CN105484731A CN201510923675.8A CN201510923675A CN105484731A CN 105484731 A CN105484731 A CN 105484731A CN 201510923675 A CN201510923675 A CN 201510923675A CN 105484731 A CN105484731 A CN 105484731A
Authority
CN
China
Prior art keywords
deviational survey
hole
inclinometer pipe
pipe
inclination measurement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510923675.8A
Other languages
Chinese (zh)
Inventor
李喜
殷坤龙
刘毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Geosciences
Original Assignee
China University of Geosciences
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Geosciences filed Critical China University of Geosciences
Priority to CN201510923675.8A priority Critical patent/CN105484731A/en
Publication of CN105484731A publication Critical patent/CN105484731A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/02Determining slope or direction
    • E21B47/022Determining slope or direction of the borehole, e.g. using geomagnetism

Landscapes

  • Physics & Mathematics (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Geophysics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Foundations (AREA)

Abstract

The invention provides an inclination measurement hole construction method. The method includes the steps of inclination measurement connector processing, mortar manufacturing, mud pipe processing, pouring and pier foundation pouring. An opening in the bottom of the first lowered inclination measurement pipe is closed before inclination measurement pipes are lowered, the joints of the inclination measurement pipes and casting pipes are sealed in the lowering process, rivet anchoring positions are closed through plasticine, and seams possibly existing between the inclination measurement pipes and inclination measurement drilled holes are completely closed through external wound adhesive tape; mortar with which the gaps between the inclination measurement pipes and the inclination measurement drilled holes are filled is composed of gravel and cement paste, and gravel is evenly added when cement paste is poured from bottom to top through a high-pressure pump; cement paste pipes fixed to the inclination measurement pipes each comprise a smooth-surface mud pipe located on the top and a mud pipe located on the lower portion and provided with holes, and in other words, grouting holes are evenly formed in the pipe walls of the multiple mud pipes located on the lower portion; the pouring method from bottom to top is ensured, and meanwhile guniting pressure is effectively reduced and the aim of safe construction is achieved.

Description

A kind of deviational survey hole construction method
Technical field
The present invention relates to a kind of deviational survey hole construction method, belong to monitoring technology for geological hazards field.
Background technology
China is the multiple country of a geological disaster, the landslide disaster in mountain area is particularly outstanding, but, because landslide control expense is large, the landslide effectively administered a just wherein very little part can be obtained, landslide is greatly also had to need to carry out landslide monitoring, as groundwater monitoring, ground displacement, GPS monitoring, deep inclination monitoring etc.Wherein deep soils is mainly applicable to creepage type landslide, and the type Landslide Deformation is slow, and displacement is often in a centimetre even millimeter rank fluctuation, therefore high to instrument monitoring required precision, very strict to the construction process requirement in deviational survey hole.
As shown in Figure 4, the construction of tradition deviational survey hole adopts clay 15 backfill compacting, because clay is uneven bulk, inclinometer pipe 2 outer wall and deviational survey are holed the problems such as space between 1 hole wall is little, often form backfill compacting insufficient, cause inclinometer pipe outer local hollow, inclinometer pipe weak vibrations, the problems such as data error is large.
Summary of the invention
The object of the invention is to overcome the deficiencies in the prior art and provide a kind of and effectively can reduce the deviational survey hole construction method that inclinometer pipe self rocks, certainty of measurement is high.
Realizing the technical scheme that the object of the invention adopts is that a kind of deviational survey hole construction method, comprises the steps:
(1) deviational survey boring is crept into, the inclinometer pipe of more than 2 surface band guide grooves is transferred successively in deviational survey boring, adjacent two inclinometer pipes, by sleeve connection and by rivet anchoring, seal inclinometer pipe and the junction of sleeve and the bottom opening of first inclinometer pipe of transferring; Transfer in the process of inclinometer pipe synchronously to transfer and be with the mud tube in mud hole and be fixed on inclinometer pipe by mud tube, the top of the inclinometer pipe and mud tube that are positioned at the top all protrudes from deviational survey drilling orifice;
(2) when inclinometer pipe and mud tube are all transferred to deviational survey foot of hole, according to the landslide direction of motion adjustment inclinometer pipe direction of deviational survey boring location, make the direction of inclinometer pipe wherein a pair relative guide groove consistent with the direction of motion that comes down;
(3) configure cement paste, between holing to inclinometer pipe and deviational survey, in gap, evenly, at the uniform velocity pour the blinding that particle diameter is 5 ~ 20mm into, simultaneously by compression pump by cement paste through mud tube pump into inclinometer pipe and deviational survey hole between in gap;
(4) in deviational survey drilling orifice, embed pvc pipe and build pier foundation, completing the construction of deviational survey hole.
Junction and the rivet installation place of the middle inclinometer pipe of step (1) and sleeve are all sealed by plasticine, are fastened subsequently by adhesive plaster.
In step (1), the particular content of anchoring rivet is bore single installing hole by electric drill in the junction of inclinometer pipe and sleeve, rear installation rivet of having holed, and repeats to bore single installing hole and is connected to inclinometer pipe and sleeve are stable with installation rivet.
In step (1) deviational survey crept into backward deviational survey hole at the uniform velocity injected clear water carry out hole flushing.
Mud tube comprises the non-perforated mud tube that is arranged in deviational survey drilling orifice place and more than 2 and to be positioned at below it and tube wall offers the punching mud tube in mud hole in step (1).
Mud tube is fixed on inclinometer pipe by adhesive plaster in (1) by step.
Reduce compression pump pressure when there is the situation that cement paste overflows in step (3) in cement paste slip casting process, and then slow down injection speed and precipitate to cement paste, carry out benefit when cement paste falls phenomenon after rise and starch.
The particular content of building pier foundation in step (4) is, by deviational survey boring centered by around it 1.0m 2~ 1.2m 2scope removes earth's surface surface dust; in deviational survey drilling orifice, embed pvc pipe, the mouth of pipe of pvc pipe lower end is goed deep into earth's surface and is fixed by soil compaction, pier of constructing in the earth's surface after cleaning surface dust; protection box is installed at the mouth of pipe place of the pvc pipe of pier end face, completes the construction of pier foundation.
In step (2), inclinometer pipe is transferred and on top of inclinometer pipe opening, is installed interim sealing to during deviational survey foot of hole, and the middle pier of step (4) solidifies rear dismounting and seals temporarily.
As shown from the above technical solution, deviational survey hole construction method provided by the invention, inclinometer pipe closes the bottom opening of first inclinometer pipe of transferring before transferring, in decentralization process, the junction of inclinometer pipe and sleeve to be sealed and by anchoring place of plasticine blind rivet, the gap that the completely closed inclinometer pipe of the adhesive plaster coordinating outside to be wound around and deviational survey may exist between holing, can effectively prevent cement paste from entering the local stoppages that inclinometer pipe causes inclinometer pipe; Mud tube fixing on inclinometer pipe comprises the non-perforated mud tube that is arranged in top and more than 2 and to be positioned at below it and tube wall offers the punching mud tube in mud hole, namely the multistage mud tube tube wall being positioned at bottom evenly offers injected hole, while ensureing casting method from bottom to top, effectively reduce spray pressure again, reach the object of safe construction; Pier foundation is set and protects box protection deviational survey drilling orifice and inclinometer pipe upper end, and conveniently carry out daily deviational survey.
Provided by the invention hole for filling inclinometer pipe and deviational survey between the mortar in gap be made up of blinding and cement paste, evenly blinding is added from bottom to top while cement paste carries out building by high-pressure pump, the particle diameter of blinding is 5 ~ 20mm, the gap of the blinding in this particle size range forms capillarity to cement paste, can ensure that cement paste flows down gap between abundant filling blinding smoothly, this gap own dimensions is less simultaneously, and after filling cement slurry sets wherein, body pole-changing is little; Blinding and cement paste be filled to simultaneously inclinometer pipe and deviational survey hole between in gap, blinding is fully contacted with cement paste, blinding and cement paste and the filling of the two order ensure that the requirement of strength of mortar, also ensure that inclinometer pipe and deviational survey hole between fully the building of gap.
In prior art, the anchor connection of inclinometer pipe and sleeve all adopts the good all installing holes of disposable brill, the mode of anchoring rivet together again, because between inclinometer pipe and sleeve, activity is larger, adopting disposable brill good all installing holes that installing hole easily occurs can not completely to upper situation, increase follow-up work difficulty, even cause unnecessary waste, anchors step provided by the invention is bore single installing hole by electric drill in the junction of inclinometer pipe and sleeve, to hole rear installation rivet, repeat to bore single installing hole to be connected to inclinometer pipe and sleeve are stable with installation rivet, guarantee that installing hole is aimed at completely, improve stable connection and installation effectiveness.
Owing to adopting mud off pore-forming during probing more, constantly washed by water at the bottom of deviational survey drilling hole by drilling rod, in hole, silt is taken out of from during the overflow of aperture by mud entirely, the sand content of mud own is very large, and at the bottom of hole, precipitate comparatively high concentration of sediment, consider that having crept into sediment deposition in metapore can form thicker silt layer at the bottom of drilling hole, inclinometer pipe is caused to be difficult to transfer at the bottom of hole, therefore deviational survey crept into after by drilling rod to deviational survey boring at the uniform velocity injected clear water carry out hole flushing, till being filled to deviational survey drilling orifice spilling clear water, ensure that inclinometer pipe is transferred smoothly at the bottom of hole, avoid fathoming because construction reason reduces.
The invention has the beneficial effects as follows, work progress is simple, construction safety, Be very effective, compared to the inclinometer pipe of existing deviational survey hole construction method construction, can effectively reduce rocking of inclinometer pipe self by deviational survey hole construction method provided by the invention, improve certainty of measurement, the inclinometer pipe self stability of construction is stronger.
Accompanying drawing explanation
Fig. 1 is the Construction Principle figure of deviational survey hole construction method provided by the invention.
Fig. 2 is the syndeton schematic diagram of inclinometer pipe and sleeve.
Fig. 3 is the structural representation of pier foundation.
Fig. 4 is the backfill design sketch of prior art.
Fig. 5 is the mortar cast design sketch of deviational survey hole construction method provided by the invention.
Wherein, 1-deviational survey is holed, 2-inclinometer pipe, 3-non-perforated mud tube, and 4-punch mud tube, 5-compression pump, 6-cement paste container, 7-sleeve, 8-guide groove, 9-plasticine, 10-rivet, 11-adhesive plaster, 12-pier, and 13-PVC pipe, 14-protects box, 15-clay, 16-mortar.
Detailed description of the invention
Illustrate in detail the present invention below in conjunction with drawings and Examples, content of the present invention is not limited to following examples.
Deviational survey hole construction method provided by the invention, its Construction Principle as shown in Figure 1, comprises the steps:
(1) creep into deviational survey boring 1, in being holed to deviational survey by drilling rod after having crept into, at the uniform velocity injected clear water carries out hole flushing, and till being filled to deviational survey drilling orifice spilling clear water, hole flushing is complete, the inclinometer pipe 2 of more than 2 surface band guide grooves 8 is transferred successively in deviational survey boring, adjacent two inclinometer pipes are connected by sleeve 7 and by rivet 10 anchoring, single installing hole is bored in the junction of inclinometer pipe and sleeve by electric drill, to hole rear installation rivet, repeat to bore single installing hole to be connected to inclinometer pipe and sleeve are stable with installation rivet, inclinometer pipe and the junction of sleeve and the bottom opening of first inclinometer pipe of transferring are sealed, junction and the rivet installation place of inclinometer pipe and sleeve are all sealed by plasticine 9, be fastened by adhesive plaster 11 subsequently, as shown in Figure 2, transfer synchronous lower mud tube in the process of inclinometer pipe and by adhesive plaster, mud tube be fixed on inclinometer pipe, described mud tube comprises and is arranged in the hole non-perforated mud tube 3 at 1 aperture place and more than 2 of deviational survey and is positioned at below it and tube wall offers the punching mud tube 4 in mud hole, the top of the inclinometer pipe and non-perforated mud tube 3 that are positioned at the top all protrudes from deviational survey and to hole 1 aperture, and the top being positioned at the inclinometer pipe of the top protrudes from deviational survey and to hole 1 aperture 1.2m,
(2) when inclinometer pipe and mud tube are all transferred to deviational survey foot of hole, inclinometer pipe 2 open top is installed interim sealing, prevent the foreign material such as mud, leaf from falling in inclinometer pipe 2, according to the landslide direction of motion adjustment inclinometer pipe direction of deviational survey boring location, make the direction of inclinometer pipe wherein a pair relative guide groove 8 consistent with the direction of motion that comes down;
(3) by water: the mass ratio configuration cement paste of cement=1:1 ~ 1:2, the cement paste configured is placed in cement paste container 6, even in gap between holing to inclinometer pipe and deviational survey, at the uniform velocity pour the blinding that particle diameter is 5 ~ 20mm into, by compression pump 5, cement paste is pumped in mud tube simultaneously, blinding and cement paste are uniformly mixed to form mortar 16, it builds effect as shown in Figure 5, compression pump pressure is reduced when there is the situation that cement paste overflows in cement paste slip casting process, and then slow down injection speed and precipitate to cement paste, cement paste carries out benefit slurry when falling phenomenon after rise,
(4) in deviational survey drilling orifice, embed pvc pipe and build pier foundation, the particular content of building pier foundation for centered by deviational survey boring around it 1.0m 2~ 1.2m 2square scope in remove the surface dust of earth's surface 20cm ~ 60cm, until more solid stratum, pvc pipe 13 is embedded in deviational survey drilling orifice, the mouth of pipe of pvc pipe lower end is goed deep into earth's surface and is fixed by soil compaction, pier 12 of constructing in earth's surface after cleaning surface dust makes the mouth of pipe of pvc pipe upper end protrude from pier surface and flush with the mouth of pipe of inclinometer pipe, pier end face is face 1.1m highlightedly, protection box 14 is installed at the mouth of pipe place of the pvc pipe of pier end face, the mouth of pipe of pvc pipe and inclinometer pipe protected by protection box 14, pier foundation has been constructed, and its structure as shown in Figure 3; Pier solidifies rear dismounting inclinometer pipe 2 top and seals temporarily, completes the construction of deviational survey hole.

Claims (9)

1. a deviational survey hole construction method, is characterized in that, comprises the steps:
(1) deviational survey boring is crept into, the inclinometer pipe of more than 2 surface band guide grooves is transferred successively in deviational survey boring, adjacent two inclinometer pipes, by sleeve connection and by rivet anchoring, seal inclinometer pipe and the junction of sleeve and the bottom opening of first inclinometer pipe of transferring; Transfer in the process of inclinometer pipe synchronously to transfer and be with the mud tube in mud hole and be fixed on inclinometer pipe by mud tube, the top of the inclinometer pipe and mud tube that are positioned at the top all protrudes from deviational survey drilling orifice;
(2) when inclinometer pipe and mud tube are all transferred to deviational survey foot of hole, according to the landslide direction of motion adjustment inclinometer pipe direction of deviational survey boring location, make the direction of inclinometer pipe wherein a pair relative guide groove consistent with the direction of motion that comes down;
(3) configure cement paste, between holing to inclinometer pipe and deviational survey, in gap, evenly, at the uniform velocity pour the blinding that particle diameter is 5 ~ 20mm into, simultaneously by compression pump by cement paste through mud tube pump into inclinometer pipe and deviational survey hole between in gap;
(4) in deviational survey drilling orifice, embed pvc pipe and build pier foundation, completing the construction of deviational survey hole.
2. deviational survey hole construction method according to claim 1, is characterized in that: junction and the rivet installation place of the middle inclinometer pipe of step (1) and sleeve are all sealed by plasticine, are fastened subsequently by adhesive plaster.
3. deviational survey hole construction method according to claim 1, it is characterized in that: in step (1), the particular content of anchoring rivet is, single installing hole is bored in the junction of inclinometer pipe and sleeve by electric drill, to hole rear installation rivet, repeated to bore single installing hole and installation rivet to inclinometer pipe and to stablize with sleeve and be connected.
4. deviational survey hole construction method according to claim 1, is characterized in that: in step (1) deviational survey crept into backward deviational survey hole at the uniform velocity injected clear water carry out hole flushing.
5. deviational survey hole construction method according to claim 1, is characterized in that: mud tube comprises the non-perforated mud tube that is arranged in deviational survey drilling orifice place and more than 2 and to be positioned at below it and tube wall offers the punching mud tube in mud hole in step (1).
6. deviational survey hole construction method according to claim 1, is characterized in that: mud tube is fixed on inclinometer pipe by adhesive plaster in (1) by step.
7. deviational survey hole construction method according to claim 1, it is characterized in that: minimizing compression pump pressure when there is the situation that cement paste overflows in step (3) in cement paste slip casting process, and then slow down injection speed and precipitate to cement paste, carry out benefit slurry when cement paste falls phenomenon after rise.
8. deviational survey hole construction method according to claim 1, is characterized in that: the particular content of building pier foundation in step (4) is, by deviational survey boring centered by around it 1.0m 2~ 1.2m 2scope removes earth's surface surface dust; in deviational survey drilling orifice, embed pvc pipe, the mouth of pipe of pvc pipe lower end is goed deep into earth's surface and is fixed by soil compaction, pier of constructing in the earth's surface after cleaning surface dust; protection box is installed at the mouth of pipe place of the pvc pipe of pier end face, completes the construction of pier foundation.
9. deviational survey hole construction method according to claim 8, it is characterized in that: in step (2), inclinometer pipe is transferred and on top of inclinometer pipe opening, installed interim sealing to during deviational survey foot of hole, the middle pier of step (4) solidifies rear dismounting and seals temporarily.
CN201510923675.8A 2015-12-11 2015-12-11 Inclination measurement hole construction method Pending CN105484731A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510923675.8A CN105484731A (en) 2015-12-11 2015-12-11 Inclination measurement hole construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510923675.8A CN105484731A (en) 2015-12-11 2015-12-11 Inclination measurement hole construction method

Publications (1)

Publication Number Publication Date
CN105484731A true CN105484731A (en) 2016-04-13

Family

ID=55671976

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510923675.8A Pending CN105484731A (en) 2015-12-11 2015-12-11 Inclination measurement hole construction method

Country Status (1)

Country Link
CN (1) CN105484731A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756856A (en) * 2018-06-21 2018-11-06 广东赛达交通科技股份有限公司 A kind of construction method of distribution type fiber-optic drillhole inclination survey
CN110411393A (en) * 2019-07-25 2019-11-05 中国地质大学(武汉) For monitoring the inclination measurement device and method of landslide depth displacement
CN112781481A (en) * 2021-01-05 2021-05-11 重庆工程职业技术学院 Landslide sensitivity detection early warning device
WO2022127136A1 (en) * 2020-12-17 2022-06-23 南京工业大学 Device for monitoring soil displacement by means of hydraulic burying, and use method thereof
CN115821881A (en) * 2022-12-15 2023-03-21 广东交科检测有限公司 Tilt-finding water level shared pipe dense sand filling method and auxiliary sand filling device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2116637B (en) * 1982-03-11 1985-10-23 Harben Systems Ltd Improvements in and relating to conveying systems
CN1502751A (en) * 2002-11-27 2004-06-09 陈志坚 Flexible pipe pipe-following hole bottom grouting technology
CN101915094A (en) * 2010-08-04 2010-12-15 煤炭科学研究总院重庆研究院 Continuous monitoring system of overburden rock displacement in ore bed mining process and structuring method thereof
CN104329076A (en) * 2014-11-24 2015-02-04 中国电建集团中南勘测设计研究院有限公司 Inclination measuring hole osmometer device and installation method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2116637B (en) * 1982-03-11 1985-10-23 Harben Systems Ltd Improvements in and relating to conveying systems
CN1502751A (en) * 2002-11-27 2004-06-09 陈志坚 Flexible pipe pipe-following hole bottom grouting technology
CN101915094A (en) * 2010-08-04 2010-12-15 煤炭科学研究总院重庆研究院 Continuous monitoring system of overburden rock displacement in ore bed mining process and structuring method thereof
CN104329076A (en) * 2014-11-24 2015-02-04 中国电建集团中南勘测设计研究院有限公司 Inclination measuring hole osmometer device and installation method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756856A (en) * 2018-06-21 2018-11-06 广东赛达交通科技股份有限公司 A kind of construction method of distribution type fiber-optic drillhole inclination survey
CN110411393A (en) * 2019-07-25 2019-11-05 中国地质大学(武汉) For monitoring the inclination measurement device and method of landslide depth displacement
WO2022127136A1 (en) * 2020-12-17 2022-06-23 南京工业大学 Device for monitoring soil displacement by means of hydraulic burying, and use method thereof
CN112781481A (en) * 2021-01-05 2021-05-11 重庆工程职业技术学院 Landslide sensitivity detection early warning device
CN112781481B (en) * 2021-01-05 2024-01-16 重庆工程职业技术学院 Landslide sensitivity detection early warning device
CN115821881A (en) * 2022-12-15 2023-03-21 广东交科检测有限公司 Tilt-finding water level shared pipe dense sand filling method and auxiliary sand filling device

Similar Documents

Publication Publication Date Title
CN105484731A (en) Inclination measurement hole construction method
CN104453913B (en) A kind of Shaft Stopes front pre-grouting method
CN106320354B (en) The Seepage method on solution cavity development stratum under coating
CN102505684B (en) Hollow stiffness-core slurry-solidified discrete material pile and construction method thereof
CN107975375B (en) A kind of miniature steel pipe pile reinforced soft foundation construction method of city tunnel
CN102852141B (en) Rock-socketed pipe pile foundation with pile core by concrete pouring and pile side by static pressure grouting and construction method for rock-socketed pipe pile foundation
CN109763483B (en) Up-going type sectional grouting process for thick fourth-system deep-buried mining cave-in broken stratum
CN103075148A (en) Method and device for fast measuring coal bed gas pressure through upward remote-distance hole drilling
CN203569578U (en) Recharge well capable of preventing well casing blocking and water bursting
CN102787602A (en) Curtain grouting technique
CN103088836A (en) Sedimentation control method for pumping water and performing reinjection in well casing simultaneously
CN103510501A (en) Method for preventing blocking and water gushing in recharge well
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN110130825B (en) Method for increasing flow area of in-situ leaching uranium mining production well
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN203462463U (en) Construction device of pile-peripheral cemented-soil cast-in-situ stiffening core pile
CN104988914A (en) Cast-in-situ bored pile breakage processing method under water area environment
JP2022553449A (en) External expansion pipe construction method for drilling in the mining zone
CN104005768A (en) Construction strengthening method for soft geological layer in middle section of vertical shaft
CN206173947U (en) Underground continuous wall easily abolishes pile head
CN107035389B (en) A kind of construction method for grouting reinforcement and earth's surface construction method
CN105672309A (en) Encasing method for hole forming of socketed piles at karst terrain through recoverable extra-long steel pile casings
CN102536115B (en) Gas drainage borehole and construction method thereof
CN210564650U (en) Assembled slurry storage device for filling underwater deep closed space
CN204357437U (en) A kind of vertical monobloc cast section wall seat

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160413