CN206581217U - Flood control checkdam monomer and flood control checkdam - Google Patents

Flood control checkdam monomer and flood control checkdam Download PDF

Info

Publication number
CN206581217U
CN206581217U CN201720064930.2U CN201720064930U CN206581217U CN 206581217 U CN206581217 U CN 206581217U CN 201720064930 U CN201720064930 U CN 201720064930U CN 206581217 U CN206581217 U CN 206581217U
Authority
CN
China
Prior art keywords
checkdam
monomer
water retaining
flood control
retaining film
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720064930.2U
Other languages
Chinese (zh)
Inventor
田守朋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Sanyi Dayu Technology Co Ltd
Original Assignee
Beijing Sanyi Dayu Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Sanyi Dayu Technology Co Ltd filed Critical Beijing Sanyi Dayu Technology Co Ltd
Priority to CN201720064930.2U priority Critical patent/CN206581217U/en
Application granted granted Critical
Publication of CN206581217U publication Critical patent/CN206581217U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses anti-checkdam monomer and flood control checkdam, wherein flood control checkdam monomer includes mounting system and flexible water retaining film, mounting system includes attachment means between at least two pack support groups and frame, support group is removably fixed on ground or mounting surface, attachment means are removably fixed between two adjacent groups support group between frame, water retaining film front end is removably fixed with ballast, on ground that water retaining film front end is removably fixed in before mounting system by ballast or mounting surface, water retaining film rear end is removably fixed between support group and/or frame in attachment means, the basal surface of water retaining film latter half is brought into close contact with mounting system upstream face.Anti- checkdam monomer of the present utility model, is easy to quick arrangement and reclaims, transport and storage, high intensity, high reliability, carrying pressure are big, can effectively stop current seepage;The dash equipment of multiple use can also be connected into, to tackle the flood fighting demand of various scales.

Description

Flood control checkdam monomer and flood control checkdam
Technical field
The utility model is related to dam structure, more particularly to a kind of flood control checkdam monomer.
The utility model further relates to a kind of flood control checkdam by above-mentioned flood control checkdam monomer composition.
Background technology
At present, in flood fighting, tradition uses sandbag, the flood fighting material such as building stones.But traditional material volume is big, weight weight, And transport and deposit are required for substantial amounts of human and material resources and space.Meanwhile, constructing interim dam needs to come for quite a long time Complete, this tends not to meet the requirement quickly deployed troops on garrison duty the very first time.Therefore, flood-fighting department be badly in need of it is a kind of it is simple in construction, Small volume, it is lightweight, can Fast Installation and recovery, be readily transported and store, structural strength it is high, dash effect is good, can be multiple The emergent dash equipment reused tackles flood-fighting operation.
The content of the invention
In order to overcome the above-mentioned deficiencies of the prior art, the utility model provides a kind of flood control checkdam monomer, described anti- Big vast checkdam monomer, simple in construction, small volume, it is lightweight, can Fast Installation and recovery, be readily transported and store intensity it is high, Reliability is high, and can repeatedly use, and is the dash equipment served many purposes.
A kind of flood control checkdam monomer of the present utility model, including mounting system and flexible water retaining film, the mounting system Including attachment means between at least two pack support groups and frame, the support group is removably fixed on ground or mounting surface, described Support group front end upstream face is that attachment means are removably fixed in adjacent two between sweptback inclined plane from down to up, the frame Between the group support group, the water retaining film front end is removably fixed with ballast, and the water retaining film front end passes through the pressure Carry and put on the ground being removably fixed in before the mounting system or mounting surface, the water retaining film rear end is removably fixed in Between the support group and/or the frame in attachment means, basal surface and the mounting system of the water retaining film latter half are met The water surface is brought into close contact.
Flood control checkdam monomer technical scheme of the present utility model can also be:
The support group includes at least two panels monolithic support and at least one set of clamping plate, and the clamping plate is at least fixed on two panels phase The adjacent monolithic frame upper.
The monolithic support longitudinal cross-section is triangle, and the monolithic support front end upstream face is to tilt backwards from the bottom to top Inclined plane.
Attachment means are connecting cross beam between the frame, and at least one connecting cross beam is removably fixed in two adjacent groups institute State between support group.
The connecting cross beam grafting is fixed between the adjacent support group.
The water retaining film rear end is provided with fixing device, and the water retaining film rear end is removably fixed in by the fixing device Between the support group and/or the frame in attachment means.
The fixing device of the water retaining film rear end is bridle port, and the bridle port is banded with rope, and the rope is detachable It is fixed on the monolithic support and/or cross bearer.
The ballast is ballast iron chains, and the water retaining film front end is removably fixed in described by the ballast iron chains On the ground of support group front end upstream face or mounting surface.
Flood control checkdam monomer of the present utility model, including mounting system and flexible water retaining film, the mounting system include Attachment means between at least two pack support groups and frame, the support group is removably fixed on ground or mounting surface, the support Group front end upstream face is that attachment means are removably fixed in two adjacent groups institute between sweptback inclined plane from down to up, the frame State between support group, the water retaining film front end is removably fixed with ballast, the water retaining film front end is filled by the ballast Put on the ground being removably fixed in before the mounting system or mounting surface, the water retaining film rear end is removably fixed in described Between support group and/or the frame in attachment means, the basal surface of the water retaining film latter half and the mounting system upstream face It is brought into close contact.In use, the support group by attachment means between the frame link together composition mounting system be installed on ground On face or mounting surface, mounting system front end upstream face is sweptback inclined plane from down to up, then will be detachable Be fixed with the water retaining film front end of ballast be positioned over distance bracket meet water the segment distance of surface side one ground on, other end It is removably fixed between the support group and/or the frame in attachment means.The basal surface of the water retaining film first half and institute State the ground before mounting system or mounting surface is brought into close contact, basal surface and the mounting system of the water retaining film latter half Upstream face is brought into close contact, and then the water retaining film and the mounting system is removably fixed on ground or mounting surface, structure Into flood control checkdam monomer;With the arrival of flood, the water retaining film front end quilt controlled flood on the ground of checkdam monomer upstream face side Ballast pressure makes it not moved with current on the ground, and water retaining film, which can play a part of closing water, makes its not permeable drain to the back side.Water Ballast is covered, because the slope of support and water retaining film formation stops that current advance, water level can only go up.With flood level Go up, pressure is increasing, and water retaining film is laid on above ground portion and is pressed on ground securely under hydraulic pressure, has shut water and has been oozed from bottom Enter;Inclined-plane bears water cycle factors to the system frame simultaneously, and the support presses to ground more securely under hydraulic pressure makes it All the more stablize.The waterproof membrane of flood control checkdam monomer can effectively block flood under the support of support, almost without seepage. Optimal water effect is blocked so as to reach.After flood is decorporated, system frame is dismantled and withdrawn, then flexible water retaining film is merged into volume Rise.So, the flood control checkdam monomer when deploying troops on garrison duty can Quick-forming, and process operation of deploying troops on garrison duty is simple, when reclaiming Handling that are light quick and being easy in storage, transportation are not take up big quantity space, and flood control resultses are good.It is of the present utility model One kind flood control checkdam, is easy to quick arrangement there is provided one kind compared with prior art and reclaims, transport and storage space-consuming It is small, lightweight, high intensity, high reliability and serve many purposes dash equipment.Carry pressure big, can effectively stop current Seepage.
Another object of the present utility model, which is to provide one kind, quickly to arrange and reclaim, and stop flood effect is good, cost A kind of flood control checkdam that is cheap and being capable of Reusability.
Flood control checkdam of the present utility model, including at least one set of flood control checkdam monomer, the flood control checkdam monomer Two ends are provided with monomer attachment means, the monomer attachment means be removably fixed in the two neighboring flood control dam monomer it Between.The monomer attachment means can also be removably fixed in the flood control checkdam monomer head and the tail two ends, the flood control dash Dam monomer, it is characterised in that:Including mounting system and flexible water retaining film, the mounting system includes at least two pack support groups and frame Between attachment means, the support group is removably fixed on ground or mounting surface, and the support group front end upstream face is under To upper sweptback inclined plane, attachment means are removably fixed between support group described in two adjacent groups between the frame, described Water retaining film front end is removably fixed with ballast, and the water retaining film front end is removably fixed in described by the ballast On ground or mounting surface before mounting system, the water retaining film rear end is removably fixed in the support group and/or the frame Between in attachment means, the basal surface of the water retaining film latter half is brought into close contact with the mounting system upstream face.
Flood control checkdam monomer technical scheme of the present utility model can also be
The monomer attachment means include attachment means and the intermembranous attachment means of dash, the mounting system between mounting system Between attachment means be removably fixed in successively two adjacent groups flood control checkdam monomer mounting system ending two ends, the dash Intermembranous attachment means are set in turn in the ending two ends of water retaining film described in two adjacent groups.
Flood control checkdam of the present utility model, including at least one set of flood control checkdam monomer, the flood control checkdam monomer Both sides are provided with monomer attachment means.The monomer attachment means are removably fixed between the two neighboring flood control dam monomer Or it is removably fixed in the flood control checkdam monomer head and the tail two ends, the flood control checkdam monomer, it is characterised in that:Including branch Frame system and flexible water retaining film, the mounting system include attachment means between at least two pack support groups and frame, and the support group can Dismounting is fixed on ground or mounting surface, and the support group front end upstream face is sweptback inclined plane, institute from down to up Attachment means are removably fixed between support group described in two adjacent groups between stating frame, and the water retaining film front end is removably fixed with pressure Carry and put, the water retaining film front end is removably fixed in ground or installation before the mounting system by the ballast On face, the water retaining film rear end is removably fixed between the support group and/or the frame in attachment means, after the water retaining film The basal surface of half part is brought into close contact with the mounting system upstream face.So, when flood comes, the support group is led to first Cross the composition mounting system that links together of attachment means between the frame to be installed on ground or mounting surface, before the mounting system It is sweptback inclined plane from down to up to hold upstream face, then will be removably fixed with the water retaining film front end of ballast Be positioned over distance bracket meet water the segment distance of surface side one ground on, other end is removably fixed in the support group and/or institute State between frame in attachment means.The basal surface of the water retaining film first half and the ground before the mounting system or mounting surface are tight It is closely connected to close, and then multiple flood control dam monomers are quickly assembled into, then will be adjacent by least two by monomer attachment means The flood control checkdam of length needed for flood control checkdam monomer connects into flood control scene, because the support group between the frame by connecting Connection device, which is detachably fixed, to link together, and can change closure in junction, therefore flood control checkdam can form difference Angle, so as to stop flood to attack.After flood is decorporated, under monomer attachment means are dismantled from adjacent flood-protection dam monomer Come, as it is multiple flood control dam monomers, then by control flood checkdam monomer disassembly & recycling.Flood control checkdam of the present utility model, In terms of existing technologies, it this have the advantage that:Quickly it can arrange and reclaim, stop flood effect is good, space-consuming It is small, with low cost and being capable of Reusability.
Brief description of the drawings
Fig. 1 is the main body figure of flood control checkdam monomer of the present utility model and flood control checkdam;
Fig. 2 is the schematic cross-section of flood control checkdam monomer of the present utility model and flood control checkdam mounting system;
Fig. 3 is the material structure schematic diagram of flood control checkdam monomer of the present utility model and flood control checkdam.
Figure number explanation:
1 ... monolithic support 2 ... clamping plate 3 ... cross bearer
4 ... needle beam 5 ... water retaining film 6 ... ballast iron chains
7 ... bridle port 8 ... inner flexible coatings 9 ... weave base cloth layer
10 ... external flexible coatings
Embodiment
To this, practical flood control checkdam monomer is new is described in further details below in conjunction with the accompanying drawings.
Flood control checkdam monomer of the present utility model, including mounting system and flexible water retaining film 5, the mounting system include Attachment means between at least two pack support groups and frame, the support group is removably fixed on ground or mounting surface, the support Group front end upstream face is that attachment means are removably fixed in two adjacent groups institute between sweptback inclined plane from down to up, the frame State between support group, the water retaining film front end is removably fixed with ballast, the front end of water retaining film 5 is filled by the ballast Put on the ground being removably fixed in before the mounting system or mounting surface, the rear end of water retaining film 5 is removably fixed in institute State between support group and/or the frame in attachment means, the basal surface of the latter half of water retaining film 5 meets water with the mounting system Face is brought into close contact.In use, the support group by attachment means between the frame link together composition mounting system be installed on On ground or mounting surface, mounting system front end upstream face is sweptback inclined plane from down to up, then will be removable Unload be fixed with the front end of the water retaining film 5 of ballast be positioned over distance bracket meet water the segment distance of surface side one ground on, in addition One end is removably fixed between the support group and/or the frame in attachment means.The basal surface of the first half of water retaining film 5 It is brought into close contact with the ground before the mounting system or mounting surface, basal surface and the branch of the latter half of water retaining film 5 Frame system upstream face is brought into close contact, and then the water retaining film 5 and the mounting system are removably fixed in into ground or installation On face, flood control checkdam monomer is constituted;With the arrival of flood, the water retaining film controlled flood on the ground of checkdam monomer upstream face side Front end is ballasted device pressure makes it not moved with current on the ground, and water retaining film 5, which can play a part of closing water, makes its not permeable drain to The back side.Water covers ballast, and because the slope of support and the formation of water retaining film 5 stops that current advance, water level can only go up.With flood The rise of water water level, pressure is increasing, and water retaining film 5 is laid on above ground portion and is pressed on ground securely under hydraulic pressure, has shut water Penetrated into from bottom;Inclined-plane bears water cycle factors to the system frame simultaneously, and the support is pressed to more securely under hydraulic pressure Ground makes it stablize all the more.The waterproof membrane of flood control checkdam monomer can effectively block flood under the support of support, almost There is no seepage.Optimal water effect is blocked so as to reach.After flood is decorporated, system frame is dismantled and withdrawn, then by flexible dash Film 5, which merges, to be rolled.So, the flood control checkdam monomer when deploying troops on garrison duty can Quick-forming, and process operation of deploying troops on garrison duty is simple, When reclaiming, handling that are light quick and being easy in storage, transportation are not take up big quantity space, and flood control resultses are good.This reality With new flood control checkdam, it is easy to quick arrangement and recovery there is provided one kind compared with prior art, transport and storage take empty Between small, lightweight, high intensity, high reliability and serve many purposes dash equipment.Carry pressure big, can effectively stop water Flow seepage.
Flood control checkdam monomer of the present utility model, referring to figs. 1 to shown in the related each figures of Fig. 3, in previous technique scheme On the basis of can also be:The support group includes at least two panels monolithic support 1 and at least one set of clamping plate 2, and the clamping plate 2 is at least solid Due on the adjacent monolithic support 1 of two panels.Because the clamping plate 2 can be by the fixation be fixed on the monolithic support 1 The difference of point height and then the support group for being combined into different angles, so by the support group of different angles, to adapt to gear The requirement of water site contour.Further preferred technical scheme is:The longitudinal cross-section of monolithic support 1 is triangle, the list The front end upstream face of plate rack 1 is sweptback inclined plane from the bottom to top.The monolithic support 1 can be fixed to connect by three pipes Connect and form, simple in construction, firmly fixed not foldable, intensity is big.The front end upstream face of monolithic support 1 for from the bottom to top to This structure of inclined plane of rear-inclined, enhances impact resistance of the carrier base to flood, and under the pressure of flood More it is firmly fixed to ground.Can certainly be pipe fitting of the monolithic support 1 by the other quantity such as four or five Be formed by fixedly connecting, as long as structural strength is sufficiently large, it is preferable that the monolithic support 1 be fixedly connected by three pipes and Into.Further preferred technical scheme can also be:The monolithic support 1 is made up of metal material, and the monolithic support 1 has three Root pipe is welded and fixed together, and can so reduce the quantity of parts, is easy to fast quick-detach and the assembling of the mounting system. Certain mounting system can also be made by wooden structure or by other materials such as synthetic materials.Further preferred technology Scheme can also be:The thickness and big I of the monolithic support 1 are made according to the size of the flood control checkdam monomer done Fixed, the monolithic support 1 side bottom that meets water is parallel with ground or contact surface, so, is easy to the support group to be erected in On ground or mounting surface and support is more firm in the presence of hydraulic pressure.
Flood control checkdam monomer of the present utility model, referring to figs. 1 to shown in the related each figures of Fig. 3, in previous technique scheme On the basis of can also be:Attachment means are connecting cross beam between the frame, and at least one connecting cross beam is removably fixed in phase Between support group described in adjacent two groups.So, quickly support group described in adjacent two groups can be consolidated by the connecting cross beam It is scheduled on together, it is simple in construction, it is easy to operate.Further preferred technical scheme is:The connecting cross beam grafting is fixed on adjacent Between the support group.So, quickly the support group can be linked together by way of the crossbeam is with grafting excessively, Greatly improve operating efficiency high.Other are dismountable solid for the form or the form of buckle that can certainly be fixed with bolt etc. Fixed form links together the support group by attachment means between the frame.Further preferred technical scheme is:Institute Stating connecting cross beam includes entablature 3 and sill 4, and support group top described in two adjacent groups, institute are fixed in the grafting of entablature 3 State the grafting of sill 4 and be fixed at least grafting between support group bottom described in two adjacent groups, two adjacent pack support groups and be fixed with one Entablature 3 described in root.So many pack support groups are simple by support group described in adjacent two groups by the entablature 3 and sill 4 Single quick grafting successively is fixed together.At the same time, each part should all remove flash removed, and acute angle is polished smooth, it is to avoid to gear Moisture film 5 stabs abrasion.Further preferred technical scheme is:The top of monolithic support 1 and bottom are designed with slot, it is described on The two ends grafting of crossbeam 3 is fixed in the slot on the top of monolithic support 1, and the list is fixed in the two ends grafting of sill 4 In the slot of the bottom of plate rack 1.At the same time, the entablature 3 is designed with inserted link, the inserted link with the two ends of sill 4 With the slot grafting.So, be not only convenient between the support group and the entablature 3, sill 4 Rapid Combination install with Dismounting, and be also convenient for the replacing of parts and facilitate fixation of the water retaining film 5 in the mounting system, convenient storage In transport and the replacing of part, the service life of extension the utility model flood control checkdam monomer.The diameter of the inserted link with The slot aperture matches, and the depth of the inserted link length and slot matches, and the inserted link length of the sill 4 is oversize to be held The water retaining film 5 is easily contradicted, unnecessary harm is caused to the water retaining film 5, inserted link is too short, in the flood control checkdam monomer In the presence of hydraulic pressure, make the easy discontinuity of support and deform, influence the service life of the mounting system.Can certainly Be made of every entablature 3 and sill 4 by a cross bar, cross bar two ends two bending wrap direction in 90 ° is identical and same In one plane, the effective length of bending and the depth of slot coordinate, and the diameter of the crossbeam is engaged with the slot aperture, side Just dismantle.Further preferred technical scheme can also be:The mounting system is made up of metal material, the monolithic support 1 There are three pipe fitting weldings to be fixed together, slot is offered on the monolithic support 1, the slot can also be welded in the list On plate rack 1, the crossbeam two ends are fixed in the inserted link grafting.The quantity of parts can be so reduced, is easy to the branch The fast quick-detach of frame system and assembling.Certain mounting system can also be by wooden structure or by other materials such as synthetic material Matter is made.
Flood control checkdam monomer of the present utility model, referring to figs. 1 to shown in the related each figures of Fig. 3, in previous technique scheme On the basis of can also be:The rear end of water retaining film 5 is provided with fixing device, and the rear end of water retaining film 5 can by the fixing device Dismounting is fixed between the support group and/or the frame in attachment means.The water retaining film 5 can be so removably fixed in Mounting system is to surround in region.Further preferred technical scheme is:The fixing device of the rear end of water retaining film 5 is bridle port 7, the bridle port 7 is banded with rope, and the rope is removably fixed on the monolithic support and/or entablature 3.It is described Bridle port 7 is banded with rope, and the rope is removably fixed on the monolithic support and/or entablature 3.So, in assembling The water retaining film 5 can be quickly fixed on during flood control checkdam in mounting system, improve the operating efficiency of flood-fighting. The form that bridle port 7 can certainly be substituted for cloth set is sheathed in the system frame, or bridle port 7 is set as into nylon Thread gluing, makes the installation of the water retaining film 5 more convenient with dismantling.
Flood control checkdam monomer of the present utility model, referring to figs. 1 to shown in the related each figures of Fig. 3, in previous technique scheme On the basis of can also be:The ballast is ballast iron chains 6, and the front end of water retaining film 5 is detachable by the ballast iron chains 6 It is fixed on the ground of the support group front end upstream face or mounting surface.So, the ballast makes flood control checkdam monomer The flexible water retaining film 5 of bottom will not come and float with gushing for dampening, and the water retaining film 5 meets water the flexible dash of hydraulic pressure system of side The bottom close proximity to ground of film 5 or mounting surface, and then prevent water from largely leaking.With the rise of water level, pressure is increasing, described Water retaining film 5 is laid on the basal surface of above ground portion and is close to ground securely under hydraulic pressure, has shut water and has been penetrated into from bottom;Stand simultaneously Water cycle factors are born to the system frame in face, and the support presses to ground more securely under hydraulic pressure makes it stablize all the more. Checkdam entirety water retaining film 5 can effectively block flood under the support of support, almost without seepage;After flood is decorporated, tear open Except the ballast of bottom, the water retaining film 5 remnants water and silt displacement above, then the checkdam monomer that will control flood is allowed to dismantle Reclaim, in case using next time.At the same time, the ballast can also add sandbag or stone on the basis of ballast iron chains 6 The weights such as block, with ensure the bottom of water retaining film 5 will not because of excessive pouring in for flood float, it is ensured that property water retaining film 5 Bottom close proximity to ground or mounting surface.Certain ballast can also be other devices, for example fragment of brick, sandbag, stone or Person's iron nail etc. is easily installed the releasable device with dismounting, avoids water big as long as playing ballast effect to flood control checkdam bottom Amount leaks.
A kind of anti-checkdam monomer of the present utility model, with reference to shown in the related each figures of Fig. 3, on the basis of previous technique scheme On can also be:The water retaining film 5 includes inner flexible coating 8, braiding base cloth layer 9 and external flexible coating from inside to outside 10, the outer surface of inner flexible coating 8 is adhesively fixed with weaving the inner surface of base cloth layer 9, the external flexible coating 10 Inner surface and the layer outer surface of the braiding base fabric are adhesively fixed.So, the flexible coating has good flexibility, shaping Property and water proofing property, flood can be besieged in the mounting system upstream face side, prevent carriage support by the water retaining film 5 The flood of system upstream face side largely leaks, and the braiding base cloth layer 9 has good anti-stretch, and toughness is high, and intensity is big, from And ensure that the flexibility and formability of top flexible coating and lower flexible coating, it is to avoid as water level ascending water is pressed through greatly And burst flexible coating, enhance the service life of top flexible coating and lower flexible coating.Further preferred technology Scheme is:The inner flexible coating 8 and the external flexible coating 10 are by PVC material or TPU materials or PVC and TPU Mixing material is made, and the braiding base cloth layer 9 is made up of EP materials.So, PVC, TPU material is pressure-resistant, anti-stab wear-resisting, soft Soft foldable, is easily worked shaping, and weight is light, and also multiple color is optional, has so both enhanced flood control checkdam Service life, adds the diversity of the water retaining film 5 again.Can certainly be that the top flexible coating and the bottom are soft Property coating is made up of other high polymer materials.
Flood control checkdam of the present utility model, with reference to shown in the related each figures of Fig. 3, including at least one set of flood control checkdam list Body, the flood control checkdam monomer both sides are provided with monomer attachment means, and the monomer attachment means are removably fixed in adjacent two Between the individual flood control dam monomer or it is removably fixed in the flood control checkdam monomer head and the tail two ends, the flood control checkdam Monomer, it is characterised in that:Including mounting system and flexible water retaining film 5, the mounting system includes at least two pack support groups and frame Between attachment means, the support group is removably fixed on ground or mounting surface, and the support group front end upstream face is under To upper sweptback inclined plane, attachment means are removably fixed between support group described in two adjacent groups between the frame, described Water retaining film front end is removably fixed with ballast, and the front end of water retaining film 5 is removably fixed in institute by the ballast State on ground or the mounting surface before mounting system, the rear end of water retaining film 5 is removably fixed in the support group and/or described Between frame in attachment means, basal surface and the mounting system upstream face of the latter half of water retaining film 5 are brought into close contact.
Flood control checkdam of the present utility model, referring to figs. 1 to shown in the related each figures of Fig. 3, on the basis of previous technique scheme On can also be:The monomer attachment means include attachment means and the intermembranous attachment means of dash, the support between mounting system Attachment means are removably fixed in the ending two ends of the mounting system of two adjacent groups flood control checkdam monomer successively between system, described The intermembranous attachment means of dash are set in turn in the ending two ends of water retaining film 5 described in two adjacent groups.So, the flood control checkdam leads to Connecting device quickly connects the system frame for checkdam monomer of being controlled flood described in adjacent two groups between crossing described mounting system Together, the monomer of water retaining film 5 is quickly connected by connecting device between described water retaining film described in adjacent two group correspondingly It is connected together, quick assembly and disassembly of the checkdam of certain length at flood fighting scene needed for being easy to.Can also sequentially it connect from beginning to end Connect and surround circular or various polygons, so that the tank of arbitrary dimension requirement is formed or well monomer is enclosed in flood control, for storing The condition of a disaster such as each class I liquid I or compacting dike piping.Needed by the connection between checkdam monomer of controlling flood with the flood fighting for tackling various scales Ask so that the application of dam body is more extensive.Further preferred technical scheme is:Attachment means are between the mounting system Attachment means are connecting cross beam between attachment means between the frame, the frame, and the connecting cross beam includes entablature 3 and sill 4, The simplicity of flood control checkdam structure can so be ensured, assembly and disassembly and replacing is easily facilitated.Further preferred skill Art scheme is:The intermembranous attachment means of dash at the two ends of water retaining film 5 are nylon adherent buckle, and the nylon adherent buckle is arranged at the gear The monomer two ends of moisture film 5, the nylon adherent buckle is mutually adhesively fixed.So, glued successively by nylon adherent buckle described in adjacent both sides Multigroup monomer of water retaining film 5 is quickly connected to together by patch.
It is above-mentioned that only several specific embodiments of the present utility model are illustrated, protection of the present utility model can not be used as Scope, as long as according to equivalent change or modification made by design spirit of the present utility model, all should fall into of the present utility model Protection domain.

Claims (10)

1. checkdam monomer of controlling flood, it is characterised in that:Including mounting system and flexible water retaining film (5), the mounting system includes Attachment means between at least two pack support groups and frame, the support group is removably fixed on ground or mounting surface, the support Group front end upstream face is that attachment means are removably fixed in two adjacent groups institute between sweptback inclined plane from down to up, the frame State between support group, water retaining film (5) front end is removably fixed with ballast, water retaining film (5) front end passes through described Ballast is removably fixed on the ground before the mounting system or mounting surface, and water retaining film (5) rear end is detachable It is fixed between the support group and/or the frame in attachment means, basal surface and the branch of water retaining film (5) latter half Frame system upstream face is brought into close contact.
2. flood control checkdam monomer according to claim 1, it is characterised in that:The support group includes at least two panels monolithic Support (1) and at least one set of clamping plate (2), the clamping plate (2) are at least fixed on adjacent monolithic support (1) top of two panels.
3. flood control checkdam monomer according to claim 2, it is characterised in that:Monolithic support (1) longitudinal cross-section is Triangle, monolithic support (1) front end upstream face is sweptback inclined plane from the bottom to top.
4. flood control checkdam monomer according to claim 1, it is characterised in that:Attachment means are horizontal for connection between the frame Beam, at least one connecting cross beam is removably fixed between support group described in two adjacent groups.
5. a kind of flood control checkdam monomer according to claim 4, it is characterised in that:The connecting cross beam grafting is fixed on Between the adjacent support group.
6. the flood control checkdam monomer according to claim 2-3 any one claims, it is characterised in that:The dash Film (5) rear end is provided with fixing device, and water retaining film (5) rear end is removably fixed in the support group by the fixing device And/or between the frame in attachment means.
7. flood control checkdam monomer according to claim 6, it is characterised in that:The fixed dress of water retaining film (5) rear end Be set to bridle port (7), the bridle port (7) is banded with rope, the rope be removably fixed in the monolithic support and/or on On crossbeam.
8. flood control checkdam monomer according to claim 1, it is characterised in that:The ballast is ballast iron chains (6), Water retaining film (5) front end by the ballast iron chains (6) be removably fixed in the support group front end upstream face ground or On mounting surface.
9. checkdam of controlling flood, it is characterised in that:Including at least one set flood control dam monomer, the flood control dam monomer both sides are provided with Monomer attachment means, the monomer attachment means are removably fixed between the two neighboring flood control dam monomer, described anti- Flood dam monomer is the flood control dam monomer described in the claim 1-8.
10. flood control checkdam according to claim 9, it is characterised in that:The monomer attachment means include mounting system Between attachment means are removably fixed in adjacent two successively between attachment means, the mounting system between attachment means and water retaining film (5) Attachment means are set in turn in adjacent two between the ending two ends of the mounting system of group flood control checkdam monomer, the water retaining film (5) The ending two ends of the group water retaining film (5).
CN201720064930.2U 2017-01-19 2017-01-19 Flood control checkdam monomer and flood control checkdam Expired - Fee Related CN206581217U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720064930.2U CN206581217U (en) 2017-01-19 2017-01-19 Flood control checkdam monomer and flood control checkdam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720064930.2U CN206581217U (en) 2017-01-19 2017-01-19 Flood control checkdam monomer and flood control checkdam

Publications (1)

Publication Number Publication Date
CN206581217U true CN206581217U (en) 2017-10-24

Family

ID=60110765

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720064930.2U Expired - Fee Related CN206581217U (en) 2017-01-19 2017-01-19 Flood control checkdam monomer and flood control checkdam

Country Status (1)

Country Link
CN (1) CN206581217U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853464A (en) * 2019-01-22 2019-06-07 张谦 A kind of vehicle-mounted floatage-type checkdam and its application method
CN110080165A (en) * 2019-03-29 2019-08-02 张谦 A kind of arch thin-wall construction checkdam and its application method that can quickly construct

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853464A (en) * 2019-01-22 2019-06-07 张谦 A kind of vehicle-mounted floatage-type checkdam and its application method
CN110080165A (en) * 2019-03-29 2019-08-02 张谦 A kind of arch thin-wall construction checkdam and its application method that can quickly construct

Similar Documents

Publication Publication Date Title
CN206581217U (en) Flood control checkdam monomer and flood control checkdam
CN107208390A (en) Improved receiving dykes and dams
CN206428653U (en) A kind of flood control small dike
CN205857125U (en) Emergent dash removable splicing water-retention dam combined equipment
CN105544873A (en) Wavy hollow roof and construction method thereof
DK144071B (en) Erosion-inhibiting surface coatings
CN204898602U (en) Emergent stifled waterwall
CN108104058A (en) A kind of dykes and dams flood crevasse plugging device and its method for blocking
CN206256425U (en) A kind of Water flood protection device
CN205242788U (en) Wave roofing structure of continuous gradation
CN205975490U (en) Flood control dam monomer and flood control dam subassembly
CN208934013U (en) A kind of basement bottom board pouring after settlement structure
JP2017166149A (en) Waterproof sheet for tunnel, and waterproof structure of tunnel
CN210368982U (en) Stay cable supporting construction
CN109083195B (en) Comprehensive pipe gallery waterproof system and construction method thereof
CN204080733U (en) Combination moving type rubber dam
CN209040863U (en) A kind of tunnel waterproofing construction
CN208317936U (en) A kind of fence mesh stake net connector
US3155280A (en) Buoyant flexible container and underwater anchorage therefor
CN204139119U (en) A kind of flood control dam monomer
CN205975491U (en) Flood control dam monomer and flood control dam subassembly
CN206784389U (en) Quick block up fabricated construction system and erecting device
CN209308379U (en) A kind of driven hanging basket balance weight mechanism
CN102561710B (en) Construction method of overhead stone plate of slope roof
CN207714255U (en) A kind of stackable folding flood fighting water blocking small dike

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171024

Termination date: 20190119

CF01 Termination of patent right due to non-payment of annual fee