned

Granted publication date: 20171222

Effective date of abandoning: 20220819