CN103741715A - Novel waterproof hydrophobic construction method for basement - Google Patents

Novel waterproof hydrophobic construction method for basement Download PDF

Info

Publication number
CN103741715A
CN103741715A CN201310747139.8A CN201310747139A CN103741715A CN 103741715 A CN103741715 A CN 103741715A CN 201310747139 A CN201310747139 A CN 201310747139A CN 103741715 A CN103741715 A CN 103741715A
Authority
CN
China
Prior art keywords
gutter
waterproof
basement
sole plate
blanket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310747139.8A
Other languages
Chinese (zh)
Other versions
CN103741715B (en
Inventor
王丽梅
张云富
徐士林
陆海英
赵猛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Engineering Bureau Civil Engineering Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Engineering Bureau Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, China Construction Sixth Engineering Bureau Civil Engineering Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201310747139.8A priority Critical patent/CN103741715B/en
Publication of CN103741715A publication Critical patent/CN103741715A/en
Application granted granted Critical
Publication of CN103741715B publication Critical patent/CN103741715B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a novel waterproof hydrophobic construction method for a basement. The method comprises the following steps: (1) forming a water inlet in the lower part of the wall of a collector well, forming a drain hole in the upper part of the wall of the collector well, and inserting a drain pipe in the drain hole; (2) sequentially performing the following construction on a foundation slab around the collector well from the bottom to the top: (a) bedding a grading grait hydrophobic layer connected with the water inlet; (b) paving a non-woven layer; (c) backfilling sand cushions in layers; (d) pouring a macadam grout blanket connected with the drain hole, and paving a drain pipe in the macadam grout blanket; and (e) pouring a surface layer, wherein a drainage ditch communicated with the collector well is preserved when the construction of the steps (c), (d) and (e) is performed. The working efficiency can be improved by the method.

Description

The hydrophobic construction method of a kind of Novel underground chamber waterproof
Technical field
The present invention relates to the hydrophobic construction method of a kind of waterproof, relate in particular to the hydrophobic construction method of a kind of new waterproof.
Background technology
Along with urban construction constantly develops, the construction of highrise building and super highrise building is more and more, the degree of depth of basement and the number of plies are also in continuous increase, be with the construction works such as underground people's air defense, underground store, underground parking also more and more general, but its basement leakage phenomenon of bringing also increases thereupon, had a strong impact on construction engineering quality, used normally and manage and brought very large inconvenience also to basement.
Due to construction accidentally or the reason such as ground water pressure is large, the building of the basement degree of depth below groundwater table is easy to occur drainage, conventional underground waterproof engineering thinking is to rely mainly on prevention, after occurring leaking, just repair leak stopping, but some basements have been fitted up and have been come into operation, the source leaking is difficult to be found, even if leakage point is repaired, also the very difficult assurance later stage does not leak again, therefore cause the long-term existence of basement infiltration hidden danger, and then shorten the application life of basement and even whole building.
By retrieval, learn the patent of having authorized:
1 application number is: the Chinese patent of CN200720097389.1 discloses " a kind of basement waterproofing drainage structure ", it comprises along the multiple gutters that are filled with cobble in it that arrange on basement surrounding retaining wall inner side and sole plate, the top in each described gutter is provided with drain cover, its bottom is provided with rhone to join mutually and to be provided with drain cover in junction, in adjacent gutter intersection, be provided with catch pit, described catch pit is connected with water pump by gutter.This structure can solve basement leaking problem, and changing passive leak stopping is Active Drainage, guarantees that basement is all the time in dry use state, and solved basement leak stopping in the past not complete can not to carry out next procedure construction not enough simultaneously, accelerated the construction speed of engineering.Measure is not sealed in this patent ground cushion bottom, while having infiltration phenomenon to occur in basement bottom board, can not play certain sealing process, also can make the other materials of indoor backfill not sink, and causes the problem of ground cracking.On the sole plate of this patent, be provided with gutter in addition, if once gutter is stopped up, will cause basement infiltration to leak, and it is also very large to repair difficulty.
2 application numbers are: the Chinese patent of CN201210200958.6 discloses " a kind of basement waterproofing structure structure and construction method " a kind of basement waterproofing structure structure and construction method, belongs to building operations structurally waterproof technical field.Waterproof construction structure is mainly comprised of following structure: element soil; Element concrete bed course; Water-tight concrete base plate; Graded broken stone drainage blanket; Nonwoven separation layer; Steel concrete surface layer; Gutter; PVC gutter; Brick wall; Outer wall of basement.In this patent, the water in drainage blanket is dredged to gutter, the water in gutter often observation is drained in time, can not realize self-draining modern method.And do not seal measure bottom steel concrete surface layer, once underground water is arranged not in time, will make steel concrete surface layer cracking.The 2nd patent is also not suitable for applying in basement sole plate ground face thickness exceedes the engineering of 1m.And this patent is all to form on the basis that has overcome above shortcomings.
3 application numbers are: the Chinese patent of CN201310077111.8 discloses " antiseepage drainage blanket structure and construction method ", this disclosure of the invention a kind of antiseepage drainage blanket structure and construction method, described construction method comprises the following steps: cast one basement water resistant base plate, and in the reserved collecting well of described basement water resistant base plate, synchronize the sidewall of collecting well described in monobloc cast with described basement water resistant base plate; According to design height, pre-buried plural gutter in the sidewall of described collecting well; On described basement water resistant base plate, lay a drainage blanket, the first end of described gutter connects described drainage blanket, and the second end of described gutter connects described collecting well; In described drainage blanket upper one roof support with reinforced concrete, described roof support with reinforced concrete connects the sidewall of described collecting well.In this patent, the water in drainage blanket is discharged to collecting well, the water in collecting well can not be realized self-draining modern method.And do not seal measure bottom roof support with reinforced concrete, once underground water is arranged not in time, will make roof support with reinforced concrete cracking.And this patent is also not suitable for applying in basement sole plate ground face thickness exceedes the engineering of 1m.
Summary of the invention
The object of the invention is to overcome the shortcoming of prior art, provide a kind of simple in structure, construction cost is low, reach good waterproof hydrophobic effect, the hydrophobic construction method of a kind of Novel underground chamber waterproof that can reduce basement sole plate buoyancy, increase work efficiency simultaneously.
The hydrophobic construction method of a kind of Novel underground of the present invention chamber waterproof, it comprises the following steps:
(1) on foundation pad, laid successively from bottom to up waterproof roll, fish tail and waterproof layer and there is the sole plate of rigid self-waterproof function, when having the sole plate of rigid self-waterproof function, cast completes the construction of the collecting well being connected with sole plate, bottom at the described borehole wall that catchments has inlet opening, top at the described borehole wall that catchments has drain hole, in described drain hole, is inserted with gutter;
(2) on the described sole plate around collecting well, construct as follows successively from bottom to up:
(a) place mat grating cobble drainage blanket, described grating cobble drainage blanket is connected with inlet opening; (b) paving nonwoven layer; (c) back-filling in layers sand cushion; (d) cast rubble grout blanket, described rubble grout blanket is connected with drain hole, and described gutter is laid in rubble grout blanket; (e) cast surface layer; Reserved gutter when carrying out step (c), (d) and construction (e), described gutter and collecting well are connected.
The beneficial effect of the inventive method is: basement sole plate draining system can insert backfill and ground construction after basement construction completes in any time, and needn't wait until basement all complete and check leakproof after just carry out above work, increase work efficiency.By the draining system on sole plate and the combination of ground gutter, percolating water on sole plate and ground surface water all can be drained in collecting well, when water level in collecting well reaches certain height, automatically start drainage pump draining, to guarantee the dry state on basement ground, guarantee normal usage function.
Accompanying drawing explanation
Fig. 1 is the schematic diagram that adopts a kind of novel basement waterproofing drainage structure that prevents the hydrophobic construction method construction of basement waterproofing of the present invention;
Fig. 2 is the node schematic diagram at the place, basement waterproofing drainage structure gutter shown in Fig. 1;
Fig. 3 is the node schematic diagram at the collecting well place of the basement waterproofing drainage structure shown in Fig. 1.
The specific embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is described in detail.
The hydrophobic construction method of a kind of Novel underground of the present invention chamber waterproof as shown in drawings, it comprises the following steps: (1) has been laid successively from bottom to up waterproof roll, fish tail and waterproof layer and had the sole plate 1 of rigid self-waterproof function on foundation pad, when having the sole plate 1 of rigid self-waterproof function, cast completes the construction of the collecting well 8 being connected with sole plate, bottom at the described borehole wall that catchments has inlet opening 11, on the top of the described borehole wall that catchments, have drain hole 12, in described drain hole, be inserted with gutter; When coming into operation, gutter 13 is connected with the drainage pump 14 in collecting well.(2) on the described sole plate 1 around collecting well 8, construct as follows successively from bottom to up: (a) place mat grating cobble drainage blanket 2, described grating cobble drainage blanket 2 is connected with inlet opening; (b) paving nonwoven layer 3; (c) back-filling in layers sand cushion 4; (d) cast rubble grout blanket 5, described rubble grout blanket 5 is connected with drain hole, and described gutter is laid in rubble grout blanket 5; (e) cast surface layer 6; Reserved gutter 7 when carrying out step (c), (d) and construction (e), described gutter 7 and collecting well 8 are connected.During preferred described step (c) back-filling in layers sand cushion 4, every layer of sand backfill thickness is not more than 0.3m, and coefficient of consolidation reaches more than 0.95.Preferred sand cushion 4, rubble grout blanket 5 and surface layer 6 are domatic setting so that surface water discharges to gutter 7 to gutter 7.
Rubble grout blanket 5 objects of constructing on described sand cushion are to form scleroma layer, as water level in basement bottom board goes up, can play certain sealing process, also can make the other materials of indoor backfill not sink, and prevent ground cracking.The thickness of preferred rubble grout blanket 5 is 0.2m-0.25m.Form firm scleroma layer, even if underground water comes up by sand cushion is general, also rush not crushed stone grout blanket.
Preferred described surface layer 6 is pea gravel concreten ground, and thickness is advisable with 0.1-0.15m, joins one deck reinforced mesh in surface layer, and reinforced mesh is advisable from concrete pavement 2cm, to prevent ground cracking.
Embodiment 1
(1) on foundation pad, laid successively from bottom to up waterproof roll, fish tail and waterproof layer and there is the sole plate 1 of rigid self-waterproof function, when having the sole plate 1 of rigid self-waterproof function, cast completes the construction of the collecting well 8 being connected with sole plate, bottom at the described borehole wall that catchments has inlet opening 11, on the top of the described borehole wall that catchments, have drain hole 12, in described drain hole, be inserted with gutter; When coming into operation, gutter 13 is connected with the drainage pump 14 in collecting well.(2) on the described sole plate 1 around collecting well 8, construct as follows successively from bottom to up: (a) place mat grating cobble drainage blanket 2, described grating cobble drainage blanket 2 is connected with inlet opening; (b) paving nonwoven layer 3; (c) back-filling in layers sand cushion 4; (d) cast rubble grout blanket 5, described rubble grout blanket 5 is connected with drain hole, and described gutter is laid in rubble grout blanket 5; The thickness of rubble grout blanket 5 is 0.2m.(e) cast surface layer 6, surface layer 6 is pea gravel concreten ground, and thickness is 0.1m, inside joins one deck reinforced mesh, and reinforced mesh is from concrete pavement 2cm.Reserved gutter 7 when carrying out step (c), (d) and construction (e), described gutter 7 and collecting well 8 are connected.During described step (c) back-filling in layers sand cushion 4, every layer of sand backfill thickness is 0.3m, and coefficient of consolidation reaches 0.98.Sand cushion 4, rubble grout blanket 5 and surface layer 6 are domatic setting so that surface water discharges to gutter 7 to gutter 7.
After tested: by the draining system on sole plate and the combination of ground gutter, successfully the percolating water on sole plate and ground surface water are all drained in collecting well, in collecting well, water level reaches certain height, will automatically start drainage pump draining.Dry state and the normal usage function on basement ground have been guaranteed.And basement sole plate draining system can be after basement construction completes any time in insertion backfill and ground construction, and needn't wait until basement all complete and check leakproof after just carry out above work, increase work efficiency and the duration.
Embodiment 2
(1) on foundation pad, laid successively from bottom to up waterproof roll, fish tail and waterproof layer and there is the sole plate 1 of rigid self-waterproof function, when having the sole plate 1 of rigid self-waterproof function, cast completes the construction of the collecting well 8 being connected with sole plate, bottom at the described borehole wall that catchments has inlet opening 11, on the top of the described borehole wall that catchments, have drain hole 12, in described drain hole, be inserted with gutter; When coming into operation, gutter 13 is connected with the drainage pump 14 in collecting well.(2) on the described sole plate 1 around collecting well 8, construct as follows successively from bottom to up: (a) place mat grating cobble drainage blanket 2, described grating cobble drainage blanket 2 is connected with inlet opening; (b) paving nonwoven layer 3; (c) back-filling in layers sand cushion 4; (d) cast rubble grout blanket 5, described rubble grout blanket 5 is connected with drain hole, and described gutter is laid in rubble grout blanket 5; The thickness of rubble grout blanket 5 is 0.25m.(e) cast surface layer 6, surface layer 6 is pea gravel concreten ground, and thickness is 0.15m, inside joins one deck reinforced mesh, and reinforced mesh is from concrete pavement 2cm.Reserved gutter 7 when carrying out step (c), (d) and construction (e), described gutter 7 and collecting well 8 are connected.During described step (c) back-filling in layers sand cushion 4, every layer of sand backfill thickness is 0.28m, and coefficient of consolidation reaches 0.97.Sand cushion 4, rubble grout blanket 5 and surface layer 6 are domatic setting so that surface water discharges to gutter 7 to gutter 7.
After tested: by the draining system on sole plate and the combination of ground gutter, successfully the percolating water on sole plate and ground surface water are all drained in collecting well, in collecting well, water level reaches certain height, will automatically start drainage pump draining.Dry state and the normal usage function on basement ground have been guaranteed.And basement sole plate draining system can be after basement construction completes any time in insertion backfill and ground construction, and needn't wait until basement all complete and check leakproof after just carry out above work, increase work efficiency and the duration.
Embodiment 3
(1) on foundation pad, laid successively from bottom to up waterproof roll, fish tail and waterproof layer and there is the sole plate 1 of rigid self-waterproof function, when having the sole plate 1 of rigid self-waterproof function, cast completes the construction of the collecting well 8 being connected with sole plate, bottom at the described borehole wall that catchments has inlet opening 11, on the top of the described borehole wall that catchments, have drain hole 12, in described drain hole, be inserted with gutter; When coming into operation, gutter 13 is connected with the drainage pump 14 in collecting well.(2) on the described sole plate 1 around collecting well 8, construct as follows successively from bottom to up: (a) place mat grating cobble drainage blanket 2, described grating cobble drainage blanket 2 is connected with inlet opening; (b) paving nonwoven layer 3; (c) back-filling in layers sand cushion 4; (d) cast rubble grout blanket 5, described rubble grout blanket 5 is connected with drain hole, and described gutter is laid in rubble grout blanket 5; The thickness of rubble grout blanket 5 is 0.22m.(e) cast surface layer 6, surface layer 6 is pea gravel concreten ground, and thickness is 0.13m, inside joins one deck reinforced mesh, and reinforced mesh is from concrete pavement 2cm.Reserved gutter 7 when carrying out step (c), (d) and construction (e), described gutter 7 and collecting well 8 are connected.During described step (c) back-filling in layers sand cushion 4, every layer of sand backfill thickness is 0.3m, and coefficient of consolidation reaches 0.96.Sand cushion 4, rubble grout blanket 5 and surface layer 6 are domatic setting so that surface water discharges to gutter 7 to gutter 7.
After tested: by the draining system on sole plate and the combination of ground gutter, successfully the percolating water on sole plate and ground surface water are all drained in collecting well, in collecting well, water level reaches certain height, will automatically start drainage pump draining.Dry state and the normal usage function on basement ground have been guaranteed.And basement sole plate draining system can be after basement construction completes any time in insertion backfill and ground construction, and needn't wait until basement all complete and check leakproof after just carry out above work, increase work efficiency and the duration.

Claims (5)

1. the hydrophobic construction method of Novel underground chamber waterproof, is characterized in that it comprises the following steps:
(1) on foundation pad, laid successively from bottom to up waterproof roll, fish tail and waterproof layer and there is the sole plate of rigid self-waterproof function, when having the sole plate of rigid self-waterproof function, cast completes the construction of the collecting well being connected with sole plate, bottom at the described borehole wall that catchments has inlet opening, top at the described borehole wall that catchments has drain hole, in described drain hole, is inserted with gutter;
(2) on the described sole plate around collecting well, construct as follows successively from bottom to up:
(a) place mat grating cobble drainage blanket, described grating cobble drainage blanket is connected with inlet opening; (b) paving nonwoven layer; (c) back-filling in layers sand cushion; (d) cast rubble grout blanket, described rubble grout blanket is connected with drain hole, and described gutter is laid in rubble grout blanket; (e) cast surface layer; Reserved gutter when carrying out step (c), (d) and construction (e), described gutter and collecting well are connected.
2. the hydrophobic construction method of Novel underground according to claim 1 chamber waterproof, is characterized in that: during described step (c) back-filling in layers sand cushion, every layer of sand backfill thickness is not more than 0.3m, and coefficient of consolidation reaches more than 0.95.
3. the hydrophobic construction method of Novel underground according to claim 1 and 2 chamber waterproof, is characterized in that: described sand cushion, rubble grout blanket and surface layer are domatic setting to gutter.
4. the hydrophobic construction method of Novel underground according to claim 3 chamber waterproof, is characterized in that: the thickness of described rubble grout blanket is 0.2m-0.25m.
5. the hydrophobic construction method of Novel underground according to claim 1 and 2 chamber waterproof, is characterized in that: described surface layer is pea gravel concreten ground, and thickness is 0.1-0.15m, joins one deck reinforced mesh in surface layer, and reinforced mesh is from concrete pavement 2cm.
CN201310747139.8A 2013-12-25 2013-12-25 The hydrophobic construction method of a kind of basement waterproofing Active CN103741715B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310747139.8A CN103741715B (en) 2013-12-25 2013-12-25 The hydrophobic construction method of a kind of basement waterproofing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310747139.8A CN103741715B (en) 2013-12-25 2013-12-25 The hydrophobic construction method of a kind of basement waterproofing

Publications (2)

Publication Number Publication Date
CN103741715A true CN103741715A (en) 2014-04-23
CN103741715B CN103741715B (en) 2016-02-17

Family

ID=50498774

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310747139.8A Active CN103741715B (en) 2013-12-25 2013-12-25 The hydrophobic construction method of a kind of basement waterproofing

Country Status (1)

Country Link
CN (1) CN103741715B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104234089A (en) * 2014-08-21 2014-12-24 中国十七冶集团有限公司 Construction method for waterproof and water-draining combination of basement
CN104895327A (en) * 2015-06-17 2015-09-09 青岛海川建设集团有限公司 High-rise building basement concrete self-waterproofing construction process
CN104988955A (en) * 2015-06-11 2015-10-21 中建一局集团第六建筑有限公司 Anti-drainage combined waterproof system for super-deep basements, and construction method
CN107386416A (en) * 2017-07-31 2017-11-24 中国十七冶集团有限公司 A kind of basement boulder is from draining construction method of ground
CN107439077A (en) * 2017-06-23 2017-12-08 福建省春天生态科技股份有限公司 A kind of method of cell salt-soda soil comprehensive improvement
CN108247823A (en) * 2017-12-21 2018-07-06 江苏广兴集团有限公司 Make the steam curing device and installation method of fabricated construction
CN111851600A (en) * 2020-08-07 2020-10-30 昆山市天工建设工程有限公司 House underground water waterproof structure and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2635921Y (en) * 2003-08-29 2004-08-25 张新强 Water drainage device for basement
JP2006328894A (en) * 2005-05-30 2006-12-07 Nakamura Doboku Kk Construction method of underground structure
CN201125391Y (en) * 2007-09-11 2008-10-01 中国建筑第六工程局有限公司 Basement waterproofing drainage structure
CN201695408U (en) * 2010-02-02 2011-01-05 中国建筑第四工程局有限公司 Basement baseplate integrating water-proofing and drainage functions
CN102720217A (en) * 2012-06-12 2012-10-10 浙江城建建设集团有限公司 Basement watertightness structure and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2635921Y (en) * 2003-08-29 2004-08-25 张新强 Water drainage device for basement
JP2006328894A (en) * 2005-05-30 2006-12-07 Nakamura Doboku Kk Construction method of underground structure
CN201125391Y (en) * 2007-09-11 2008-10-01 中国建筑第六工程局有限公司 Basement waterproofing drainage structure
CN201695408U (en) * 2010-02-02 2011-01-05 中国建筑第四工程局有限公司 Basement baseplate integrating water-proofing and drainage functions
CN102720217A (en) * 2012-06-12 2012-10-10 浙江城建建设集团有限公司 Basement watertightness structure and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
钟鹏: "地下室构造防水方式研究——以绵阳博物馆设计为例", 《建筑学报》, no. 6, 30 June 2013 (2013-06-30) *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104234089A (en) * 2014-08-21 2014-12-24 中国十七冶集团有限公司 Construction method for waterproof and water-draining combination of basement
CN104234089B (en) * 2014-08-21 2016-08-24 中国十七冶集团有限公司 The construction method that a kind of basement guarded drainage combines
CN104988955A (en) * 2015-06-11 2015-10-21 中建一局集团第六建筑有限公司 Anti-drainage combined waterproof system for super-deep basements, and construction method
CN104895327A (en) * 2015-06-17 2015-09-09 青岛海川建设集团有限公司 High-rise building basement concrete self-waterproofing construction process
CN107439077A (en) * 2017-06-23 2017-12-08 福建省春天生态科技股份有限公司 A kind of method of cell salt-soda soil comprehensive improvement
CN107386416A (en) * 2017-07-31 2017-11-24 中国十七冶集团有限公司 A kind of basement boulder is from draining construction method of ground
CN108247823A (en) * 2017-12-21 2018-07-06 江苏广兴集团有限公司 Make the steam curing device and installation method of fabricated construction
CN111851600A (en) * 2020-08-07 2020-10-30 昆山市天工建设工程有限公司 House underground water waterproof structure and construction method
CN111851600B (en) * 2020-08-07 2022-01-25 昆山市天工建设工程有限公司 House underground water waterproof structure and construction method

Also Published As

Publication number Publication date
CN103741715B (en) 2016-02-17

Similar Documents

Publication Publication Date Title
CN103741715B (en) The hydrophobic construction method of a kind of basement waterproofing
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN103510528A (en) Blind trench water discharging structure used for underground structure up-floating prevention
CN110219313B (en) Drainage system and construction method for underground construction blind well
CN109797769B (en) Collapsible loess area underground comprehensive pipe gallery foundation structure and construction method thereof
CN108677982A (en) Complex geological condition foundation pit substrate excavates Tunnel gushing treatment method
CN111236284A (en) Basement bottom and periphery underground water drainage method and structure
CN106284434A (en) The anti-float method of a kind of underground structure and every oozing device
CN105569094A (en) Water discharge and drainage system and construction method adopting basement bottom plate water buoyant force releasing method
CN104234089B (en) The construction method that a kind of basement guarded drainage combines
CN103967015B (en) A kind of water seal for deep foundation pit excavation method and structure thereof
CN109577380B (en) Construction method for basement bottom plate water seepage under karst landform condition
CN107100206A (en) A kind of prevention and controls of basement leakage
CN103469828A (en) Construction method of hydrophobic structure of post-cast strip of bottom plate of basement
CN203654332U (en) Novel water prevention and dredge construction structure of basement
CN105569063A (en) Collecting and utilizing method for underground water on periphery of basement retaining wall and water collecting structure
CN104805873A (en) Multi-defense line type anti-floating system capable of monitoring release of water pressure of basement
TWI565859B (en) Construction Method for Decompression of Water Supply and Drainage in Exterior Wall of Building
CN218148458U (en) Deep water deep foundation pit drainage system of fissure development rock stratum
CN110080234A (en) A method of it is excavated in the secondary central island of deep foundation pit of soft soil foundation
CN107724405B (en) Dewatering of foundation construction method in a kind of underground pipe construction
KR101291098B1 (en) collecting well connector for eternal drainage construction technique
CN214245855U (en) Water-proof pressure-control anti-floating structure
CN211547830U (en) Structure for preventing ground from being wetted
CN115012452A (en) Post-cast strip construction process and basement drainage pressure relief structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20180914

Granted publication date: 20160217

PD01 Discharge of preservation of patent
PD01 Discharge of preservation of patent

Date of cancellation: 20190618

Granted publication date: 20160217