- CN2372368Y CN2372368Y CN 98231212 CN98231212U CN2372368Y CN 2372368 Y CN2372368 Y CN 2372368Y CN 98231212 CN98231212 CN 98231212 CN 98231212 U CN98231212 U CN 98231212U CN 2372368 Y CN2372368 Y CN 2372368Y
- Authority
- CN
- China
- Prior art keywords
- plugging
- iron cage
- plugging iron
- water
- breach
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Revetment (AREA)
Abstract
The utility model relates to a mouth plugging iron cage, which is suitable for plugging equipment for flood levee crevasse and is a long cylindrical iron cage or an iron cage with a trapezia structure made of shaped steel. When flood levee crevasse is occurred, a plurality of the mouth plugging iron cages are arranged in a gap to form a frame, a water plugging wall is built by using the frame, and the arranged plugging materials can be prevented from washing away by water for 100 percent. The utility model is free from the limit of foundational conditions, a stable plugging dam can be built in the same way even if on swampy clay, a gap is plugged rapidly, and human and material resources are saved more than 90 percent.
Description
The present invention relates to a kind of Plugging iron cage of making by shaped steel, be adapted to set up when flood bursts the dam of blocking up especially.
At present, when flood damage takes place, adopt ways such as piling, parabolic, shipwreck to block up.By " the steel, wood, soil and stone mixed dam " of the invention of Beijing army, be to adopt pricking several rows of steel pipe frame on the basis of breach recently, be thrown into a large amount of sandy gravel bags and piece stone again, this technology only is adapted to 7 meters of the depth of waters, the current operation of flow velocity 1.5 metre per second (m/s)s.When adopting the piling method, because can only adopt manually, work efficiency is extremely low, and labour intensity is high, also can not beat very deeply, and must beat on levee foundation, and the intensity of levee foundation is had destruction.Too soft or too hard as basic soil property, stake just is difficult to beat steady, and construction is difficulty quite, and when breach had occurred and enlarging, piling was just quite dangerous.When adopting the shipwreck method, because of the proportion of ship is lighter than water, is difficult to control and sinks, the shipwreck position is difficult to accurately, and when closure, might produce impact force the water blockoff wall that has formed is uprooped, or the dykes and dams avalanche that does not collapse.Moreover this method does not fit into big breach.Adopt methods such as Rhizoma Smilacis Chinensis, iron cage mounted stone, because after Rhizoma Smilacis Chinensis or iron cage mounted go into stone, the proportion sharp fall, resistance increases suddenly, so though they weigh nearly 10 tons, still can be swept away by the torrent.The breach big for drop, that current are anxious also is " getting half the result with twice the effort ", and the area of blocking up that said method once forms is all quite limited, and manpower, amount of materials consumed are surprising.Occurring in Anxiang, Hunan peace in 1998 seven-August makes the breach of protective embankment and blocks up, all existing ways have been adopted, last 16 days, just join the two sections of a bridge, etc in the time of at last also can only drop is reduced to 1.61 meters by more than 10 meters inside and outside breach, long especially if not peak water level duration then, the meaning of blocking up specifically is little.
According to the above, also there is not a kind of equipment of blocking up of special use at present, can not be subjected to the restriction of geological conditions, and block breach rapidly with minimum manpower, material consumption as far as possible.
The purpose of this invention is to provide a kind of Plugging iron cage, it is not subjected to the restriction of breach geological conditions, and the breach that can promptly stem the flood and inrush can reach minimum manpower and material consumption again.
The object of the present invention is achieved like this: Plugging iron cage is the elongated cylindrical iron cage by section steel manufacture, it is linked together with many long purlins by a plurality of outer rings, the outer ring outside, its center is welded with cross to increase its radially bearing capacity, between outer ring and the diagonal angle, outer ring, be welded with many groups and be the diagonal brace that a plurality of directions are provided with, to increase the axial and angle supporting capacity of iron cage.The end that Plugging iron cage meets water is welded with the reinforcing bar fence, is convenient to set up the water blockoff wall, in order to increase Plugging iron cage and basic binding ability, is welded with many row's spike-tooths around the part Plugging iron cage, and this Plugging iron cage is arranged at lower floor.Laterally being easy to of Plugging iron cage rolled, and is convenient to carrying and is provided with.When a plurality of Plugging iron cages are stacked,, can not axially promote wherein any one because its outer ring and cylindrical block mutually.Its diameter can reach more than one meter, the water blockoff area of each can reach more than 1 square metre, length can reach the several times of diameter, weight hundreds of kilogram is to several tons, because resistance is little during its entry, proportion is 7.8 times of water, can be not washed away in the breach so push, also not too influence the flow velocity of water, need not any reinforcement measure just can form a stable framework, set up the water blockoff wall then or synchronously.The water blockoff wall can be used sand pocket, steel plate or other equipment special.Because this moment, breach formed a stable framework, the ship of delivery goods and materials can have been accelerated the process of blocking up near the breach operation.After Plugging iron cage pushes in the breach, embed in the earth on basis, can bear very big thrust because of the spike-tooth around it always has one side.After the water blockoff wall was set up, Plugging iron cage was not influenced by buoyancy of water, and the hydraulic pressure outside the dike has increased the weight of dam body like this to the angled dam foundation (the arrow A place among Fig. 5) of pressing in the whole dam of blocking up with regard to the pressure that has utilized water-head.Even the earth that the basis is soft, the Plugging iron cage of lower floor (can adopt the anti-iron cage that falls into) is absorbed in the earth, or base integral sinks, and still can form the firm dam of blocking up, soft earth, and effect is remarkable.When the breach drop is too high, can establish many row's Plugging iron cages in lower floor, and they vertically are chained together, its length can reach more than 30 meters, like this, even breach is up-and-down physical features, still can play a role effectively.After the water blockoff wall was set up, the iron cage was in the backwater end, is exposed to fully in the air, and the water blockoff wall can be found rapidly and be handled if any leakage.
Plugging iron cage is a kind of emergency flood fighting of special use equipment of blocking up, can make standby in advance, in case flood takes place to burst, can be transported to the scene rapidly, they can be manually, hydrotransport and sinking, also can adopt helicopter to hang, their characteristics are the framework of setting up the water blockoff dam and set up the water blockoff wall and proceed in two phases, both avoided buoyancy of water and impact force to setting up the destruction of water blockoff wall, the pressure of water-head increases the weight of the weight of dam body inside and outside utilizing again, the action of gravity that makes dam body on the dam foundation, thereby dam body and basis are combined.
According to the above, Plugging iron cage has solved the technical barrier that the flood breach is blocked up, and can set up a support at breach quickly and effectively and set up the framework of water blockoff wall, as mix other facility, can prevent the expansion of breach rapidly, and then set up or set up synchronously the water blockoff wall; Highly difficult engineering when it does not have closure, the goods and materials that can guarantee to block up are absolutely not washed away.It can make standby in advance, can be transported to the scene rapidly, can adopt artificial, waterpower sinking or helicopter to hang, consume human and material resources and have only below 1/10th of existing method; It is not subjected to the restriction of breach basic geology condition, the soft place of soil property, and effect is remarkable, even base integral sinks, also its stability of entail dangers to not.It is through after the antirust processing, can long-term storage, and repeated multiple times is used, and its life-span can reach more than 100 years, and use cost is quite cheap, and is convenient to cleaning after using, and has reduced the difficulty and the cost that recover the damaged or destroyed by flood engineering.
Be further described inventing again in conjunction with the accompanying drawings more below:
Fig. 1 is the structural representation of Plugging iron cage;
Fig. 2 is the Plugging iron cage structural representation of band anti-trapping board;
Fig. 3 is a triangle Plugging iron cage structural representation;
Fig. 4 is that Plugging iron cage uses the arrangement schematic diagram;
Fig. 5 is the schematic cross-section of Fig. 4;
Among Fig. 1, Plugging iron cage is made a firm elongated cylindrical or polygonal iron cage by some outer rings 1, stringer 2, diagonal brace 3, cross 4, spike-tooth 5, its outer ring 1 outside, stringer 2 is interior, the middle part of outer ring 1 is welded with cross 4, to bear radial load, diagonal brace 3 diagonal angles are welded on two outer rings, can bear the axial of any direction and angle load, when a plurality of Plugging iron cages rows stack, block mutually its outer ring 1, can not axially promote wherein any one.In order to increase Plugging iron cage and basic adhesive power, the spike-tooth 5 of can burn-oning around the Plugging iron cage of lower floor can be set up fence 6 at metope, is beneficial to set up the water blockoff wall, prevents to establish stifled goods and materials and is washed away by current.
Among Fig. 2, too soft for anti-breach basis, can longitudinally establish several piece anti-trapping board 7 in the total length in the centre of Plugging iron cage, after Plugging iron cage poached, anti-trapping board 7 was big with the contact area of earth, and pressure is little, just can bear the pressure of whole water blockoff wall.Even whole immerge still can not influence the stability on whole water blockoff dam.
Among Fig. 3, the cross section of Plugging iron cage is a triangle, and its three all are welded with many row's spike-tooths 5, and any one side contacts with ground all has spike-tooth 5 to insert ground, has increased the adhesive power of Plugging iron cage with the basis, and its shortcoming is the manpower transport and throws in difficulty.
Among Fig. 4,5, when the flood breach takes place after, Plugging iron cage is transported to the scene, they is pushed the breach, when breach is big from the Xu Di two ends, take springboard 8 in the above, be convenient to continue operation, after Plugging iron cage enters in the breach, because its outer ring 1 is stuck mutually, can not axially promote, just can set up water blockoff wall 9 at end facing water.When cut height was big, lower floor can set up many row's Plugging iron cages, to strengthen its stability, in case of necessity, establishes one deck iron bar 10 between Plugging iron cage and water blockoff wall, is beneficial to the foundation of water blockoff wall, and fence 10 usefulness shaped steel are made.After water blockoff wall 9 was set up, the outer hydraulic pressure of dike will form the pressure of an oblique below in dike, and Fig. 5 A is pressed to the dam foundation to Plugging iron cage in the place, has increased the weight of dam body like this with regard to the pressure that utilizes water-head.The water blockoff wall can adopt sand pocket, steel plate or other equipment special.After the water blockoff wall was set up, Plugging iron cage was in the backwater end, exposes the water surface fully, if leakage is arranged, can find rapidly, in time handled.
Claims (4)
1, a kind of a kind of Plugging iron cage of being made by shaped steel is characterized in that by outer ring, stringer, cross, diagonal brace or adds that spike-tooth is formed an elongated cylindrical or the cross section is polygonal equipment of blocking up.
2, Plugging iron cage according to claim 1 is characterized in that: outer ring, stringer, cross, diagonal brace or add spike-tooth and all weld together securely.
3, Plugging iron cage according to claim 1 is characterized in that when two or more Plugging iron cages were stacked, blocked mutually its outer ring, can not axially promote wherein any one.
4, Plugging iron cage according to claim 1 is characterized in that the end face of end facing water can be welded with fence.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 98231212 CN2372368Y (en) | 1998-08-19 | 1998-08-19 | Plugging iron cage |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 98231212 CN2372368Y (en) | 1998-08-19 | 1998-08-19 | Plugging iron cage |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 99233465 Division CN2391910Y (en) | 1999-06-03 | 1999-06-03 | Truss for blocking break of a dike |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2372368Y true CN2372368Y (en) | 2000-04-05 |
Family
ID=33980636
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 98231212 Expired - Fee Related CN2372368Y (en) | 1998-08-19 | 1998-08-19 | Plugging iron cage |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2372368Y (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101974893A (en) * | 2010-09-28 | 2011-02-16 | 张照华 | Tripod plug cage for river closure of flood-resisting buster and watercourse |
CN102330434A (en) * | 2010-07-13 | 2012-01-25 | 长江水利委员会长江科学院 | Throwing material for lightening interception difficulty and protecting dikes of rivers |
CN107938605A (en) * | 2017-12-29 | 2018-04-20 | 郑州玄机器人有限公司 | One kind supports fixed breach plugging device and method |
CN107988996A (en) * | 2017-12-29 | 2018-05-04 | 郑州玄机器人有限公司 | One kind moves anti-wire type breach plugging device, method |
CN108005021A (en) * | 2017-12-29 | 2018-05-08 | 郑州玄机器人有限公司 | One kind supports anti-wire type breach plugging device, method |
CN108118665A (en) * | 2017-12-29 | 2018-06-05 | 郑州玄机器人有限公司 | A kind of breach plugging device and method using fixed tower |
CN108203969A (en) * | 2017-12-29 | 2018-06-26 | 郑州玄机器人有限公司 | The flexible board-like breach plugging device of one kind, method |
CN108547253A (en) * | 2018-04-23 | 2018-09-18 | 青岛破浪舟车船装备科技有限公司 | A kind of device preventing dam break |
CN109281287A (en) * | 2017-12-29 | 2019-01-29 | 郑州玄机器人有限公司 | It is a kind of to use breach plugging device, the method for fixing tower |
CN106400740B (en) * | 2016-09-23 | 2019-06-11 | 武汉大学 | A kind of method and device of blocking up after dyke breaking |
CN113882315A (en) * | 2021-10-09 | 2022-01-04 | 尚风科技股份有限公司 | Dam closure construction method |
CN115125912A (en) * | 2022-08-06 | 2022-09-30 | 安徽瑞迪工程科技有限公司 | Be used for on-spot rapid Assembly prism body component of permeating water of stifled mouth |
-
1998
- 1998-08-19 CN CN 98231212 patent/CN2372368Y/en not_active Expired - Fee Related
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102330434A (en) * | 2010-07-13 | 2012-01-25 | 长江水利委员会长江科学院 | Throwing material for lightening interception difficulty and protecting dikes of rivers |
CN102330434B (en) * | 2010-07-13 | 2014-01-22 | 长江水利委员会长江科学院 | Throwing material for lightening interception difficulty and protecting dikes of rivers |
CN101974893A (en) * | 2010-09-28 | 2011-02-16 | 张照华 | Tripod plug cage for river closure of flood-resisting buster and watercourse |
CN106400740B (en) * | 2016-09-23 | 2019-06-11 | 武汉大学 | A kind of method and device of blocking up after dyke breaking |
CN108118665A (en) * | 2017-12-29 | 2018-06-05 | 郑州玄机器人有限公司 | A kind of breach plugging device and method using fixed tower |
CN108005021A (en) * | 2017-12-29 | 2018-05-08 | 郑州玄机器人有限公司 | One kind supports anti-wire type breach plugging device, method |
CN107988996A (en) * | 2017-12-29 | 2018-05-04 | 郑州玄机器人有限公司 | One kind moves anti-wire type breach plugging device, method |
CN108203969A (en) * | 2017-12-29 | 2018-06-26 | 郑州玄机器人有限公司 | The flexible board-like breach plugging device of one kind, method |
CN109281287A (en) * | 2017-12-29 | 2019-01-29 | 郑州玄机器人有限公司 | It is a kind of to use breach plugging device, the method for fixing tower |
CN107938605A (en) * | 2017-12-29 | 2018-04-20 | 郑州玄机器人有限公司 | One kind supports fixed breach plugging device and method |
CN108547253A (en) * | 2018-04-23 | 2018-09-18 | 青岛破浪舟车船装备科技有限公司 | A kind of device preventing dam break |
CN113882315A (en) * | 2021-10-09 | 2022-01-04 | 尚风科技股份有限公司 | Dam closure construction method |
CN115125912A (en) * | 2022-08-06 | 2022-09-30 | 安徽瑞迪工程科技有限公司 | Be used for on-spot rapid Assembly prism body component of permeating water of stifled mouth |
CN115125912B (en) * | 2022-08-06 | 2024-04-19 | 安徽瑞迪工程科技有限公司 | Water permeable prismatic member for on-site rapid assembly of plugging port |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN2372368Y (en) | Plugging iron cage | |
CN108193606B (en) | A kind of means of defence of local scour near pier | |
CN210341949U (en) | Slope protection structure with anti-landslide function | |
CN113089571A (en) | Assembled water-permeable energy-dissipating tetrahedral embankment plugging member and construction method thereof | |
CN205999849U (en) | A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system | |
CN106192896B (en) | A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system and method | |
CN2391910Y (en) | Truss for blocking break of a dike | |
CN111560917A (en) | Detachable rapid breach repairing structure | |
CN107237292B (en) | A kind of area the Lower Reaches of The Yellow River Kuan Tan village Bi Shui platform | |
CN207597339U (en) | A kind of assembled for punishing piping encloses well | |
CN106677121B (en) | Protect the movable permeable spur structure and construction method of Coastal erosion | |
CN101974893A (en) | Tripod plug cage for river closure of flood-resisting buster and watercourse | |
CN214033660U (en) | Ecological wind-prevention and sand-fixation system for railway protection | |
CN211948228U (en) | Support arrangement for be used for breach shutoff | |
CN212477800U (en) | Anchoring gabion retaining wall | |
CN210507492U (en) | Cofferdam structure | |
CN107447720B (en) | A kind of village Lower Reaches of The Yellow River Kuan Tanqu platform method | |
CN118422641B (en) | Embankment breach plugging structure based on rocket anchors and tubular piles and construction method | |
CN114960540B (en) | Ecological wave-dissipating scour-preventing multi-bell hollow block and application thereof | |
CN216712792U (en) | Railway ecological alloy sand prevention system | |
CN215593753U (en) | Dangerous rock falling stone blocking structure | |
CN220394522U (en) | Anchor-pull type supporting structure for steep slope dangerous rock cavity and supporting pier casting template thereof | |
CN217419494U (en) | Domatic type mud-rock flow structure of blocking | |
CN218291845U (en) | Clay core wall dam | |
CN114846964B (en) | Method for reclamation of closed tailings pond of large pit type |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C19 | Lapse of patent right due to non-payment of the annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |