CN202788739U - High pressure water inrush point non-pressure plugging structure - Google Patents

High pressure water inrush point non-pressure plugging structure Download PDF

Info

Publication number
CN202788739U
CN202788739U CN201220329243.6U CN201220329243U CN202788739U CN 202788739 U CN202788739 U CN 202788739U CN 201220329243 U CN201220329243 U CN 201220329243U CN 202788739 U CN202788739 U CN 202788739U
Authority
CN
China
Prior art keywords
wall
water
water inrush
pressure
pressure water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201220329243.6U
Other languages
Chinese (zh)
Inventor
杨平
郭恒斌
石立军
王青振
徐新启
徐春生
王玉
许德新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BUCUN COAL MINE OF ZIBO MINING GROUP Co Ltd
Original Assignee
BUCUN COAL MINE OF ZIBO MINING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BUCUN COAL MINE OF ZIBO MINING GROUP Co Ltd filed Critical BUCUN COAL MINE OF ZIBO MINING GROUP Co Ltd
Priority to CN201220329243.6U priority Critical patent/CN202788739U/en
Application granted granted Critical
Publication of CN202788739U publication Critical patent/CN202788739U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a high pressure water inrush point non-pressure plugging structure and belongs to the technical field of coal mining equipment. The high pressure water inrush point non-pressure plugging structure is used for coal mine lower baseboard confined water water inrush management and comprises a retention wall (2) and a slip stop wall (1). The high pressure water inrush point non-pressure plugging structure is characterized in that the retention wall (2) and the slip stop wall (1) are respectively wall bodies and are respectively arranged on the same side of a high pressure water inrush point (6). The width and the height of the slip stop wall (1) are no less than that of a roadway. The left face, the right face and the lower face of the retention wall (2) are respectively connected with the roadway. The upper face of the retention wall (2) approaches a back (7) as far as possible. A slip casting pipe (3) and water drain pipe (4) are arranged on the lower portion of the slip stop wall (1) in a buried mode. According to the high pressure water inrush point non-pressure plugging structure, a non-pressure slip filling plugging technique is adopted, and therefore the high pressure water inrush point non-pressure plugging structure has the advantages of being low in cost, simple in construction process, easy in slip casting and good in plugging effect.

Description

高压突水点无压封堵结构Pressureless plugging structure for high pressure water inrush point

技术领域 technical field

高压突水点无压封堵结构,属于采煤设备技术领域,用于煤矿井下底板承压水突水治理中。  The utility model relates to a pressureless plugging structure for a high-pressure water inrush point, which belongs to the technical field of coal mining equipment and is used for controlling water inrush of pressurized water in underground floors of coal mines. the

背景技术 Background technique

现在煤矿井下底板高压突水点封堵技术主要有动水打钻封堵和建水闸墙静水高压封堵。动水打钻注浆:施工工期长,如遇到底板破碎地段施工钻孔难度大,注浆容易使底板发生二次破坏;建水闸墙静水高压注浆:施工工期短,费用高,如遇到底板破碎地段建水闸墙难度大,高压注浆容易使底板发生二次破坏。  At present, the plugging technologies for high-pressure water inrush points on the underground floor of coal mines mainly include dynamic water drilling and sealing and hydrostatic high-pressure sealing of sluice walls. Dynamic water drilling and grouting: The construction period is long. If the floor is broken, it is difficult to drill holes, and the grouting is likely to cause secondary damage to the floor. The construction of the sluice wall. It is very difficult to build a sluice wall in the area where the floor is broken, and high-pressure grouting is likely to cause secondary damage to the floor. the

实用新型内容 Utility model content

本实用新型要解决的技术问题是:克服现有技术的不足,提供一种工期短,费用低,难度小的一种高压突水点无压封堵结构。  The technical problem to be solved by the utility model is to overcome the deficiencies of the prior art and provide a pressureless plugging structure for high-pressure water inrush points with short construction period, low cost and low difficulty. the

本实用新型解决其技术问题所采用的技术方案是:该高压突水点无压封堵结构,包括挡水墙和止浆墙,其特征在于:所述在高压突水点的一侧依次设置挡水墙和止浆墙,止浆墙在挡水墙的外侧;止浆墙的宽度和高度大于等于巷道的宽度和高度;挡水墙的左、右两侧面分别连接两巷道侧壁,挡水墙底面与巷道底板联接,挡水墙上沿靠近巷道顶板;在止浆墙的下部埋设有注浆管,注浆管的上方埋设有穿过止浆墙和挡水墙的泄水管。  The technical scheme adopted by the utility model to solve the technical problem is: the pressureless sealing structure of the high-pressure water inrush point, including a water retaining wall and a slurry wall, and is characterized in that: the said one side of the high-pressure water inrush point is arranged The water retaining wall and the slurry wall, the slurry wall is on the outside of the water retaining wall; the width and height of the slurry wall are greater than or equal to the width and height of the roadway; the left and right sides of the water retaining wall are respectively connected to the side walls of the two roadways. The bottom surface of the water wall is connected with the bottom plate of the roadway, and the edge of the retaining wall is close to the roof of the roadway; a grouting pipe is embedded in the lower part of the grouting wall, and a drain pipe passing through the grouting wall and the water retaining wall is buried above the grouting pipe. the

所述的泄水管设有2~4根,分别埋设在止浆墙和挡水墙的不同高度上,设在最上方的泄水管的泄水口在高压突水点的正上方。所述的泄水管可根据实际情况增加数量。  There are 2 to 4 drain pipes, which are respectively buried at different heights of the slurry wall and the water retaining wall, and the outlet of the uppermost drain pipe is directly above the high-pressure water inrush point. Described drainpipe can increase quantity according to actual conditions. the

所述的挡水墙与止浆墙为混凝土浇筑而成。  The water retaining wall and the grouting wall are poured concrete. the

所述的止浆墙与挡水墙之间注有水泥浆。  Cement grout is injected between the grout stop wall and the retaining wall. the

本实用新型高压突水点无压封堵结构采用高压突水无压封堵技术,避免了底板破坏建水闸墙难度大,高压注浆使底板发生二次破坏的现象,提高注浆堵水成功率,防止底板再次受到破坏。  The high-pressure water inrush point pressureless sealing structure of the utility model adopts the high-pressure water inrush non-pressure sealing technology, which avoids the difficulty of building the sluice wall due to the damage of the bottom plate, and the phenomenon of secondary damage to the bottom plate caused by high-pressure grouting, and improves the success of grouting water blocking rate to prevent the bottom plate from being damaged again. the

与现有技术相比,本实用新型的高压突水点无压封堵结构所具有的有益效果是:高压突水点无压封堵结构应用于煤矿井下底板承压水突水治理中,杜绝了因底板破碎无法实现打钻高压注浆或建水闸墙高压注浆封堵的情况,提高了底板破碎地段高压突水注浆封堵效果。高压突水点无压封堵技术替代了传统的底板打钻注浆和建水闸墙高压注浆封堵技术,本实用新型高压突水点无压封堵结构采用无压充填注浆封堵技术,具有费用低、施工工艺简单、注浆容易、封堵效果好的特点。  Compared with the prior art, the beneficial effect of the pressureless plugging structure of the high-pressure water inrush point of the utility model is that the pressureless plugging structure of the high-pressure water inrush point is applied to the treatment of the pressurized water inrush of the underground floor of the coal mine, preventing It solves the situation that high-pressure grouting for drilling or high-pressure grouting for building sluice walls cannot be realized due to the broken floor, and improves the sealing effect of high-pressure water inrush grouting in the section where the floor is broken. The pressureless sealing technology of high-pressure water inrush points replaces the traditional bottom plate drilling and grouting and high-pressure grouting sealing technology for building sluice walls. The utility model adopts pressureless filling and grouting sealing technology , has the characteristics of low cost, simple construction process, easy grouting and good plugging effect. the

附图说明 Description of drawings

图1是本实用新型高压突水点无压封堵结构俯视结构示意图。  Fig. 1 is a top view structural diagram of the high-pressure water inrush point non-pressure plugging structure of the utility model. the

图2是本实用新型高压突水点无压封堵结构A-A剖视结构示意图。  Fig. 2 is a schematic diagram of the cross-sectional structure A-A of the non-pressure plugging structure of the high-pressure water inrush point of the present invention. the

其中:1、止浆墙  2、挡水墙  3、注浆管  4、泄水管  5、巷道侧壁  6、高压突水点  7、巷道顶板  8、巷道底板。  Among them: 1. Grout stop wall 2. Water retaining wall 3. Grouting pipe 4. Drain pipe 5. Roadway side wall 6. High pressure water inrush point 7. Roadway roof 8. Roadway floor. the

图1~2是本实用新型高压突水点无压封堵结构的最佳实施例,下面结合附图1~2对本实用新型做进一步说明。  Fig. 1-2 is the best embodiment of the pressureless plugging structure of the high-pressure water inrush point of the utility model, and the utility model will be further described below in conjunction with the accompanying drawings 1-2. the

具体实施方式 Detailed ways

参照附图1~2:本实用新型高压突水点无压封堵结构,包括止浆墙1和挡水墙2。所述的挡水墙2和止浆墙1均为立方形的墙体,设在高压突水点6的同侧,止浆墙1又在挡水墙2的外侧。止浆墙1的宽度和高度大于等于巷道的宽度和高度,能对整条巷道实现密封。挡水墙2的左右下三面分别连接两巷道侧壁5和巷道底板8,上边靠近巷道顶板7。止浆墙1与挡水墙2之间注有水泥浆。在止浆墙1的下部埋设有注浆管3,再往上埋设有穿过止浆墙1和挡水墙2的泄水管4,使高压突水点无压封堵墙内侧高压突水点6突出的水能够导出。所述最上方的泄水管的泄水口在高压突水点的正上方。所述的挡水墙2与止浆墙1为混凝土浇筑而成。  Referring to accompanying drawings 1-2: the pressureless sealing structure of the high-pressure water inrush point of the utility model includes a grout-stopping wall 1 and a water-retaining wall 2 . The water-retaining wall 2 and the grout-stop wall 1 are both cubic walls, which are located on the same side of the high-pressure water inrush point 6, and the grout-stop wall 1 is outside the water-retaining wall 2. The width and height of the grout-stop wall 1 are greater than or equal to the width and height of the roadway, and can seal the whole roadway. The left, right and lower sides of the water retaining wall 2 are respectively connected to the two roadway side walls 5 and the roadway floor 8, and the upper side is close to the roadway roof 7. Cement slurry is injected between the slurry wall 1 and the retaining wall 2 . A grouting pipe 3 is buried in the lower part of the grout-stop wall 1, and a drain pipe 4 passing through the grout-stop wall 1 and the water retaining wall 2 is buried upward, so that the high-pressure water inrush point is blocked without pressure at the high-pressure water inrush point inside the wall 6 protruding water can be exported. The discharge port of the uppermost discharge pipe is directly above the high-pressure water inrush point. The water retaining wall 2 and the grout stop wall 1 are poured concrete. the

本实用新型的具体实施方式:根据高压突水点周围的地质情况,使用混凝土浇筑一道止浆墙1,在高压突水点6外再建一道挡水墙2,墙高尽量接近巷道顶板7,并保证挡水墙2与止浆墙1之间无水即挡水墙不能漏水,在挡水墙2和止浆墙1里埋设泄水管4(兼注浆管),让水顺泄水管4流至止浆墙1外。从止浆墙1至高压突水点6对应的巷道顶板7埋设泄水管4(兼注浆管),根据现场实际情况埋设注浆管3(泄水管)条数。止浆墙1施工完毕后可进行连续注浆,注浆顺序为:先注止浆墙1最下方注浆管路,保证挡水墙2里的泄水管4能够正常泄水,待水泥浆液超过挡水墙2从泄水管4流出时,关闭注浆阀。改为用泄水管4进行注浆,并保证出水点顶部的泄水管4能正常泄水,待顶部的泄水管4有浆液流出时,关闭注浆阀。改为用注浆管3进行注浆。达到设计要求时,停止注浆。  Specific implementation of the utility model: according to the geological conditions around the high-pressure water inrush point, use concrete to pour a slurry wall 1, build a water-retaining wall 2 outside the high-pressure water inrush point 6, the wall height is as close as possible to the roadway roof 7, and Ensure that there is no water between the water retaining wall 2 and the grout stop wall 1, that is, the water retaining wall cannot leak, and the drain pipe 4 (also a grouting pipe) is buried in the water retaining wall 2 and the grout stop wall 1, so that the water flows along the drain pipe 4 To the outside of the slurry wall 1. From the grout stop wall 1 to the roadway roof 7 corresponding to the high-pressure water inrush point 6, the drain pipe 4 (and grouting pipe) is buried, and the number of grouting pipes 3 (drainage pipe) is buried according to the actual situation on site. Continuous grouting can be carried out after the construction of the grout stop wall 1 is completed. The grouting sequence is as follows: first inject the grouting pipeline at the bottom of the grout stop wall 1 to ensure that the drain pipe 4 in the retaining wall 2 can discharge water normally. When the retaining wall 2 flows out from the drain pipe 4, close the grouting valve. Carry out grouting with drainpipe 4 instead, and guarantee that the drainpipe 4 at the top of the outlet point can drain normally, and when the drainpipe 4 at the top has grout to flow out, close the grouting valve. Carry out grouting with grouting pipe 3 instead. When the design requirements are met, stop grouting. the

以上所述,仅是本实用新型的较佳实施例而已,并非是对本实用新型作其它形式的限制,任何熟悉本专业的技术人员可能利用上述揭示的技术内容加以变更或改型为等同变化的等效实施例。但是凡是未脱离本实用新型技术方案内容,依据本实用新型的技术实质对以上实施例所作的任何简单修改、等同变化与改型,仍属于本实用新型技术方案的保护范围。  The above is only a preferred embodiment of the utility model, and is not intended to limit the utility model in other forms. Any skilled person who is familiar with this profession may use the technical content disclosed above to change or remodel it into an equivalent change. Equivalent embodiment. However, any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the present utility model without departing from the content of the technical solution of the utility model still belong to the protection scope of the technical solution of the utility model. the

Claims (4)

1.高压突水点无压封堵结构,包括挡水墙(2)和止浆墙(1),其特征在于:所述在高压突水点(6)的一侧依次设置挡水墙(2)和止浆墙(1),止浆墙(1)在挡水墙(2)的外侧;止浆墙(1)的宽度和高度大于等于巷道的宽度和高度;挡水墙(2)的左、右两侧面分别连接两巷道侧壁(5),挡水墙(2)底面与巷道底板(8)联接,挡水墙(2)上沿靠近巷道顶板(7);在止浆墙(1)的下部埋设有注浆管(3),注浆管(3)的上方埋设有穿过止浆墙(1)和挡水墙(2)的泄水管(4)。 1. The pressureless sealing structure of the high-pressure water inrush point, including the water retaining wall (2) and the slurry wall (1), characterized in that: the water retaining wall ( 2) and the grout-stop wall (1), the grout-stop wall (1) is on the outside of the water-retaining wall (2); the width and height of the grout-stop wall (1) are greater than or equal to the width and height of the roadway; the water-retaining wall (2) The left and right side surfaces of the water retaining wall (2) are connected to the roadway side walls (5) respectively, the bottom surface of the water retaining wall (2) is connected with the roadway floor (8), and the upper edge of the water retaining wall (2) is close to the roadway roof (7); A grouting pipe (3) is embedded in the lower part of (1), and a drain pipe (4) passing through the grout stop wall (1) and the water retaining wall (2) is buried above the grouting pipe (3). 2.根据权利要求1所述的高压突水点无压封堵结构,其特征在于:所述的泄水管(4)设有2~4根,分别埋设在止浆墙(1)和挡水墙(2)的不同高度上,设在最上方的泄水管(4)的泄水口在高压突水点(6)的正上方。 2. The non-pressure sealing structure of high-pressure water inrush point according to claim 1, characterized in that: said drain pipes (4) are provided with 2~4 pieces, which are buried in the grout-stop wall (1) and the water-retaining wall respectively. On the different heights of the wall (2), the discharge port of the topmost discharge pipe (4) is directly above the high-pressure water inrush point (6). 3.根据权利要求1所述的高压突水点无压封堵结构,其特征在于:所述的挡水墙(2)与止浆墙(1)为混凝土浇筑而成。 3. The non-pressure sealing structure for high-pressure water inrush points according to claim 1, characterized in that: the water retaining wall (2) and the grout-stop wall (1) are made of concrete. 4.根据权利要求1所述的高压突水点无压封堵结构,其特征在于:所述的止浆墙(1)与挡水墙(2)之间注有水泥浆。 4. The pressureless sealing structure for high-pressure water inrush points according to claim 1, characterized in that: grout is injected between the grout-stop wall (1) and the water-retaining wall (2).
CN201220329243.6U 2012-07-09 2012-07-09 High pressure water inrush point non-pressure plugging structure Expired - Fee Related CN202788739U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201220329243.6U CN202788739U (en) 2012-07-09 2012-07-09 High pressure water inrush point non-pressure plugging structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201220329243.6U CN202788739U (en) 2012-07-09 2012-07-09 High pressure water inrush point non-pressure plugging structure

Publications (1)

Publication Number Publication Date
CN202788739U true CN202788739U (en) 2013-03-13

Family

ID=47816015

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201220329243.6U Expired - Fee Related CN202788739U (en) 2012-07-09 2012-07-09 High pressure water inrush point non-pressure plugging structure

Country Status (1)

Country Link
CN (1) CN202788739U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104234750A (en) * 2014-06-23 2014-12-24 王经明 Rapid self-built movable sluice wall of mine and construction method of rapid self-built movable sluice wall
CN104790904A (en) * 2014-12-29 2015-07-22 神华集团有限责任公司 High-pressure water gushing-out drill hole sealing device and method
CN106948846A (en) * 2017-05-10 2017-07-14 贵阳市城市轨道交通有限公司 Shallow embedding Karst Tunnel gushing water method of disposal
CN104790904B (en) * 2014-12-29 2018-02-09 神华集团有限责任公司 A kind of hole sealing device and method for sealing of the drilling of high pressure gushing water
CN108252729A (en) * 2018-01-30 2018-07-06 临沂矿业集团有限责任公司 A kind of prevention high pressure projective water point is without press seal wall
CN114737915A (en) * 2022-04-19 2022-07-12 安徽理工大学 Deep mining water inrush rock burst prevention and control device
CN119353046A (en) * 2024-12-24 2025-01-24 河南省豫西煤田地质勘察有限公司 Mine water burst blocking device and blocking method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104234750A (en) * 2014-06-23 2014-12-24 王经明 Rapid self-built movable sluice wall of mine and construction method of rapid self-built movable sluice wall
CN104790904A (en) * 2014-12-29 2015-07-22 神华集团有限责任公司 High-pressure water gushing-out drill hole sealing device and method
CN104790904B (en) * 2014-12-29 2018-02-09 神华集团有限责任公司 A kind of hole sealing device and method for sealing of the drilling of high pressure gushing water
CN106948846A (en) * 2017-05-10 2017-07-14 贵阳市城市轨道交通有限公司 Shallow embedding Karst Tunnel gushing water method of disposal
CN106948846B (en) * 2017-05-10 2019-07-09 贵阳市城市轨道交通有限公司 Shallow embedding Karst Tunnel gushing water method of disposal
CN108252729A (en) * 2018-01-30 2018-07-06 临沂矿业集团有限责任公司 A kind of prevention high pressure projective water point is without press seal wall
CN114737915A (en) * 2022-04-19 2022-07-12 安徽理工大学 Deep mining water inrush rock burst prevention and control device
CN114737915B (en) * 2022-04-19 2024-02-09 安徽理工大学 Deep mining water burst rock burst control device
CN119353046A (en) * 2024-12-24 2025-01-24 河南省豫西煤田地质勘察有限公司 Mine water burst blocking device and blocking method
CN119353046B (en) * 2024-12-24 2025-05-09 河南省豫西煤田地质勘察有限公司 Mine water burst blocking device and blocking method

Similar Documents

Publication Publication Date Title
CN204357484U (en) The drainage system of anti-tunnel invert constuction joint infiltration
CN204552818U (en) The drainage system of ditch, side, anti-tunnel bottom leaky
CN202788739U (en) High pressure water inrush point non-pressure plugging structure
CN103195477B (en) Gravity drainage system for underground roadway high-pressure water inrush
CN109488371B (en) Waterproof system of full-enclosed waterproof station and dynamic setting and quantity-limiting drainage method
CN102635402A (en) Siphon drainage method for tunnel wall water seepage disposal by using dipping borehole
CN102108869B (en) Grout stop pad construction method for kilometer vertical shaft grouting for water control
CN207597428U (en) Prefabricated piping lane is connected waterproof construction with cast-in-place piping lane
CN205422815U (en) Big flood underground mine tunnel waterwall
CN107859064A (en) A kind of prefabricated piping lane is connected waterproof construction and construction method with cast-in-place piping lane
CN205976019U (en) Wicresoft prevents water blocking drain structure
CN201125391Y (en) A basement waterproof and hydrophobic structure
CN105484204A (en) Stone masonry dam or concrete dam sealing anti-seepage reinforcement structure and construction method thereof
CN115787693A (en) Water stopping method for water gushing in deep foundation pit under riverside slow-dip interbed
CN103821114B (en) A kind of reservoir culvert method for blocking discarded under seepage pressure effect
CN204212168U (en) Dam water retaining structure for jointly building dam by utilizing karst cave
CN203296026U (en) Air exhausting device for locked and plugged diversion tunnel
CN110144918A (en) Construction method of anti-seepage and plugging of underground building dewatering well
CN206554042U (en) A kind of lining waterproof structure of seepage tunnel
CN104712145A (en) Grouting method for middle embedded grouting water stop belt
CN209129631U (en) The wall for grouting speedily carried out rescue work for Water-rich deposit tunnel gushing water
CN207194952U (en) A kind of flood mine working bottom plate is harnessed the river structure
CN210113318U (en) Foundation ditch basement gushes water and gushes sand plugging device
CN207673370U (en) A kind of existing tunnel road surface drainage modernization system
CN203374309U (en) Inverted truncated cone type large hydraulic pressure mine waterproof gate chamber

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130313

Termination date: 20130709