CN205893868U - Ecological pavement - Google Patents

Ecological pavement Download PDF

Info

Publication number
CN205893868U
CN205893868U CN201620650642.0U CN201620650642U CN205893868U CN 205893868 U CN205893868 U CN 205893868U CN 201620650642 U CN201620650642 U CN 201620650642U CN 205893868 U CN205893868 U CN 205893868U
Authority
CN
China
Prior art keywords
brick
road
shoulder
layer
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620650642.0U
Other languages
Chinese (zh)
Inventor
胡建渠
陈晓琼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Huaxi Environment Construction Co Ltd
Original Assignee
Shenzhen Huatian Garden And Afforest Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Huatian Garden And Afforest Co Ltd filed Critical Shenzhen Huatian Garden And Afforest Co Ltd
Priority to CN201620650642.0U priority Critical patent/CN205893868U/en
Application granted granted Critical
Publication of CN205893868U publication Critical patent/CN205893868U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses an ecological pavement aims at solving current ecological pavement and easily the crooked phenomenon of sinking appears at a brick intermediate position, and its technical scheme main points are: an ecological pavement, including the way shoulder that is located both sides, lay the way brick at a shoulder -mounted, say that the bottom of brick is equipped with the support group spare that is used for supporting way brick intermediate position, support group spare is connected way brick intermediate position and is takeed on both sides in order to realize transmitting the power that is used in the brick intermediate position to saying with saying to take on, nutrition matrix layer, water -storage layer, isolative protection layer, lime layer and former soil layer have been laid from top to bottom in proper order to way brick bottom, many infiltration pipes have been buried in the water -storage layer underground, every the infiltration pipe all communicates there are many drain pipes, the drain pipe extends to in the former soil layer. The utility model discloses an ecological pavement has reduced the probability that the crooked sagging phenomenon of way brick intermediate position appearance appears, the afforestation that has improved the city internal environment simultaneously.

Description

A kind of ecological footpath
Technical field
The utility model is related to urban landscaping technical field, more specifically, it relates to a kind of ecological footpath.
Background technology
Ecological footpath is usually applied among garden landscape, and ecological footpath, for conserving water and soil, prevents from caving in, consolidates mountain Body, improves the scenery of landscape, has very important effect, the ecological footpath of prior art, how using the original soil layer in compacting Upper directly laying band opening brick or slabstone or cement plate, the ecological footpath construction cost of this kind of design is cheap, speed, But through after a period of time, because road occurs local to settle, often result in brick and subside or tilt, keep in repair nor complete Solve problem.
For the problems referred to above, at present, the Chinese patent of Publication No. cn204199144u discloses a kind of ecological footpath, its Drip irrigation device is: includes the ecological pavement being made up of road brick and turf interval setting, described road brick is pressed on ecological pavement On the step surface of road shoulder of both sides setting;The lower section of described road brick is from top to bottom followed successively by sod culture hypothallus, fine sand layer, stone Grieshoch, original soil layer, the surface of described road brick is arranged with multiple drainage chutes deepened from Dao Zhuan center, described road brick toward surrounding The side wall of both sides of the road on be additionally provided with vertical rhone;The lower section of described road shoulder is from top to bottom followed successively by gravel layer and broken Rock layers, the step surface of described road shoulder is provided with multiple vertical drainage through holes, the lower section of described drainage hole be located at shoulder bottom surface Ponding hole be connected, be additionally provided with the locking hole parallel with road in described road shoulder, described locking in the hole is provided with cable wire, described cable wire The road shoulder components that multiple roads shoulder is connected.
Although this ecological footpath has the effect slowing down sedimentation, due to being laid on the sod culture matrix of brick bottom Layer, fine sand layer, lkd layer, original soil layer are more soft, and these soil layers are compacted after walking on road for a long time by people, in compacting During be equivalent to and define gap between road brick and these soil horizons, so that the centre position of road brick easily bends Sagging phenomenon.
Utility model content
In view of the shortcomings of the prior art, the purpose of this utility model is to provide a kind of ecological footpath, to road brick Centre position has preferable enabling capabilities, decreases the probability occurring that bending sag in brick centre position.
Above-mentioned technical purpose of the present utility model has the technical scheme that a kind of ecological footpath, bag Include the road shoulder positioned at both sides, be laid on the road brick on takeing on, the bottom of described road brick is provided with for supporting brick centre position Support component, described support component connects road brick centre position and road shoulder to realize will act at the power transmission in brick centre position To road shoulder both sides;Described road brick bottom is from top to bottom equipped with nutrient matrix layer, aquifer, isolating and protecting layer, lkd layer successively With original soil layer;It is embedded with many soakaway trench, every described soakaway trench is all communicated with many drainpipes, described row in described aquifer Water pipe extends in original soil layer.
By adopting technique scheme, when on blocking the way brick, someone walks about, the power part acting on brick is dispersed to On the road shoulder of both sides, the power acting on brick centre position is then delivered on the road shoulder of both sides by support component, divides further Dissipate act on shoulder on power, thus there is more preferable support effect to road brick, decrease brick centre position occur bending and Sagging probability;Nutrient matrix layer is used for providing growth required nutrient for turf, and aquifer is used for what storage was oozed by subsurface Moisture, isolating and protecting layer is used for separating the weeds in original soil layer, and lkd layer is used for sterilizing;When rainstorm weather occurring or precipitation is more Season when, aquifer cannot store so many moisture, and unnecessary moisture just penetrates in soakaway trench, is then arranged by drainpipe Enter in original soil layer, decrease the phenomenon that rainwater is gathered on ecological footpath surface.
The utility model is further arranged to: described support component includes being obliquely installed and be fixed on propping up on two side line shoulders Fagging and being fixed between gripper shoe and the abutting plate inconsistent with road brick bottom surface.
By adopting technique scheme, the bottom surface abutting Ban Yu road brick is inconsistent, when someone's walking is on road brick, makees Can be delivered on abutting plate used in the power on road brick, then be transferred in the gripper shoe of both sides by abutting plate, finally be dispersed to two On the curb of side, thus effective supporting role is served to road brick;Simultaneously because gripper shoe is obliquely installed, with Dao Zhuanhe road shoulder Between define stable triangular support configurations, make support effect more preferable.
The utility model is further arranged to: is fixed with multiple support bars in described gripper shoe, described support bar is conflicted The bottom surface of road brick.
By adopting technique scheme, support bar can peptizaiton other positions on road brick further pressure, Thus improve the support effect to road brick.
The utility model is further arranged to: described support component includes the supporting plate of curved setting, described supporting plate Two ends be fixed on that two side lines shoulders are upper and conflict in road brick bottom surface in centre position.
By adopting technique scheme, when on someone Zou road brick, the power on brick that acts on can be delivered to holds The centre position of supporting plate, then be dispersed on the road shoulder of both sides by supporting plate, thus effective supporting role is served to road brick;With When due to the curved setting of supporting plate, have when being under pressure that centre position is recessed and two side positions outwards ride out becomes Gesture, and fill up soil above supporting plate i.e. supporting plate effect by jack-up upwards, pressure is produced to the bottom surface of supporting plate, and This pressure can be cancelled out each other with the pressure acting on supporting plate upper surface, thus forming preferable support effect to road brick.
The utility model is further arranged to: is fixed with multiple support support plates on described supporting plate, described support support plate supports The bottom surface of Chu road brick.
By adopting technique scheme, support support plate can peptizaiton other positions on road brick further pressure Power, thus improve the support effect to road brick.
The utility model is further arranged to: described support support plate one end inconsistent with road brick is in that circular arc is arranged.
By adopting technique scheme, when the end of support support plate is in that circular arc is arranged, have one when being under pressure Fixed elasticity, thus decreasing the rigidity effect with road brick bottom surface, reduces the damage to road brick.
The utility model is further arranged to: is fixed with many connection straps between the described road shoulder of both sides.
By adopting technique scheme, the road shoulder of both sides is linked together by connection strap, so that the road shoulder phase of both sides To fixation, when the road shoulder of wherein arbitrarily side trickle sagging, the road shoulder of both sides can be made in the presence of connection strap to become Mutual stable structure and decline simultaneously, maintain the balance of whole ecological footpath.
The utility model is further arranged to: described connection strap takes on the stepped distribution of length direction along road.
By adopting technique scheme, connection strap is made to achieve Mulit-point Connection to road shoulder, so that the connection of road shoulder More stable.
The utility model is further arranged to: the upper surface of described road brick offers a gutter, and described gutter is by road Brick center is gradually deepened to both sides.
By adopting technique scheme, gutter can be accelerated to discharge the ponding on road surface, reduce and surface gathered water Phenomenon.
In sum, the utility model has the advantages that
First, assembly is made by setting, improve the enabling capabilities to road brick centre position, decrease and occur in brick Between position occur bending sag probability;
Second, by arranging soakaway trench and drainpipe, improve drainability, decreasing the phenomenon that surface gathered water occurs;
Third, road shoulder is linked together by setting connection strap, improve stability and the balance of shoulder;
Fourth, by arranging this ecological footpath, improve the greening of city metropolitan environments, being that the life of people in city increases Color.
Brief description
Fig. 1 is the structural representation of embodiment one;
Fig. 2 is the structural representation of embodiment two.
In figure: 1, road shoulder;11st, connection strap;2nd, road brick;21st, gutter;3rd, support component;31st, gripper shoe;32nd, abut Plate;33rd, support bar;34th, supporting plate;35th, support support plate;4th, nutrient matrix layer;5th, aquifer;51st, soakaway trench;52nd, drainpipe; 6th, isolating and protecting layer;7th, lkd layer;8th, original soil layer.
Specific embodiment
With reference to the accompanying drawings and examples, the utility model is described in detail.
Embodiment one: a kind of ecological footpath, as shown in figure 1, road shoulder 1 is located at the both sides of ecological footpath, road shoulder 1 is equipped with Polylith road brick 2, plants between neighboring track brick 2 and is implanted with turf, road brick 2 is provided with multiple gutters 21, and gutter 21 is takeed in the middle of 1 by road Gradually deepen to both sides;Road brick 2 bottom is from top to bottom equipped with nutrient matrix layer 4, aquifer 5, isolating and protecting layer 6, stone successively Grieshoch 7 and original soil layer 8.
As shown in figure 1, nutrient matrix layer 4 is mixed by bio-matrix and soil, for providing growth required for turf Nutrient, be embedded with nutrient matrix layer 4 and make assembly;Support component 3 includes integrally formed gripper shoe 31, abuts plate 32 and Multiple support bars 33, gripper shoe 31 is located at the both sides abutting plate 32, and gripper shoe 31 is obliquely installed and is fixed on the road shoulder 1 of both sides On, abut plate 32 and all conflict in the bottom of road brick 2 with support bar 33, thus road brick 2 is formed supporting.
As shown in figure 1, aquifer 5 is made up of river sand, for storing the moisture oozing from earth's surface, it is embedded with aquifer 5 Many soakaway trench 51, soakaway trench 51 carries some water seepage holes, and moisture can be penetrated in soakaway trench 51 by water seepage hole;Every Soakaway trench 51 is all communicated with many drainpipes 52, and drainpipe 52 extends in original soil layer 8.
Isolating and protecting layer 6 has rubble to make, for separating the weeds in original soil layer 8;Lkd layer 7 is used for sterilizing.
As shown in figure 1, being fixed with many connection straps 11 between twice shoulder 1, many connection straps 11 are takeed on 1 length direction along road and are in Stepped distribution, the road shoulder 1 of both sides is linked together by connection strap 11, so that the road shoulder 1 of both sides is relatively fixed, wherein arbitrarily When the road shoulder 1 of side trickle sagging, can make in the presence of connection strap 11 road of both sides take on 1 formed mutual stable Structure and decline simultaneously, maintain the balance of whole ecological footpath.
As shown in figure 1, when on blocking the way brick 2, someone walks about, the power on brick 2 that acts on can be delivered to abutting plate 32 and prop up On strut 33, then it is transferred in the gripper shoe 31 of both sides by abutting plate 32 and support bar 33, be finally dispersed on the curb of both sides, Thus effective supporting role is served to road brick 2;Simultaneously because gripper shoe 31 is obliquely installed, shape and road brick 2 and road shoulder 1 between Become stable triangular support configurations, made support effect more preferably, decrease brick 2 centre position occur bending and sink several Rate;When rainstorm weather or precipitation more season, aquifer 5 cannot store so many moisture, and unnecessary moisture is just Penetrate in soakaway trench 51, be then drained in original soil layer 8 by drainpipe 52, decrease ecological footpath surface and gather showing of rainwater As.
Embodiment two: a kind of ecological footpath, as shown in Fig. 2 being with the difference of embodiment one, support component 3 is wrapped Include supporting plate 34 and multiple support support plate 35 being fixed on supporting plate 34, the two ends of supporting plate 34 are fixed on two side line shoulders 1 And centre position is conflicted in road brick 2 bottom surface, conflict in the bottom surface of road brick 2 in the end of support support plate 35, and support support plate 35 and road The inconsistent one end of brick 2 is in that circular arc is arranged.
As shown in Fig. 2 when on someone Zou road brick 2, acting on the power on brick 2 and can be delivered in supporting plate 34 Between on position and support support plate 35, then be dispersed on the road shoulder 1 of both sides by supporting plate 34, thus serving effectively to road brick 2 Supporting role;Simultaneously because the curved setting of supporting plate 34, have when being under pressure that centre position is recessed and two side positions The trend outwards riding out, and fill up soil above supporting plate 34 i.e. supporting plate 34 effect by jack-up upwards, to support Pressure is produced in the bottom surface of plate 34, and this pressure can be cancelled out each other with the pressure acting on supporting plate 34 upper surface, thus to road Brick 2 forms preferable support effect.
The above is only preferred embodiment of the present utility model, and protection domain of the present utility model is not limited merely to Above-described embodiment, all technical schemes belonging under the utility model thinking belong to protection domain of the present utility model.Should refer to Go out, for those skilled in the art, some improvement under the premise of without departing from the utility model principle and Retouching, these improvements and modifications also should be regarded as protection domain of the present utility model.

Claims (9)

1. a kind of ecological footpath, including the road positioned at both sides take on (1), the road brick (2) that is laid on shoulder (1) it is characterised in that: The bottom in described road brick (2) is provided with the support component (3) for supporting brick (2) centre position, and described support component (3) connects Road brick (2) centre position and road shoulder (1) are transferred to take on (1) both sides with the power realizing will act at brick (2) centre position;Institute State brick (2) bottom and be from top to bottom equipped with nutrient matrix layer (4), aquifer (5), isolating and protecting layer (6), lkd layer successively And original soil layer (8) (7);It is embedded with many soakaway trench (51), every described soakaway trench (51) is all communicated with described aquifer (5) Many drainpipes (52), described drainpipe (52) extends in original soil layer (8).
2. a kind of ecological footpath according to claim 1 it is characterised in that: described support component (3) includes being obliquely installed And be fixed on two side lines shoulder (1) on gripper shoe (31) and be fixed between gripper shoe (31) and offset with road brick (2) bottom surface Tactile abutting plate (32).
3. a kind of ecological footpath according to claim 2 it is characterised in that: be fixed with multiple on described gripper shoe (31) Strut (33), described support bar (33) is conflicted in the bottom surface of road brick (2).
4. a kind of ecological footpath according to claim 1 it is characterised in that: described support component (3) includes curved setting The supporting plate (34) put, the two ends of described supporting plate (34) are fixed on two side lines shoulder (1) above and conflict in road brick (2) in centre position Bottom surface.
5. a kind of ecological footpath according to claim 4 it is characterised in that: be fixed with multiple holding on described supporting plate (34) Support support plate (35), described support support plate (35) is conflicted in the bottom surface of road brick (2).
6. a kind of ecological footpath according to claim 5 it is characterised in that: described support support plate (35) and road brick (2) phase The one end conflicted is in that circular arc is arranged.
7. a kind of ecological footpath according to claim 1 it is characterised in that: solid between described road shoulder (1) of both sides Surely there are many connection straps (11).
8. a kind of ecological footpath according to claim 7 it is characterised in that: described connection strap (11) along road take on (1) length The stepped distribution in direction.
9. a kind of ecological footpath according to claim 1 it is characterised in that: the upper surface in described road brick (2) offers Gutter (21), described gutter (21) is gradually deepened from road brick (2) center to both sides.
CN201620650642.0U 2016-06-27 2016-06-27 Ecological pavement Expired - Fee Related CN205893868U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620650642.0U CN205893868U (en) 2016-06-27 2016-06-27 Ecological pavement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620650642.0U CN205893868U (en) 2016-06-27 2016-06-27 Ecological pavement

Publications (1)

Publication Number Publication Date
CN205893868U true CN205893868U (en) 2017-01-18

Family

ID=57768924

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620650642.0U Expired - Fee Related CN205893868U (en) 2016-06-27 2016-06-27 Ecological pavement

Country Status (1)

Country Link
CN (1) CN205893868U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106958177A (en) * 2017-04-02 2017-07-18 北京军秀咨询有限公司 A kind of construction method of municipal road, pavement structure and highway pavement
CN107960231A (en) * 2017-12-10 2018-04-27 成都隶盈科技有限公司 A kind of town road and its construction method
CN108412034A (en) * 2018-03-27 2018-08-17 南京汤泉建设集团有限公司 The construction method and water guiding system of house balcony, balcony water guiding system
CN108560350A (en) * 2018-06-05 2018-09-21 王晨宇 A kind of park anti-ponding floor brick structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106958177A (en) * 2017-04-02 2017-07-18 北京军秀咨询有限公司 A kind of construction method of municipal road, pavement structure and highway pavement
CN107960231A (en) * 2017-12-10 2018-04-27 成都隶盈科技有限公司 A kind of town road and its construction method
CN107960231B (en) * 2017-12-10 2019-09-27 浙江诚通市政建设有限公司 A kind of town road and its construction method
CN108412034A (en) * 2018-03-27 2018-08-17 南京汤泉建设集团有限公司 The construction method and water guiding system of house balcony, balcony water guiding system
CN108560350A (en) * 2018-06-05 2018-09-21 王晨宇 A kind of park anti-ponding floor brick structure

Similar Documents

Publication Publication Date Title
CN106759825B (en) Construction method of sponge urban green land water storage system
CN205893868U (en) Ecological pavement
CN105421470B (en) Assembled anchor pole arched framework combined type ecological revetment construction method
CN204753297U (en) Ecological grass planting brick parking area
CN101622931B (en) Greening sloping surface for rock side slope facing wall and construction method thereof
CN201826318U (en) Simple ecological slope protecting structure for loose soil of road
CN206681021U (en) A kind of multi-functional slope reinforcement structure
CN103485321A (en) Karst landform stony desertification treatment method
CN106065656A (en) Guard system and construction method is oozed under the regularization of Collapsible Loess District rainwater
CN108166520B (en) Water and soil conservation method for electric power transmission line engineering construction
CN211240745U (en) Saline-alkali soil salt elimination and prevention ecological structure
CN204898465U (en) Ecological drainage facility of permafrost region dish
CN109853590B (en) Device for infiltrating foreign soil base layer on rock steep slope surface by utilizing rainfall and construction method
CN102704437A (en) Coal mining subsidence area cultivation water source reconstruction method suitable for complex mountain area
CN215562318U (en) Ecological bank protection
CN105525551B (en) To the remodeling method and grass planting pavement structure of Wind Power Stations temporary construction road
CN206591533U (en) Careless blanket ecoscape slope protection system
CN202090354U (en) Side slope ecological protection structure
CN115288168A (en) Sand soil subgrade construction period slope comprehensive anti-scouring structure and protection method
CN111501667B (en) Ecological slope protection structure for hydraulic engineering
CN213507894U (en) Permeable pavement for sidewalk
CN103898844B (en) A kind of slabstone buttress reinforced earth compound embankment culvert pipe structure
CN206800423U (en) Subsiding land counterfort virescence brick
CN105178133A (en) Disc-shaped ecological water drainage facility in permafrost region and construction method for disc-shaped ecological water drainage facility
CN217241615U (en) Planting hole structure for street tree in urban road

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: Henggang street Longgang District Shenzhen city Guangdong province 518000 six about community building 2, Zhenye City second floor apartment No. 8

Patentee after: Shenzhen Huaxi Environment Construction Co., Ltd.

Address before: Henggang street Longgang District Shenzhen city Guangdong province 518000 six about community building 2, Zhenye City second floor apartment No. 8

Patentee before: Shenzhen Huatian garden and afforest Co., Ltd.

CP01 Change in the name or title of a patent holder
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170118

Termination date: 20210627

CF01 Termination of patent right due to non-payment of annual fee