CN108265702A - Diaphram wall cage top reinforcing bar protects structure and construction method - Google Patents

Diaphram wall cage top reinforcing bar protects structure and construction method Download PDF

Info

Publication number
CN108265702A
CN108265702A CN201810077114.4A CN201810077114A CN108265702A CN 108265702 A CN108265702 A CN 108265702A CN 201810077114 A CN201810077114 A CN 201810077114A CN 108265702 A CN108265702 A CN 108265702A
Authority
CN
China
Prior art keywords
reinforcing bar
steel reinforcement
cage
sleeve pipe
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810077114.4A
Other languages
Chinese (zh)
Inventor
周洪光
周静增
戴军
许崇甲
高丹
钱琨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huahai Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Original Assignee
Huahai Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huahai Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC filed Critical Huahai Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Priority to CN201810077114.4A priority Critical patent/CN108265702A/en
Publication of CN108265702A publication Critical patent/CN108265702A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to construction of diaphragm wall device and method technical fields; specifically a kind of diaphram wall cage top reinforcing bar protection structure and construction method; including steel reinforcement cage; and the superfilled concrete above the diaphragm wall and diaphragm wall poured along steel reinforcement cage; the reinforcing bar of steel reinforcement cage cage top is beyond the top of diaphragm wall and in superfilled concrete; protection structure further includes steel reinforcement protective sleeve pipe, and steel reinforcement protective sleeve pipe is fixed on by several bands on the outside of the reinforcing bar of cage top.Compared with the existing technology, composite structure simple possible is easily installed and dismantles the present invention, and construction method is succinctly efficient, the advantage is that:It is apparent to reinforcing bar protecting effect, avoid reinforcing bar bending, damage when cutting concrete;When cutting ground-connecting-wall end concrete, process is simplified, labour is configured less, labor intensity is low, mechanical efficiency is high, convenient for rapid construction;Protection sleeve pipe is made using EPE pearl wool, it is at low cost, flexible, degradable.

Description

Diaphram wall cage top reinforcing bar protects structure and construction method
[technical field]
The present invention relates to construction of diaphragm wall device and method technical field, a kind of specifically diaphram wall cage Push up reinforcing bar protection structure and construction method.
[background technology]
Construction method of underground continuous wall is wide in the engineering constructions such as water conservancy, building, municipal administration, traffic, mine, railway and environmental protection General application, it is especially very universal in terms of coal mine shaft, subway station and Deep Underground pit enclosure.At present, in diaphram wall In order to ensure wall body concrete quality, there is >=superfilled the concrete of 500mm in design requirement work progress to diaphram wall top, this The superfilled concrete in part is cut when diaphragm wall top Guan Liang is constructed, due to the diaphram wall cage top reinforcing bar for anchoring into Guan Liang be contained in it is superfilled In concrete, bar bending is caused when cutting, is lost and secondary damage, cuts inefficient, correction reinforcing bar is time-consuming and laborious, to follow-up Construction quality is affected, and there are no effective technical methods to solve the problems, such as this.
[invention content]
It is an object of the invention to solve the deficiencies in the prior art, a kind of diaphram wall cage top reinforcing bar protection structure is provided And construction method, when cutting the superfilled concrete of diaphram wall, the cage top reinforcing bar inside superfilled concrete is protected, reaches and avoids Bar bending is caused when cutting, is lost and secondary damage, improves the purpose for cutting efficiency.
To achieve these goals, a kind of diaphram wall cage top reinforcing bar protection structure is designed, including steel reinforcement cage, Yi Jiyan The superfilled concrete above diaphragm wall and diaphragm wall that steel reinforcement cage pours, the reinforcing bar of the steel reinforcement cage cage top is beyond diaphragm wall Top simultaneously be located at superfilled concrete in, the protection structure further includes steel reinforcement protective sleeve pipe, if the steel reinforcement protective sleeve pipe by Dry band is fixed on the outside of the reinforcing bar of cage top.
The steel reinforcement protective sleeve pipe meets following condition:
d≥D+5mm;δ≥1/5Dmm;L'≥1.05Lmm;
In formula:D is the bar diameter of cage top, L is cage top reinforcing bar length, d are the internal diameter of steel reinforcement protective sleeve pipe, δ is steel The thickness of pipe of muscle protection sleeve pipe, the length that L' is steel reinforcement protective sleeve pipe.
The steel reinforcement protective sleeve pipe also meets following condition:Steel reinforcement protective sleeve tube material density≤0.03G/cm3;Tension Intensity >=3.40KG/cm3;Tearing toughness >=2.60KG/cm3;Ductility >=125%.
The protection of steel bar gabion casing is made of EPE pearl wool.
The band meets following condition:
L >=5Dmm and tensile strength >=8.10KG;
In formula:The length that D is the bar diameter of cage top, l is band.
The band is self-locking type plastic band.
The present invention also designs a kind of construction method using the diaphram wall cage top reinforcing bar protection structure, described Method and step is as follows:
A. before steel reinforcement cage installation is in place, steel reinforcement protective sleeve pipe is set with, and pass through at least two to the reinforcing bar of steel reinforcement cage cage top Band mutually fixes steel reinforcement protective sleeve pipe and the reinforcing bar of cage top, transfers steel reinforcement cage to the diaphram wall steel led under wall after fixed At muscle cage designed elevation position, and concreting is carried out until reaching design strength, to form diaphragm wall and superfilled concrete.
B. after the completion of pouring, wall is led in dismounting, by excavating the superfilled concrete on diaphragm wall top for exposing and needing to cut, and is delimited Line is cut, then using the mechanical superfilled concrete for cutting diaphragm wall top is cut, steel reinforcement protective sleeve pipe is made when cutting together with superfilled The concrete of concrete is stripped together, ultimately forms the diaphram wall to conform to quality requirements.
Compared with the existing technology, composite structure simple possible is easily installed and dismantles the present invention, and construction method letter is easy to be high Effect, the advantage is that:
1st, it is apparent to reinforcing bar protecting effect, avoid reinforcing bar bending, damage when cutting concrete.
When the 2nd, cutting ground-connecting-wall end concrete, process is simplified, labour is configured less, labor intensity is low, mechanical efficiency is high, Convenient for rapid construction.
3rd, protection sleeve pipe is made using EPE pearl wool, it is at low cost, flexible, degradable.
[description of the drawings]
Fig. 1 is the front view of the diaphram wall cage top reinforcing bar protection structure of the present invention;
Fig. 2 is the scheme of installation of the diaphram wall cage top reinforcing bar protection structure of the present invention;
In figure:1. 4. diaphram wall of reinforcing bar of 2. band of steel reinforcement protective sleeve pipe, 3. steel reinforcement cage cage top.
[specific embodiment]
The invention will be further described below in conjunction with the accompanying drawings, and the structure and principle of this device and method are to this profession It is very clearly for people.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not used to Limit the present invention.
In the present embodiment, research and development application is carried out by reinforcing bar, concrete and flexible material coupling technique, experiment has found work To protect the suitable material of structure, i.e. it is continuous to design a kind of new-type underground for EPE pearl wool, and use EPE pearl wool as material Wall cage top reinforcing bar protects structure.
In practice of construction, after steel reinforcement cage is positioned over setting position, need to pour into diaphragm wall along steel reinforcement cage, and Continue to pour superfilled concrete above diaphragm wall, when follow-up diaphragm wall top Guan Liang is constructed, row is cut superfilled concrete again.The reinforcing bar The reinforcing bar of cage cage top is beyond the top of diaphragm wall and in superfilled concrete, and referring to Fig. 1, the protection structure is mainly by two parts Composition:Steel reinforcement protective sleeve pipe and band pass through several band fixed steel bars protection sleeve pipes, the number of band on the outside of the reinforcing bar of cage top Amount is at least two, it is preferable that the band is uniformly arranged on the length direction of steel reinforcement protective sleeve pipe.In present embodiment The steel reinforcement protective sleeve pipe is EPE pearl wool steel reinforcement protective sleeve pipe, and the band is self-locking type plastic band.
The structural parameters and performance parameter of the EPE pearl wool steel reinforcement protective sleeve pipe, with protection bar diameter D and protection Parameter on the basis of length L, internal diameter d >=D+5mm;Thickness of pipe δ >=1/5Dmm;Pipe range L' >=1.05Lmm.EPE pearl wool reinforcing bar is protected Shell material density≤0.03G/cm3;It is sealed using foaming structure-non-crosslinked;Tensile strength >=3.40KG/cm3;Tear-proof Intensity >=2.60KG/cm3;Ductility >=125%;Flexibility is good.
The structural behavior of the self-locking type plastic band, by parameter, length l >=5Dmm on the basis of protection bar diameter D; Tensile strength >=8.10KG.In the present embodiment, described band one end be equipped with buckle structure, buckle structure be equipped with buckle teeth and And the block that sets opposite with buckle teeth, the band surface are correspondingly provided with dentalation, and the band other end can pass through institute The buckle structure stated is meshed at this time by dentalation with buckle teeth, and is passed through block and be fixed.
By installing protection structure on reinforcing bar, mitigate concrete and reinforcing bar is bonded, when being cut to ground-connecting-wall end Convenient for concrete is removed from reinforcing bar, so as to reduce labor intensity, construction cost is reduced, is accelerated construction progress, protecting ecology Environment.
Embodiment
Referring to Fig. 2, the installation steps of the protection structure are as follows:Before the installation of diaphram wall steel reinforcement cage is in place, including Before reinforcement cage hoisting or cage top reinforcing bar enter slot it is in place before, to it is required protection diaphram wall steel reinforcement cage cage top reinforcing bar set EPE pearl wool steel reinforcement protective sleeve pipe is filled, and is tied tight with the fastening of self-locking type plastic band, every reinforcing bar binding no less than two, this Two self-locking type plastic bands are employed in embodiment, thereafter transfer steel reinforcement cage to the diaphram wall reinforcing bar led under wall At cage designed elevation position, then carry out concreting.
After the diaphram wall and superfilled concrete poured reaches design strength, wall is led in dismounting, needs to cut by excavating to expose Diaphram wall top superfilled concrete, delimitation cuts line, the superfilled concrete on diaphram wall top cut using machinery is cut.Due to The effect of structure is protected, superfilled concrete reduces bond stress to reinforcing bar, and steel reinforcement protective sleeve pipe is easy to together with concrete when cutting It is stripped together, the diaphram wall to conform to quality requirements is completed after cutting.The protection structure, which protects reinforcing bar, imitates Fruit is apparent, reinforcing bar bending, damage when avoiding the concrete superfilled concrete for cutting diaphragm wall top, and is set by rational structure Meter and structural parameters and performance parameter setting, when cutting ground-connecting-wall end concrete, protection sleeve pipe can remove together and Do not damage reinforcing bar, realize process is simplified, labour's configuration less, labor intensity is low, mechanical efficiency is high, having convenient for rapid construction Beneficial effect.

Claims (8)

1. a kind of diaphram wall cage top reinforcing bar protects structure, the diaphragm wall poured including steel reinforcement cage and along steel reinforcement cage With the superfilled concrete above diaphragm wall, the reinforcing bar of the steel reinforcement cage cage top beyond the top of diaphragm wall and is located in superfilled concrete, It is characterized in that the protection structure further includes steel reinforcement protective sleeve pipe, the steel reinforcement protective sleeve pipe is fixed on by several bands On the outside of the reinforcing bar of cage top.
2. diaphram wall cage top reinforcing bar as described in claim 1 protects structure, it is characterised in that the steel reinforcement protective sleeve Pipe meets following condition:
d≥D+5mm;δ≥1/5Dmm;L'≥1.05Lmm;
In formula:D is the bar diameter of cage top, L is cage top reinforcing bar length, d are the internal diameter of steel reinforcement protective sleeve pipe, δ is that reinforcing bar is protected The thickness of pipe of protecting pipe, the length that L' is steel reinforcement protective sleeve pipe.
3. diaphram wall cage top reinforcing bar as described in claim 1 protects structure, it is characterised in that the steel reinforcement protective sleeve Pipe also meets following condition:Steel reinforcement protective sleeve tube material density≤0.03G/cm3;Tensile strength >=3.40KG/cm3;Tear-proof is strong Degree >=2.60KG/cm3;Ductility >=125%.
4. the diaphram wall cage top reinforcing bar protection structure as described in claims 1 or 2 or 3, it is characterised in that the reinforcing bar Cage protection sleeve pipe is made of EPE pearl wool.
5. diaphram wall cage top reinforcing bar as described in claim 1 protects structure, it is characterised in that the band meets such as Lower condition:
L >=5Dmm and tensile strength >=8.10KG;
In formula:The length that D is the bar diameter of cage top, l is band.
6. the diaphram wall cage top reinforcing bar protection structure as described in claim 1 or 5, it is characterised in that the band is certainly Locking-type Plastic Bandage.
7. a kind of construction method of diaphram wall cage top reinforcing bar protection structure using as described in claims 1 or 2 or 3, It is characterized in that the method and step is as follows:
A. before steel reinforcement cage installation is in place, steel reinforcement protective sleeve pipe is set with, and pass through at least two bands to the reinforcing bar of steel reinforcement cage cage top Steel reinforcement protective sleeve pipe and the reinforcing bar of cage top are mutually fixed, transfer steel reinforcement cage to the diaphram wall steel reinforcement cage led under wall after fixed At designed elevation position, and concreting is carried out until reaching design strength, to form diaphragm wall and superfilled concrete;
B. after the completion of pouring, wall is led in dismounting, by excavating the superfilled concrete on diaphragm wall top for exposing and needing to cut, and delimited and is cut Then using the mechanical superfilled concrete for cutting diaphragm wall top is cut, steel reinforcement protective sleeve pipe is made when cutting together with superfilled concrete for line Concrete is stripped together, ultimately forms diaphram wall.
8. as claimed in claim 7 using the construction method of diaphram wall cage top reinforcing bar protection structure, it is characterised in that adopt The protection of steel bar gabion casing is made of EPE pearl wool.
CN201810077114.4A 2018-01-26 2018-01-26 Diaphram wall cage top reinforcing bar protects structure and construction method Pending CN108265702A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810077114.4A CN108265702A (en) 2018-01-26 2018-01-26 Diaphram wall cage top reinforcing bar protects structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810077114.4A CN108265702A (en) 2018-01-26 2018-01-26 Diaphram wall cage top reinforcing bar protects structure and construction method

Publications (1)

Publication Number Publication Date
CN108265702A true CN108265702A (en) 2018-07-10

Family

ID=62776675

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810077114.4A Pending CN108265702A (en) 2018-01-26 2018-01-26 Diaphram wall cage top reinforcing bar protects structure and construction method

Country Status (1)

Country Link
CN (1) CN108265702A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110295589A (en) * 2019-07-18 2019-10-01 天津深基工程有限公司 Ground-connecting-wall anchor rib protects structure
CN110700259A (en) * 2019-11-06 2020-01-17 陕西建工第八建设集团有限公司 Breaking device and method for breaking super-poured concrete of underground continuous wall in advance

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05321248A (en) * 1992-05-20 1993-12-07 Ohbayashi Corp Method for removing head part of underground contrinuous wall
JP2001355242A (en) * 2000-06-13 2001-12-26 Toda Constr Co Ltd Construction method for underground beam in underground continuous wall pile
KR200296444Y1 (en) * 2002-09-12 2002-11-23 (주)한빛하이테크엔지니어링 Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
CN102312429A (en) * 2011-07-12 2012-01-11 中铁西北科学研究院有限公司 Rapid separation and integral hoisting method for pile head of cast-in-place concrete pile
CN204000837U (en) * 2014-05-30 2014-12-10 浙江大学宁波理工学院 A kind of prefabricated diaphragm wall
CN204000925U (en) * 2014-05-30 2014-12-10 浙江大学宁波理工学院 Prefabricated diaphragm wall
CN205804324U (en) * 2016-06-23 2016-12-14 上海市政工程设计研究总院(集团)有限公司 A kind of Prefabricated pre-tensioned prestressed underground continuous wall
CN206173947U (en) * 2016-11-19 2017-05-17 北京市地质工程公司 Underground continuous wall easily abolishes pile head
CN106978809A (en) * 2017-04-19 2017-07-25 广州亿顺建筑工程劳务有限公司 A kind of construction method of casing off concrete protective reserved steel bar
CN207987913U (en) * 2018-01-26 2018-10-19 中铁上海工程局集团华海工程有限公司 Diaphram wall cage top reinforcing bar protects structure

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05321248A (en) * 1992-05-20 1993-12-07 Ohbayashi Corp Method for removing head part of underground contrinuous wall
JP2001355242A (en) * 2000-06-13 2001-12-26 Toda Constr Co Ltd Construction method for underground beam in underground continuous wall pile
KR200296444Y1 (en) * 2002-09-12 2002-11-23 (주)한빛하이테크엔지니어링 Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
CN102312429A (en) * 2011-07-12 2012-01-11 中铁西北科学研究院有限公司 Rapid separation and integral hoisting method for pile head of cast-in-place concrete pile
CN204000837U (en) * 2014-05-30 2014-12-10 浙江大学宁波理工学院 A kind of prefabricated diaphragm wall
CN204000925U (en) * 2014-05-30 2014-12-10 浙江大学宁波理工学院 Prefabricated diaphragm wall
CN205804324U (en) * 2016-06-23 2016-12-14 上海市政工程设计研究总院(集团)有限公司 A kind of Prefabricated pre-tensioned prestressed underground continuous wall
CN206173947U (en) * 2016-11-19 2017-05-17 北京市地质工程公司 Underground continuous wall easily abolishes pile head
CN106978809A (en) * 2017-04-19 2017-07-25 广州亿顺建筑工程劳务有限公司 A kind of construction method of casing off concrete protective reserved steel bar
CN207987913U (en) * 2018-01-26 2018-10-19 中铁上海工程局集团华海工程有限公司 Diaphram wall cage top reinforcing bar protects structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨恒峰;: "地下连续墙结合逆作法在地下结构施工中的应用", 江苏建筑, no. 02, pages 74 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110295589A (en) * 2019-07-18 2019-10-01 天津深基工程有限公司 Ground-connecting-wall anchor rib protects structure
CN110700259A (en) * 2019-11-06 2020-01-17 陕西建工第八建设集团有限公司 Breaking device and method for breaking super-poured concrete of underground continuous wall in advance
CN110700259B (en) * 2019-11-06 2024-05-31 陕西建工第八建设集团有限公司 Device and method for advanced breaking of underground diaphragm wall superfilling concrete

Similar Documents

Publication Publication Date Title
CN106320346B (en) Campshed adds anchor cable grouting behind shaft or drift lining deep foundation pit supporting construction method
CN202000380U (en) Basement outer wall post-pouring belt backfill protective plate
CN202925922U (en) Combination reinforcing device for brick masonry wall
CN106400802A (en) Integral quick lifting method for pile head of drilled pile during pre-embedding and drilling-free ring-cutting
CN108265702A (en) Diaphram wall cage top reinforcing bar protects structure and construction method
CN204456100U (en) A kind of part adhesive type prestress anchorage cable with outer anchoring section
CN103266901A (en) Temporary water stopping structure of shield tunnel portal and construction method thereof
CN108150187A (en) A kind of huge loose talus shield encircles the method into hole
CN207987913U (en) Diaphram wall cage top reinforcing bar protects structure
CN106760004A (en) A kind of construction method of the uniform joint bar in guide trough structure surface
CN104295001B (en) The construction technology of variable cross-section prestressing force cant beam
CN206487183U (en) Pool wall of pool construction joint water sealing structure
CN210380191U (en) Lightweight power communication combination prefabricated cable channel
CN206844109U (en) A kind of prestress anchorage cable
CN102587421A (en) Advanced water-stopping isolation structure of later poured band for basement
CN203403891U (en) Temporary water sealing structure for shield tunnel portal
CN207538032U (en) Perceive anchor pole
CN209508958U (en) A kind of application static(al) abolishes pile crown system
CN207568634U (en) Soap-free emulsion polymeization ring anchor pre-stress lining structure anchorage slot concrete backfill device
CN207314348U (en) A kind of fixed structure of flare template
CN207919552U (en) A kind of package releasable anchor cable
CN206987826U (en) Tunnel duct piece and its external anti-seismic chute used
CN202925923U (en) Combination reinforcing device for block masonry wall
CN109133846A (en) A kind of application method of microwave heat molten type sulphide mastic in anchor cable anchor head
CN207685696U (en) A kind of moveable anchor for the old rope dismounting of bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination