CN204455858U - A kind of hanger of large sections steel box-girder - Google Patents

A kind of hanger of large sections steel box-girder Download PDF

Info

Publication number
CN204455858U
CN204455858U CN201520095345.XU CN201520095345U CN204455858U CN 204455858 U CN204455858 U CN 204455858U CN 201520095345 U CN201520095345 U CN 201520095345U CN 204455858 U CN204455858 U CN 204455858U
Authority
CN
China
Prior art keywords
steel box
hanger
otic placode
girder
large sections
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201520095345.XU
Other languages
Chinese (zh)
Inventor
张连江
孙建波
徐波
王文山
沈家海
史虎彬
朱武华
郑伟涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN GANGHANG INSTALLATION ENGINEERING Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
TIANJIN GANGHANG INSTALLATION ENGINEERING Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN GANGHANG INSTALLATION ENGINEERING Co Ltd, No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical TIANJIN GANGHANG INSTALLATION ENGINEERING Co Ltd
Priority to CN201520095345.XU priority Critical patent/CN204455858U/en
Application granted granted Critical
Publication of CN204455858U publication Critical patent/CN204455858U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

一种大节段钢箱梁的吊耳,其特征在于所述吊耳包括一基板,该基板与大节段钢箱梁间固定设置,该基板上焊接设置一竖立的耳板,该耳板上开设有耳孔,所述基板与耳板间连接设置有加强肋板。该大节段钢箱梁的吊耳结构设计合理、牢固可靠,其能够提供较为牢固稳定的吊装承载,并具备良好的安全性。同时该吊耳与钢箱梁之间的施工安装方便,安装效率高。

A lifting lug of a large-segment steel box girder, characterized in that the lifting lug includes a base plate fixedly arranged between the base plate and the large-segment steel box girder, and a vertical lug plate is welded on the base plate, the lug plate Ear holes are opened on the top, and reinforcing ribs are connected between the base plate and the ear plate. The design of the lifting lug structure of the large section steel box girder is reasonable, firm and reliable, which can provide a relatively firm and stable lifting load, and has good safety. At the same time, the construction and installation between the lifting lug and the steel box girder is convenient and the installation efficiency is high.

Description

一种大节段钢箱梁的吊耳A lifting lug of a large section steel box girder

技术领域technical field

本实用新型属于预制大节段钢箱梁的吊装施工技术,具体的涉及一种提供大节段钢箱梁吊装用的吊耳。The utility model belongs to the hoisting construction technology of a prefabricated large section steel box girder, in particular to a lifting lug for hoisting a large section steel box girder.

背景技术Background technique

随着建筑工业和技术的日益发展,我国已经在沿海进行了多个海上高架桥梁的施工。为了实现高效率和高性能的高架梁施工,现有高架路桥普遍采用具有较大跨度的大节段钢箱梁,其长度已经达到80至130多米,重量高达2000多吨。由于大节段钢箱梁的长度、体积及重量均过于庞大,一般通过在钢箱梁上分布设置多组吊点群的方式进行钢箱梁的吊装施工。虽然采用多达数十个吊点的方式对钢箱梁进行吊装,其每个吊点所承受的重量依然很大,因此需要设计一种满足吊装要求的吊耳。With the development of construction industry and technology, our country has carried out the construction of many sea viaducts along the coast. In order to achieve high-efficiency and high-performance viaduct construction, existing viaducts generally use large-span steel box girders with a length of 80 to 130 meters and a weight of over 2,000 tons. Since the length, volume and weight of the large-segment steel box girder are too large, the hoisting construction of the steel box girder is generally carried out by distributing multiple sets of lifting point groups on the steel box girder. Although dozens of lifting points are used to hoist the steel box girder, each lifting point bears a heavy weight, so it is necessary to design a lifting lug that meets the lifting requirements.

实用新型内容Utility model content

本实用新型提供了一种结构设计合理、牢固可靠的大节段钢箱梁的吊耳,其能够提供较为牢固稳定的吊装承载,并具备良好的安全性。同时该吊耳与钢箱梁之间的施工安装方便,安装效率高。The utility model provides a lifting lug of a large-segment steel box girder with a reasonable structural design, firmness and reliability, which can provide relatively firm and stable hoisting and load bearing, and has good safety. At the same time, the construction and installation between the lifting lug and the steel box girder is convenient and the installation efficiency is high.

本实用新型所采用的技术方案如下:The technical scheme adopted in the utility model is as follows:

一种大节段钢箱梁的吊耳,其特征在于所述吊耳包括一基板,该基板与大节段钢箱梁间固定设置,该基板上焊接设置一竖立的耳板,该耳板上开设有耳孔,所述基板与耳板间连接设置有加强肋板。A lifting lug of a large-segment steel box girder, characterized in that the lifting lug includes a base plate, which is fixedly arranged between the large-segment steel box girder, and a vertical ear plate is welded on the base plate, and the ear plate There are ear holes on the top, and reinforcing ribs are connected between the base plate and the ear plate.

具体的讲,所述耳板的板面具有加厚部,该加厚部的中央开设耳孔;所述加厚部为耳板两端面焊接设置的加厚板。Specifically, the plate surface of the ear plate has a thickened portion, and an ear hole is opened in the center of the thickened portion; the thickened portion is a thickened plate welded on both ends of the ear plate.

一实施方式中,所述耳板的两端面下部分布设置加强肋板,所述加强肋板具有一平面弯折主体,该加强肋板的一侧面焊接连接耳板,加强肋板的下部焊接连接基板。In one embodiment, reinforcing ribs are arranged on the lower parts of both ends of the lugs, the reinforcing ribs have a plane bent body, one side of the reinforcing ribs is welded to the lugs, and the lower part of the reinforcing ribs is welded to substrate.

一实施方式中,所述加强肋板垂直于所述耳板和基板设置。In one embodiment, the reinforcing ribs are arranged perpendicular to the ear plates and the base plate.

另一实施方式中,所述加强肋板为六个,于耳板的两端面对称分别设置三个。In another embodiment, there are six reinforcing ribs, three of which are arranged symmetrically on both ends of the ear plates.

再一实施方式中,所述基板上开设有与钢箱梁的端面间连接固定用的固定孔。In still another embodiment, the base plate is provided with fixing holes for connection and fixing with the end faces of the steel box girder.

该大节段钢箱梁的吊耳采用较为简洁的钢构件制备,基板是与钢箱梁的端面进行连接的部件,其可以通过螺栓连接的方式进行固定。基板上竖立的耳板上形成有吊装连接用的耳孔,为了提高耳孔的牢固性和强度,本实用新型采用在耳板上焊装或连接加厚板的方式实现,耳孔外周的耳板均具有该加厚板,耳孔的承载性能大幅度提高。耳板与基板间采用多个加强肋板进行对称加固。平面弯折主体的加强肋板与耳板和基板间为断点焊接。加强肋板能够借助其平面弯折主体来消除耳板受力产生的部分形变,保持其加强性能。The lugs of the large-segment steel box girder are made of relatively simple steel components, and the base plate is a part connected with the end face of the steel box girder, which can be fixed by bolt connection. Ear holes for hoisting and connection are formed on the ear plates erected on the base plate. In order to improve the firmness and strength of the ear holes, the utility model is realized by welding or connecting thickened plates on the ear plates. The ear plates around the ear holes all have With the thickened plate, the load-bearing performance of the ear hole is greatly improved. A plurality of reinforcing ribs are used for symmetrical reinforcement between the lug plate and the base plate. The reinforcing ribs of the plane bending main body are welded at breakpoints with the ear plates and the base plate. The reinforcing ribs can eliminate part of the deformation caused by the stress on the ear plate by means of its plane bending main body, and maintain its reinforcing performance.

本实用新型的有益效果在于,该大节段钢箱梁的吊耳结构设计合理、牢固可靠,其能够提供较为牢固稳定的吊装承载,并具备良好的安全性。同时该吊耳与钢箱梁之间的施工安装方便,安装效率高。The beneficial effect of the utility model lies in that the design of the lug structure of the large-section steel box girder is reasonable, firm and reliable, which can provide relatively firm and stable hoisting and load bearing, and has good safety. At the same time, the construction and installation between the lifting lug and the steel box girder is convenient and the installation efficiency is high.

下面结合附图和具体实施方式对本实用新型做进一步的阐述。Below in conjunction with accompanying drawing and specific embodiment, the utility model is further elaborated.

附图说明Description of drawings

图1是本实用新型具体实施方式的一结构示意图;Fig. 1 is a structural representation of the specific embodiment of the present utility model;

图2是本实用新型具体实施方式的另一方位结构示意图。Fig. 2 is a schematic structural diagram of another orientation of the specific embodiment of the present invention.

具体实施方式Detailed ways

如图1和图2所示,该大节段钢箱梁的吊耳主要由基板20、耳板10和加强肋板13组成。基板20与大节段钢箱梁30间固定设置,基板20上可开设有与钢箱梁的端面间连接固定用的固定孔。基板20上焊接设置一竖立的耳板10,耳板上开设有耳孔12,耳板的板面具有加厚部11,该加厚部11的中央设置耳孔;所述加厚部为耳板两端面焊接设置的加厚板。基板与耳板间连接设置有加强肋板13,即耳板的两端面下部分布设置加强肋板,所述加强肋板具有一平面弯折主体,该加强肋板的一侧面焊接连接耳板,加强肋板的下部焊接连接基板。加强肋板垂直于所述耳板和基板设置。加强肋板为六个,于耳板的两端面对称分别设置三个。As shown in FIG. 1 and FIG. 2 , the lug of the large-segment steel box girder is mainly composed of a base plate 20 , an ear plate 10 and a reinforcing rib plate 13 . The base plate 20 is fixedly arranged with the large section steel box girder 30, and the base plate 20 may be provided with fixing holes for connection and fixing between the end faces of the steel box girder. An upright ear plate 10 is welded on the base plate 20, and an ear hole 12 is provided on the ear plate. Thickened plate with end weld setup. A reinforcing rib 13 is connected between the base plate and the ear plate, that is, a reinforcing rib is arranged on the lower part of both ends of the ear plate, and the reinforcing rib has a plane bending body, and one side of the reinforcing rib is welded to connect the ear plate The lower part of the reinforcement rib is welded to the base plate. The reinforcing ribs are arranged perpendicular to the ear plates and the base plate. There are six reinforcing ribs, three of which are arranged symmetrically on the two ends of the ear plates.

Claims (6)

1. the hanger of a large sections steel box-girder, it is characterized in that described hanger comprises a substrate, be fixedly installed between this substrate and large sections steel box-girder, on this substrate, welding arranges the otic placode of a setting, this otic placode offers earhole, between described substrate and otic placode, is connected with deep floor.
2. the hanger of large sections steel box-girder according to claim 1, it is characterized in that the plate mask of described otic placode has thickening part, the central authorities of this thickening part offer earhole; Described thickening part is the thickening plate that the welding of otic placode both ends of the surface is arranged.
3. the hanger of large sections steel box-girder according to claim 1, it is characterized in that the both ends of the surface lower part cloth of described otic placode arranges deep floor, described deep floor has a plane bending main body, and a side of this deep floor is welded to connect otic placode, the lower weld connection substrate of deep floor.
4. the hanger of large sections steel box-girder according to claim 3, is characterized in that described deep floor is arranged perpendicular to described otic placode and substrate.
5. the hanger of large sections steel box-girder according to claim 3, it is characterized in that deep floor is six, the both ends of the surface symmetry in otic placode arranges three respectively.
6. the hanger of large sections steel box-girder according to claim 1, it is characterized in that described substrate offers and steel box-girder end face between the fixing hole that is connected and fixed.
CN201520095345.XU 2015-02-10 2015-02-10 A kind of hanger of large sections steel box-girder Expired - Lifetime CN204455858U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520095345.XU CN204455858U (en) 2015-02-10 2015-02-10 A kind of hanger of large sections steel box-girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520095345.XU CN204455858U (en) 2015-02-10 2015-02-10 A kind of hanger of large sections steel box-girder

Publications (1)

Publication Number Publication Date
CN204455858U true CN204455858U (en) 2015-07-08

Family

ID=53662767

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520095345.XU Expired - Lifetime CN204455858U (en) 2015-02-10 2015-02-10 A kind of hanger of large sections steel box-girder

Country Status (1)

Country Link
CN (1) CN204455858U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105438964A (en) * 2015-12-16 2016-03-30 南车二七车辆有限公司 Hoisting seat device and railway vehicle provided with same
CN109081235A (en) * 2018-09-30 2018-12-25 中交二公局第二工程有限公司 A hoisting method of steel truss girder unit applied in single hoisting point hoisting mode
CN109112965A (en) * 2018-09-04 2019-01-01 中铁宝桥集团有限公司 A kind of half-through steel box x-arch bridge segment lifting device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105438964A (en) * 2015-12-16 2016-03-30 南车二七车辆有限公司 Hoisting seat device and railway vehicle provided with same
CN109112965A (en) * 2018-09-04 2019-01-01 中铁宝桥集团有限公司 A kind of half-through steel box x-arch bridge segment lifting device
CN109081235A (en) * 2018-09-30 2018-12-25 中交二公局第二工程有限公司 A hoisting method of steel truss girder unit applied in single hoisting point hoisting mode

Similar Documents

Publication Publication Date Title
CN202465064U (en) Truss type electric single-beam crane main beam
CN102943546A (en) Main girder for boiler steel structure
CN201077954Y (en) Steel anchor beam of canting pull stayd-cable bridge cable tower end coupling of stayd-cable bridge
CN204455858U (en) A kind of hanger of large sections steel box-girder
CN100545392C (en) The construction method of hoop gusset plate and its suspended ceiling keel
CN103898834B (en) A kind of steel tube concrete combination beam and truss-like Sarasota cable-stayed bridge and construction method thereof
CN202688848U (en) Anchoring connecting structure for nodes of composite truss girder cable-stayed bridge
CN207713242U (en) Suspender equipment suitable for the asynchronous lifting construction of steel-concrete composite beam cable-stayed bridge girder
CN201433509Y (en) Prestressed steel girder
CN106144877A (en) A kind of attachment means for Longspan Bridge lifting and construction method
CN204738229U (en) Two bearing plate cable -stay bridge cable wire tower steel anchor case anchor structures
CN204728217U (en) Positioning plate device for assembling steel box girder segments
CN201372163Y (en) Bailey truss combined portal crane
CN103663190A (en) Cantilever crane and crane
CN202913338U (en) Steel truss full-welded truss piece
CN209685126U (en) A kind of steel vestibule integrally promotes lifting lug device
CN107720542A (en) A kind of ceiling mounted tracks composite beam
CN203961027U (en) A kind of chord member of truss node that joins
CN204151698U (en) T beam transverse prestress reinforcing construction
CN207581213U (en) A kind of ceiling mounted tracks composite beam
CN105421251A (en) Plate-girder jacking support mechanism and plate-girder jacking support tool
CN205576737U (en) Trompil steel pipe steel and concrete composite beam bridge structure
CN205116431U (en) Eccentric connection structure who aligns of beam column
CN205688778U (en) A kind of elevating scaffold special over sling structure
CN213539440U (en) Assembled coincide floor

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20150708