CN205999849U - A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system - Google Patents

A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system Download PDF

Info

Publication number
CN205999849U
CN205999849U CN201620998473.XU CN201620998473U CN205999849U CN 205999849 U CN205999849 U CN 205999849U CN 201620998473 U CN201620998473 U CN 201620998473U CN 205999849 U CN205999849 U CN 205999849U
Authority
CN
China
Prior art keywords
preventer
gabion
frigid
mountainous areas
protection system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201620998473.XU
Other languages
Chinese (zh)
Inventor
栾桂涛
宋战平
王慧
李世豪
张鑫
王鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Road and Bridge Corp
Original Assignee
China Road and Bridge Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Road and Bridge Corp filed Critical China Road and Bridge Corp
Priority to CN201620998473.XU priority Critical patent/CN205999849U/en
Application granted granted Critical
Publication of CN205999849U publication Critical patent/CN205999849U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system, including:First preventer, it is arranged in the rhone between roadbed and side slope, and described first preventer is made up of the gabion net cage being filled with stone that multiple longitudinal extension directions along described rhone are arranged in order;Second preventer, it is installed in the top of described first preventer, described second preventer is made up of the gabion wall of multiple gabion posts and the two neighboring gabion post of connection, and gabion post is connected with the anchor pole in side slope described in partial insertion, so that described first preventer and described second preventer are connected with described side slope flexible.The ecological protection system that this utility model provides is applied to high-intensity earthquake area, the weak ecology of reducible frigid mountainous areas, has good water permeability, treatment in accordance with local conditions, easy construction, the rational advantage of structural system.

Description

A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system
Technical field
This utility model is related to side slope protection technical field, and more specifically, it is tight that this utility model is related to a kind of highlight lines Cold mountain highway cutting gradient slope ecological protection system.
Background technology
With the development of transportation business, the highway construction of highlight lines frigid mountainous areas is also more and more ripe.Highlight lines are tight The gradient slope that cold mountain highway construction of road cutting is formed is put forward higher requirement to protection.
High and cold mountain area highway cutting construction causes very big destruction to the weak ecological environment in high and cold mountain area, therefore in opposite side Slope needs during building safeguard procedures to take certain measure to recover the weak ecology in high and cold mountain area, it is to avoid ecological environment continues Deteriorate, during rainy season set, the disaster such as mud-rock flow occurs.The gradient slope that highway cutting construction in high and cold mountain area is formed have the gradient precipitous, The feature that rainy season flow rate of water flow is big, erosion is serious, stably causes great threat to the highway embankment built.High intensity Zone Domain can cause landslide and native stone to be scattered when coming earthquake, and side slope has larger vibration, or even produces compared with large deformation.
The stone masonry structure that traditional bank protection measure is mainly constructed using stone and cement mortar is as gravity retaining wall Side slope carries out a gear protection.This safeguard structure is only protected from the amechanical angle of plane stress, does not consider that space is divided Cloth and the impact to ecological environment, and the gravity retaining wall of this form is not appropriate for the ground of mountain area high slope, gradient slope Shape is protected.In rainy season set, the weak high and cold mountain area of ecosystem easily forms the big mud-rock flow of high flow capacity flow velocity, this rigidity Retaining wall easily be subject to temporary impact and destroy.Additionally, this gravity retaining wall drainage performance does not adapt to dash forward as it The mountain torrents mud-rock flow coming, easily puts aside behind in wall, and continuous lifting water level increases hydrostatic pressure and threatens stablizing of retaining wall.High and cold Mountain area freezing season, this kind of retaining wall is susceptible to frost heaving failure or freeze-thaw cycle destroys.It is increasingly subject to weight in ecological, environmental protective Depending on today, the out-of-date anti-cob wall of gravity type of this tradition seems incompatible with the Ecological Concept of environmental protection.High and cold mountain area After building highway, ecological environment suffers from certain destroying, and certain measure that what exigence was artificial take is gone back ecosystem as early as possible System.Traditional retaining wall is rigid structure, can not resist strong earthquake when high-intensity earthquake area is when coming earthquake and make With and occur compared with havoc.
Utility model content
A purpose of the present utility model is to solve at least the above, and provides the advantage that at least will be described later.
This utility model is prevented it is also an object that providing a kind of highlight lines frigid mountainous areas highway cutting gradient slope ecology Protecting system, this ecological protection system takes full advantage of the building stones that construction of road cutting is discarded, and has flexible structure, strong adaptability, energy Enough resist mud-rock-flow-impact and earthquake damage, there is easy construction, green economy, ecological, environmental protective, treatment in accordance with local conditions, water penetration The good, advantage of decompression draining.
This utility model is prevented it is also an object that providing a kind of highlight lines frigid mountainous areas highway cutting gradient slope ecology Protecting system, this ecological protection system can sluice in draining, stops mudstone, protection side slope and roadbed, can recover protection ground simultaneously The ecology in area.
To achieve these goals, this utility model provides a kind of highlight lines frigid mountainous areas highway cutting gradient slope ecology Guard system, including:
First preventer, it is arranged in the rhone between roadbed and side slope, and described first preventer is by multiple Form along the gabion net cage that the longitudinal extension direction of described rhone is arranged in order, be separately filled with the plurality of gabion net cage Stone;
Second preventer, it is installed in the top of described first preventer, and described second preventer is by multiple stones Cage post and the gabion wall composition connecting two neighboring gabion post, described gabion wall is upper and lower by the double-deck gabion net being filled with rubble Superposition setting is formed, and each gabion post is connected to form by the vertical superposition of the multiple gabions being filled with rubble, and forms cylinder Structure, and described gabion post is connected with the anchor pole in side slope described in partial insertion, so that described first preventer and institute State the second preventer to be connected with described side slope flexible.
This utility model treatment in accordance with local conditions, centralized recovery discards the building stones of residual using construction of road cutting, has green economy, takes The convenient feature of material.By building stones being filled in gabion net cage, gabion net and gabion it is achieved that good permeability, row The feature of water decompression, can sluice in rainy season set in draining, stops mudstone, protection side slope and roadbed.
The annexation of the first preventer in this utility model and the second preventer and side slope is flexible connection, no It is same as traditional retaining wall and local failure occurs when by local assault, this utility model, can when Freshets roar down from the mountains During resisting mud-rock flow temporary impact, cooperative bearing is deformed according to stressing conditions adjust automatically, play first well and prevent Protection unit and the protective action of the second preventer, efficiency is higher, and can be repaiied by the method resetting after the deformation that is hit Multiple, simple and practical economy and facility.The connected mode of anchor pole simultaneously:On the one hand the second preventer can be made in the feelings of material-saving Under condition, continuous accumulation superposition is raised, and adaptation mountain area is tall and big, and on the other hand the engineering situation of gradient slope can make the second preventer Become an entirety with side slope well.
This utility model arranges the first preventer of filling megalith, the larger energy of stone interblock gap under the second preventer Enough rainwater-collectings leaving side slope are discharged.This design has rapid drainability, and more traditional retaining wall arranges gutter It is more suitable for tackling precipitate instantaneous high-speed large-flow mountain torrents mud-rock flow, being capable of draining rapidly, it is to avoid on water level after retaining wall Rise, hydrostatic pressure increases, destroy retaining wall.The rainwater that side slope of embankment flows down can be received simultaneously, safeguard that it is stable.
Based on this utility model arranges the first larger preventer in the second preventer bottom, the inside is filled relatively Big stone, has larger gap between ratchel, for bottom water flow flowing.Second preventer is according to geological conditions and stress Characteristic is connected with the anchor pole throwing side slope into, provides skid resistance for whole guard system, and side slope applies active pressure and keeps stable.
Preferably, in described highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system, described ecological anti- Protecting system also includes:
3rd preventer, it is filled between described second preventer and described side slope, described 3rd preventer It is made up of multiple ecology bags, each ecology bag is built with the flourishing plant seed of rhizome.
This utility model is built in view of frigid mountainous areas highway and is caused destruction to the weak ecological environment in location, therefore Certain measure need to be taken to recover ecological.This utility model landfill ecology bag between the second preventer and side slope, to recovery Original ecological environment has very big power-assisted.In later stage ecology bag, plant germination is taken root, and the protective action of side slope further enhances, will The side slope protection effect in later stage is upgraded further.What ecology bag was built-in simultaneously is that location is primary, root for soil nutrient and protection The plant seed that stem is flourishing, easily survive:This measure one side is to prevent from introducing alien species, breaks original biological chain, causes this Ground ecology is unbalance further;On the other hand it is that original species are more suitable for protecting the ecological environment of on-site high and cold mountain area, more hold Easily survive, rooting propagation, to original ecological environment without interference with side slope also can be protected.But, need to fold with caution in work progress Put ecology bag, it is to avoid ecology bag compressing anchor pole damages.
Preferably, in described highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system, described ecological anti- Protecting system also includes:
At least one gutter, it is arranged under the steady layer of water of described roadbed, described at least one gutter respectively with Described rhone vertically connects, and extends to described side slope away from the side of described roadbed.According to on-site rainy season side slope water The density in flow set gutter, concentrates the quantity in sluicing location encryption gutter, with rapid draining at mountain pass.
Preferably, in described highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system, each gabion post In multiple gabions between by steel wire lashing together.
Preferably, in described highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system, described gabion net The ratio of the length, width and height of case is 3:2:2.
Preferably, in described highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system, described gabion net Case is the rectangular configuration that many transverse steel wire and the welding of multiple longitudinal steel wire are formed, and is provided with a longitudinal steel wire wherein The quoit being connected with anchor pole.
High-strength tenacity steel wire colligation is adopted, gabion is many transverse steel wire and multiple longitudinal steel wire between gabion The rectangular configuration that welding is formed, transverse steel wire and longitudinal steel wire are the steel wire with high-strength corrosion-resisting or the height being enclosed with PVC Intensity steel wire, and the frame of gabion is welded using suitable anticorrosion reinforcing bar.Gabion welds on longitudinal reinforcement Connect quoit, be connected with anchor pole with facilitating.
This utility model at least includes following beneficial effect:
1st, highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system described in the utility model has well Water flowing drainability, there is flexible structure it is adaptable to high-intensity earthquake area steep side slope protection, can when earthquake happens suddenly Produce larger deformation to resist earthquake potential damage it is ensured that effect still can be played after the earthquake, it is to avoid send out Raw landslide, falling rocks etc. damages road, the phenomenon stopping traffic, hindering earthquake rescue.
2nd, highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system described in the utility model has well Water penetration, the rainwater that the side slope when rainy season set flows down can discharge quickly, it is to avoid rainwater is accumulated, and endangers the first preventer Stability with the second preventer.There is good interception result to silt stone, it is to avoid mud-rock-flow-impact embankment road simultaneously.
3rd, first in highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system described in the utility model prevents In protection unit, filling stone, is filled with rubble in the second preventer, by the cooperation of larger stone and rubble, can be fine Reply instantaneous mud-rock flow impact.Deformation, cooperative bearing can be automatically generated when suffering from mud-rock-flow-impact, a gear effect is bright Aobvious lifting.And only need to reset in later stage repair process and just can restore.Later maintenance low cost.
4th, highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system described in the utility model recycles and repaiies Build the waste stone that highway stays so as to turn waste into wealth, draw materials conveniently, substantial amounts of cement, environmental protection will not be consumed simultaneously, apply Work is convenient, economy and facility.
5th, the anchor pole in highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system described in the utility model with The cooperation of the second preventer, can make the second preventer constantly raise, and keep the stablizing of the second preventer, and be second to prevent Protection unit provides antiskid, anchorage, adapts to towering precipitous side slope protection, has the advantages that low cost.
Part is embodied by further advantage of the present utility model, target and feature by description below, and part also will be passed through Research of the present utility model and practice are understood by the person skilled in the art.
Brief description
Fig. 1 is that the highlight lines frigid mountainous areas highway cutting gradient slope described in the one of embodiment of this utility model is ecological The structural representation of guard system;
Fig. 2 is that the highlight lines frigid mountainous areas highway cutting gradient slope described in the one of embodiment of this utility model is ecological The structural representation of guard system;
Fig. 3 is that the highlight lines frigid mountainous areas highway cutting gradient slope described in the one of embodiment of this utility model is ecological Profile after gabion geo-grid reinforcement in guard system;
Fig. 4 is that the highlight lines frigid mountainous areas highway cutting gradient slope described in the one of embodiment of this utility model is ecological The structural representation of the first preventer and the second preventer annexation in guard system;
Fig. 5 is that the highlight lines frigid mountainous areas highway cutting gradient slope described in the one of embodiment of this utility model is ecological The schematic diagram of gabion post and anchor pole annexation in guard system;
Fig. 6 is that the highlight lines frigid mountainous areas highway cutting gradient slope described in the one of embodiment of this utility model is ecological The structural representation of the gabion of guard system.
Specific embodiment
Below in conjunction with the accompanying drawings this utility model is described in further detail, to make those skilled in the art with reference to explanation Book word can be implemented according to this.
It should be appreciated that used herein such as " have ", "comprising" and " inclusion " term are not precluded from one or many The presence of individual other element or a combination thereof or interpolation.
As shown in Fig. 1, Fig. 4, Fig. 5 and Fig. 6, in the one of embodiment of this utility model, provide a kind of highlight lines severe cold Mountain highway cutting gradient slope ecological protection system, including:
First preventer 1, it is arranged in the rhone between roadbed 2 and side slope 3, described first preventer 1 by The gabion net cage 110 that multiple longitudinal extension directions along described rhone are arranged in order forms, in the plurality of gabion net cage 110 It is separately filled with stone;
Second preventer 4, it is installed in the top of described first preventer 1, and described second preventer 4 is by multiple Gabion post 410 and connect the gabion wall 420 of two neighboring gabion post 410 and form, described gabion wall 420 is by being filled with rubble Double-deck gabion net is superimposed setting up and down and is formed, and each gabion post 410 is vertically superimposed by the multiple gabions 411 being filled with rubble It is connected to form, to form column structure, and described gabion post 410 is connected with the anchor pole 5 in side slope described in partial insertion 3, with Described first preventer 1 and described second preventer 4 are flexibly connected with described side slope 3.
This embodiment treatment in accordance with local conditions, centralized recovery is discarded the building stones of residual using construction of road cutting, is had green economy, draws materials Convenient feature.By building stones being filled in gabion net cage 110, gabion net and gabion 411 it is achieved that breathability The good, feature of drainage pressure-reducing, can sluice in rainy season set in draining, stops mudstone, protection side slope and roadbed.
The annexation of the first preventer 1 in this embodiment and the second preventer 4 and side slope 3 is flexible connection, There is local failure different from traditional retaining wall when by local assault, this embodiment, can when Freshets roar down from the mountains During resisting mud-rock flow temporary impact, cooperative bearing is deformed according to stressing conditions adjust automatically, play whole gear well The effect of cob wall, efficiency is higher, and can be by the method reparation resetting, simple and practical economy and facility after the deformation that is hit. The connected mode of anchor pole simultaneously:On the one hand the constantly accumulation superposition lift in the case of material-saving of the second preventer 4 can be made Height, adaptation mountain area is tall and big, and on the other hand the engineering situation of gradient slope can make the second preventer 4 and side slope 3 become well One entirety.
This embodiment is in the first preventer 1 of 4 times setting filling megaliths of the second preventer, the larger energy of stone interblock gap Enough rainwater-collectings leaving side slope are discharged.This design has rapid drainability, and more traditional retaining wall arranges gutter It is more suitable for tackling precipitate instantaneous high-speed large-flow mountain torrents mud-rock flow, being capable of draining rapidly, it is to avoid on water level after retaining wall Rise, hydrostatic pressure increases, destroy retaining wall.The rainwater that side slope of embankment flows down can be received simultaneously, safeguard that it is stable.
As shown in Figures 2 and 3, when gabion 411 oversized when, for example length be more than 70cm when, need to stone Cage post 410 carries out geo-grid reinforcement, using gabion mesh sheet 7.
Wherein in an embodiment, described ecological protection system also includes:
3rd preventer 6, it is filled between described second preventer 4 and described side slope 3, described 3rd protection dress Put 6 to be made up of multiple ecology bags, each ecology bag is built with the flourishing plant seed of rhizome.
This embodiment is built in view of frigid mountainous areas highway and is caused destruction to the weak ecological environment in location, therefore needs Certain measure is taken to recover ecological.This embodiment landfill ecology bag between the second preventer 4 and side slope 3, former to recovery Ecological environment is had to have very big power-assisted.In later stage ecology bag, plant germination is taken root, and the protective action of side slope further enhances, after inciting somebody to action The side slope protection effect of phase is upgraded further.What ecology bag was built-in simultaneously is that location is primary, rhizome for soil nutrient and protection Plant seed that is flourishing, easily surviving:This measure one side is to prevent from introducing alien species, breaks original biological chain, causes local Ecology is unbalance further;On the other hand be original species be more suitable for protecting on-site high and cold mountain area ecological environment it is easier to Survive, rooting propagation.To original ecological environment without interference with side slope also can be protected.But, need to stack with caution in work progress Ecology bag, it is to avoid ecology bag compressing anchor pole 5 damages.
Wherein in an embodiment, described ecological protection system also includes:
At least one gutter, it is arranged under the steady layer of water of described roadbed 2, described at least one gutter respectively with The perpendicular connection of described rhone, and extend to described side slope 3 away from the side of described roadbed 2.According to side of on-site rainy season Slope discharge arranges the density in gutter, concentrates the quantity in sluicing location encryption gutter at mountain pass, with rapid draining.
Wherein in an embodiment, existed by steel wire lashing between the multiple gabions 411 in each gabion post 410 Together.
Wherein in an embodiment, the ratio of the length, width and height of described gabion 411 is 3:2:2.
Wherein in an embodiment, as shown in figure 5, described gabion 411 is many transverse steel wire and multiple longitudinal direction The rectangular configuration that steel wire weld is formed, and it is provided with the quoit 412 being connected with anchor pole on a longitudinal steel wire wherein.
High-strength tenacity steel wire colligation is adopted, gabion 411 is many transverse steel wire and multiple vertical between gabion 411 The rectangular configuration being formed to steel wire weld, transverse steel wire and longitudinal steel wire are that have the steel wire of high-strength corrosion-resisting or be enclosed with The high-tensile steel wires of PVC, and the frame of gabion 411 is welded using suitable anticorrosion reinforcing bar.Gabion 411 exists Welding metal circle 412 on longitudinal reinforcement, is connected with anchor pole 5 with facilitating.
Using the highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system described in above-mentioned one of embodiment The method carrying out ecological protection, specially:
Step one, between side slope 3 and roadbed 2 and along the longitudinal extension direction of described roadbed, open up rhone, and to institute State the bottom surface of rhone and side wall carries out cement sand plaster, then under the steady layer of water of described roadbed 2, open up at least one Gutter, the perpendicular connection with described rhone respectively of described at least one gutter, and to described side slope away from described roadbed Side extend, cement sand plaster is carried out to the bottom surface and side wall in described at least one gutter simultaneously;
Step 2, it is arranged in order and multiple is filled with stone in described rhone and along the longitudinal extension direction of described rhone The gabion net cage 110 of block, to form the first preventer 1, passes through steel wire lashing one between the plurality of gabion net cage 110 Rise;And
Step 3, into multiple gabions 411, fill rubble respectively, the multiple gabions that will be filled with rubble are vertical It is superimposed and uses steel wire lashing together, to form gabion post 410, then will be filled with the double of rubble by be superimposed setting up and down The gabion wall 420 that layer gabion net is formed is arranged between two neighboring gabion post 410, by multiple gabion posts 410 and multiple stone Cage wall 420 links together, and forms the second preventer 4, by the anchor pole 5 that is fixed in described side slope 3 with the plurality of The connection of gabion post 410, realizes described first preventer 1 and described second preventer 4 is connected with the flexible of described side slope 3 Connect.
And step 4, fill multiple ecology bags between described second preventer 4 and described side slope 3, and to each The flourishing plant seed of rhizome is loaded, to form the 3rd preventer 6 in ecology bag.
Although embodiment of the present utility model is disclosed as above, it is not restricted in description and embodiment Listed utilization, it can be applied to various suitable fields of the present utility model completely, for those skilled in the art, It is easily achieved other modification, therefore under the general concept being limited without departing substantially from claim and equivalency range, this reality It is not limited to specific details with new and shown here as the legend with description.

Claims (6)

1. a kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system is it is characterised in that include:
First preventer, it is arranged in the rhone between roadbed and side slope, and described first preventer is by multiple along institute State the gabion net cage composition that the longitudinal extension direction of rhone is arranged in order, in the plurality of gabion net cage, be separately filled with stone Block;
Second preventer, it is installed in the top of described first preventer, and described second preventer is by multiple gabion posts And the gabion wall of the two neighboring gabion post of connection forms, described gabion wall is superimposed up and down by the double-deck gabion net being filled with rubble Setting is formed, and each gabion post is connected to form by the vertical superposition of the multiple gabions being filled with rubble, and forms column structure, And described gabion post is connected with the anchor pole in side slope described in partial insertion, so that described first preventer and described second Preventer is connected with described side slope flexible.
2. highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system as claimed in claim 1 is it is characterised in that go back Including:
3rd preventer, it is filled between described second preventer and described side slope, and described 3rd preventer is by many Individual ecology bag composition, each ecology bag is built with the flourishing plant seed of rhizome.
3. highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system as claimed in claim 1 is it is characterised in that go back Including:
At least one gutter, it is arranged under the steady layer of water of described roadbed, described at least one gutter respectively with described Rhone vertically connects, and extends to described side slope away from the side of described roadbed.
4. highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system as claimed in claim 1 is it is characterised in that every Pass through steel wire lashing together between multiple gabions in individual gabion post.
5. highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system as claimed in claim 1 is it is characterised in that institute The ratio stating the length, width and height of gabion is 3:2:2.
6. highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system as claimed in claim 1 is it is characterised in that institute State the rectangular configuration that gabion is that many transverse steel wire and the welding of multiple longitudinal steel wire are formed, and a longitudinal steel wire wherein On be provided with the quoit being connected with anchor pole.
CN201620998473.XU 2016-08-30 2016-08-30 A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system Withdrawn - After Issue CN205999849U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620998473.XU CN205999849U (en) 2016-08-30 2016-08-30 A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620998473.XU CN205999849U (en) 2016-08-30 2016-08-30 A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system

Publications (1)

Publication Number Publication Date
CN205999849U true CN205999849U (en) 2017-03-08

Family

ID=58195303

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620998473.XU Withdrawn - After Issue CN205999849U (en) 2016-08-30 2016-08-30 A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system

Country Status (1)

Country Link
CN (1) CN205999849U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106192896A (en) * 2016-08-30 2016-12-07 中国路桥工程有限责任公司 A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system and method
CN110055985A (en) * 2019-05-15 2019-07-26 中国葛洲坝集团第一工程有限公司 High-durability earth rock cofferdam or flood bank construction method
CN110984192A (en) * 2019-12-24 2020-04-10 河北水熠木丰工程技术有限责任公司 Highway reconstruction excavated slope reinforcing structure and reinforcing method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106192896A (en) * 2016-08-30 2016-12-07 中国路桥工程有限责任公司 A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system and method
CN106192896B (en) * 2016-08-30 2018-02-16 中国路桥工程有限责任公司 A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system and method
CN110055985A (en) * 2019-05-15 2019-07-26 中国葛洲坝集团第一工程有限公司 High-durability earth rock cofferdam or flood bank construction method
CN110055985B (en) * 2019-05-15 2020-04-14 国电大渡河猴子岩水电建设有限公司 Construction method of high-durability earth-rock cofferdam or flood bank
CN110984192A (en) * 2019-12-24 2020-04-10 河北水熠木丰工程技术有限责任公司 Highway reconstruction excavated slope reinforcing structure and reinforcing method

Similar Documents

Publication Publication Date Title
CN105317459B (en) A kind of subregion placement method for being used to control tight roof large area caving disaster
CN204849509U (en) Highway roadbed structure of antidetonation sand prevention
CN205999849U (en) A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system
CN106192653A (en) A kind of Duo Xue district road crossing avalanche slide rock body subgrade drainage system and construction method
CN110777819A (en) High and steep mine mountain reconstruction ecological restoration method
CN106192896B (en) A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system and method
CN102605749A (en) Construction method of shuttle-shaped dam for intercepting debris flow
CN105862659B (en) High-frequency debris flow shore protection and diversion method
CN207714344U (en) A kind of passive protection net for complex mountainous cut slope
CN207714168U (en) Stone discharge device is blocked for mud-rock flow protection
CN102619195A (en) Combined dam for stopping debris flow
CN110344374A (en) Mud-rock flow flexible blocking backstop and mud-rock flow flexibility blocking dam
CN212077787U (en) Water conservancy and hydropower engineering bank wall
CN110093939B (en) Ecological restoration method for mining area side slope
CN109162297A (en) A kind of the solid-liquid separating shed hole structure and its construction method of anti-mud-rock flow
CN110593205B (en) High-order debris flow multistage self-adaptive barrier pile group disaster reduction structure and implementation method
CN212477800U (en) Anchoring gabion retaining wall
CN104314046B (en) Adopt geo-grid structure to carry out river course and attack and occupy the method with spats construction
CN107938457A (en) A kind of neighbouring the express highway roadbed of existing Subway Facilities fills out river structure and construction method
Kandaris Use of gabions for localized slope stabilization in difficult terrain
CN206279410U (en) A kind of Duo Xue areas road crossing avalanche slide rock body subgrade drainage system
CN208056130U (en) Power transmission tower foundation protective device in mud-rock flow raceway groove
CN2391910Y (en) Truss for blocking break of a dike
CN106120663A (en) A kind of CFRD
CN207362869U (en) One species gravity type can afforest barrier wall structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20170308