CN206386134U - A kind of Underground Subway Station guarded drainage construction - Google Patents

A kind of Underground Subway Station guarded drainage construction Download PDF

Info

Publication number
CN206386134U
CN206386134U CN201621361650.XU CN201621361650U CN206386134U CN 206386134 U CN206386134 U CN 206386134U CN 201621361650 U CN201621361650 U CN 201621361650U CN 206386134 U CN206386134 U CN 206386134U
Authority
CN
China
Prior art keywords
arch wall
bottom plate
drainage system
drainage
subway station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621361650.XU
Other languages
Chinese (zh)
Inventor
史宣陶
罗世培
徐亮
周明亮
喻波
苟明中
张建祥
朱宏海
柴家远
陈军
林刚
何旭苏
李辉
岳楹沁
徐搴
彭健海
陈思阳
李科志
金乃麒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201621361650.XU priority Critical patent/CN206386134U/en
Application granted granted Critical
Publication of CN206386134U publication Critical patent/CN206386134U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

A kind of Underground Subway Station guarded drainage construction, so that construction investment is greatly reduced on the premise of tunnel water proofing requirement is met.Including arch wall part and bottom parts, the arch wall part is the composite lining structure being made up of arch wall preliminary bracing and arch wall secondary lining, and bottom parts are straight tunnel floor, and the lower section of straight tunnel floor sets bottom cushion.Arch wall drainage system is set between the arch wall preliminary bracing, arch wall secondary lining, bottom plate drainage system is set between straight tunnel floor and bottom cushion, and arch wall drainage system, bottom plate drainage system are connected with the gutter of tunnel both sides.

Description

A kind of Underground Subway Station guarded drainage construction
Technical field
The utility model is related to Tunnel Engineering, more particularly to a kind of Underground Subway Station guarded drainage construction.
Background technology
Cause pipeline to move to evade bright, lid excavation construction to change, afforest migration and the problem such as traffic congestion, it is Chongqing, Qingdao, big Main structure of subway station is placed in by the shallow city of the urban district such as company, Xiamen buried depth of bedrock substantially by appropriately pressing down rail level absolute altitude In ground consisting of hard rock, using shallow mining method.
Underground Subway Station tunnel structure typically by preliminary bracing, secondary lining and is arranged at preliminary bracing and secondary lining Waterproof layer or separation layer composition between block.Because waterproofing for subway station grade is one-level, structure does not allow infiltration and body structure surface Also should be without wet stain, therefore usual subway station is set complete by anti-aqueous mode consideration is wrapped entirely that is, between supporting in the early stage and two lining cutting Ring waterproof layer, all external loads such as water, soil pressures whole during use are born by secondary lining.But underground water in lithostratigraphy Generally Bedrock Crevice Water, though water is less, head is higher, according to anti-aqueous mode is wrapped entirely, need to set thicker secondary lining Build and inverted arch structure, while structure bears high hydraulic pressure for a long time easily triggers seepage in construction joint, deformation joint, therefore it is contemplated that adopt With " anti-row's combination " water-proof system.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of Underground Subway Station guarded drainage construction, to meet Construction investment is greatly reduced on the premise of tunnel water proofing requirement.
The technical scheme that the utility model solution above-mentioned technical problem is used is as follows:
A kind of Underground Subway Station guarded drainage construction of the utility model, including arch wall part and bottom parts, it is characterized in that: The arch wall part is the composite lining structure being made up of arch wall preliminary bracing and arch wall secondary lining, and bottom parts are straight Tunnel floor, the lower section of straight tunnel floor sets bottom cushion;Set between the arch wall preliminary bracing, arch wall secondary lining Arch wall drainage system, sets bottom plate drainage system, arch wall drainage system, bottom plate draining between straight tunnel floor and bottom cushion System is connected with the gutter of tunnel both sides.
The beneficial effects of the utility model are, using " anti-row's combination " water-proof system, to meet subway station one-level waterproof It is required that on the premise of, it can not only reduce secondary lining thickness, cancel inverted arch structure, substantially reduce construction investment, and construction peace Entirely, it is easy for installation.
Brief description of the drawings
This specification includes following four width accompanying drawing:
Fig. 1 is a kind of Underground Subway Station guarded drainage construction standard cross-section figure of the utility model;
Fig. 2 is a kind of Underground Subway Station guarded drainage construction bottom plate discharge pipe line plane outspread drawing of the utility model;
Fig. 3 is a kind of Underground Subway Station guarded drainage construction arch wall guarded drainage layer plane expanded view of the utility model;
Component name and corresponding mark are shown in figure:Arch wall preliminary bracing 11, arch wall secondary lining 12, straight tunnel Bottom plate 13, bottom cushion 14, arch wall splash guard 21, arch wall drain bar 22, foundation longitudinal drainage pipe 23, foundation transverse drain 24th, gutter 25, bottom plate transverse drain 26, bottom plate longitudinal drainage pipe 27, loaded filter 31.
Embodiment
Below in conjunction with accompanying drawing, the utility model is described in further detail.
1. reference picture 1, Fig. 2 and Fig. 3, a kind of Underground Subway Station guarded drainage construction of the utility model include arch wall part with Bottom parts, the arch wall part is the composite lining structure being made up of arch wall preliminary bracing 11 and arch wall secondary lining 12, Bottom parts are straight tunnel floor 13, and the lower section of straight tunnel floor 13 sets bottom cushion 14.The arch wall preliminary bracing The 11st, arch wall drainage system is set between arch wall secondary lining 12, bottom plate is set between straight tunnel floor 13 and bottom cushion 14 Drainage system, arch wall drainage system, bottom plate drainage system are connected with the gutter 25 of tunnel both sides.
Using " anti-row's combination " water-proof system, on the premise of subway station one-level waterproof requirement is met, it can not only reduce Secondary lining thickness, cancel inverted arch structure, substantially reduce construction investment, and it is construction safety, easy for installation.
Reference picture 1, Fig. 2 and Fig. 3, arch wall drainage system include arch wall splash guard 21, arch wall drain bar 22 and foundation longitudinal direction Drainpipe 23.Arch wall splash guard 21 is arranged on the inner side of arch wall drain bar 22, is laid along arch wall part loopful.Arch wall drain bar 22 is set Put between arch wall preliminary bracing 11 and arch wall splash guard 21, it is longitudinally spaced to lay.Foundation longitudinal drainage pipe 23 is set AT STATION Both sides foundation, in reverse V-shaped, foundation transverse water drain pipe 24 is set in the minimum point of foundation longitudinal drainage pipe 23, foundation laterally sluices Gutter 25 is led in the one end of pipe 24.
Reference picture 1, Fig. 2 and bottom plate drainage system described in Fig. 3 include bottom plate longitudinal drainage pipe 27 and bottom plate transverse drain 26, bottom plate transverse drain 26 is connected with bottom plate longitudinal drainage pipe 27 in infall, and bottom plate transverse drain 26 is set in reverse V-shaped Put, the gutter 25 of tunnel both sides is led in its outside.
Reference picture 1, the underground water of station arch wall part passes sequentially through arch wall drain bar 22, foundation longitudinal drainage pipe 23 and horizontal stroke Gutter 25 is discharged to foundation transverse water drain pipe 24.Underground water is horizontal by bottom plate longitudinal drainage pipe 27 and bottom plate below the bottom plate of station Drainpipe 26 is discharged to gutter 25.Both sides gutter 25 is connected with station waste water pump house, is most discharged to municipal pipe through waste water pump room afterwards Net.
A kind of general principle of Underground Subway Station guarded drainage construction of the utility model that simply explains through diagrams described above And way, it is not intended to the utility model being confined in shown and described specific practice and parameter area, thus it is every all The corresponding modification that may be utilized and equivalent, belong to the apllied the scope of the claims of the utility model.

Claims (3)

1. a kind of Underground Subway Station guarded drainage construction, including arch wall part and bottom parts, it is characterized in that:The arch wall part For the composite lining structure being made up of arch wall preliminary bracing (11) and arch wall secondary lining (12), bottom parts are straight tunnel Bottom plate (13), the lower section of straight tunnel floor (13) sets bottom cushion (14);The arch wall preliminary bracing (11), arch wall are secondary Setting arch wall drainage system between lining cutting (12), bottom plate drainage system between straight tunnel floor (13) and bottom cushion (14), Arch wall drainage system, bottom plate drainage system are connected with the gutter (25) of tunnel both sides.
2. a kind of Underground Subway Station guarded drainage construction as claimed in claim 1, it is characterized in that:Arch wall drainage system includes arch Wall splash guard (21), arch wall drain bar (22) and foundation longitudinal drainage pipe (23);Arch wall splash guard (21) is arranged on arch wall draining On the inside of plate (22), laid along arch wall part loopful;Arch wall drain bar (22) is arranged on arch wall preliminary bracing (11) and arch wall waterproof It is longitudinally spaced to lay between plate (21);Foundation longitudinal drainage pipe (23) sets both walls pin AT STATION, vertical in foundation in reverse V-shaped Foundation transverse water drain pipe (24) is set to the minimum point of drainpipe (23), gutter is led in foundation transverse water drain pipe (24) one end (25)。
3. a kind of Underground Subway Station guarded drainage construction as claimed in claim 2, it is characterized in that:The bottom plate drainage system bag Include bottom plate longitudinal drainage pipe (27) and bottom plate transverse drain (26), bottom plate transverse drain (26) and bottom plate longitudinal drainage pipe (27) connected in infall, bottom plate transverse drain (26) is set in reverse V-shaped, and the gutter of tunnel both sides is led in its outside (25)。
CN201621361650.XU 2016-12-13 2016-12-13 A kind of Underground Subway Station guarded drainage construction Active CN206386134U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621361650.XU CN206386134U (en) 2016-12-13 2016-12-13 A kind of Underground Subway Station guarded drainage construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621361650.XU CN206386134U (en) 2016-12-13 2016-12-13 A kind of Underground Subway Station guarded drainage construction

Publications (1)

Publication Number Publication Date
CN206386134U true CN206386134U (en) 2017-08-08

Family

ID=59488639

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621361650.XU Active CN206386134U (en) 2016-12-13 2016-12-13 A kind of Underground Subway Station guarded drainage construction

Country Status (1)

Country Link
CN (1) CN206386134U (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107630707A (en) * 2017-10-26 2018-01-26 上海市隧道工程轨道交通设计研究院 A kind of single arch Station section arrangement and its application process
CN107905811A (en) * 2017-12-27 2018-04-13 中铁二院工程集团有限责任公司 The hollow longeron of foundation carries domes without the lining cutting of inverted arch type and its drainage system
CN107905812A (en) * 2017-12-27 2018-04-13 中铁二院工程集团有限责任公司 The hollow compound arch tunnel-liner in type tunnel bottom and its drainage system construction of falling from power
CN107905809A (en) * 2017-12-27 2018-04-13 中铁二院工程集团有限责任公司 Diplopore hollow, rectangular section load bearing beam road cutting type protecting arched tunnel liner structure and separate type drainage system
CN108005679A (en) * 2017-12-27 2018-05-08 中铁二院工程集团有限责任公司 A kind of dumbbell shape tunnel bottom liner structure with bilateral collection gallery
CN108005678A (en) * 2017-12-27 2018-05-08 中铁二院工程集团有限责任公司 π shape tunnels bottom liner structure with low level sluicing kinetic energy
CN108005688A (en) * 2017-12-27 2018-05-08 中铁二院工程集团有限责任公司 The external dewatering type lining cutting of buried lateral sulcus and its drainage system
CN108005690A (en) * 2017-12-27 2018-05-08 中铁二院工程集团有限责任公司 Boot last pedestal domes are without the lining cutting of inverted arch type and its drainage system
CN108194096A (en) * 2017-12-27 2018-06-22 中铁二院工程集团有限责任公司 Foundation base type is without inverted arch type tunnel lining structure and its drainage system
CN112780299A (en) * 2021-02-02 2021-05-11 中铁二局第六工程有限公司 Waterproof subway station access and exit passage structure and construction method thereof
CN112832862A (en) * 2021-03-16 2021-05-25 中铁城建集团第三工程有限公司 Construction method of drainage system for preventing water from flowing backwards after tunnel structure bottom plate leaks

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107630707A (en) * 2017-10-26 2018-01-26 上海市隧道工程轨道交通设计研究院 A kind of single arch Station section arrangement and its application process
CN108005688A (en) * 2017-12-27 2018-05-08 中铁二院工程集团有限责任公司 The external dewatering type lining cutting of buried lateral sulcus and its drainage system
CN108194096A (en) * 2017-12-27 2018-06-22 中铁二院工程集团有限责任公司 Foundation base type is without inverted arch type tunnel lining structure and its drainage system
CN107905809A (en) * 2017-12-27 2018-04-13 中铁二院工程集团有限责任公司 Diplopore hollow, rectangular section load bearing beam road cutting type protecting arched tunnel liner structure and separate type drainage system
CN108005679A (en) * 2017-12-27 2018-05-08 中铁二院工程集团有限责任公司 A kind of dumbbell shape tunnel bottom liner structure with bilateral collection gallery
CN108005678A (en) * 2017-12-27 2018-05-08 中铁二院工程集团有限责任公司 π shape tunnels bottom liner structure with low level sluicing kinetic energy
CN107905811A (en) * 2017-12-27 2018-04-13 中铁二院工程集团有限责任公司 The hollow longeron of foundation carries domes without the lining cutting of inverted arch type and its drainage system
CN108005690A (en) * 2017-12-27 2018-05-08 中铁二院工程集团有限责任公司 Boot last pedestal domes are without the lining cutting of inverted arch type and its drainage system
CN107905812A (en) * 2017-12-27 2018-04-13 中铁二院工程集团有限责任公司 The hollow compound arch tunnel-liner in type tunnel bottom and its drainage system construction of falling from power
CN108005690B (en) * 2017-12-27 2024-01-19 中铁二院工程集团有限责任公司 Arch structure non-inverted arch type lining of boot-shaped base
CN107905809B (en) * 2017-12-27 2024-01-19 中铁二院工程集团有限责任公司 Double-hole hollow rectangular section beam bearing cutting type arched tunnel lining structure
CN107905811B (en) * 2017-12-27 2024-01-19 中铁二院工程集团有限责任公司 Inverted arch-free lining of foundation hollow longitudinal beam bearing arch structure
CN112780299A (en) * 2021-02-02 2021-05-11 中铁二局第六工程有限公司 Waterproof subway station access and exit passage structure and construction method thereof
CN112832862B (en) * 2021-03-16 2022-04-19 中铁城建集团第三工程有限公司 Construction method of drainage system for preventing water from flowing backwards after tunnel structure bottom plate leaks
CN112832862A (en) * 2021-03-16 2021-05-25 中铁城建集团第三工程有限公司 Construction method of drainage system for preventing water from flowing backwards after tunnel structure bottom plate leaks

Similar Documents

Publication Publication Date Title
CN206386134U (en) A kind of Underground Subway Station guarded drainage construction
CN103590425B (en) A kind of Peaty soft soil stratum subway station construction technology
CN101298782B (en) Method and system for basement engineering water proof and water drain
CN206386150U (en) A kind of Underground Subway Station draining and examination and repair system
CN206874310U (en) Be applicable to high-pressure rich water district tunnel decompression drainage device
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN102995599B (en) Anti-freeze anti-seepage water diversion treatment method of collapsible loess water-conveyance canal
CN203947484U (en) Foundation pit drainage and circulating water utilization system
CN204532378U (en) Subway tunneling boring rock tunnel development machine engineering method tunnel water handling constructs
CN209212297U (en) A kind of guarded drainage and decompression system for rich water section tunnel
CN206530363U (en) One kind can the outer drainage system of maintenance type railway tunnel bottom structure
CN109488371B (en) Waterproof system of full-enclosed waterproof station and dynamic setting and quantity-limiting drainage method
CN108316354A (en) With waterproof, the underground pipe gallery structure of drain function and its construction method
CN208088344U (en) With waterproof, the underground pipe gallery structure of drain function
CN106284434A (en) The anti-float method of a kind of underground structure and every oozing device
CN103741715A (en) Novel waterproof hydrophobic construction method for basement
CN104234089B (en) The construction method that a kind of basement guarded drainage combines
CN204532364U (en) Tunneling boring rock tunnel development machine engineering method subway tunnel pressure release type liner structure
CN206448286U (en) It is a kind of to be used to reduce the radial system of grey field dam seepage line
CN113464174B (en) Construction method of tunnel row waterproof comprehensive treatment system
CN107245989A (en) Bear the tunnel structure and its construction technology of external water pressure in height
CN105113513A (en) Anti-seepage foundation pit supporting structure and construction method
CN107642101A (en) A kind of rocky bed steel cofferdam back cover leak stopping and guarded drainage construction method
CN208619166U (en) Waterproof drainage structure of tunnel roof
CN105926665A (en) Prefabricated large-sized building block assembly type concrete drainage pipeline base and construction method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant