CN105525551B - Transformation method for temporary construction road of wind power field and grass planting pavement structure - Google Patents

Transformation method for temporary construction road of wind power field and grass planting pavement structure Download PDF

Info

Publication number
CN105525551B
CN105525551B CN201510622515.XA CN201510622515A CN105525551B CN 105525551 B CN105525551 B CN 105525551B CN 201510622515 A CN201510622515 A CN 201510622515A CN 105525551 B CN105525551 B CN 105525551B
Authority
CN
China
Prior art keywords
grass planting
layer
road
laid
basic unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510622515.XA
Other languages
Chinese (zh)
Other versions
CN105525551A (en
Inventor
谢春生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201510622515.XA priority Critical patent/CN105525551B/en
Publication of CN105525551A publication Critical patent/CN105525551A/en
Application granted granted Critical
Publication of CN105525551B publication Critical patent/CN105525551B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Cultivation Of Plants (AREA)

Abstract

The invention discloses a method for transforming a temporary construction road of a wind power field and a grass planting road surface, wherein after the construction of the wind power field is finished, the temporary road paved during construction is used as the bottom layer of the road, and the top surface of the bottom layer is transformed into a cross slope road surface with a middle high and two sides low to form a slope of 3%; then a layer of geomembrane is laid on the top surface of the bottom layer, a base layer is laid on the geomembrane by using broken stones or pebbles, a layer of geotextile is laid on the base layer, then a surface layer is constructed on the geotextile, the surface layer is formed by laying the plowing and planting soil, the soil base fertilizer and the broken stones which are suitable for the growth of plants, and the turf is laid on the surface layer to form the grass planting road surface. The grass planting road surface has simple structure, low manufacturing cost and convenient construction. And has the advantages of nature, beautiful appearance, no noise, no dust, no water accumulation and the like, and the driving comfort is good. The road construction and operation of the invention have little influence on the environment.

Description

To the remodeling method and grass planting pavement structure of Wind Power Stations temporary construction road
Technical field
The present invention relates to a kind of remodeling method and grass planting pavement structure to Wind Power Stations temporary construction road, belong to road Renovation technique field.
Background technology
During Construction of Wind Power, corresponding each Fans are required for building a temporary road to complete material, equipment Transport and excavation, the construction operation such as pour, install.But when entering the operation phase, these roads just lose original function, turn It is changed into making an inspection tour, overhauling road, and makes an inspection tour, overhauls its volume of traffic of road typically light vehicle that is few, and passing through.At this time, The inferior grade temporary pavement carried over before just becomes a lot of " scar " between blue mountains and green waters, either from holding ecological landscape See or from the perspective of controlling soil erosion, be required for transforming it.And or existing pavement structure is difficult to reach To environmental protection, the requirement of landscape, otherwise cost is excessive, uneconomical.
The content of the invention
It is an object of the present invention to provide a kind of remodeling method to Wind Power Stations temporary construction road and grass planting road surface to tie Structure, to transform the temporary pavement during wind power plant construction, makes improved road surface can be in terms of environmental protection, landscape Obtain good effect, and can meet the requirement under light traffic, light loading condition, and low cost, easy to construct, from And overcome the deficiencies in the prior art.
Technical scheme:
A kind of remodeling method to Wind Power Stations temporary construction road of the present invention is that this method is constructed in Wind Power Stations After, temporary road that to construct when is laid with is as the bottom of road, and the low gradient that formed in high both sides is 3% among bottom top surface Horizontal slope road surface;Then curb is constructed in bottom both sides, curb bottom sets one group equidistantly to arrange along curb length direction French drain;Then the bottom top surface between the curb of both sides of the road is laid with one layer of geomembrane, and geomembrane is extended in french drain, To prevent rainwater from penetrating into bottom;Then basic unit is laid with rubble or cobble on geomembrane, in order to which rainwater can be by permeable Layer is discharged from french drain;One layer of geotextiles are laid with basic unit again, to prevent sandy soil from entering basic unit's obstruction water stream channel;Then exist Surface layer is constructed on geotextiles, surface layer is laid with using cultivated plant soil, soil base manure and the rubble of suitable plant growth and formed, surface layer In be embedded with three dimension geotechnical gauze pad and TGXG, turf has been sodded on surface layer and has formed grass planting road surface.
In preceding method, the weight of the surface layer medium stone, which accounts for plough, plants the 10~30% of soil and soil base manure gross weight;Rubble Particle diameter be 15~30mm.
In preceding method, the three dimension geotechnical gauze pad and TGXG level are laid in surface layer, three dimension geotechnical gauze pad away from The distance of surface layer top surface is 50~100mm;TGXG sets 1~3 layer, upper strata TGXG top surface and three dimension geotechnical gauze pad it Between distance be 100~150mm, the distance between TGXG and TGXG are not less than 60 mm.
In preceding method, the laying height of the basic unit is concordant with the top of french drain;The geotextiles for being laid on substrate top surface are prolonged Extend in the gap between french drain and curb.
In preceding method, when grass planting road surface side is located at grass planting cutting bottom, between grass planting cutting and grass planting road surface Equipped with gutter;When grass planting road surface side is located at the top of grass planting embankment, french drain bottom is directly connected with grass planting embankment.
A kind of grass planting pavement structure of the invention formed as stated above, the grass planting pavement structure are included from top to bottom It is followed successively by surface layer, basic unit and bottom;Geomembrane is equipped between basic unit and bottom, geotechnique is equipped between surface layer and basic unit Cloth, level is equipped with three dimension geotechnical gauze pad and TGXG in surface layer, and turf is implanted with surface layer and forms grass planting road surface.
In foregoing grass planting pavement structure, the bottom is the high both sides in centre formed on original road bed by finishing The low gradient is 3% horizontal slope road surface;Basic unit is the pervious bed being laid with rubble or cobble;Surface layer is ploughing with suitable plant growth Plant the vegetable layer being laid with after soil, soil base manure and rubble mixing.
In foregoing grass planting pavement structure, distance of the upper surface of the three dimension geotechnical gauze pad away from surface layer top surface for 50~ 100mm;TGXG sets 1~3 layer, the distance between the top surface of the TGXG of its superiors and three dimension geotechnical gauze pad bottom surface For 100~150mm, TGXG spaces between distance with TGXG and is not less than 60 mm.
In foregoing grass planting pavement structure, the laying height of the basic unit is concordant with the top of french drain, and french drain is also equipped with and base The building stones of layer phase same material;The geotextiles for being laid on substrate top surface are extended in the gap between french drain and curb.
In foregoing grass planting pavement structure, when grass planting road surface side is located at grass planting cutting bottom, grass planting cutting and grass planting Gutter is equipped between road surface;When grass planting road surface side is located at the top of grass planting embankment, french drain bottom directly connects with grass planting embankment Connect.
By adopting the above-described technical solution, compared with prior art, the present invention the present invention grass planting road surface reached with Lower beneficial effect:It is natural, beautiful, it is adapted to light traffic, light load, makes under conditions of particularly stringent to landscape, environmental requirement With, and noiseless, not free from dust, ponding, thus road-ability is good.The pavement construction of the present invention and operation are to the shadow of environment Ring very little.With simple structure, the characteristics of low cost, convenient construction and later maintenance.The grass planting road surface of the present invention is not only Available for Wind Power Stations, it can also be used to scenic environment road surface etc..
Brief description of the drawings
Fig. 1 is the structure diagram of the embodiment of the present invention 1;
Fig. 2 is the structure diagram of the embodiment of the present invention 2.
Description of reference numerals:1- turfs, 2- three dimension geotechnical gauze pads, 3- TGXG, 4- surface layers, 5- basic units, 6- bottoms, 7- Geotextiles, 8- geomembranes, 9- french drains, 10- curbs, 11- grass planting embankments, 12- grass planting cuttings, 13- gutters.
Embodiment
The present invention is described in further detail with reference to the accompanying drawings and examples, but not as to any of the present invention Limitation.
A kind of remodeling method to Wind Power Stations temporary construction road of the present invention is that this method is constructed in Wind Power Stations After, temporary road that to construct when is laid with is as the bottom 6 of road, and the low gradient that formed in high both sides is 3% among bottom top surface Horizontal slope road surface;Then curb 10 is constructed in bottom both sides, curb bottom sets one group along curb length direction and equidistantly arranges French drain 9;Then the bottom top surface between the curb of both sides of the road is laid with one layer of geomembrane 8, and geomembrane extends to blind In ditch, to prevent rainwater from penetrating into bottom;Then basic unit 5 is laid with rubble or cobble on geomembrane, in order to which rainwater can lead to Pervious bed is crossed to discharge from french drain;One layer of geotextiles 7 are laid with basic unit 5 again, to prevent sandy soil enter basic unit's obstruction current from leading to Road;Then surface layer 4 is constructed on geotextiles, surface layer is using the cultivated plant soil, soil base manure and rubble paving for being adapted to plant growth Three dimension geotechnical gauze pad 2 and TGXG 3 are embedded with if forming, in surface layer, turf 1 has been sodded on surface layer and has formed grass planting road surface. The weight of 4 medium stone of surface layer, which accounts for plough, plants the 10~30% of soil and soil base manure gross weight;The particle diameter of rubble is 15~30mm. The three dimension geotechnical gauze pad 2 and 3 level of TGXG are laid in surface layer 4, and distance of the three dimension geotechnical gauze pad away from surface layer top surface is 50~100mm;TGXG set 1~3 layer, the distance between upper strata TGXG top surface and three dimension geotechnical gauze pad be 100~ 150mm, the distance between TGXG and TGXG are not less than 60 mm.The laying height of the basic unit 5 and the top of french drain 9 Concordantly;The geotextiles 7 for being laid on substrate top surface are extended in the gap between french drain and curb 10.Grass planting road surface side position When grass planting 12 bottom of cutting, gutter 13 is equipped between grass planting cutting and grass planting road surface;Grass planting road surface side is located at grass planting During 11 top of embankment, 9 bottom of french drain is directly connected with grass planting embankment.
A kind of grass planting pavement structure of the invention formed as stated above as depicted in figs. 1 and 2, tie by the grass planting road surface Structure includes from top to bottom being followed successively by surface layer 4, basic unit 5 and bottom 6;Be equipped with geomembrane 8 between basic unit 5 and bottom 6, surface layer 4 with Geotextiles 7 are equipped between basic unit 5, level is equipped with three dimension geotechnical gauze pad 2 and TGXG 3 in surface layer 4, surface layer 4 it On be implanted with turf 1 and form grass planting road surface.The bottom 6 is that the high both sides in centre formed on original road bed by finishing are low The gradient is 3% horizontal slope road surface;Basic unit 5 is the pervious bed being laid with rubble or cobble;Surface layer 4 is ploughing with suitable plant growth Plant the vegetable layer being laid with after soil, soil base manure and rubble are mixed by the method for traditional vegetation.The three dimension geotechnical gauze pad 2 Distance of the upper surface away from 4 top surface of surface layer is 50~100mm;TGXG 3 sets 1~3 layer, the TGXG 3 of its superiors The distance between top surface and 2 bottom surface of three dimension geotechnical gauze pad are 100~150mm, and TGXG 3 and TGXG 3 are mutual Spacing distance is not less than 60 mm.The laying height of the basic unit 5 is concordant with the top of french drain 9, and french drain 9 is also equipped with and 5 phase of basic unit The building stones of same material;The geotextiles 7 for being laid on 5 top surface of basic unit are extended in the gap between french drain and curb 10.The grass planting When road surface side is located at grass planting 12 bottom of cutting, gutter 13 is equipped between grass planting cutting 12 and grass planting road surface;The grass planting road surface When side is located at grass planting 11 top of embankment, 9 bottom of french drain is directly connected with grass planting embankment 11.
Embodiment 1:
A kind of grass planting pavement structure of the present invention includes three V dimensional as shown in Figure 1, including surface layer 4 among surface layer Gauze pad 2 and TGXG 3, and turf 1 has been sodded on three dimension geotechnical gauze pad and surface layer.Surface layer is native stone mixing material, Mainly it is made of the cultivated plant soil, soil base manure and the rubble that are adapted to plant growth.Preferably, the particle diameter of rubble using 15~ 30mm, its content weight ratio are 10~30%.Three dimension geotechnical gauze pad and TGXG level are laid in surface layer, three-dimensional earthwork Pad is located at most last layer, and the distance away from surface layer top surface is 50~100mm.TGXG is located under three dimension geotechnical gauze pad, the two Between spacing be 100~150mm, its number of plies is 1~3 layer.For surface layer making between the curb 10 of roadbed both sides, its top surface is certainly The horizontal slope i of road camber central tendency both sides, horizontal slope i are 3%, thus the horizontal slope of turf 1 is also 3%.Grass planting road surface further includes 5 He of basic unit Bottom 6, the pervious bed that basic unit is made of seepy material, such as rubble, cobble material.Basic unit is located under surface layer, bottom position Under basic unit.Curb is equipped with french drain 9 below 10, and french drain aligns with basic unit.The bottom surface of french drain and basic unit is from road camber The heart is inclined to the horizontal slope j of both sides, and horizontal slope j is 2~3%.Rainwater can be penetrated into basic unit by surface layer and be discharged to grass planting embankment 11 through french drain In addition.Geotextiles 7 are equipped between basic unit and surface layer, between the bottom and basic unit and bottom of french drain 9 is equipped with geomembrane 8.
The specific implementation step of the present invention:
1. the making bottom on the roadbed implemented, makes its top surface smooth, closely knit through rolling;
2. geomembrane is laid with bottom;
3. making basic unit and french drain;
4. geotextiles are laid with basic unit;
5. installation pours curb;
6. cultivated plant soil, base manure and rubble etc. being mixed and stirred native stone mixing material being made, and it is layered and paves to form surface layer, at the same time Order installation TGXG and three dimension geotechnical gauze pad;
7. sod turf;
Embodiment 2:
As shown in Fig. 2, it is used for the embodiment of original Pavement Improvement for the grass planting pavement structure of the present invention.It is specific to implement step Suddenly it is:
Original road surface is repaired first, makes its smooth, closely knit.
Then geomembrane, making basic unit are laid with, and gutter 13 is set in road surface side.
Install or pour again curb.
Last making surface layer, installs TGXG and three dimension geotechnical gauze pad, sods turf.
In addition, it is grass planting cutting to transform original side slope.
Above is the concrete application example of the present invention, all technical solutions formed using equivalent substitution or equivalent transformation, Belong to protection domain of the presently claimed invention.
The invention discloses a kind of remodeling method to Wind Power Stations temporary construction road and grass planting road surface.Its method be After Wind Power Stations are constructed, bottom top surface is transformed into centre by the temporary road that to construct when is laid with as the bottom of road High both sides are low to form the horizontal slope road surface that the gradient is 3%;Then one layer of geomembrane is laid with bottom top surface, rubble is used on geomembrane Or cobble is laid with basic unit, then one layer of geotextiles are laid with basic unit, surface layer are then constructed on geotextiles, surface layer is using suitable The cultivated plant soil, soil base manure and rubble laying for closing plant growth form, and turf has been sodded on surface layer and has formed grass planting road surface.This The grass planting pavement structure of invention is simple, and low cost is easy for construction.And there is nature, beauty, it is adapted to light traffic, light load, Used under conditions of particularly stringent to landscape, environmental requirement, and noiseless, not free from dust, ponding, thus road-ability It is good.Influence very little of the pavement construction and operation of the present invention to environment.

Claims (2)

  1. A kind of 1. remodeling method to Wind Power Stations temporary construction road, it is characterised in that:This method is constructed in Wind Power Stations After, temporary road that to construct when is laid with is as the bottom of road, and the low gradient that formed in high both sides is 3% among bottom top surface Horizontal slope road surface;Then curb is constructed in bottom both sides, curb bottom sets one group equidistantly to arrange along curb length direction French drain;Then the bottom top surface between the curb of both sides of the road is laid with one layer of geomembrane, and geomembrane is extended in french drain, To prevent rainwater from penetrating into bottom;Then basic unit is laid with rubble or cobble on geomembrane, in order to which rainwater can be by permeable Layer is discharged from french drain;One layer of geotextiles are laid with basic unit again, to prevent sandy soil from entering basic unit's obstruction water stream channel;Then exist Surface layer is constructed on geotextiles, surface layer is laid with using cultivated plant soil, soil base manure and the rubble of suitable plant growth and formed, surface layer In be embedded with three dimension geotechnical gauze pad and TGXG, turf has been sodded on surface layer and has formed grass planting road surface;The weight of surface layer medium stone Amount, which accounts for plough, plants the 10~30% of soil and soil base manure gross weight;The particle diameter of rubble is 15~30mm;Three dimension geotechnical gauze pad and geotechnological lattice Grid level is laid in surface layer, and distance of the three dimension geotechnical gauze pad away from surface layer top surface is 50~100mm;TGXG sets 1~3 Layer, the distance between upper strata TGXG top surface and three dimension geotechnical gauze pad are 100~150mm, TGXG and TGXG it Between distance be not less than 60 mm;The laying height of basic unit is concordant with the top of french drain;The geotextiles for being laid on substrate top surface extend to In gap between french drain and curb;When grass planting road surface side is located at grass planting cutting bottom, between grass planting cutting and grass planting road surface Equipped with gutter;When grass planting road surface side is located at the top of grass planting embankment, french drain bottom is directly connected with grass planting embankment.
  2. A kind of 2. grass planting pavement structure formed by claim 1 the method, it is characterised in that:The grass planting pavement structure bag Include and be from top to bottom followed successively by surface layer(4), basic unit(5)And bottom(6);In basic unit(5)With bottom(6)Between be equipped with geomembrane (8), in surface layer(4)With basic unit(5)Between be equipped with geotextiles(7), in surface layer(4)Interior level is equipped with three dimension geotechnical gauze pad (2)And TGXG(3), in surface layer(4)On be implanted with turf(1)Form grass planting road surface;Bottom(6)It is in original road bed The horizontal slope road surface that the upper low gradient in the high both sides in centre formed by finishing is 3%;Basic unit(5)Be be laid with rubble or cobble it is saturating Water layer;Surface layer(4)It is the vegetable layer by being laid with after the cultivated plant soil, soil base manure and rubble mixing with suitable plant growth; Three dimension geotechnical gauze pad(2)Upper surface away from surface layer(4)The distance of top surface is 50~100mm;TGXG(3)1~3 layer is set, The TGXG of its superiors(3)Top surface and three dimension geotechnical gauze pad(2)The distance between bottom surface is 100~150mm, Tu Gongge Grid(3)With TGXG(3)Space between distance and be not less than 60 mm;Basic unit(5)Laying height and french drain(9)Top Portion is concordant, french drain(9)Also it is equipped with and basic unit(5)The building stones of phase same material;It is laid on basic unit(5)The geotextiles of top surface(7)Prolong Extend french drain(9)With curb(10)Between gap in;Grass planting road surface side is located at grass planting cutting(12)During bottom, grass planting cutting (12)Gutter is equipped between grass planting road surface(13);Grass planting road surface side is located at grass planting embankment(11)During top, french drain(9) Bottom directly with grass planting embankment(11)Connection.
CN201510622515.XA 2015-11-25 2015-11-25 Transformation method for temporary construction road of wind power field and grass planting pavement structure Active CN105525551B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510622515.XA CN105525551B (en) 2015-11-25 2015-11-25 Transformation method for temporary construction road of wind power field and grass planting pavement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510622515.XA CN105525551B (en) 2015-11-25 2015-11-25 Transformation method for temporary construction road of wind power field and grass planting pavement structure

Publications (2)

Publication Number Publication Date
CN105525551A CN105525551A (en) 2016-04-27
CN105525551B true CN105525551B (en) 2018-05-15

Family

ID=55768048

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510622515.XA Active CN105525551B (en) 2015-11-25 2015-11-25 Transformation method for temporary construction road of wind power field and grass planting pavement structure

Country Status (1)

Country Link
CN (1) CN105525551B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565488A (en) * 2019-08-31 2019-12-13 上海宝冶集团有限公司 Temporary road macadam paving method
CN114525713A (en) * 2021-12-09 2022-05-24 上海现代建筑装饰环境设计研究院有限公司 Construction method for building forest protection sidewalk with little environmental impact

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100453734C (en) * 2003-11-26 2009-01-21 上海市政工程设计研究院 Plant macadam pavement and its construction method
KR101065207B1 (en) * 2010-06-04 2011-09-19 장은환 Artificial garden manufacturing method and for water drainage module manufacturing artificial garden
KR101302553B1 (en) * 2010-11-15 2013-09-02 어번닉스 주식회사 Planting structure for slab and construction method thereof
CN103103905B (en) * 2011-11-11 2017-05-03 上海市政工程设计研究总院(集团)有限公司 Road pavement draining method and drainage structure system
CN204039863U (en) * 2014-08-13 2014-12-24 江苏中设工程咨询集团有限公司 Road soil curb edge waterproof/drainage structure
CN104452518B (en) * 2014-12-05 2017-01-04 中交第一公路勘察设计研究院有限公司 The earth shoulder blind-drainage system of road surface edge central drainage

Also Published As

Publication number Publication date
CN105525551A (en) 2016-04-27

Similar Documents

Publication Publication Date Title
CN204753297U (en) Ecological grass planting brick parking area
CN105887609A (en) Method for constructing ecological infiltration pavement in sponge city
CN106758638A (en) A kind of city sponge brick and its construction technology
CN206681021U (en) Multi-functional side slope reinforced structure
CN107938480A (en) A kind of microorganism cures the desert highway embankment and its construction method of joint TGXG
CN106193245A (en) A kind of paddy field underground reservoir for sponge city and construction method thereof
CN103669167B (en) A kind of permeable pavement structure
CN207062672U (en) A kind of permeable pavement structure
CN108532406A (en) Can rapid construction high-bearing capacity pervious surface and laying method
CN205475261U (en) Ash dam structure of power plant
CN205591075U (en) Ecology structure of mating formation
CN105525551B (en) Transformation method for temporary construction road of wind power field and grass planting pavement structure
CN102071695A (en) Protection construction of vegetation concrete side slope
CN105421314B (en) A kind of construction method of the three-dimensional regulator control system of accumulated water Farmland Water
CN206553848U (en) Embankment section road surface edge structure
CN206752237U (en) Stealthy passageway for fire apparatus
CN110184874A (en) A kind of garden landscape road and its construction technology
CN103590301B (en) The construction method of Cushion-layer-free permeable ecological grassing terrace
CN212052138U (en) Urban road structure applied to collapsible loess mountain area
CN206070276U (en) Full basis water-permeable brick
CN105474942B (en) The construction method on ground parking lawn
CN211472454U (en) Structure is administered to soil crack
CN114319297A (en) Land restoration method for coal mine coal gangue land in alpine region
CN108360321B (en) Structure and method for controlling post-construction settlement of fine-grained soil high-fill embankment
CN201865114U (en) Protective structure for vegetation concrete side slope

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant