CN204552818U - The drainage system of ditch, side, anti-tunnel bottom leaky - Google Patents

The drainage system of ditch, side, anti-tunnel bottom leaky Download PDF

Info

Publication number
CN204552818U
CN204552818U CN201420786529.6U CN201420786529U CN204552818U CN 204552818 U CN204552818 U CN 204552818U CN 201420786529 U CN201420786529 U CN 201420786529U CN 204552818 U CN204552818 U CN 204552818U
Authority
CN
China
Prior art keywords
inverted arch
ditch
tunnel
packed layer
central drain
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420786529.6U
Other languages
Chinese (zh)
Inventor
刘述才
乔红彦
王元清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fifth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Original Assignee
Fifth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fifth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd filed Critical Fifth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Priority to CN201420786529.6U priority Critical patent/CN204552818U/en
Application granted granted Critical
Publication of CN204552818U publication Critical patent/CN204552818U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses the drainage system of ditch, side, a kind of anti-tunnel bottom leaky, comprise set gradually from tunnel base scar to road surface or orbital plane direction inverted arch preliminary bracing, inverted arch secondary lining, inverted arch packed layer and supercrust, the Central drain extended along tunnel longitudinal direction is provided with in inverted arch packed layer, the ditch, side extended along tunnel longitudinal direction is respectively equipped with in both sides, ditch, both sides is communicated with Central drain respectively by railway roadbed gutter, and the bottom surface in ditch, both sides is all lower than the end face of inverted arch packed layer.Can avoid forming longitudinal constuction joint between the bottom surface and the end face of inverted arch packed layer in ditch, both sides by this drainage system, eliminate lateral sulcus bottom leaky hidden danger.

Description

The drainage system of ditch, side, anti-tunnel bottom leaky
Technical field
The utility model relates to construction of tunnel guarded drainage construction technology, is specifically related to the drainage system of ditch, side, anti-tunnel bottom leaky.
Background technology
The bottom surface in the ditch, side in existing tunnel generally higher than or flush in the end face of inverted arch packed layer, because constructed and the own shrinkage of concrete etc. affects, between the bottom surface in ditch, side and the end face of inverted arch packed layer, easily define longitudinal constuction joint.After tunnel builds up, very easily there is percolating water phenomenon in the root in ditch, side, later regulation difficulty control greatly, for a long time without cease, security risk is high, economic and social benefits weight losses.
Therefore, be necessary to improve existing tunnel drainage system.
Summary of the invention
The purpose of this utility model is to provide the drainage system of ditch, side, a kind of anti-tunnel bottom leaky, can effectively avoid occurring longitudinal constuction joint between the bottom of trench in ditch, side and inverted arch packed layer end face, to eliminate lateral sulcus bottom leaky hidden danger.
In order to achieve the above object, the utility model provides the drainage system of ditch, side, a kind of anti-tunnel bottom leaky, comprise set gradually from tunnel base scar to road surface or orbital plane direction inverted arch preliminary bracing, inverted arch secondary lining, inverted arch packed layer and supercrust, the Central drain extended along tunnel longitudinal direction is provided with in inverted arch packed layer, the ditch, side extended along tunnel longitudinal direction is respectively equipped with in both sides, ditch, both sides is communicated with Central drain respectively by railway roadbed gutter, and its key is: the bottom surface in ditch, both sides is all lower than the end face of inverted arch packed layer.
Be interval with discharge pressure pipe in the below of Central drain along tunnel longitudinal direction, the upper end of described discharge pressure pipe is communicated with Central drain, and the lower end of discharge pressure pipe is successively through inverted arch packed layer, inverted arch secondary lining, inverted arch preliminary bracing being communicated with tunnel base scar.Tunnel Central drain is communicated with tunnel base scar by discharge pressure pipe, forms drainage channel.When lining concrete ponding behind to collect at the bottom of tunnel and produces hydraulic pressure, overstocked moisture district can be disposed in tunnel Central drain, thus efficiently solve inverted arch constuction joint seepage problem.
The upper end of described discharge pressure pipe is communicated with Central drain and stretches in Central drain, and the lower end of discharge pressure pipe passes perpendicularly through inverted arch packed layer, inverted arch secondary lining, inverted arch preliminary bracing being communicated with tunnel base scar successively.
The beneficial effects of the utility model are:
(1) the bottom surface absolute altitude in ditch, both sides in tunnel is reduced to below the end face of inverted arch packed layer, can effectively avoids occurring longitudinal constuction joint between the bottom of trench in ditch, side and inverted arch packed layer end face, to eliminate lateral sulcus bottom leaky hidden danger.
(2) in the below of Central drain, discharge pressure pipe is set along longitudinal direction interval, tunnel, tunnel Central drain is communicated with tunnel base scar, form drainage channel.When lining concrete ponding behind to collect at the bottom of tunnel and produces hydraulic pressure, overstocked moisture district can be disposed in tunnel Central drain, thus efficiently solve inverted arch constuction joint seepage problem.
(3) the utility model has the advantages such as little, easy and simple to handle, the required plant equipment of construction interference is simple and easy, cost input is low, effectively can solve the leakage problems of ditch, both sides, tunnel root.Control high economic cost, prestige cost and the high-level security risk of oozing leak stopping after decreasing tunnel operation, remarkable in economical benefits, social benefit is given prominence to, practical, has good popularization, using value, good development prospect.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is described in further detail.
The drainage system of ditch, side, anti-tunnel bottom leaky as shown in Figure 1, comprise the inverted arch preliminary bracing 2 set gradually to road surface or orbital plane 10 direction from tunnel base scar 1, inverted arch secondary lining 3, inverted arch packed layer 4 and supercrust 5, the Central drain 8 extended along tunnel longitudinal direction is provided with in inverted arch packed layer 4, the ditch, side 6 extended along tunnel longitudinal direction is respectively equipped with in the both sides of supercrust 5, ditch, both sides 6 is communicated with Central drain 8 respectively by railway roadbed gutter 7, railway roadbed gutter 7 is laterally located in inverted arch packed layer 4, one end of railway roadbed gutter 7 is communicated with the sidewall of Central drain 8, the other end of railway roadbed gutter 7 is upwards communicated with the sidewall in ditch, side 6 by elbow.The bottom surface 6a in ditch, both sides 6 is all lower than the end face 4a of inverted arch packed layer 4.
In inverted arch packed layer 4 work progress, behind unwrapping wire location, mounting edge mould concreting, the bottom surface 6a in ditch, both sides 6 is down to below the end face 4a of inverted arch packed layer 4, reduce and highly can refer to the rich water yield size in tunnel, but unsuitable too high, avoid between the bottom surface 6a and the end face 4a of inverted arch packed layer 4 in ditch, both sides 6, forming longitudinal constuction joint, to eliminate lateral sulcus root hidden leakage defect.
As shown in Figure 1, in the below of Central drain 8, discharge pressure pipe 9 is set along longitudinal direction interval, tunnel, the upper end of discharge pressure pipe 9 is communicated with Central drain 8 and stretches in Central drain 8, the lower end of discharge pressure pipe 9 passes perpendicularly through inverted arch packed layer 4, inverted arch secondary lining 3, inverted arch preliminary bracing 2 being communicated with tunnel base scar 1 successively, when lining concrete ponding behind to collect at the bottom of tunnel and produces hydraulic pressure, overstocked moisture district can be disposed in tunnel Central drain 8 by discharge pressure pipe 9, then is drained into outside tunnel by Central drain 8.
In inverted arch preliminary bracing 2, inverted arch secondary lining 3, inverted arch packed layer 4 work progress, the center line in tunnel to keep at a certain distance away a pre-buried discharge pressure pipe 9 along tunnel longitudinal direction, makes to form drainage channel between Central drain 8 and tunnel base scar 1.After discharge pressure pipe 9 is provided with, the mouth of pipe should to stretch in Central drain 8 and higher than the flowing water face in Central drain 8.Discharge pressure pipe 9 gradation connects the modular connection adopting corresponding model, and setting space is determined according to the rich water yield size in tunnel.
The utility model is applicable to general tunnel, is specially adapted to rich water tunnel.Be more than better embodiment of the present utility model, all do within spirit of the present utility model and principle any amendment, equivalent replace and improve all should be included within protection domain of the present utility model.

Claims (3)

1. the drainage system of ditch, side, anti-tunnel bottom leaky, comprise the inverted arch preliminary bracing (2) set gradually to road surface or orbital plane (10) direction from tunnel base scar (1), inverted arch secondary lining (3), inverted arch packed layer (4) and supercrust (5), the Central drain (8) extended along tunnel longitudinal direction is provided with in inverted arch packed layer (4), the ditch, side (6) extended along tunnel longitudinal direction is respectively equipped with in the both sides of supercrust (5), ditch, both sides (6) is communicated with Central drain (8) respectively by railway roadbed gutter (7), it is characterized in that: the bottom surface (6a) of ditch, both sides (6) is all lower than the end face (4a) of inverted arch packed layer (4).
2. the drainage system of ditch, side, anti-tunnel according to claim 1 bottom leaky, it is characterized in that: be interval with discharge pressure pipe (9) in the below of Central drain (8) along tunnel longitudinal direction, the upper end of described discharge pressure pipe (9) is communicated with Central drain (8), and the lower end of discharge pressure pipe (9) is successively through inverted arch packed layer (4), inverted arch secondary lining (3), inverted arch preliminary bracing (2) being communicated with tunnel base scar (1).
3. the drainage system of ditch, side, anti-tunnel according to claim 2 bottom leaky, it is characterized in that: the upper end of described discharge pressure pipe (9) is communicated with Central drain (8) and stretches in Central drain (8), the lower end of discharge pressure pipe (9) passes perpendicularly through inverted arch packed layer (4), inverted arch secondary lining (3), inverted arch preliminary bracing (2) being communicated with tunnel base scar (1) successively.
CN201420786529.6U 2014-12-11 2014-12-11 The drainage system of ditch, side, anti-tunnel bottom leaky Active CN204552818U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420786529.6U CN204552818U (en) 2014-12-11 2014-12-11 The drainage system of ditch, side, anti-tunnel bottom leaky

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420786529.6U CN204552818U (en) 2014-12-11 2014-12-11 The drainage system of ditch, side, anti-tunnel bottom leaky

Publications (1)

Publication Number Publication Date
CN204552818U true CN204552818U (en) 2015-08-12

Family

ID=53827945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420786529.6U Active CN204552818U (en) 2014-12-11 2014-12-11 The drainage system of ditch, side, anti-tunnel bottom leaky

Country Status (1)

Country Link
CN (1) CN204552818U (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105986836A (en) * 2016-06-14 2016-10-05 中铁隧道勘测设计院有限公司 Single-line railway tunnel substrate waterproof and drainage reinforcing system
CN106089297A (en) * 2016-07-29 2016-11-09 中铁工程设计咨询集团有限公司 Railway tunnel bottom structure drainage device and method to set up thereof
CN107630706A (en) * 2017-10-24 2018-01-26 中交第二航务工程局有限公司 A kind of tunnel bottom structure and construction method for eliminating highland nip tunnel inverted arch protuberance
CN107905811A (en) * 2017-12-27 2018-04-13 中铁二院工程集团有限责任公司 The hollow longeron of foundation carries domes without the lining cutting of inverted arch type and its drainage system
CN108286443A (en) * 2018-02-11 2018-07-17 中铁二院工程集团有限责任公司 The prevention and control device and its construction method of a kind of non-fragment orbit tunnel bottom deformation
CN108331593A (en) * 2018-02-11 2018-07-27 中铁二院工程集团有限责任公司 A kind of cavity type preventing mean and construction method for the deformation of non-fragment orbit tunnel bottom
CN108533315A (en) * 2018-04-17 2018-09-14 河南省交通规划设计研究院股份有限公司 A kind of percolating water ejectment structure and construction method for wall in tunnel, tunnel
CN108798778A (en) * 2018-07-23 2018-11-13 中铁十九局集团第六工程有限公司 The levelling layer sewerage system of the reserved filling in tunnel and its construction method
CN109578018A (en) * 2019-01-22 2019-04-05 青岛理工大学 A kind of tunnel inverted arch structure of anti-pucking
CN111535855A (en) * 2020-03-16 2020-08-14 中铁西南科学研究院有限公司 Cooperative drainage system and drainage method for ditches in railway double-track tunnel
CN112727543A (en) * 2021-01-25 2021-04-30 中南大学 Tunnel intelligent multistage depressurization drainage system and use method thereof

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105986836B (en) * 2016-06-14 2018-12-14 中铁隧道勘测设计院有限公司 A kind of single-track railway tunnel substrate guarded drainage strengthen the system
CN105986836A (en) * 2016-06-14 2016-10-05 中铁隧道勘测设计院有限公司 Single-line railway tunnel substrate waterproof and drainage reinforcing system
CN106089297A (en) * 2016-07-29 2016-11-09 中铁工程设计咨询集团有限公司 Railway tunnel bottom structure drainage device and method to set up thereof
CN107630706A (en) * 2017-10-24 2018-01-26 中交第二航务工程局有限公司 A kind of tunnel bottom structure and construction method for eliminating highland nip tunnel inverted arch protuberance
CN107630706B (en) * 2017-10-24 2023-05-26 中交第二航务工程局有限公司 Tunnel bottom structure for eliminating tunnel inverted arch bulge in high-earth-pressure area and construction method
CN107905811A (en) * 2017-12-27 2018-04-13 中铁二院工程集团有限责任公司 The hollow longeron of foundation carries domes without the lining cutting of inverted arch type and its drainage system
CN107905811B (en) * 2017-12-27 2024-01-19 中铁二院工程集团有限责任公司 Inverted arch-free lining of foundation hollow longitudinal beam bearing arch structure
CN108286443A (en) * 2018-02-11 2018-07-17 中铁二院工程集团有限责任公司 The prevention and control device and its construction method of a kind of non-fragment orbit tunnel bottom deformation
CN108286443B (en) * 2018-02-11 2019-10-11 中铁二院工程集团有限责任公司 A kind of construction method of the prevention and control device of non-fragment orbit tunnel bottom deformation
CN108331593B (en) * 2018-02-11 2019-11-05 中铁二院工程集团有限责任公司 A kind of construction method of the cavity type preventing mean for the deformation of non-fragment orbit tunnel bottom
CN108331593A (en) * 2018-02-11 2018-07-27 中铁二院工程集团有限责任公司 A kind of cavity type preventing mean and construction method for the deformation of non-fragment orbit tunnel bottom
CN108533315A (en) * 2018-04-17 2018-09-14 河南省交通规划设计研究院股份有限公司 A kind of percolating water ejectment structure and construction method for wall in tunnel, tunnel
CN108798778A (en) * 2018-07-23 2018-11-13 中铁十九局集团第六工程有限公司 The levelling layer sewerage system of the reserved filling in tunnel and its construction method
CN109578018A (en) * 2019-01-22 2019-04-05 青岛理工大学 A kind of tunnel inverted arch structure of anti-pucking
CN111535855A (en) * 2020-03-16 2020-08-14 中铁西南科学研究院有限公司 Cooperative drainage system and drainage method for ditches in railway double-track tunnel
CN111535855B (en) * 2020-03-16 2021-09-28 中铁西南科学研究院有限公司 Cooperative drainage system and drainage method for ditches in railway double-track tunnel
CN112727543A (en) * 2021-01-25 2021-04-30 中南大学 Tunnel intelligent multistage depressurization drainage system and use method thereof
CN112727543B (en) * 2021-01-25 2022-05-10 中南大学 Tunnel intelligent multistage depressurization drainage system and use method

Similar Documents

Publication Publication Date Title
CN204552818U (en) The drainage system of ditch, side, anti-tunnel bottom leaky
CN204357484U (en) The drainage system of anti-tunnel invert constuction joint infiltration
CN204357485U (en) The drainage system of anti-tunnel double-lining behind ponding crossfire
CN203742623U (en) Water-pressure-resistant composite structure for tunnel
CN206386134U (en) A kind of Underground Subway Station guarded drainage construction
CN204266220U (en) A kind of plugging device of precipitation well in foundation pit
CN103410175B (en) A kind of water seepage control construction method for karst water-rich geological underground structure waterproof construction
CN205711788U (en) A kind of underground piping protection is contained
WO2012077941A3 (en) Drain system of shield tunnel lining and method for constructing shield tunnel using same
CN106869946B (en) Make bottom frozen construction method in a kind of sand-pebble layer tunneling subway station
CN204899980U (en) Ballastless track basement drainage system
CN202416263U (en) Concrete faced rockfill dam compounded with gravity dam
CN105350581A (en) Advanced sealing structure for basement top slab settlement post-cast strips
CN104846935B (en) Head-tank treating seepage remodeling method
CN203855990U (en) High-drawdown tube well plugging structure
CN103806412B (en) A kind of expansion joint of pool leaks repair structure
CN202788739U (en) High pressure water inrush point non-pressure plugging structure
CN204941551U (en) A kind of subway station of Curve Pipe Jacking supporting and protection structure enlarging shield-tunneling construction
CN204174496U (en) A kind of novel town road structure
CN204212180U (en) A kind of reinforcing cage for basement plugging dewatering well
CN207672616U (en) A kind of outdoor cable penetration pipe is passed by one's way laying structure
CN204402513U (en) A kind of device solving the infiltration of underground chamber lining cutting surface and leak
CN203978442U (en) A kind of public iron is built submerged tunnel jointly
CN203321586U (en) Multifunctional prefabricated side type ditch in road tunnel for clean-up and separation of sewage and maintenance
CN204532379U (en) The pre-buried gutter structure of subway sectional tunnel waste water pump house

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant