Mud-rock flow flexible blocking backstop and mud-rock flow flexibility blocking dam Download PDF

Info

Publication number
CN110344374A
CN110344374A CN201910645413.8A CN201910645413A CN110344374A CN 110344374 A CN110344374 A CN 110344374A CN 201910645413 A CN201910645413 A CN 201910645413A CN 110344374 A CN110344374 A CN 110344374A
Authority
CN
China
Prior art keywords
rope
flexible
flexible net
mud
rock flow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910645413.8A
Other languages
Chinese (zh)
Inventor
康波
徐敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Brooke Engineering (Suzhou) Co.,Ltd.
Original Assignee
BROOK (CHENGDU) ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BROOK (CHENGDU) ENGINEERING Co Ltd filed Critical BROOK (CHENGDU) ENGINEERING Co Ltd
Priority to CN201910645413.8A priority Critical patent/CN110344374A/en
Publication of CN110344374A publication Critical patent/CN110344374A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The invention discloses a kind of mud-rock flow flexible blocking backstop and mud-rock flow flexibility blocking dams, are related to facility field of blocking, and provide a kind of convenient and fast mud-rock flow flexibility blocking dam and net of blocking suitable for the blocking dam of constructing.Mud-rock flow flexible blocking backstop includes flexible net, top braces rope, span rope, bottom supporting rope and edge rope;The setting of flexible net horizontal spreading, flexible net both ends upwarp to form flexible net alar part, and rest part is flexible net main body;Top braces rope cross directional stretch is set to flexible net body top, the upper edge mesh and top braces rope slidable connection of flexible net main body;Span rope is arranged along flexible net upper edge, the upper edge mesh and span rope slidable connection of flexible net;Bottom supporting rope cross directional stretch is set to flexible sieve bottom, the lower edge mesh and bottom supporting rope slidable connection of flexible net;Edge rope is arranged in flexible net both ends, and the side of flexible net is along mesh and edge rope slidable connection.The net that will block is installed in cheuch and obtains blocking dam.

Description

Mud-rock flow flexible blocking backstop and mud-rock flow flexibility blocking dam
Technical field
The present invention relates to block facility field more particularly to a kind of mud-rock flow flexible blocking backstop and mud-rock flow flexibility is blocked Dam.
Background technique
Mud-rock flow be in the cheuch of mountain area, it is that mountain torrents made of being collected as heavy rainfall or snowmelt runoff are excited, containing big Measure the special mighty torrent of the solid matters such as silt stone.Its feature often breaks out, before muddy fluid is along steep gully It postpones and gathers around, Pentium roars down, and ground location vibration, mountain valley are like thunderous.A large amount of silt particles, stone are gone out within a very short time It outside ditch, pushes way by shoving or bumping in broad accumulation area, cross flow accumulation, usually causes significant damage to human life's property.By mud-rock flow The form of ditch is divided into ditch (river) paddy type and debris flow on slopes etc..
The common engineering prevention and control of Geological Hazards of debris mainly includes arranging two classes of leading and block.Row leads its effect of engineering It is to improve the mud-rock flow force and velocity of a current, increases the discharge capacity of the buildings such as bridge, drain mud-rock flow smoothly by design idea.Row leads work Journey includes trraning pole, chute, line dike etc..Column keeps off solid matter and heavy rain, flood runoff of the engineering to control mud-rock flow, Weaken flow, lower discharge and the energy of mud-rock flow, with reduce mud-rock flow to the washing away of downstream architectural engineering, hit and the danger such as silt is buried Evil.The measure of blocking has column slag dam, storage silt field, retaining engineering, section big vast engineering etc..It wherein blocks the permeable of solid matter in mud-rock flow Property blocking dam mainly has the gap dam, sieve dam, crib dam etc..Traditional mud-rock flow blocking dam mainly using armored concrete as Fundamental mechanism, by the modes solid base such as excavate or drive piles, then on the basis of setting rigidity block structure, structure of blocking has Armored concrete, mortar flag stone, fashioned iron etc. resist mud-rock-flow-impact load by the rigidity of structure of blocking.
It is blocked in structural research and application process in existing mud-rock flow, it has been found that, it is anti-much to need to carry out mud-rock flow The position controlled does not have excavation foundation and transports the condition of the raw material such as a large amount of concrete, building stones, and heavy construction equipment can not arrive It reaches, difficulty of construction is big, long construction period, can not implement traditional structure blocking dam, or implement less economical.In addition, traditional Blocking dam water penetration it is bad, be easy to appear plug-hole, water erosion, dam body cracking etc. destroy.Furthermore the anti-mudstone of traditional blocking dam Flowing primary battle array stream, to hit weight bearing power weak.
Summary of the invention
It blocks technical problem solved by the present invention is providing a kind of mud-rock flow flexibility suitable for mud-rock flow flexibility blocking dam Net.
In order to solve the above problem the technical solution adopted is that: mud-rock flow flexible blocking backstop include flexible net, top braces rope, Span rope, bottom supporting rope and edge rope;The setting of flexible net horizontal spreading, flexible net both ends upwarp to form flexible net alar part, soft Property wing portion except flexible net be flexible net main body;Top braces rope cross directional stretch is set to flexible net body top, flexible The upper edge mesh and top braces rope slidable connection of host's body;Span rope along flexible net upper edge be arranged, flexible net it is upper Edge mesh and span rope slidable connection;Bottom supporting rope cross directional stretch is set to flexible sieve bottom, the lower edge of flexible net Mesh and bottom supporting rope slidable connection;Flexible net both ends are respectively provided with edge rope, and edge rope up and down direction stretches setting, flexible The side of net is along mesh and edge rope slidable connection.
Further, mud-rock flow flexible blocking backstop includes midfoot support rope, midfoot support rope cross directional stretch is set to soft Property net in the middle part of and flexible net mesh slidable connection corresponding with position.
Further, being provided on top braces rope, span rope, bottom supporting rope, edge rope and midfoot support rope Sinker.
Further, mud-rock flow flexible blocking backstop includes wear strip, wear strip is set to flexibility along flexible net upper edge Net front is simultaneously connect with flexible net, and wear strip protects span rope and the atop part supporting rope at flexible net upper edge.
Further, mud-rock flow flexible blocking backstop includes column, column is vertically arranged in the middle part of flexible net and branch support Portion's supporting rope and span rope.
Another technical problem that the present invention solves is: providing a kind of convenient and fast mud-rock flow flexibility blocking dam of construction.
In order to solve the above problem the technical solution adopted is that: mud-rock flow flexibility blocking dam includes cheuch and mud-rock flow flexible blocking Backstop, mud-rock flow flexible blocking backstop are arranged in cheuch, and top braces rope is tensed by being located at the upper bolt at flexible net both ends, the wing Exhibition rope is tensed by being located at the top anchor pole at flexible net both ends, and bottom supporting rope is tensed by being located at the lower bolt at flexible net both ends, Edge rope is at least connect with top anchor pole and lower bolt, and top anchor pole, upper bolt and lower bolt are anchored on the side wall of cheuch;Cheuch Bottom plate on be provided with ditch.
Further, mud-rock flow flexible blocking backstop includes midfoot support rope, midfoot support rope cross directional stretch is set to soft Property net in the middle part of and flexible net mesh slidable connection corresponding with position, midfoot support rope pass through be located at flexible net both ends middle anchor Bar tenses;In it is anchor rod anchored on the side wall of cheuch.
Further, being provided on top braces rope, span rope, bottom supporting rope, edge rope and midfoot support rope Sinker.
Further, mud-rock flow flexible blocking backstop includes wear strip, wear strip is set to flexibility along flexible net upper edge Net front is simultaneously connect with flexible net, and wear strip protects span rope and the top braces rope positioned at flexible net upper edge.
Further, mud-rock flow flexible blocking backstop includes column, column is vertically arranged in the middle part of flexible net and branch support Portion's supporting rope and span rope;Column lower end and the pedestal being fixed on cheuch bottom plate are hinged, and column passes through upper drawstring and lower drawstring Overturning-preventing is pulled, is provided with sinker on upper drawstring.
The beneficial effects of the present invention are: 1, the application is in actual use, if one of mud-rock flow flexibility blocking dam, mud is only arranged Stone and part mud are intercepted by flexible net in rock glacier.Although part mud still can pass through flexible net, due to stone and part Mud is intercepted by flexible net, and the destructiveness of mud-rock flow weakens significantly.Often flow is huge for mud-rock flow, therefore it is more to usually require setting Road mud-rock flow flexibility blocking dam, one of mud-rock flow flexibility blocking dam are blocked part mud-rock flow, and remaining mud-rock flow crosses the mud-rock flow Flexible blocking dam continues to flow, and is intercepted by latter mud-rock flow flexibility blocking dam, so intercepts layer by layer, can almost block mud Rock glacier weakens mud-rock flow destructiveness to minimum.
2, after the completion of each component of the application manufactures and designs, transport to installation site is installed.Material transportation amount is much smaller than Existing reinforced concrete dam, mortar flag stone dam or fashioned iron dam.Each anchor pole need to only be anchored into when installation cheuch side wall or bottom plate and Each component is assembled, simple installation does not need large scale equipment.The application can be set on any position of debris flow gully, ground Shape is adaptable;Low to fundamental importance, quick for installation, construction investment is few, good economy performance.
3, flexible net has flexible and is slidably attached on each supporting rope.When by mud-rock-flow-impact, flexible net becomes Shape extends and moves along each supporting rope, can buffer the impulsive force of mud flow;The deformation or destruction of sinker can also be mentioned further in energy dissipating Blocking dam deformability is risen, to further promote impact resistance;Flexible net has obviously comprehensive permeability, part Mud can be by flexible net mesh, so that mud-rock-flow-impact is minimized.Therefore, the application has strong shock resistance, is not easy The advantages of damage.
4, the application is provided with flexible net alar part, when mud-rock flow crosses flexible net, passes through from flexible net middle part top, without Pass through from flexible network edge, corrosion function of the mud-rock flow to two sides at dam site behind full dam can be prevented, mud-rock flow is avoided to wash away damage Bad dam site two sides cause flexible blocking dam to loosen.Further setting wear strip protects span rope and top braces rope, can avoid mud Rock glacier is crossed at the top of the erosion failure flexibility blocking dam of flexible blocking dam.Therefore the present invention, which has, prevents erosion failure, and the service life is long The advantages of.
5, ditch was provided on the bottom plate of cheuch, then normal flowing water, silt and finger stone can pass through cheuch throughout the year It crosses ditch and flows through blocking dam, guarantee that cheuch is unimpeded, blocking dam is avoided to block, guarantee to play the role of when mud-rock flow occurs good.
Detailed description of the invention:
Fig. 1 is shorter mud-rock flow flexibility blocking dam structure chart;
Fig. 2 is longer mud-rock flow flexibility blocking dam structure chart;
Fig. 3 is mud-rock flow flexible blocking backstop partial enlarged view;
Fig. 4 is mud-rock flow flexibility blocking dam side view;
Fig. 5 is mud-rock flow flexibility blocking dam partial top view;
In the figure, it is marked as flexible net 1, flexible net alar part 1-1, flexible net main body 1-2, top braces rope 2, span rope 3, bottom Portion's supporting rope 4, edge rope 5, midfoot support rope 6, upper bolt 7, top anchor pole 8, lower bolt 9, middle anchor pole 10, sinker 11, abrasionproof Plate 12, shackle 14, cheuch 15, crosses ditch 16, pedestal 17, upper drawstring 18, lower drawstring 19 at column 13.
Specific embodiment
The present invention is further described with reference to the accompanying drawings and detailed description.
As shown in Figure 1 to Figure 3, mud-rock flow flexible blocking backstop includes flexible net 1, top braces rope 2, span rope 3, bottom branch Support rope 4 and edge rope 5;The setting of 1 horizontal spreading of flexible net, 1 both ends of flexible net upwarp to form flexible net alar part 1-1, flexible wing Flexible net 1 except portion 1-1 is flexible net main body 1-2;2 cross directional stretch of top braces rope is set at the top of flexible net main body 1-2, The upper edge mesh and 2 slidable connection of top braces rope of flexible net main body 1-2;Span rope 3 is arranged along 1 upper edge of flexible net, The upper edge mesh and 3 slidable connection of span rope of flexible net 1;Supporting rope 4 cross directional stretch in bottom is set to flexible sieve bottom, soft Property net 1 lower edge mesh and 4 slidable connection of bottom supporting rope;1 both ends of flexible net are respectively provided with edge rope 5, about 5 edge rope Direction stretches setting, and the side of flexible net 1 is along mesh and 5 slidable connection of edge rope.
Since stress is very big, flexible net 1 should be metal flexible net in the prior art, also be not excluded for technology in the future certainly Progress can use the enough nonmetal flexible nets of other stress-bearing capabilities.The side that each mesh of flexible net 1 is connect with each supporting rope Formula may each be to be connected by shackle 14.Top braces rope 2, span rope 3, bottom supporting rope 4 quantity may each be one, but In order to improve stress-bearing capability, it also can be set more, such as mud-rock flow flexible blocking backstop shown in illustrations has two 2, two span ropes 3 of supporting rope and three root bottom part supporting ropes 4.
As shown in Figure 1, Figure 2 and shown in Fig. 5, mud-rock flow flexible blocking backstop is installed in cheuch 15, mud-rock flow flexibility can be obtained Blocking dam.Mud-rock flow flexibility blocking dam includes cheuch 15 and mud-rock flow flexible blocking backstop, and mud-rock flow flexible blocking backstop is arranged in ditch In paddy 15, top braces rope 2 is tensed by being located at the upper bolt 7 at 1 both ends of flexible net, and span rope 3 is by being located at 1 both ends of flexible net Top anchor pole 8 tense, bottom supporting rope 4 by be located at 1 both ends of flexible net lower bolt 9 tense, edge rope 5 at least with top anchor pole 8 and lower bolt 9 connect, top anchor pole 8, upper bolt 7 and lower bolt 9 are anchored on the side wall of cheuch 15;On the bottom plate of cheuch 15 It was provided with ditch 16.
In order to improve the stress-bearing capability in the middle part of mud-rock flow flexibility blocking dam, mud-rock flow flexible blocking backstop includes midfoot support rope 6,6 cross directional stretch of midfoot support rope is set to 1 middle part of flexible net and 1 mesh slidable connection of flexible net corresponding with position, in Portion's supporting rope 6 is tensed by being located at the middle anchor pole 10 at 1 both ends of flexible net;Middle anchor pole 10 is anchored on the side wall of cheuch 15.
A top anchor pole 8, upper bolt 7, lower bolt 9 and middle anchor pole 10 can be only arranged in 1 both ends of flexible net, push up anchor pole 8, upper anchor Bar 7, lower bolt 9 and middle anchor pole 10 can also be arranged in a one-to-one correspondence with supporting rope.
In order to which further energy dissipating promotes blocking dam stress-bearing capability, top braces rope 2, span rope 3, bottom supporting rope 4, edge Sinker 11 is provided on rope 5 and midfoot support rope 6.Sinker 11 is the prior art, can be in a manner of deforming or destroy Energy dissipating and the deformation buffer ability for promoting mud-rock flow flexible blocking backstop.
In order to avoid mud-rock flow is crossed at the top of the erosion failure flexibility blocking dam of flexible blocking dam, mud-rock flow flexible blocking backstop Including wear strip 12, wear strip 12 is set to 1 front of flexible net along 1 upper edge of flexible net and connect with flexible net 1, wear strip 12 protection span ropes 3 and the atop part supporting rope 2 at 1 upper edge of flexible net.
When mud-rock flow flexibility blocking dam top width is less than 15 meters, column can not be used as shown in Figure 1.But mud-rock flow is flexible When blocking dam top width is greater than 15 meters, in order to improve middle part stress-bearing capability, as shown in figure 4, mud-rock flow flexible blocking backstop includes Column 13, column 13 are vertically arranged to 1 middle part of flexible net and support top braces rope 2 and span rope 3.When column 13 is installed, under The pedestal 17 held and be fixed on 15 bottom plate of cheuch is hinged, and column 13 pulls overturning-preventing by upper drawstring 18 and lower drawstring 19.It can Sinker 11 is set on upper drawstring 18.Upper drawstring 18 is attached on the anchor pole being anchored on 15 side wall of cheuch or bottom plate, on Drawstring 18 at least should be two with angle, avoid avoiding rolling while 13 hypsokinesis of column.Lower drawstring 19 can connect On pedestal 17.

Claims (10)

1. mud-rock flow flexible blocking backstop, it is characterised in that: including flexible net (1), top braces rope (2), span rope (3), bottom Supporting rope (4) and edge rope (5);The setting of flexible net (1) horizontal spreading, flexible net (1) both ends upwarp to form flexible net alar part (1- 1), the flexible net (1) except flexible net alar part (1-1) is flexible net main body (1-2);The setting of top braces rope (2) cross directional stretch At the top of flexible net main body (1-2), the upper edge mesh and top braces rope (2) slidable connection of flexible net main body (1-2);The wing Exhibition rope (3) is arranged along flexible net (1) upper edge, the upper edge mesh and span rope (3) slidable connection of flexible net (1);Bottom Supporting rope (4) cross directional stretch is set to flexible sieve bottom, and the lower edge mesh of flexible net (1) and bottom supporting rope (4) are slidably Connection;Flexible net (1) both ends are respectively provided with edge rope (5), and rope (5) up and down direction in edge stretches setting, the side edge of flexible net (1) Mesh and edge rope (5) slidable connection.
2. mud-rock flow flexible blocking backstop according to claim 1, it is characterised in that: including midfoot support rope (6), middle part branch Support rope (6) cross directional stretch is set in the middle part of flexible net (1) and flexible net corresponding with position (1) mesh slidable connection.
3. mud-rock flow flexible blocking backstop according to claim 2, it is characterised in that: top braces rope (2), span rope (3), Sinker (11) are provided on bottom supporting rope (4), edge rope (5) and midfoot support rope (6).
4. mud-rock flow flexible blocking backstop according to claim 3, it is characterised in that: including wear strip (12), wear strip (12) it is set to immediately ahead of flexible net (1) along flexible net (1) upper edge and is connect with flexible net (1), wear strip (12) protects the wing Exhibition rope (3) and the atop part supporting rope (2) being located at flexible net (1) upper edge.
5. mud-rock flow flexible blocking backstop according to claim 4, it is characterised in that: including column (13), column (13) is perpendicular To being set in the middle part of flexible net (1) and support top braces rope (2) and span rope (3).
6. mud-rock flow flexibility blocking dam, including cheuch (15), it is characterised in that: flexible including mud-rock flow described in claim 1 It blocks net, for the setting of mud-rock flow flexible blocking backstop in cheuch (15), top braces rope (2), which passes through, is located at flexible net (1) both ends Upper bolt (7) tenses, and span rope (3) is tensed by being located at the top anchor pole (8) at flexible net (1) both ends, and bottom supporting rope (4) passes through Lower bolt (9) positioned at flexible net (1) both ends tenses, and edge rope (5) is at least connect with top anchor pole (8) and lower bolt (9), pushes up anchor Bar (8), upper bolt (7) and lower bolt (9) are anchored on the side wall of cheuch (15);Water was provided on the bottom plate of cheuch (15) Ditch (16).
7. mud-rock flow flexibility blocking dam according to claim 6, it is characterised in that: mud-rock flow flexible blocking backstop includes middle part Supporting rope (6), midfoot support rope (6) cross directional stretch is set in the middle part of flexible net (1) and flexible net corresponding with position (1) mesh Slidable connection, midfoot support rope (6) are tensed by being located at the middle anchor pole (10) at flexible net (1) both ends;Middle anchor pole (10) anchoring On the side wall of cheuch (15).
8. mud-rock flow flexibility blocking dam according to claim 7, it is characterised in that: top braces rope (2), span rope (3), Sinker (11) are provided on bottom supporting rope (4), edge rope (5) and midfoot support rope (6).
9. mud-rock flow flexibility blocking dam according to claim 8, it is characterised in that: mud-rock flow flexible blocking backstop includes abrasionproof Plate (12), wear strip (12) are set to immediately ahead of flexible net (1) along flexible net (1) upper edge and connect with flexible net (1), abrasionproof Plate (12) protects span rope (3) and the top braces rope (2) for being located at flexible net (1) upper edge.
10. mud-rock flow flexibility blocking dam according to claim 9, it is characterised in that: mud-rock flow flexible blocking backstop includes vertical Column (13), column (13) are vertically arranged in the middle part of flexible net (1) and support top braces rope (2) and span rope (3);Column (13) Hingedly, column (13) is led by preceding drawstring (18) and rear-pulling rope (19) for lower end and the pedestal (17) being fixed on cheuch (15) bottom plate Overturning-preventing is drawn, is provided with sinker (11) on preceding drawstring (18).
CN201910645413.8A 2019-07-17 2019-07-17 Mud-rock flow flexible blocking backstop and mud-rock flow flexibility blocking dam Pending CN110344374A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910645413.8A CN110344374A (en) 2019-07-17 2019-07-17 Mud-rock flow flexible blocking backstop and mud-rock flow flexibility blocking dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910645413.8A CN110344374A (en) 2019-07-17 2019-07-17 Mud-rock flow flexible blocking backstop and mud-rock flow flexibility blocking dam

Publications (1)

Publication Number Publication Date
CN110344374A true CN110344374A (en) 2019-10-18

Family

ID=68176622

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910645413.8A Pending CN110344374A (en) 2019-07-17 2019-07-17 Mud-rock flow flexible blocking backstop and mud-rock flow flexibility blocking dam

Country Status (1)

Country Link
CN (1) CN110344374A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110670538A (en) * 2019-10-19 2020-01-10 哈尔滨学院 Debris flow gully ecological engineering protection system
CN111877276A (en) * 2020-06-30 2020-11-03 水利部交通运输部国家能源局南京水利科学研究院 Bag-net type rain and flood weir for dispersing and collecting water in hilly areas and construction method thereof
CN112854127A (en) * 2021-01-13 2021-05-28 重庆交通大学 Debris flow blocking method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410162A (en) * 2013-08-28 2013-11-27 布鲁克(成都)工程有限公司 Flexible blocking net
CN104018440A (en) * 2014-06-30 2014-09-03 布鲁克(成都)工程有限公司 Flexible barrier net
CN109183705A (en) * 2018-12-01 2019-01-11 西南交通大学 A kind of design method intercepted for the segmentation of mud-rock flow flexible protection systems
CN210562017U (en) * 2019-07-17 2020-05-19 布鲁克(成都)工程有限公司 Mud-rock flow flexible blocking net and mud-rock flow flexible blocking dam

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410162A (en) * 2013-08-28 2013-11-27 布鲁克(成都)工程有限公司 Flexible blocking net
CN104018440A (en) * 2014-06-30 2014-09-03 布鲁克(成都)工程有限公司 Flexible barrier net
CN109183705A (en) * 2018-12-01 2019-01-11 西南交通大学 A kind of design method intercepted for the segmentation of mud-rock flow flexible protection systems
CN210562017U (en) * 2019-07-17 2020-05-19 布鲁克(成都)工程有限公司 Mud-rock flow flexible blocking net and mud-rock flow flexible blocking dam

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110670538A (en) * 2019-10-19 2020-01-10 哈尔滨学院 Debris flow gully ecological engineering protection system
CN111877276A (en) * 2020-06-30 2020-11-03 水利部交通运输部国家能源局南京水利科学研究院 Bag-net type rain and flood weir for dispersing and collecting water in hilly areas and construction method thereof
CN112854127A (en) * 2021-01-13 2021-05-28 重庆交通大学 Debris flow blocking method
CN112854127B (en) * 2021-01-13 2022-09-27 重庆交通大学 Debris flow blocking method

Similar Documents

Publication Publication Date Title
CN202298556U (en) Novel prevention structure for landslide converting-type debris flow
CN110344374A (en) Mud-rock flow flexible blocking backstop and mud-rock flow flexibility blocking dam
CN111236161A (en) Debris flow prevention and control system
CN211948485U (en) Comprehensive treatment device for rockfill easy-sliding area
CN110004882A (en) The dissipation of mud-rock flow multistage is blocked structure
CN207376562U (en) A kind of key water control project that can filter silt
CN108951441A (en) Ecological shed tunnel structure for protecting high and steep slope off-road
KR100965467B1 (en) Eco-pillar debris barrier
CN210562017U (en) Mud-rock flow flexible blocking net and mud-rock flow flexible blocking dam
CN207714344U (en) A kind of passive protection net for complex mountainous cut slope
CN207904879U (en) A kind of Debris Flow on Slope Surface improvement integration engineering structure
CN219262379U (en) Double-arch tunnel portal structure suitable for bias terrain
CN205999849U (en) A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system
KR101008839B1 (en) Hybrid type debris barrier
CN110172884B (en) Mountain highway subgrade and construction method
CN106192896A (en) A kind of highlight lines frigid mountainous areas highway cutting gradient slope ecological protection system and method
CN108560503A (en) A kind of mud-rock flow is blocked structure and method of blocking
CN110593205B (en) High-order debris flow multistage self-adaptive barrier pile group disaster reduction structure and implementation method
KR102351049B1 (en) Debris barrier with integrated side wall
KR101170789B1 (en) Complex debris barrier of eco-friendly
RU157458U1 (en) SELF-PROTECTIVE DAM OF COMBINED DESIGN
CN211735267U (en) Protective structure of hydraulic and hydroelectric engineering side slope
CN207597544U (en) A kind of high resiliency water conservancy chute
Margreth et al. Avalanche Mitigation Measures for Siglufjörður–Realization of the Largest Project with Snow Supporting Structures in Iceland
KR100776621B1 (en) Pile structure for preventing a disaster by debris flow

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20220216

Address after: 215000 5-101-1, building 5, No. 88, Jinling East Road, Suzhou Industrial Park, Suzhou City, Jiangsu Province

Applicant after: Brooke Engineering (Suzhou) Co.,Ltd.

Address before: 611731 Brooke (Chengdu) Engineering Co., Ltd., West high tech Industrial Development Zone, Chengdu City, Sichuan Province