CN206173947U - Underground continuous wall easily abolishes pile head - Google Patents

Underground continuous wall easily abolishes pile head Download PDF

Info

Publication number
CN206173947U
CN206173947U CN201621257491.9U CN201621257491U CN206173947U CN 206173947 U CN206173947 U CN 206173947U CN 201621257491 U CN201621257491 U CN 201621257491U CN 206173947 U CN206173947 U CN 206173947U
Authority
CN
China
Prior art keywords
plastic tube
pile crown
fragile
reinforcing bar
sealing member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621257491.9U
Other languages
Chinese (zh)
Inventor
田文洋
关博文
张澳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING GEO-ENGINEERING Co
Original Assignee
BEIJING GEO-ENGINEERING Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING GEO-ENGINEERING Co filed Critical BEIJING GEO-ENGINEERING Co
Priority to CN201621257491.9U priority Critical patent/CN206173947U/en
Application granted granted Critical
Publication of CN206173947U publication Critical patent/CN206173947U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses an underground continuous wall easily abolishes pile head, its technical scheme main points are a plurality of sections reinforcing bars of benchmark above ground level in the diaphragm wall, the plastic tubing on a plurality of sections reinforcing bars is located to the cover for the sealing member in clearance between sealed plastic pipe upper end opening and plastic tubing lower extreme and the reinforcing bar, reinforcing bar, plastic tubing and sealing member are pour in the concrete together. The utility model provides a current low diaphragm wall pile head problem that is difficult to to abolish.

Description

Diaphram wall is fragile except pile crown
Technical field
This utility model is related to diaphragm wall and excavates field, and more particularly to a kind of diaphram wall is fragile except pile crown.
Background technology
Diaphram wall excavation technology originates from Europe.It is to use mud and underwater pouring according to well-digging and oil drilling The method of concrete and grow up, nineteen fifty in Milan, ITA initially with slurry coat method construction of diaphragm wall, 50 ~ sixties of 20th century, the technology was promoted in western developed country and the former Soviet Union, becomes underground engineering and deep foundation is applied Effective technology in work.
Diaphram wall is that foundation engineering adopts a kind of trench machine on the ground, along the periphery axle of deep excavation project Line, under the conditions of mud off, excavates out a long and narrow deep trouth, after clear groove, steel reinforcement cage is hung in groove, then use tremie method Underwater concreting with tremie method builds up a unit groove section, so carries out paragraph by paragraph, builds up continuous reinforced concrete wall together in underground Wall, as intercepting water, antiseepage, load-bearing, water-retaining structure.Basement, market place builet below the ground suitable for construction of buildings, parking lot, underground Oil depot, retaining wall, the deep foundation of skyscraper, reverse construction building enclosure, the deep pond of industrial building, hole, vertical shaft etc..
In diaphram wall casting process, due in process of vibrating with inside concrete bubble or hole rising It is laitance to stake top part, stake top certain limit, or mud during underwater concrete pouring, mortar mix, in order to ensure stake The empty stake on top need to be cut by body concrete strength.
Only need to reach using the vertical pile body direction drilling of air drill, drilling depth during broken pile head at stake top setting The 1/5 of stake footpath, then will separate in contract son insertion drilling, and be tapped using external force, until drill hole pile crown and stake Body face produces separation, and then recurrence hangs out top pile crown.
Because which is more tight with internal bar connecting after concrete coagulation, is broken and separated more from reinforcing bar Arduously, so needing to design a kind of diaphram wall fragile except pile crown.
Utility model content
The purpose of this utility model is that a kind of diaphram wall of offer is fragile except pile crown, and it has the spy for being easy to abolish Point.
Above-mentioned purpose of the present utility model technical scheme is that:A kind of diaphram wall is fragile to be removed Some sections of reinforcing bars of benchmark above ground level, the plastic tube being sheathed on some sections of reinforcing bars, for sealing in pile crown, including diaphragm wall The sealing member in gap between plastic tube upper end open and plastic tube lower end and reinforcing bar, the reinforcing bar, plastic tube and sealing member Poured in concrete together.
By adopting above-mentioned technical proposal, first plastic tube is arranged on reinforcing bar is above the ground level the lengths of rebar of the part of benchmark, Then the opening of plastic tube upper end and lower end and the clearance seal of reinforcing bar, after such casting concrete, are mixed using sealing member Solidifying soil is detached with reinforcing bar, there is no bonding relation between the two.When abolishing pile crown, staff only needs to abolish concrete The bonding relation of itself, and without the need for viscous as what is will destroyed between concrete itself and concrete and rebar in prior art simultaneously Relation is connect, compared to existing technology, the pile crown of the diaphram wall of the design is easy to be abolished.
This utility model is further arranged to:Diaphragm wall is above the ground level in the part of benchmark and is arranged at intervals with demarcation strip, institute State in demarcation strip concreting.
By adopting above-mentioned technical proposal, if the concrete on pile crown can be divided into stem portion by demarcation strip, compare original Integral structure, with demarcation strip segmentation after pile crown caking property reduce, it is easy to abolished.
This utility model is further arranged to:The sealing member includes covering the door held on the plastic tube and is sheathed on Reinforcing bar and it is close to the rubber ring of plastic tube lower end.
Sealed by adopting above-mentioned technical proposal, door and rubber ring, for preventing concrete from touching reinforcing bar. Rubber ring is elastomer, and which can preferably fill gap, so the sealing of rubber ring is preferable.Rubber ring is because have one simultaneously Fixed elastic deformability, the requirement to quality of fit are low, so easy for installation.
This utility model is further arranged to:The door is made using elastomeric material.
By adopting above-mentioned technical proposal, using elastomeric material made by elastomeric material, with certain elastic deformation energy Power, the requirement to quality of fit are low, so easy for installation.
This utility model is further arranged to:The rubber ring is provided with inward flange and outward flange, inward flange and outward flange Annular bayonet socket is formed, annular bayonet socket snaps in the lower end of plastic tube.
Can quickly be set on reinforcing bar and pacify by interface arrangment by adopting above-mentioned technical proposal, such rubber ring The lower end of plastic tube is attached to, it is easy for installation.
This utility model is further arranged to:The diapire of the door has extended downwardly annular ridge, the side wall of door and Annular ridge forms caulking groove, the upper end of the embedded plastic tube of caulking groove.
By adopting above-mentioned technical proposal, door more solid can effectively be connected to plastic tube upper end, sealability, anti- Exfoliation ability is more preferable.
This utility model is further arranged to:The sealing member adopts the upper and lower end of adhesive tape, plastic tube to use adhesive tape circumvolution Sealing.
By adopting above-mentioned technical proposal, just can be close by plastic tube in a few circles of upper and lower end circumvolution of plastic tube using adhesive tape Envelope, it is without the need for specially remanufacturing sealing member, cost-effective.
This utility model is further arranged to:The demarcation strip is made using sheet metal.
Batch machining is easier by adopting above-mentioned technical proposal, sheet metal, while it is more smooth to compare its surface of plank, It is worse with the cementability of concrete so as to abolish pile crown more laborsaving.
In sum, this utility model has the advantages that:First it is arranged on reinforcing bar is above the ground level the part of benchmark Then the opening of plastic tube upper end and lower end and the clearance seal of reinforcing bar are so poured coagulation using sealing member by plastic tube After soil, concrete and rebar will not be contacted, and there is no bonding relation between the two.
Simultaneously the concrete on pile crown is split by demarcation strip again so that this part concrete caking property of itself is entered One step is reduced.When abolishing pile crown, staff only needs to the bonding relation for abolishing concrete itself, and without the need for as in prior art The bonding relation destroyed between concrete itself and concrete and rebar simultaneously, compared to existing technology, the underground of the design The pile crown of diaphragm wall is easy to be abolished.
Description of the drawings
Axonometric charts of the Fig. 1 for embodiment 1;
Front views of the Fig. 2 for embodiment 1;
Fig. 3 is the sectional view in A-A directions in Fig. 2;
A portion enlarged drawings of the Fig. 4 for Fig. 3;
Fig. 5 is for the view that done of cooperation for showing reinforcing bar, plastic tube, door, rubber ring.
In figure:1st, diaphragm wall;100th, pile crown;2nd, reinforcing bar;3rd, plastic tube;4th, sealing member;400th, door;4000th, convex annular Rib;401st, rubber ring;4010th, inward flange;4011st, outward flange;5th, demarcation strip;6th, terrestrial reference.
Specific embodiment
This utility model is described in further detail below in conjunction with accompanying drawing.
Embodiment 1:A kind of diaphram wall is fragile except pile crown, and with reference to Fig. 1, Fig. 2, Fig. 3, pile crown 100 refers to that diaphragm wall 1 is high In terrestrial reference 6(What technical staff confirmed, the reference level surface that abolished)Part, pile crown 100 includes demarcation strip 5, Demarcation strip 5 is made using plank or sheet metal and is disposed in pile crown 100, demarcation strip 5 made by preferred sheet metal.
Reinforcing bar 2 of the pile crown 100 also including the benchmark 6 that is above the ground level in diaphragm wall 1, is arranged with plastic tube on the part reinforcing bar 2 3, the opening of 3 upper end of plastic tube and lower end are sealed by sealing member 4 with the gap of reinforcing bar 2.
With reference to Fig. 4, Fig. 5, sealing member 4 includes door 400 of the buckle closure in 3 upper end open of plastic tube and is sheathed on reinforcing bar 2 and shelter from 2 gap of plastic tube 3 and reinforcing bar rubber volume.In order that door 400 is easily installed and sealing is preferable, preferably Door 400 made by elastomeric material, and the diapire of door 400 has extended downwardly annular ridge 4000, the side wall of door 400 and Annular ridge 4000 forms caulking groove, the upper end of the embedded plastic tube 3 of caulking groove of door 400.Rubber ring 401 is provided with inward flange 4010 With outward flange 4011, inward flange 4010 and outward flange 4011 form annular bayonet socket, and annular bayonet socket snaps in the lower end of plastic tube 3.
Sealing member 4 can also use adhesive tape, by adhesive tape by the upper end open and lower ending opening of plastic tube 3 and reinforcing bar 2 Between gap circumvolution live, so as to play sealing function.
The specifically used method of the present embodiment is to dig the foundation ditch for arranging diaphragm wall 1, is put into 2 cage of reinforcing bar or reinforcing bar 2, Terrestrial reference 6 is determined according to design drawing, plastic tube 3, the upper and lower side of plastic tube 3 are arranged on the reinforcing bar 2 for being above the ground level benchmark 6 Sealed using sealing member 4, then the part interval setting demarcation strip 5 of the benchmark 6 that is above the ground level in diaphragm wall 1 is poured again, mixed Solidifying soil will cover reinforcing bar 2, plastic tube 3 and demarcation strip 5.
This specific embodiment is only which is not to restriction of the present utility model, ability to explanation of the present utility model Field technique personnel can make the modification for not having creative contribution after this specification is read as needed to the present embodiment, but As long as all being protected by Patent Law in right of the present utility model.

Claims (8)

1. a kind of diaphram wall is fragile except pile crown, it is characterised in that:Including benchmark (6) above ground level in diaphragm wall (1) if Dry section reinforcing bar (2), the plastic tube (3) being sheathed on some sections of reinforcing bars (2), for sealed plastic pipe (3) upper end open and modeling The sealing member (4) in gap between expects pipe (3) lower end and reinforcing bar (2), the reinforcing bar (2), plastic tube (3) and sealing member (4) Rise and pour in concrete.
2. a kind of diaphram wall according to claim 1 is fragile except pile crown, it is characterised in that:Diaphragm wall (1) is above Ground Demarcation strip (5) is arranged at intervals with the part of face benchmark (6), the demarcation strip (5) is with concreting.
3. a kind of diaphram wall according to claim 1 is fragile except pile crown, it is characterised in that:Sealing member (4) bag Include cover plastic tube (3) upper end door (400) and be sheathed on reinforcing bar (2) and be close to the rubber ring of plastic tube (3) lower end (401)。
4. a kind of diaphram wall according to claim 3 is fragile except pile crown, it is characterised in that:The door (400) makes Made with elastomeric material.
5. a kind of diaphram wall according to claim 3 is fragile except pile crown, it is characterised in that:The rubber ring (401) Inward flange (4010) and outward flange (4011) are provided with, inward flange (4010) and outward flange (4011) form annular bayonet socket, annular Bayonet socket snaps in the lower end of plastic tube (3).
6. a kind of diaphram wall according to claim 4 is fragile except pile crown, it is characterised in that:The door (400) Diapire has extended downwardly annular ridge (4000), and the side wall of door (400) and annular ridge (4000) form caulking groove, and caulking groove is embedded in The upper end of plastic tube (3).
7. a kind of diaphram wall according to claim 1 is fragile except pile crown, it is characterised in that:The sealing member (4) is adopted With adhesive tape, the upper and lower end of plastic tube (3) is sealed using adhesive tape circumvolution.
8. a kind of diaphram wall according to claim 2 is fragile except pile crown, it is characterised in that:The demarcation strip (5) is adopted Made with sheet metal.
CN201621257491.9U 2016-11-19 2016-11-19 Underground continuous wall easily abolishes pile head Expired - Fee Related CN206173947U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621257491.9U CN206173947U (en) 2016-11-19 2016-11-19 Underground continuous wall easily abolishes pile head

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621257491.9U CN206173947U (en) 2016-11-19 2016-11-19 Underground continuous wall easily abolishes pile head

Publications (1)

Publication Number Publication Date
CN206173947U true CN206173947U (en) 2017-05-17

Family

ID=58685816

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621257491.9U Expired - Fee Related CN206173947U (en) 2016-11-19 2016-11-19 Underground continuous wall easily abolishes pile head

Country Status (1)

Country Link
CN (1) CN206173947U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106968251A (en) * 2017-05-26 2017-07-21 中交第二航务工程局有限公司 A kind of concrete filling pile head abolishes device and its construction method
CN107829426A (en) * 2017-12-13 2018-03-23 广西大学 A kind of restructuring bankrupt of diaphram wall, forming method and its top of a wall part
CN108265702A (en) * 2018-01-26 2018-07-10 中铁上海工程局集团华海工程有限公司 Diaphram wall cage top reinforcing bar protects structure and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106968251A (en) * 2017-05-26 2017-07-21 中交第二航务工程局有限公司 A kind of concrete filling pile head abolishes device and its construction method
CN107829426A (en) * 2017-12-13 2018-03-23 广西大学 A kind of restructuring bankrupt of diaphram wall, forming method and its top of a wall part
CN108265702A (en) * 2018-01-26 2018-07-10 中铁上海工程局集团华海工程有限公司 Diaphram wall cage top reinforcing bar protects structure and construction method

Similar Documents

Publication Publication Date Title
CN103215960B (en) Grouting method for high polymer vertical support system
CN206173947U (en) Underground continuous wall easily abolishes pile head
CN103437348B (en) Construction device and method of pile peripheral cemented soil cast-in-place stiffness core pile
CN102561402A (en) Treatment method for construction joint between top plate and wall of individual underground civil air defense project constructed by covered top-down excavation method
CN104912065A (en) Underwater anchor pile construction method
CN105649094B (en) A kind of deep water foundation bearing platform construction three wall steel cofferdams and its construction method
JP4463140B2 (en) Seismic reinforcement method for masonry walls
CN105484731A (en) Inclination measurement hole construction method
CN105672250A (en) Rabbet connecting mechanism and construction method for underground diaphragm wall and underwater concrete
CN203462463U (en) Construction device of pile-peripheral cemented-soil cast-in-situ stiffening core pile
CN102626946A (en) Manufacture method for concrete irregular fender post
CN211395755U (en) Prefabricated square inspection shaft
CN206438515U (en) A kind of device for plugging being used in artesian area's pile-anchor supporting system
CN206015717U (en) The underground pipe gallery of soft soil foundation
CN106812157A (en) A kind of assembled hypogee and its construction method
CN112302136A (en) Connecting structure of new and old drainage pipelines under non-closure working condition and construction method thereof
CN208517970U (en) A kind of fully-prefabricated assembled piping lane
CN103866787B (en) A kind of spacious reverse masonry method concrete cut that digs builds construction technology
CN106193075A (en) A kind of concrete cofferdam and steel sheet-pile cofferdam combination type cofferdam structure and construction method
CN105401586A (en) Construction method for bottomless steel jacket box capable of stopping water simply
CN213038391U (en) Miniature pile structure for accelerating pit-to-pit construction speed of deep foundation pit
CN210658619U (en) Novel pipeline inspection well
CN105442528B (en) Cement grouting sheet pile with sealing ring
JP4888293B2 (en) Earth retaining wall made of parent pile sheet pile, water stop structure of earth retaining wall made of parent pile side sheet pile, construction method of earth retaining wall made of parent pile side sheet pile, and retaining wall of earth retaining wall made of parent pile side sheet pile Water method
CN211312560U (en) Simple and easy core section of thick bamboo stepping water conservancy diversion drainage structures

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170517

Termination date: 20211119

CF01 Termination of patent right due to non-payment of annual fee