CN207714256U - A kind of dykes and dams flood crevasse plugging device - Google Patents
A kind of dykes and dams flood crevasse plugging device Download PDFInfo
- Publication number
- CN207714256U CN207714256U CN201721757554.1U CN201721757554U CN207714256U CN 207714256 U CN207714256 U CN 207714256U CN 201721757554 U CN201721757554 U CN 201721757554U CN 207714256 U CN207714256 U CN 207714256U
- Authority
- CN
- China
- Prior art keywords
- rope
- crevasse
- dykes
- water fender
- flood
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 125
- RLLPVAHGXHCWKJ-IEBWSBKVSA-N (3-phenoxyphenyl)methyl (1s,3s)-3-(2,2-dichloroethenyl)-2,2-dimethylcyclopropane-1-carboxylate Chemical compound CC1(C)[C@H](C=C(Cl)Cl)[C@@H]1C(=O)OCC1=CC=CC(OC=2C=CC=CC=2)=C1 RLLPVAHGXHCWKJ-IEBWSBKVSA-N 0.000 claims abstract description 16
- 229910000831 Steel Inorganic materials 0.000 claims description 54
- 239000010959 steel Substances 0.000 claims description 54
- 230000000903 blocking effect Effects 0.000 abstract description 22
- 239000000463 material Substances 0.000 abstract description 19
- ZZUFCTLCJUWOSV-UHFFFAOYSA-N furosemide Chemical compound C1=C(Cl)C(S(=O)(=O)N)=CC(C(O)=O)=C1NCC1=CC=CO1 ZZUFCTLCJUWOSV-UHFFFAOYSA-N 0.000 abstract description 2
- 238000007789 sealing Methods 0.000 abstract description 2
- 238000000034 method Methods 0.000 description 17
- 230000008901 benefit Effects 0.000 description 7
- 239000002689 soil Substances 0.000 description 7
- 230000000694 effects Effects 0.000 description 6
- 230000032258 transport Effects 0.000 description 5
- 238000010276 construction Methods 0.000 description 3
- 238000007689 inspection Methods 0.000 description 3
- 238000004064 recycling Methods 0.000 description 3
- 239000011435 rock Substances 0.000 description 3
- 230000001360 synchronised effect Effects 0.000 description 3
- 238000005299 abrasion Methods 0.000 description 2
- 230000009471 action Effects 0.000 description 2
- 238000005452 bending Methods 0.000 description 2
- 230000008859 change Effects 0.000 description 2
- 238000006073 displacement reaction Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 239000002985 plastic film Substances 0.000 description 2
- 229920006255 plastic film Polymers 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 238000003860 storage Methods 0.000 description 2
- 239000010902 straw Substances 0.000 description 2
- 210000001519 tissue Anatomy 0.000 description 2
- 229910000954 Medium-carbon steel Inorganic materials 0.000 description 1
- 229910000754 Wrought iron Inorganic materials 0.000 description 1
- 230000004308 accommodation Effects 0.000 description 1
- 238000010009 beating Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009414 blockwork Methods 0.000 description 1
- 210000000988 bone and bone Anatomy 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000001066 destructive effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000004090 dissolution Methods 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 238000001035 drying Methods 0.000 description 1
- PCHJSUWPFVWCPO-UHFFFAOYSA-N gold Chemical compound [Au] PCHJSUWPFVWCPO-UHFFFAOYSA-N 0.000 description 1
- 239000010931 gold Substances 0.000 description 1
- 229910052737 gold Inorganic materials 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000002045 lasting effect Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 230000000116 mitigating effect Effects 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000010606 normalization Methods 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 238000009991 scouring Methods 0.000 description 1
- 239000007779 soft material Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 238000003892 spreading Methods 0.000 description 1
- 230000007480 spreading Effects 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
- 238000012549 training Methods 0.000 description 1
Landscapes
- Revetment (AREA)
Abstract
The utility model provides a kind of dykes and dams flood crevasse plugging device, it is related to building element, mechanical component and hydro science field, including the stress anchor picket above the dykes and dams of crevasse both sides, the supporting rope that both ends are fixed on stress anchor picket is set and launch rope, the water fender queue for being tensioned supporting rope and launching the tensioning rarefactor of rope and be placed on above supporting rope and dispensing rope;The water fender queue includes multiple light prefabricated water fenders disposed in parallel being connected in series by serializer, one end of light prefabricated water fender bottom is flexibly connected with supporting rope by support ring, and the other end of light prefabricated water fender bottom is directly freely placed on dispensing rope.The utility model solves the problems, such as that human and material resources are of high cost, blocking time is long, labor intensity is big existing for the sealing tech of current dykes and dams flood crevasse, emergency personnel's security risk is big.
Description
Technical field
The utility model is related to building element, mechanical component and hydro science field more particularly to a kind of parallel rope type
Dykes and dams flood crevasse plugging device.
Technical background
Flood is water caused by the rivers,lakes and seas water as caused by the natural causes such as heavy rain, hurried ice dissolution increases sharply
The flow phenomenon that position is rapidly gone up.Flood once brought huge life and property loss to human society.From ancient times to the present, the mankind are just
It struggles with flood always, building for flood control dam is exactly essential important component part in flood fighting link.It is existing
Flood fighting dykes and dams, be mostly the sub-bottom changes stayed in history, the artificial high roadbed built and built that pertains generally to fetch earth nearby is soft
Matter basis, rock-soil mechanics characteristic determine the deficiency of its anti-flood capacity.Especially dike, ant mouse hole evil, dike soil liquid are overflow in flood
The unstability that change, piping, dykes and dams basis are caused by the scouring a hole reasons such as collapse form crevasse, and flood is by crevasse surging racing current
Go out, form large area big flood, people's lives and properties sustain losses severely.
" early to block crevasse within one minute, so that it may to reduce by one point of flood loss ", this is a known by everybody common sense.To reach
As early as possible, the purpose of flood crevasse is blocked as soon as possible, and currently used method is:
1. the megalith, artificial prefabricated body etc. of the big quality of throwing, wait for the filling of these big quality in crevasse into crevasse
It has a foothold after forming support, then the earth rock material that throwing is smaller, is completed until crevasse blocks.
2. the artificial article such as shipwreck, heavy large truck, waits for that these artificial articles have a foothold to be formed in crevasse into crevasse
After support, then earth rock material that throwing is smaller, it is completed until crevasse blocks.
3. artificial lower to beating anchor spike in crevasse, after stablizing pile group and building up and to form support, then throwing earth rock material, up to
Crevasse, which blocks, to be completed.
4. during the flood that rises not as, after flood is decorporated completely, just carry out crevasse cubic metre of earth and stone reparation.
History experience have shown that:
Method 1 needs large-scale special mechanical equipment, and all very huge throwing of to be prepared in advance those quality, volume
Material, obviously there is the randomness of crevasse with flood fighting in this and closure crevasse scene greatly differs from each other mainly by the specified conditions of manpower.
Therefore it be only applicable to adequate preparation as dammed the Yangtze River situations such as.
Method 2 is a kind of accommodation of method 1, is the effect that megalith is replaced with hull, large truck car body.Obviously this is one
The unavoidable caving-in bash of kind.This method one comes that cost is very high, and two carry out the reparation crevasse engineering of these fillings afterwards
In be difficult be eliminated.The report of this flood fighting example is commonplace in recent years, reflects that ours is helpless.
Method 3 is the example typically mutually striven with the power of manpower and powerful nature.It is passed through in flood fighting report live video
Often there is such picture:We are young soldier, wear life vest, are safety rope on waist, are being difficult the crevasse flood stood firm
Sledgehammer is waved in water torrent, timber one by one or steel pipe are defied death scene when squeezing into crevasse stratum.The utility model person
Have to be filled with respect to these soldiers;Also these soldiers are filled with simultaneously and are felt ashamed and regretful.We very come without better method
Solve the problem of that this " spreading remote " perplexs us every year
Method 4 is most simple, does nothing.Obviously in this way " not as " the result is that the disaster time caused by flood most
Long, loss is also maximum.
Utility model content
The purpose of this utility model is that:Sealing tech in order to solve the dykes and dams flood crevasse that we possess at present exists
Human and material resources it is of high cost, block crevasse the time required to it is long, block the disadvantage that labor intensity is big, emergency personnel's security risk is big,
The utility model provides a kind of parallel rope type dykes and dams flood crevasse plugging device.
A kind of dykes and dams flood crevasse plugging device, including be arranged above the dykes and dams of crevasse both sides stress anchor picket, both ends
Supporting rope and dispensing rope, the tensioning rarefactor for being tensioned supporting rope and dispensing rope and the placement being fixed on stress anchor picket
In supporting rope and launch the water fender queue above rope;The water fender queue include it is multiple be connected in series by serializer it is parallel
One end of the light prefabricated water fender being arranged, light prefabricated water fender bottom is flexibly connected with supporting rope by support ring, light
The other end of water fender bottom is directly freely placed on dispensing rope.
The principles of the present invention are:Using being set up in the tensioning steel wire rope being vacantly tensioned above crevasse as light pre-
The stress supporting member of baffle wall processed;The prefabricated baffle wall of light inclination in crevasse is support to the flood that breaches a dyke in crevasse
It carries out blocking closure.Water fender queue length is less than crevasse 5-10cm of width, and after dispensing, its one end is located in dykes and dams crevasse
Water-bed face, other end oblique are hung on supporting rope, and entire prefabricated baffle wall inclination is stood in crevasse flood, to the flood in crevasse
Water plays extraordinary plugging action.The water fender queue includes multiple light prefabricated water fenders disposed in parallel, each
It is connected by serializer between light prefabricated water fender.It, according to actual needs directly will be more for different flood crevasse sizes
The modular method of a light prefabricated water fender assembly, convenient and efficient, wide adaptability.It can be saved during flood-fighting big
The human and material resources of amount and time improve and block efficiency.
Specifically, the width of the water fender queue is less than 5-10cm of width of dykes and dams flood crevasse, the water fender
Length is according to measuring, be calculated.
It is supporting steel-cable (with crevasse by latter specifically, two hanging parallel shelfs are set to the steel wire rope in crevasse
Interior flood inflow direction is front), baffle wall is by itself strong weight of water impact active force and water fender when it is closure crevasse
The main stress support member of power;By previous to launch steel wire rope, as the term suggests its effect is coordinated with supporting steel-cable, it is complete
At assembled water fender queue, the queue of conveying water fender, the launching water fender queue of the task.So-called conveying water fender queue refer to by
Assembled water fender queue is slid onto along parallel steel wire wire saws above the crevasse to be blocked, and water fender queue length, which is less than, bursts
5-10cm of mouth width degree, consistency from top to bottom.So-called dispensing refer to when water fender queue all it is accurate in place, after errorless on inspection, i.e.,
The tensioning rarefactor at rope both ends is launched in manipulation that can be under unified command, simultaneously, synchronous, and the dispensing steel wire rope of tensioning is loosened,
It allows one whole of water fender queue being put on thereon accurately to submerge in water, touches the bottom.Water fender queue one in this way at the bottom,
One oblique is hung on supporting steel-cable, forms an inclined continuous water blocking wall construction, surging flood quilt in crevasse
This tilts continuous waterwall cut-out.So far block crevasse breach a dyke flood task with regard to it is fast, efficient, safe, laborsaving, time saving,
Economic completion.
Specifically, the internal diameter of the support ring is bigger 1-2cm than the diameter of supporting rope.The internal diameter of support ring must assure that support
Ring easily can be slided freely on supporting rope, there is not allowed that clamping stagnation, the accidents such as fall off.The internal diameter of support ring is designed as comparing
The big 1-2cm of diameter of supporting rope, is conducive to the stability of support plate, and water blocking effect is more preferable.
Preferably, one end of the supporting rope is equipped with tensioning rarefactor, and the both ends for launching rope are respectively provided with tensioning relaxation
Device.It is that water fender queue is accurately put into water to and touched the ground in dykes and dams crevasse due to launching final purpose of restricting,
Must be assumed unified command of when therefore launching, manipulation simultaneously, synchronous launches the tensioning rarefactor at rope both ends, accurately launched with reaching
Purpose avoids the accident that crooked displacement occurs.
Preferably, the supporting rope and dispensing rope are mutually parallel.Supporting rope disposed in parallel and dispensing rope can ensure to keep off
The queue of water plate is not in the accident fallen when pulling and sliding, and also can guarantee that water fender queue one end forward direction falls into the water, no
It will increase the gap at water fender edge and flood crevasse edge.
Preferably, the supporting rope and dispensing rope are steel wire rope.In the utility model can other practical rope parts, steel wire
The tension of rope, abrasion resistance, hardness and flood fighting water slug degree are good.
Specifically, the light prefabricated water fender includes the skeleton made with steel profile and color steel tile outside setting skeleton;Bone
The bottom of frame is equipped with the card slot for disposing support ring, and bottom, top or the side of skeleton are equipped with the card slot for serializer.
After adopting the above scheme, the beneficial effects of the utility model are as follows:
(1) way that supporting point is established in conventional closure crevasse in crevasse is transformed into and is established outside crevasse by the utility model
Supporting point, this " transfer " of supporting point, makes the difficulty of establishing of supporting point be greatly reduced, settling time can shift to an earlier date significantly, build up
Speed can be greatly speeded up, this flood-fighting work for not blocking crevasse only as early as possible, as early as possible creates an important good basis
And it may;Also reached mitigate flood fighting soldier labor intensity, improve working conditions, ensure they safely, carry it is efficient
Purpose.
(2) the utility model conventional will block crevasse with being not easy to prepare, be not easy to transport, be not easy the large volume jettisoninged, big matter
The megalith of amount and the hack gravelstone for being not easy to stop are transformed into prefabricated light dedicated rectangle water fender water blocking, this " becomes
Change " make the source of closure crevasse material there is guarantee, the time of material to greatly shorten (all equipment Jun Yi seriations factories
Production, standardization are stored in flood fighting material depot), the utilization rate of material greatly improves, so that blocking work by the past
It is slow, difficult, dangerous, become timely, quick, safe, laborsaving, efficient again.
(3) the utility model does not need bulk transport, jettisoninging sets compared with tradition blocks crevasse method when blocking crevasse
It is standby;Some and uncomplicated common apparatus are only needed, and is easy to transport and set up, operation is also very simple.This advantage is especially suitable
It is combined and builds professional, keen-witted and capable, the motor-driven assault force that speedily carries out rescue work.Their peacetime trainings prepare equipment;It stands up and volunteer to help when crisis, with special
The level of industry is speedily carried out rescue work;Therefore it is more suitable for the event of the very strong big flood burst crevasse of randomness.
(4) the utility model is compared with tradition blocks crevasse method, almost without limitation on the time for blocking crevasse, what
When there is crevasse and can all be blocked immediately.Because the equipment needed for blocking all is complete ready, professional contingent has assembled
It awaits orders.Personnel and equipment are delivered to scene in time using modern flourishing communication and command system and traffic system, then blocking
Work can be unfolded immediately, and can complete to block work within the shortest time.This advantage of the utility model is thoroughly overturned
Flood-fighting blocks the " horse of " complicated " of preparation, " marathon " pattern and flood-fighting effect in crevasse work
Big gun afterwards " problem.The advantages of this " closure is unconditional, the time is not to wait for " of the utility model blocks crevasse, is to have found to crack
The gold of " as long as can realize earliestization and most shortization of blocking time, can be achieved with the maximization for combating a natural disaster mitigation effect " this proposition
Key.
(5) completely new flood fighting pattern of the utility model due to using technology specialty, tissue miniaturization, combat manoeuvre,
We just have ready conditions more fining, high efficiency, the normalization the work of combatting a flood tissue that will be undergone every year in this way.Compared to present
Landsturm, for the huge human and material resources spent by the neat combatant's law of sea warfare of the entire PLA, the flood fighting of the utility model at
Reality is very little.The huge of the humble and benefit of cost is the power for promoting this cause that can further develop.
(6) the utility model is not followed the beaten track, is not stuck to the old path by tradition;But utilize the method and science and technology dress of science
The strength set goes to struggle with crevasse flood, creates the miracle of " block crevasse and do not descend water, the not wet shoes of flood-fighting ".
(7) technique device of the utility model can facilitate dismounting, recycling, storage, recycling afterwards.
Description of the drawings
Fig. 1 is the vertical view after the dykes and dams flood crevasse plugging device installation of the utility model (when not working);
Fig. 2 is the vertical view of the dykes and dams flood crevasse plugging device of the utility model in use;
Fig. 3 is the side structure sectional view of the dykes and dams flood crevasse plugging device of the utility model in use;
Fig. 4 is the inner skeleton structural schematic diagram of the light prefabricated water fender of the utility model;
It is marked in figure:1- dykes and dams, 2- flood crevasses, 3- stress anchor pickets, 4- are tensioned rarefactor, 5- supporting ropes, and 6- is launched
Rope, 7- water fender queues, the light prefabricated water fenders of 8-, 9- serializers, 10- support rings, the light prefabricated water blocking frameworks of 11-.
Specific implementation mode
Below in conjunction with the utility model embodiment and attached drawing, the technical solution in the present embodiment understand completely
Description.Obviously, described example is only a part of the embodiment of the utility model, instead of all the embodiments.It is based on
The embodiments of the present invention, it is obtained by those of ordinary skill in the art without making creative efforts all
Other embodiments shall fall within the protection scope of the present invention.
As shown in Figure 1, a kind of dykes and dams flood crevasse plugging device, including the stress above crevasse both sides dykes and dams 1 is set
The supporting rope 5 and launch rope 6, for being tensioned supporting rope 5 and launching rope 6 that anchor picket 3, both ends are fixed on stress anchor picket 3
Tensioning rarefactor 4 and the water fender queue 7 for being placed on 6 top of supporting rope 5 and dispensing rope;One end of light prefabricated water fender 8
Bottom is slidably connected by support ring 10 and the assembly of supporting rope 5, and the bottom of water fender queue 7 is directly freely placed at dispensing rope 6
On, the width of water fender queue 7 is less than 5-10cm of width of flood crevasse 2, the length of the light prefabricated water fender 8 according to
It measures, be calculated.
The principles of the present invention are:Using being set up in the tensioning steel wire rope being vacantly tensioned above crevasse as prefabricated gear
The stress supporting member of water board wall;The prefabricated baffle wall of inclination that support in crevasse blocks the flood that breaches a dyke in crevasse
It blocks.Prefabricated water fender queue 7 is equal with crevasse width at length after wall, and after dispensing, its one end is located at the water in dykes and dams crevasse
Bottom surface, other end oblique are hung on supporting rope 5, and entire baffle wall inclination is stood in crevasse flood, is risen to the flood in crevasse
Extraordinary plugging action is arrived.Two hanging parallel shelfs are set to the steel wire rope in crevasse, by latter for supporting steel-cable (with
Flood inflow direction is front in crevasse), it be when blocking crevasse baffle wall by water impact active force and baffle wall from
The main stress support member of body gravity;By previous to launch steel wire rope, as the term suggests its effect is matched with supporting steel-cable
It closes, completes assembled water fender queue, the queue of conveying water fender, the launching water fender queue of the task.So-called conveying water fender queue
Refer to being slid onto assembled water fender queue above the crevasse to be blocked along parallel steel wire wire saws, water fender queue length
Less than 5-10cm of crevasse width, consistency from top to bottom.As shown in Fig. 2, so-called launch refers to when water fender queue is all accurate to
Position after errorless on inspection, can loosen under unified command, simultaneously, synchronously by the tensioning rarefactor that launch rope both ends, allow and put
It accurately submerges in water, sinks under water in one whole of water fender queue launched on rope.As shown in figure 3, water fender queue in this way
One hangs in the bottom, an oblique on supporting steel-cable, forms an inclined continuous water blocking wall construction, burbulent in crevasse
The flood gushed is cut off by this continuous waterwall of inclination.So far block crevasse breach a dyke flood task with regard to it is fast, efficient, safe,
Laborsaving, time saving, economic completion.
The internal diameter of the support ring 10 is bigger 1-2cm than the diameter of supporting rope 5.The internal diameter of support ring 10 must assure that support ring
10 can easily slide on supporting rope 5, the accidents such as clamping stagnation cannot occur, fall off., the internal diameter of support ring 10 is designed as than branch
The big 1-2cm of diameter of support rope 5, is conducive to the stability for supporting prefabricated water fender, water blocking effect is more preferable.
The water fender queue 7 includes multiple light prefabricated water fenders 8 disposed in parallel, each light prefabricated water fender 8
Between connected by serializer 9.Flood crevasse 2 varies, directly that multiple prefabricated water fenders are assembled according to the actual needs
It is convenient and efficient to adapt to the modular method of the flood crevasse 2 of different sizes, it can greatly be saved during flood-fighting
Human-saving, material resources and time cost improve efficiency.
One end of the supporting rope 5 is set there are one rarefactor 4 is tensioned, and the both ends for launching rope 6 are respectively provided with one respectively
It is tensioned rarefactor 4.It is that water fender queue is accurately put into water and touches dykes and dams crevasse due to launching 6 final purposes of rope
Interior bottom.When blocking crevasse, should under unified command, simultaneously, synchronous manipulate launch the tensioning rarefactor on rope both sides and loosen
Launch rope, to ensure water fender queue it is accurate dispensing and in place.It avoids that the accidents such as displacement, crooked occur.And supporting rope 5 is
It is connected with the assembly sliding of the bottom of prefabricated water fender 8 by support ring 10.
The supporting rope 5 and dispensing rope 6 are mutually parallel.Supporting rope 5 disposed in parallel and dispensing rope 6 can ensure water fender
Queue is not in the accident to fall off when drawing and sliding.And one end forward direction of water fender can be made to fall into the water, it not will increase gear
The gap of water edges of boards edge and 2 edge of flood crevasse.
The supporting rope 5 and dispensing rope 6 are steel wire rope.Other rope parts can be used in the utility model, steel wire rope
Tension, abrasion resistance, hardness and flood fighting water slug degree are good.
A kind of method for blocking of dykes and dams flood crevasse plugging device of the present embodiment, includes the following steps:
Step 1:Two stress anchor pickets 3, four stress systems are squeezed into respectively at the both ends of the top of 1 flood crevasse 2 of dykes and dams
Gu stake 3 is located at four vertex of same rectangle;
Step 2:It is fixed on stress anchor picket 3 after one end of steel wire supporting rope 5 is passed through tensioning rarefactor 4, simultaneously
Supporting rope 5 is tensioned.It is fixed on stress anchor picket 3 after the both ends for launching rope 6 are each passed through tensioning rarefactor 4, simultaneously will
Launch 6 tensioning of rope;Water fender queue 7 is multiple prefabricated light prefabricated water fender 8 compositions, adjacent two light prefabricated water blocking
It is connected by serializer 9 between plate 8;The light prefabricated water fender 8 does skeleton 11 with steel profile, and support is prefabricated on skeleton 11
The position of ring and serializer, facility.11 surface of skeleton is covered with color steel tile material.The seriation of all prefabricated water fenders is by factory
Production, standardization are stored in flood fighting material depot.
Step 3:Supporting rope 5 is connected by support ring 10 with the assembly sliding of 8 one end bottom of light prefabricated water fender.Together
When, the other end bottom of the light prefabricated water fender 8 is freely placed on dispensing rope 6.
Step 4:By unified command, simultaneously, synchronize loosen launch rope 6 both ends tensioning rarefactor 4 relaxation launch rope 6,
Until one end of water fender queue 7 is all accurately submerged in water and touches the ground in dykes and dams crevasse 2.Waterwall is established, flood
Water is truncated.
Step 5:With one or more materials pair in preprepared leak stopping water fender, straw bundle or plastic film
Some are still targetedly blocked in the hole of leak, hole, gap, entire crevasse of drying up.Crevasse blocks task and completes.
Specifically, the building course of the technique device of the utility model is as follows:
(1) the water-bed overall height H to levee crown of flood crevasse 2 is measured, the length h of prefabricated water fender is selected according to H.Generally
Take h>H (big 1.5-2m is advisable), to ensure prefabricated water fender, there are one rational angles of inclination with the water surface.
(2) crevasse width A is measured, is calculated with this and blocks light 8 quantity of prefabricated water fender needed for crevasse and required pre-
9 quantity of water fender serializer processed.
(3) the width L that two parallel steel wire ropes are determined according to H, takes L=H, to ensure length for the prefabricated water fender energy of h
Assembled in series is carried out on two parallel steel wire ropes and draws to be slid onto right over crevasse to be launched, and is not fallen off in sliding.
(4) according to the width L of two parallel steel wire ropes, appropriate location is advised in the plane of dykes and dams bodies top crevasse both sides
It draws selected tensioning steel wire rope and launches 3 locations of stress anchor picket of steel wire rope and start to build stake work.
Planning the principle for selecting stake location is:
A. ensure that two steel wire ropes are parallel, parallel spacing L;
B. stake location not be too near to dykes and dams edge or crevasse edge, new collapse occur to prevent dykes and dams ontology;
C. the dike soil soil property at stake location cannot be too soft, is otherwise unfavorable for building stake and undertakes tensile load;
3 pile-type of stress anchor picket has several pile-type such as light automotive stake, medium-sized driven pile, heavy melt pit stake, can fit respectively
Requirement that should be in crevasse different in width to the different tensile forces of steel wire rope.Selected pile-type is had to according to crevasse width, dykes and dams soil
The actual conditions reasonable selections such as matter, field condition, experience speciality.The characteristics of below with regard to several pile-type and its method of construction
It is described below:
(1) light automotive stake:Heavy motor vehicles are utilized respectively at the top of the dykes and dams of crevasse both sides as pile body (such as crawler type
Excavator, crawler dozer etc.), recycle the power of the heavy vehicle as the tensile force of steel wire rope.This advantage is
It easily sets up, is time saving and energy saving;The disadvantage is that lasting stability is poor, tensile force is smaller, also to occupy large scale equipment.It is adapted to crevasse
Relatively narrow situation (crevasse is less than 30m).
(2) medium-sized driven pile:Metallic rod is squeezed into as pile body into dike at the top of the dykes and dams of crevasse both sides.It is recommended that metalline stake
Diameter should select>The excellent medium carbon steel rod iron of the cylindrical, solid of 100mm, tip, comprehensive mechanical performance, piling bar are squeezed into deep in dike
Degree is more than 1000mm.The advantages of this stake is that bearing capacity is bigger than light automotive stake, and stability is good, is not take up miscellaneous equipment;It lacks
Point is that hand spike is more time-consuming.Solve the problems, such as the pre-manufactured hole before piling with regard to more preferable as being equipped with special small drilling machine
.It is adapted to the case where medium-width crevasse (crevasse 30-50m).
(3) heavy melt pit stake:In crevasse both sides, dykes and dams top down digs one and is about 1m, width about 0.6m, depth about 0.6m
Hole, length direction and the crevasse sides aligned parallel in hole.Hole is put into the original of about 800mm one section long, diameter about 400mm in hole after digging well
Juggle, the horizontal centre for lying in this log of steel wire rope i.e. pile.The operation principle of melt pit stake is:When steel wire tensioning, pulling force passes
To log, log converts pulling force to the pressure to crater wall.Since log surface area is very big, pretend with the unit pressure in crater wall
Power can very little.This allows soft dike soil also to have prodigious bearing capacity.The advantages of melt pit stake is bearing capacity far above light-duty
Motor-driven stake and medium-sized driven pile, therefore it is adapted to that crevasse is wider, the more demanding situation (crevasse of steel wire tensioning power>50m);
It is adapted to that dykes and dams soil property is too soft, is unfavorable for the special circumstances that driven pile establishes stable bearing capacity.Its shortcomings that is manpower
It digs pit more time-consuming.
Two tensioning steel wire ropes building courses be specially:
After stress anchor picket 3 is built, steel wire rope draws into steel wire loop with U-shaped card, according to connecting steel wire rope shown in Fig. 1
Stretcher rear enclosure is on built anchor picket.Finally by steel wire rope tensioning device by loose steel wire tensioning, two are tensioned steel
Cord is built and is finished.The tensioning steel wire rope built should meet following requirement:
(1) two steel wire rope keeping parallelism, and its width L meets the requirements.
(2) (prefabricated water fender quantity used is different) of different size according to crevasse, two steel wire tensioning degree are appropriate.
(3) in order to improve steel wire rope bearing capacity and reduce tensile force to the destructive bending moment force of anchor picket, steel wire rope
Set should be close to dykes and dams ground.
Light prefabricated water fender queue is built:
As shown in figure 4, being skeleton 11 with hollow steel profile, position, the facility of support ring and serializer are prefabricated on skeleton;
11 surface of skeleton is covered with color steel tile material.Light prefabricated special rectangle water fender is the specification after factory is manufactured by seriation
It is stored in flood fighting material depot.Using hollow steel profile do skeleton 11 be in order to improve bending resistance of the skeleton in stress and
Mitigate weight and is convenient for manpower transport.When blocking crevasse, which transports to tiling behind crevasse scene and is arranged in two tensionings
Parallel steel wire rope on carry out set of queues dress, on Special series device 9 reliably series connection between every two pieces of prefabricated water fenders;Every piece pre-
Support ring 10 on water fender processed is slidably connected with supporting steel-cable also reliable assembling.Water fender queue is in the flat of crevasse side
It is gradually pulled and is slid to crevasse opposite bank along tensioning steel wire rope from traction rope while assembly on row steel wire rope.When prefabricated water fender
Queue is when simultaneously Landfill covering lives entire crevasse for sliding on two steel wire ropes, prefabricated water fender queue length is less than crevasse width
5-10cm or so, up and down to just, prefabricated water fender queue is accused and is built up.
The foundation of prefabricated baffle wall:
The prefabricated water fender queue 7 above crevasse by " water fender queue width be less than crevasse 5-10cm of width, on
Under to just " build up, after errorless on inspection, under unified commander, simultaneously, synchronize the stretcher for loosening and launching steel wire rope both ends,
So that one whole of prefabricated water fender queue being put on dispensing steel wire rope is accurately submerged in water, touches the bottom.In this way, prefabricated water blocking
Plate queue as wall (oblique is hung on supporting steel-cable, it is heavy at one end enter the bottom, stood in crevasse flood at skewed),
The flood that breaches a dyke in crevasse is carried out blocking closure.Prefabricated baffle wall, which is established, to be completed.So far crevasse main task is blocked to complete.
Follow-up work after crevasse closure:
(1) after the prefabricated baffle wall is built up, the main flood in crevasse has been truncated closure, but may also have one
A little smaller holes, hole, gap are also in leak.At this moment ready leak stopping water fender, straw bundle, plastic film and other material pair can be used
These also in the hole of leak, hole, gap targetedly block and (can be generated in front when using hole, hole, clearance leakage strong
The physical phenomenon of attraction, can be fine with some soft material plugging effects).To achieve the purpose that dry entire crevasse,.
(2) after the completion of flood is decorporated or crevasse repairing, the plugging device of the utility model, that is, dismountable, recycling, storage,
It recycles.So far, entire crevasse blocks work declaration and is fully completed.
It is obvious to a person skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and
And without departing substantially from the spirit or essential attributes of the utility model, it can realize that this practicality is new in other specific forms
Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive.This practicality is new
The range of type is indicated by the appended claims rather than the foregoing description, it is intended that containing in the equivalent requirements of the claims will be fallen
All changes in justice and range are embraced therein.Any reference numeral in claim should not be considered as limitation
Involved claim.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped
Containing an independent technical solution.For the sake of this narrating mode of specification is just for the sake of understanding.Those skilled in the art answer
When considering the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms people in the art
The other embodiment that member is appreciated that.
Claims (7)
1. a kind of dykes and dams flood crevasse plugging device, which is characterized in that including the stress being arranged at the top of crevasse both sides dykes and dams (1)
Supporting rope (5) that anchor picket (3), both ends are fixed on stress anchor picket (3) and launch rope (6), for be tensioned supporting rope (5) and
It launches the tensioning rarefactor (4) of rope (6) and is placed on supporting rope (5) and launches the water fender queue (7) above rope (6);Institute
It includes multiple light prefabricated water fenders (8) disposed in parallel being connected in series by serializer (9) to state water fender queue (7), light
One end of prefabricated water fender (8) bottom is flexibly connected with supporting rope (5) by support ring (10), light prefabricated water fender (8) bottom
The other end in portion is directly freely placed on dispensing rope (6).
2. a kind of dykes and dams flood crevasse plugging device according to claim 1, which is characterized in that the water fender queue
(7) width is less than 5-10cm of width of dykes and dams flood crevasse (2).
3. a kind of dykes and dams flood crevasse plugging device according to claim 1, which is characterized in that the support ring (10)
Internal diameter is bigger 1-2cm than the diameter of supporting rope (5).
4. a kind of dykes and dams flood crevasse plugging device according to claim 1, which is characterized in that the supporting rope (5)
One end is equipped with tensioning rarefactor (4), and the both ends for launching rope (6) are respectively provided with tensioning rarefactor (4).
5. a kind of dykes and dams flood crevasse plugging device according to claim 1, which is characterized in that the supporting rope (5) and
Rope (6) is launched to be mutually parallel.
6. a kind of dykes and dams flood crevasse plugging device according to claim 1, which is characterized in that the supporting rope (5) and
It is steel wire rope to launch rope (6).
7. a kind of dykes and dams flood crevasse plugging device according to any one of claim 1-6, which is characterized in that described
Light prefabricated water fender (8) includes that the skeleton (11) made with steel profile and setting skeleton (11) cover color steel tile outside;Skeleton (11)
Bottom be equipped with card slot for disposing support ring (10), bottom, top or the side of skeleton (11), which are equipped with, is used for serializer (9)
Card slot.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721757554.1U CN207714256U (en) | 2017-12-15 | 2017-12-15 | A kind of dykes and dams flood crevasse plugging device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721757554.1U CN207714256U (en) | 2017-12-15 | 2017-12-15 | A kind of dykes and dams flood crevasse plugging device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207714256U true CN207714256U (en) | 2018-08-10 |
Family
ID=63055932
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721757554.1U Expired - Fee Related CN207714256U (en) | 2017-12-15 | 2017-12-15 | A kind of dykes and dams flood crevasse plugging device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207714256U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114232561A (en) * | 2021-12-20 | 2022-03-25 | 陆正华 | Device and method for repairing flood control dam of hydraulic engineering |
-
2017
- 2017-12-15 CN CN201721757554.1U patent/CN207714256U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114232561A (en) * | 2021-12-20 | 2022-03-25 | 陆正华 | Device and method for repairing flood control dam of hydraulic engineering |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108104058A (en) | A kind of dykes and dams flood crevasse plugging device and its method for blocking | |
US8287209B2 (en) | Protective flood barrier system | |
CN104372803B (en) | Dyke reinforcement assembled moving cofferdam | |
KR20120112315A (en) | System for apparatus of control a flood disaster using potential energy of water | |
CN206428653U (en) | A kind of flood control small dike | |
CN106948349A (en) | Quick block up fabricated construction system, erecting device and method | |
CN207714256U (en) | A kind of dykes and dams flood crevasse plugging device | |
CN107142898A (en) | A kind of dyke crevasse fast plugging device | |
WO2021063001A1 (en) | Prefabricated plugging framework and prefabricated framework plugging dam construction method | |
CN2372368Y (en) | Plugging iron cage | |
KR20200099259A (en) | Tsunami disaster prevention dispensing device | |
CN109881634A (en) | A kind of flood season dike breach rapid rescue method shut off using geosynthetics | |
CN206784389U (en) | Quick block up fabricated construction system and erecting device | |
KR20200100268A (en) | Dispatching device for landslide disaster prevention | |
CN113089571A (en) | Assembled water-permeable energy-dissipating tetrahedral embankment plugging member and construction method thereof | |
CN208647111U (en) | Wind wave prevention marine devices | |
CN110424329A (en) | A kind of dyke is quickly blocked up specific stub net anti-impact equipment and the application method of speedily carrying out rescue work | |
CN114438965B (en) | Breach blocking device and rapid blocking method | |
CN106436649A (en) | Flow control technology and series equipment thereof | |
KR102452262B1 (en) | Dependent Poisoning System for Earthquake Tsunami Prevention | |
CN204238233U (en) | Dyke reinforcement assembled moving cofferdam | |
CN2391910Y (en) | Truss for blocking break of a dike | |
CN1651658A (en) | Flood proof leak proof drought proof bag and matched reinforcing bar cage, steal girder net structure | |
CN106088145B (en) | Soft foundation water blocking wall construction and construction method | |
CN108750031A (en) | Wind wave prevention marine devices and its working method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180810 |
|
CF01 | Termination of patent right due to non-payment of annual fee |