CN206029293U - Round steel capsule for building - Google Patents
Round steel capsule for building Download PDFInfo
- Publication number
- CN206029293U CN206029293U CN201620981918.3U CN201620981918U CN206029293U CN 206029293 U CN206029293 U CN 206029293U CN 201620981918 U CN201620981918 U CN 201620981918U CN 206029293 U CN206029293 U CN 206029293U
- Authority
- CN
- China
- Prior art keywords
- round steel
- drilling
- peeling
- stripping
- smart
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model relates to a construction timber processing equipment technical field specifically is a round steel capsule for building. A round steel capsule for building, includes round steel rough machining equipment and round steel drilling equipment, according to around the technology, round steel rough machining equipment is in proper order including skinning device, cutting device and centring means, round steel drilling equipment includes feeding platform, high temperature furnace, transport rail, drilling positioner, drilling equipment and cooling device in proper order, skin the device cutting device centring means with through conveyer transportation round steel between the feeding platform. The utility model has the advantages of round steel processing integration, the accuracy is high, and is efficient, labour saving and time saving.
Description
Technical field
This utility model is related to construction timber technical field of processing equipment, specially a kind of round steel integration processing for building
System.
Background technology
Round steel is needing to be processed using front, and existing round steel process technology seldom has the work flow of complete set,
Each processing link needs individually to carry out, and intermediate link needs artificial treatment, the high labor intensive of workman, and round steel processed
Efficiency it is low.The patent of Patent No. CN203320045U provides a kind of steel-making system of processing, including smelting system, removing impurities system
System, cooling system and detecting system, the system of processing only combine several round steel processing links, lack the processed ring of early stage
Section, round steel working (machining) efficiency be not high.
Utility model content
The problem that this utility model is present for prior art, there is provided the round steel system of processing of complete set, saves
Manpower and materials, improve the efficiency of round steel processing.
This utility model solves the technical scheme adopted by its technical problem:A kind of round steel system of processing, including round steel
Roughing equipment and round steel rig;Before and after by technique, the round steel roughing equipment includes apparatus for peeling off, cutting dress successively
Put and centring means, the round steel rig includes feeding platform, high temperature furnace, conveyor track, drilling-hole positioning device, drilling successively
Device and chiller;By passing between the apparatus for peeling off, the cutter sweep, the centring means and the feeding platform
Send device transport round steel.
Apparatus for peeling off that round steel is processed by this utility model, cutter sweep, centring means, high-temperature heating equipment, drilling are fixed
Position device, drilling equipment, chiller, transporter, and drive the power-equipment of the round steel system of processing all to connect into
One entirety, saves the manpower and materials of round steel processing, improves the efficiency of round steel processing.
Preferably, the apparatus for peeling off includes support, transmission component, clamps connecting gear, peeling procedure, multiple supports
Roller, and to drive the power-equipment of the apparatus for peeling off;The clamping connecting gear is moved after including shelling front moving cart and stripping
Dynamic dolly;The peeling procedure is included for carrying out the thick blade insert of rough peeling to round steel, for finely being shelled to round steel
The smart blade insert of skin, the cleaning member for being cleaned to round steel after peeling, and the body cavity that the permission round steel passes through;Institute
State transmission component to be located above the support;Above the transmission component, front moving cart, stripping is shelled by setting gradually before and after technique
Moving cart after skin mechanism, stripping;Multiple carrying rollers set up before the stripping moving cart after the both sides of moving cart and stripping separately
Both sides.
Preferably, the thick blade insert includes thick cutterhead, the roughing tool being symmetrically mounted on the thick cutterhead, and it is located at
The thick knife chamber for allowing steel rod to pass through in the middle part of the thick cutterhead, the accent in the thick knife chamber are docked with the accent cooperation of the body cavity;
The smart blade insert includes smart cutterhead, the finishing tool being symmetrically mounted on the smart cutterhead, and is located at fair in the middle part of the smart cutterhead
Perhaps the smart knife chamber that steel rod is passed through, the accent in the smart knife chamber are docked with the accent cooperation of the body cavity;Before and after by technique, the essence
Blade insert is located at the thick blade insert rear.
Preferably, the cutter sweep includes base, fixed mechanism, cutting mechanism, and for driving the cutting to fill
The power-equipment put;The fixed mechanism be included in round steel cutting process to rise with after the completion of round steel cutting for declining
Lift Part, the fixed component that the round steel for regulating is fixed, and to consolidate place round steel appearance rod part;Institute
State cutting mechanism and be included in the regulating member that is adjusted to cutting mechanism whole height before round steel is cut and to circle
The sickle cut by steel;The fixed mechanism is located at the middle part of the base, and the cutting mechanism is symmetrically arranged at
Both sides of the fixed mechanism towards round steel cross-wise direction.
Preferably, the centring means includes frame, connecting gear, determines holes mechanism, borehole drill construction, and to drive
The power-equipment of the centring means;It is described determine holes mechanism include pedestal, the support member for supporting round steel and for determine circle
The centring elements of steel kernel of section point;The borehole drill construction is located at the frame and determines holes mechanism outlet side towards described, mainly
Flexible extensible member can be carried out including bracing frame, drill bit and in the horizontal direction;The connecting gear is located at the frame face
It is described to determining holes mechanism inlet side;The central shaft of the central shaft of the centring elements and the drill bit and the extensible member is protected
Hold in the same horizontal line.
Preferably, the high temperature furnace includes multiple heating chambers, the stepped arrangement of the heating chamber, the heating are indoor
Bottom surface is the slope of connection of cooperating;The heating chamber inner cavity top is provided with flame heater block.
Preferably, the conveyor track is connected with the outlet of the high temperature furnace by buffering slope, the conveyor track top
The first motor is provided with, multiple delivery wheels in the conveyor track, are provided with, some delivery wheels located at the conveyor track end are to described
Drilling-hole positioning device side is arranged in 60 degree of overturning angles.
Preferably, the drilling-hole positioning device is connected with the conveyor track end by platform with slope, the drilling
Positioner includes the second motor, round steel groove, push rod, two roll shafts, two block pressur plates, and the roll shaft is by universal joint and described the
The outfan of two motors is connected and is respectively arranged on the round steel groove both sides, and the pressing plate coordinates the roll shaft fixed in the drilling
Location hole is formed in the device of position.
Preferably, the drilling equipment includes the 4th motor, drilling car, boring bar, positioning seat, the drilling underbody portion
Gear is provided with, the 4th motor is connected by the second chain and drives the drilling car.
Preferably, the chiller includes cooling holding device, pond, reception device, the cooling holding device
Inside it is provided with for the clamping wheel for clamping round steel, the preliminary sparge pipe for cooling down round steel, is provided with the pond for cooling circle completely
The cooling bay of steel.
The beneficial effects of the utility model are the processing unit (plant)s for not only improving links, improve round steel processing
Each processing link has also been connected into an entirety by degree of accuracy, the manpower thing needed for saving during round steel process operation
Power, improves the whole efficiency of round steel processing.
Description of the drawings
Fig. 1 is the structural representation of this utility model apparatus for peeling off;
Fig. 2 is the structural representation of this utility model cutter sweep;
Fig. 3 is the structural representation of this utility model centring means;
Fig. 4 is the top view of this utility model rig;
Side structure schematic diagrams of the Fig. 5 for Fig. 4 high temperature stoves;
Fig. 6 be Fig. 4 in drilling-hole positioning device near the end face of chiller structural representation;
Fig. 7 is the side view of chiller in Fig. 4;
Fig. 8 is the side view of drilling equipment in Fig. 4.
In figure:11st, support, 12, peeling procedure, 121, thick blade insert, 122, smart blade insert, 123, cleaning member, 13, stripping
Moving cart afterwards, 14, moving cart before stripping, 15, carrying roller, 16, transmission component;21st, base, 22, Lift Part, 23, fixed part
Part, 24, hold rod part, 25, regulating member, 26, sickle;31st, frame, 33, pedestal, 34, support member, 35, centring elements,
37th, bracing frame, 39, drill bit, 311, extensible member;101st, feeding platform, 102, buffering slope, 103, delivery wheel, 104, slope puts down
Platform, the 105, second motor, 106, round steel groove, 107, universal joint, 108, push rod, 109, cooling holding device, 110, reception device,
111st, the first motor, the 112, first chain, 201, heating chamber, 202, maintenance door, 203, inspection rack, 301, locating rack, 302, roller
Axle, 303, pressing plate, 304, gear type slack adjuster, 401, clamping wheel, 402, sparge pipe, 403, conveying, 404, connect
Receives pond, 405, cooling bay, 406, receive and hook, the 407, the 3rd motor, the 501, the 4th motor, 502, track, 503, drilling car, 504,
Boring bar, 505, chain, 506, stopping means, 507, positioning seat, 508, increase handle.
Specific embodiment
The technical solution of the utility model is further illustrated below in conjunction with the accompanying drawings and by specific embodiment.
A kind of round steel capsule for building, including round steel roughing equipment and round steel rig;By technique
In front and back, the round steel roughing equipment successively include apparatus for peeling off, cutter sweep and centring means, the round steel rig according to
It is secondary including feeding platform 101, high temperature furnace, conveyor track, drilling-hole positioning device, drilling equipment and chiller;The apparatus for peeling off,
Round steel is transported by transporter between the cutter sweep, the centring means and the feeding platform 101.The system will be each
Individual round steel processing link has all connected into an entirety, saves manpower and materials, improves the efficiency of round steel processing.
As shown in figure 1, the peeling procedure 12 of apparatus for peeling off includes thick blade insert 121 and smart blade insert 122.Thick blade insert
121 include thick cutterhead, the roughing tool being symmetrically mounted on thick cutterhead, and the thick knife that permission round steel is passed through in the middle part of thick cutterhead
Chamber, the accent in thick knife chamber are docked with the accent cooperation of body cavity;Smart blade insert 122 includes smart cutterhead, is symmetrically mounted on smart cutterhead
Finishing tool, and allow the smart knife chamber that passes through of round steel in the middle part of smart cutterhead, accent and the accent of the body cavity cooperation in smart knife chamber is right
Connect.Before and after by technique, smart blade insert 122 is arranged on into 121 rear of thick blade insert.Roughing tool includes what is be fixedly connected with thick cutterhead
Thick handle of a knife, the negative angle blade that edge of a knife negative rake angle is 10 degree, and it is thick for connecting the chuck type of thick handle of a knife and negative angle blade
Cutter holder;Finishing tool includes the smart handle of a knife being fixedly connected with smart cutterhead, the positive angle blade that edge of a knife positive rake angle angle is 16 degree, Yi Jiyong
In the chuck type essence cutter holder of the smart handle of a knife of connection and positive angle blade.Using dual peeling structure, round steel is entered using thick blade insert 121
The rough peeling of row, carries out fine peeling using smart blade insert 122 to round steel, improves the peeling effect of round steel, save round steel
The peeling time, improve the peeling efficiency of round steel.
In addition, cleaning member 123 can be mounted in the running water pipe in 12 body of peeling procedure, it is also possible to be mounted in stripping
Automatic brush in 12 body of skin mechanism.The round steel surface neat and tidy of the complete skin of stripping can be made by using cleaning member 123.It is described
Cleaning member 123 includes water inflow and water controlled plate;The water entering section for installing the water inflow is provided with above the body cavity;It is described
Water controlled plate is used for controlling cleaning dynamics and the cleaning position of the cleaning member 123.
In addition, before and after moving cart 14 presses technique before the stripping, include adjusting the stripping front air cylinder of stripping front jig successively,
To clamp the stripping front jig of round steel, and to support round steel and the stripping of altitude mixture control can be carried out before carrying roller;Gas before the stripping
Cylinder is attached by screw mandrel with the stripping front jig.Stripping front jig is located in the middle part of the front moving cart 14 of stripping, shells front jig by two
Individual holder composition, can clamp round steel and drive round steel to keep rectilinear direction to advance.Before stripping, carrying roller is located at moving cart 14 before stripping
Left side, can adjust the height of carrying roller before stripping as needed, and before stripping, carrying roller has and supports round steel and make round steel keep straight ahead
Effect.Stripping front air cylinder is located on the right side of the front moving cart 14 of stripping, and stripping front air cylinder can be used to adjust between stripping two holder of front jig
Folding degree, when front air cylinder is shelled towards stripping front jig propulsion, two holders for shelling front jig are clamped in opposite directions, otherwise when gas before stripping
When cylinder is dorsad shelled front jig and pushed away, two holders for shelling front jig are reversely separated.
In addition, moving cart 13 is included supporting round steel and carrying out height tune as before and after technique successively after the stripping
Carrying roller after the stripping of section, to clamp the stripping rear jig of round steel, and to adjust the stripping exhaust hood of the stripping rear jig;The stripping
Exhaust hood is attached by screw mandrel with the stripping rear jig.Stripping rear jig is located at after shelling in the middle part of moving cart 13, shells rear jig
It is made up of two holders, round steel can be clamped and drive round steel to keep rectilinear direction to advance.After after stripping, carrying roller is located at stripping, movement is little
On the right side of car 13, the height of stripping after carrying roller can be adjusted as needed, before after stripping, carrying roller has support round steel and makes round steel keep straight line
The effect entered.Stripping exhaust hood is located at after stripping on the left of moving cart 13, stripping exhaust hood can be used to adjusting two holder of stripping rear jig it
Between folding degree, when shell exhaust hood towards stripping rear jig advance when, shell rear jig two holders clamp in opposite directions, otherwise when stripping
When exhaust hood is dorsad shelled rear jig and pushed away, two holders for shelling rear jig are reversely separated.
When apparatus for peeling off runs, on the carrying roller 15 that first round steel is placed on the right side of support 11;Adjusted according to practical operation demand
The opening degree of the height and fixture of good carrying roller 15;Round steel is introduced into moving cart 4 before stripping, then in the feelings for keeping linear running
Peeling procedure 12 is entered under condition;Rough peeling is carried out first with thick blade insert 121, is then carried out finely using smart blade insert 122
Peeling, followed by the cleaning round steel of cleaning member 123 surface, finally out enters moving cart 13 after stripping from peeling procedure 12;
The carrying roller 15 that round steel is passed through on the left of support 11 after moving cart 13 after stripping leaves the round steel apparatus for peeling off.
As shown in Fig. 2 cutter sweep includes base 21, fixed mechanism, cutting mechanism, and for driving the round steel to cut
The power-equipment of device;Fixed mechanism be included in round steel cutting process to rise with after the completion of round steel cutting for declining
Lift Part 22, the fixed component 23 that the round steel for regulating is fixed, and to consolidate the appearance rod part for placing round steel
24;Cutting mechanism is included in before round steel is cut the regulating member 25 that is adjusted to cutting mechanism whole height and to right
The sickle 26 cut by round steel;Fixed mechanism is located at the middle part of base 21, and cutting mechanism is symmetrically arranged at fixed machine
Both sides of the structure towards round steel cross-wise direction.
Before round steel is cut, the whole height of cutting mechanism can be carried out by regulating member 25 according to the actual requirements
Adjust.Regulating member 25 is fixedly connected with sickle 26, and sickle 26 is circular electric saw and vertical with rod part 24 is held.In round steel
In cutting process, the position of sickle 26 is fixed.Lift Part 22 is vertically arranged on base;Hold 24 bottom of rod part
Portion is vertical with Lift Part 22, parallel with base;Regulating member 25 is vertically arranged on base, is arranged on cutting on regulating member
Cutter 26, its cut direction are vertical with rod part 24 is held and towards round steel vertical cross-section direction.In cutting, the horizontal position of round steel
Put and immobilize, only the height of Lift Part 23 can change, therefore, the section cut out by round steel necessarily keeps vertical
Directly, the section regularity and after cutting is high.
Cutting mechanism is located at fixed mechanism respectively towards the both sides of round steel cross-wise direction.When round steel is cut, can be with
Two is carried out simultaneously, saves the clipping time of round steel.If the length of round steel is long or too short, can be cut at twice
Cut.After the completion of a cutting, it is only necessary to round steel is moved straightly to suitable position, is cut using opposite side cutting mechanism
Cut.Round steel need not be removed and be reinstalled, therefore, still save the clipping time of round steel.
As shown in figure 3, centring means includes frame 31, connecting gear, determines holes mechanism, borehole drill construction, and to drive
The power-equipment of the round steel centring means, simple structure are easy to operate.Determine holes mechanism include pedestal 33, for supporting round steel
Support member 34 and the centring elements 35 for determining round steel kernel of section point.Borehole drill construction is located at the frame 31 towards described
Determine holes mechanism outlet side, mainly include bracing frame 37, drill bit 39 and extensible member 311.Connecting gear be located at frame 31 towards
Determine holes mechanism inlet side.The central shaft of centring elements 35 is maintained at same water with the central shaft of drill bit 39 and extensible member 311
On horizontal line so that the centering accuracy rate of round steel is greatly improved.
As illustrated in figures 4-5, the feeding platform 101 is for sending round steel to be processed into the high temperature furnace.The high temperature
Stove includes multiple heating chambers 201, and 201 inner top of the heating chamber is provided with flame heater, and the heating chamber 201 is stepped
Arrangement, 201 inner bottom surface of the heating chamber is the slope of connection of cooperating, and the round steel for being admitted to high temperature furnace can roll across institute successively
Heating chamber 201 is stated, so that heating comprehensively is obtained while entering next device;The high temperature furnace side is provided with inspection rack 203, described
Heating chamber(201)Maintenance door 202 is provided with 203 ipsilateral of the inspection rack, is easy to staff to check situation and place in stove
Reason partial fault, such as round steel are blocked and cannot be rolled down.The conveyor track is connected with the outlet of the high temperature furnace by buffering slope 102
Connect, the conveyor track top is provided with the first motor 111, in the conveyor track, be provided with multiple delivery wheels 103, the delivery wheel 103
It is connected with the first chain 112 successively, and is driven by first motor 111.Located at some conveyings of the conveyor track end
Wheel 103 is arranged to the drilling-hole positioning device side in 60 degree of overturning angles, is easy to the round steel for conveying to roll to automatically the brill
Hole positioning device.
As shown in fig. 6, the drilling-hole positioning device is connected with the conveyor track end by ramp platform 104, it is described
Drilling-hole positioning device includes the second motor 105, the first pedestal, universal joint 107, pin-lift arrangement, positioner.The pin-lift arrangement
Including round steel groove 106, push rod 108, the round steel groove 106 is located at first pedestal upper surface, and the push rod 108 connects described
The outfan of the second motor 105 is simultaneously located above the round steel groove 106, and described in during work, the second motor 105 drives the push rod
The round steel placed in round steel groove 106 is headed into positioner by 108.The groove face of the round steel groove 106 inclines splicing by two blocks of steel plates
Form, it is to avoid heated round steel makes the round steel groove expand with heat and contract with cold and deformed damaged for a long time, is uniformly provided with multiple on the steel plate
Hole, effectively prevent steel plate and expand with heat and contract with cold causes stress concentration and damages.The positioner includes locating rack 301, two
Roll shaft 302, two block pressur plates 303, the roll shaft 302 connect the outfan of second motor 105 simultaneously by the universal joint 107
106 both sides of round steel groove are respectively arranged on, the pressing plate 303 is respectively arranged on the both sides up and down of the locating rack 301 and coordinates institute
State roll shaft 302 and location hole is formed in the locating rack 301, be provided with gear type slack adjuster at the top of the locating rack 301
304, it is easy to adjust upper-lower compacting or the release of the pressing plate 303.The drilling-hole positioning device passes through two roll shafts and two pieces of pressures
Round steel is accurately positioned by plate, while roll shaft drives round steel to rotate in drilling, greatly reduces the generation vibrated when round steel drills,
Ensure that being smoothed out for drilling.
As shown in fig. 7, the chiller includes that five parallel and the cooling holding device 109, pond of uniform placement, connects
Receiving apparatus 110.The cooling holding device 109 include clamp framework, located at it is described clamping lower portion three clamping wheels
401st, located at the sparge pipe 402 for clamping framework side and having opening in the clamping frame roof;The pond includes leaning on
The reception tank 404 for receiving cooling waste water of the nearly cooling holding device 109, away from the cooling holding device 109
For the cooling bay 405 of complete cooling pipe.The reception device is located at the cooling bay 405 away from the reception tank 404 1
Side, reception that is parallel including four and being uniformly arranged hook 406, for driving the 3rd motor 407 for receiving hook;The clamping
Framework is provided with opening to 404 side of the reception tank at the clamping wheel 401, and the clamping framework both sides are under the opening
Side is respectively equipped with two across the reception tank 404 while connection enters the conveying 403 of the cooling bay 405.It is described to connect
Receive hook 406 in mating connection with the end of the conveying 403 when extreme lower position.The chiller clamps the drilling
The round steel that positioner conveying comes, coordinates set drilling equipment to be drilled to round steel herein in time, leads to after the completion of drilling
Cross the sparge pipe tentatively to cool down steel pipe, be then delivered to the cooling bay 405 and steel pipe is cooled down completely, finally
The reception device 110 receives the steel pipe after cooling to 405 side steel pipe placing position of the cooling bay.The cooling holding device
Ensure that the steel pipe that drilling is finished is cooled down in time, while the setting of cooling bay ensure that steel pipe obtains cooling down completely significantly
The waste of water resource is reduced, the efficiency of cooling is also improved.
As shown in figure 8, the drilling equipment includes the second pedestal, the 4th motor 501, drilling car 503, boring bar 504.Institute
Caudal of the 4th motor 501 located at second pedestal is stated, second pedestal upper surface is provided with what the drilling garage entered
Track 502, is provided between the track 502 for driving the drilling car 503 outfan phase with the 4th motor 501
The chain 505 of connection, the drilling car 503 are arranged below the gear in mating connection with the chain 505, described so as to realize
Second motor 501 controls the advance or retrogressing of the drilling car 503.Drilling 503 tail end of car is provided with and increases handle 508,
On the one hand the effect of balancing drilling bar gravity is served, drilling car is stable on track, is on the other hand also allowed for work people
Member picks and places drilling car.Drilling 503 head of car is provided with multiple fixing holes for being fixedly connected the boring bar 504, is easy to
Change the boring bar of different model.The boring bar 504 includes drill bit and bar, and the end face diameter of the drill bit is more than the bar
End face diameter so that leave burr and chip clearance between the bar and steel pipe inner wall during drilling, it is ensured that drilling is smoothed out.Described second
The head of pedestal is provided with the positioning seat 507 for positioning and holding up the boring bar 504;Simultaneously as drilling 503 work of car
When making advance drilling when speed it is slower, and drill finish retrogressing it is fast to speed during original position, in order to avoid drill car roll rail away from
Road, 502 afterbody of the track are provided with the stopping means 506 for limiting 503 shift position of the drilling car, and in order to mitigate drilling car
Shock between stopping means, the stopping means 506 adopt spring structure near described track one end.The drilling equipment
Design be well matched with the drilling-hole positioning device and the chiller, drilling-hole positioning device will be the round steel after heating fixed
Position drilling equipment is drilled to round steel in time while push at chiller, after the completion of drilling, the cooling dress
Putting reasonably carries out step cooling to steel pipe.
Embodiment described above is only that preferred implementation of the present utility model is described, not new to this practicality
The spirit and scope of type are defined.On the premise of without departing from this utility model design concept, this area ordinary person is to this
Various modifications and improvement that the technical scheme of utility model is made, all should drop into protection domain of the present utility model, this practicality
The new technology contents being claimed, have all recorded in detail in the claims.
Claims (10)
1. a kind of round steel capsule for building, it is characterised in that:Set including round steel roughing equipment and round steel drilling
It is standby;Before and after by technique, the round steel roughing equipment includes apparatus for peeling off, cutter sweep and centring means, the round steel successively
Rig includes feeding platform successively(101), high temperature furnace, conveyor track, drilling-hole positioning device, drilling equipment and chiller;
The apparatus for peeling off, the cutter sweep, the centring means and the feeding platform(101)Between by transporter transport
Round steel.
2. a kind of round steel capsule for building according to claim 1, it is characterised in that:The apparatus for peeling off
Including support(11), transmission component(16), clamp connecting gear, peeling procedure(12), multiple carrying roller (15), and to drive
The power-equipment of the apparatus for peeling off;The clamping connecting gear includes shelling front moving cart(14)With moving cart after stripping(13);
The peeling procedure(12)Including for carrying out the thick blade insert of rough peeling to round steel(121), for carrying out finely to round steel
The smart blade insert of peeling(122), cleaning member for being cleaned to round steel after peeling(123), and allow the round steel
The body cavity for passing through;The transmission component(16)Positioned at the support(11)Top;The transmission component(16)Top, before technique
After set gradually stripping before moving cart(14), peeling procedure(12), moving cart after stripping(13);Multiple carrying rollers(15)Set up separately
The moving cart before the stripping(14)Both sides and stripping after moving cart(13)Both sides.
3. a kind of round steel capsule for building according to claim 2, it is characterised in that:The thick blade insert
121 include thick cutterhead, the roughing tool being symmetrically mounted on the thick cutterhead, and being located in the middle part of the thick cutterhead allows steel rod to pass through
Thick knife chamber, the accent in the thick knife chamber coordinated with the accent of the body cavity and docks;The smart blade insert 122 include smart cutterhead,
The finishing tool being symmetrically mounted on the smart cutterhead, and the smart knife chamber that permission steel rod is passed through in the middle part of the smart cutterhead, it is described
The accent in smart knife chamber is docked with the accent cooperation of the body cavity;Before and after by technique, the smart blade insert 122 is located at the thick knife portion
121 rear of part.
4. a kind of round steel capsule for building according to claim 1, it is characterised in that:The cutter sweep
Including base(21), fixed mechanism, cutting mechanism, and for driving the power-equipment of the cutter sweep;The fixed mechanism
Be included in round steel cutting process to rise and round steel cutting after the completion of for the Lift Part that declines(22), by what is regulated
The fixed component that round steel is fixed(23), and to consolidate the appearance rod part for placing round steel(24);The cutting mechanism bag
Include the regulating member being adjusted to cutting mechanism whole height before round steel is cut(25)With to cut to round steel
The sickle for cutting(26);The fixed mechanism is located at the base(21)Middle part, the cutting mechanism is symmetrically arranged at
Both sides of the fixed mechanism towards round steel cross-wise direction.
5. a kind of round steel capsule for building according to claim 1, it is characterised in that:The centring means
Including frame(31), connecting gear, determine holes mechanism, borehole drill construction, and to drive the power-equipment of the centring means;It is described
Determining holes mechanism includes pedestal(33), support member for supporting round steel(34)With for determining the centering of round steel kernel of section point
Part(35);The borehole drill construction is located at the frame(31)Holes mechanism outlet side is determined towards described, mainly including bracing frame
(37), drill bit (39) and flexible extensible member can be carried out in the horizontal direction(311);The connecting gear is located at the frame
(31)To determining holes mechanism inlet side described in face;The centring elements(35)Central shaft and the drill bit(39)And it is described flexible
Part(311)Central shaft keep in the same horizontal line.
6. a kind of round steel capsule for building according to claim 1, it is characterised in that:The high temperature furnace bag
Include multiple heating chambers(201), the heating chamber(201)Stepped arrangement, the heating chamber(201)Inner bottom surface is to cooperate
The slope of connection;Heating chamber (201) inner cavity top is provided with flame heater block.
7. a kind of round steel capsule for building according to claim 1, it is characterised in that:The conveyor track leads to
Cross buffering slope(102)Outlet with the high temperature furnace is connected, and the conveyor track top is provided with the first motor(111), it is described defeated
Send(103), located at some delivery wheels of the conveyor track end(103)Fill to the boring positioning
Put side to arrange in 60 degree of overturning angles.
8. a kind of round steel capsule for building according to claim 1, it is characterised in that:The boring positioning
Device passes through platform with slope(104)It is connected with the conveyor track end, the drilling-hole positioning device includes the second motor
(105), round steel groove(106), push rod(108), two roll shafts(302), two block pressur plates(303), the roll shaft is by universal joint
(107)With second motor(105)Outfan be connected and be respectively arranged on the round steel groove(106)Both sides, the pressing plate
(303)Coordinate the roll shaft(302)Location hole is formed in the drilling-hole positioning device.
9. a kind of round steel capsule for building according to claim 1, it is characterised in that:The drilling equipment
Including the 4th motor(501), drilling car(503), boring bar(504), positioning seat(507), the drilling car(503)Bottom is provided with
Gear, the 4th motor(501)By the second chain(505)Connect and drive the drilling car(503).
10. a kind of round steel capsule for building according to claim 1, it is characterised in that:The cooling dress
Put including cooling holding device(109), pond, reception device(110), it is provided with the cooling holding device for clamping round steel
Clamping wheel(401), preliminary cooling round steel sparge pipe(402), in the pond, it is provided with the cooling for cooling down round steel completely
Pond(405).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620981918.3U CN206029293U (en) | 2016-08-30 | 2016-08-30 | Round steel capsule for building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620981918.3U CN206029293U (en) | 2016-08-30 | 2016-08-30 | Round steel capsule for building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206029293U true CN206029293U (en) | 2017-03-22 |
Family
ID=58303588
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620981918.3U Expired - Fee Related CN206029293U (en) | 2016-08-30 | 2016-08-30 | Round steel capsule for building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206029293U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106078231A (en) * | 2016-08-30 | 2016-11-09 | 浙江中屹建设集团有限公司 | A kind of round steel capsule for building |
CN111558835A (en) * | 2020-02-17 | 2020-08-21 | 潍坊东方钢管有限公司 | Automatic integrated loading and unloading equipment for punching and drilling |
CN113084206A (en) * | 2020-01-09 | 2021-07-09 | 江阴市晓达金属制品制造股份有限公司 | Peeling machine for round steel processing |
-
2016
- 2016-08-30 CN CN201620981918.3U patent/CN206029293U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106078231A (en) * | 2016-08-30 | 2016-11-09 | 浙江中屹建设集团有限公司 | A kind of round steel capsule for building |
CN106078231B (en) * | 2016-08-30 | 2018-02-16 | 浙江中屹建设集团有限公司 | A kind of round steel capsule for building |
CN113084206A (en) * | 2020-01-09 | 2021-07-09 | 江阴市晓达金属制品制造股份有限公司 | Peeling machine for round steel processing |
CN111558835A (en) * | 2020-02-17 | 2020-08-21 | 潍坊东方钢管有限公司 | Automatic integrated loading and unloading equipment for punching and drilling |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106078231B (en) | A kind of round steel capsule for building | |
CN206029293U (en) | Round steel capsule for building | |
CN206764144U (en) | One kind can automatic charging tubing laser cutting machine | |
CN205254230U (en) | Aluminium alloy ex -trusions saw cuts automatic production line | |
CN206215588U (en) | A kind of automatic cleaning drying integral machine of CNC fixtures | |
CN206215979U (en) | A kind of sleeping washing machine | |
CN106346337A (en) | Automatic grinding device and method thereof | |
CN105269328A (en) | Automatic manifold production line | |
CN103317379A (en) | Material discharging device of pipe fitting machining equipment | |
CN105436893B (en) | The automatic milling both ends of the surface drill centres machine tool of bearing pin | |
CN110774005A (en) | Sheet steel pipe rolling, welding and polishing equipment | |
CN205218067U (en) | Automatic lathe of skinning | |
CN104858663B (en) | A kind of vertical sleeping compound multistation scratch brushing unhairing machining tool of cylinder block | |
CN209632134U (en) | A kind of equipment of automatic processing cushion block | |
CN213225068U (en) | Billet tube hot piercing production line | |
CN208234950U (en) | A kind of processing step drill quenching unit | |
CN104860110B (en) | longitudinal automatic plate collecting machine | |
CN106697826A (en) | Horizontal continuous casting intelligent feeding robot equipment | |
CN216541834U (en) | Automatic change aluminium tuyere drilling equipment | |
CN203095031U (en) | Extensible flexible double-column type industrial aluminium profile automatic processing assembly line system | |
CN109732431A (en) | A kind of round tube intelligence chamfering deburring equipment | |
CN106141869A (en) | By the quick polisher of formula with by the quick polishing process of formula | |
CN205521733U (en) | Sheet metal wafer separator | |
CN211565100U (en) | Steel rod machining device | |
CN209532962U (en) | A kind of round tube intelligence chamfering deburring equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170322 Termination date: 20190830 |
|
CF01 | Termination of patent right due to non-payment of annual fee |