CN215925647U - Arch rib buckle cable anchoring beam for tower buckle integration - Google Patents

Arch rib buckle cable anchoring beam for tower buckle integration Download PDF

Info

Publication number
CN215925647U
CN215925647U CN202121838400.1U CN202121838400U CN215925647U CN 215925647 U CN215925647 U CN 215925647U CN 202121838400 U CN202121838400 U CN 202121838400U CN 215925647 U CN215925647 U CN 215925647U
Authority
CN
China
Prior art keywords
tower
cross beam
welded
base
buckle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121838400.1U
Other languages
Chinese (zh)
Inventor
孙志雨
周建军
白浪
张�杰
李帅
张梵
王锦超
孙艺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, Road and Bridge East China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN202121838400.1U priority Critical patent/CN215925647U/en
Application granted granted Critical
Publication of CN215925647U publication Critical patent/CN215925647U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to an arch rib buckle cable anchoring beam for tower buckle integration, which comprises a cross beam, wherein the top surfaces of two ends of the cross beam are respectively welded with an anchoring seat, the bottom surfaces of two ends of the cross beam are respectively provided with a base, the top of each base is fixedly connected with the cross beam through a bolt, and the bottom of each base is provided with an arc-shaped clamping groove. The cable tower is light in weight, strong in structure and reliable in stress performance, is arranged on two opposite parallel links of the cable tower through the clamping grooves at the bottoms of the two bases, is convenient to install, and does not influence the stress structure of the cable tower.

Description

Arch rib buckle cable anchoring beam for tower buckle integration
Technical Field
The utility model belongs to the technical field of steel pipe arch bridge construction, and relates to an arch rib buckling cable anchoring beam installed on a cable tower when an arch rib is hoisted by adopting a tower buckling method.
Background
When the arch rib is hoisted by adopting a cable hoisting method, after the arch rib sections are hoisted in place, the line type of the arch rib cantilever needs to be adjusted and kept through a buckle cable. One end of the buckle cable is connected with the arch rib, and the other end of the buckle cable is anchored on the buckle tower. Usually, the buckling tower is arranged independently, but in the construction of mountainous bridges, sometimes the construction site limits, the buckling tower and the ground anchor are difficult to arrange, and the cable tower which is hung by using the cable is also used as the buckling tower, namely the tower is buckled into a whole.
When the cable tower is adopted as the buckling tower, a buckling cable anchor box or an anchor beam which is usually arranged on the buckling tower is generally directly arranged at a certain height on the cable tower, and because the anchor box has larger volume and heavy structure, a mounting platform needs to be erected by utilizing a flat link rod on the cable tower, so that the working procedures are increased, and the stress performance of the cable tower is also influenced to a certain extent.
Disclosure of Invention
The utility model aims to solve the problems and provides an arch rib buckle cable anchoring beam for tower buckle integration, which can be quickly installed and avoid influencing the stressed structure of a cable tower.
The technical scheme of the utility model is as follows:
the utility model provides an arch rib detains cable anchor roof beam for tower lock unification which characterized in that: the device comprises a cross beam, wherein an anchoring seat is welded on the top surface of each of two ends of the cross beam, a base is installed on the bottom surface of each of two ends of the cross beam, the top of each base is fixedly connected with the cross beam through a bolt, and an arc-shaped clamping groove is formed in the bottom of each base.
The utility model has light weight, strong structure and reliable stress performance, is erected on two opposite parallel links of the cable tower, has high installation speed and can bring convenience for the construction of buckling the tower.
Drawings
FIG. 1 is a schematic side view of the present invention;
FIG. 2 is a cross-sectional view of the end of the present invention;
FIG. 3 is a schematic top view of the present invention;
FIG. 4 is a plan view of the mounting structure of the present invention mounted on a cable tower;
fig. 5 is a schematic side view of the structure of the present invention mounted on a pylon.
Detailed Description
As shown in fig. 1, 2 and 3, the utility model comprises a beam 1, wherein the top surfaces of two ends of the beam are respectively welded with an anchoring seat 2, the bottom surfaces of two ends of the beam are respectively provided with a base 3, the top of each base 3 is fixedly connected with the beam 1 through a bolt 4, and the bottom of each base is provided with an arc-shaped clamping groove 5.
When the utility model is implemented, the anchoring seat 2 adopts two bearing plates 21 which are vertically welded on the top surface of the beam, a certain distance is arranged between the two bearing plates, one end of each bearing plate is welded with an anchor backing plate 22, and each bearing plate, the anchor backing plate and the top surface of the beam are welded with a plurality of reinforcing plates 23.
The base 3 comprises a top plate 31, the top plate is connected with the cross beam through a bolt 4, two vertical plates 32 perpendicular to the top plate are welded on the bottom surface of the top plate, a certain distance is reserved between the two vertical plates, the clamping grooves 5 are formed in the bottom edges of the two vertical plates, and a plurality of stiffening plates 33 are welded between the two sides of each vertical plate and the top plate.
In the specific implementation of the utility model, in order to further reduce the overall weight, a plurality of strip-shaped through holes 11 can be formed on the cross beam along the longitudinal direction. The cross beam can be made of double-spliced I-shaped steel.
As shown in fig. 4 and 5, the four columns 6 of the cable tower are usually provided with flat link rods 7, and the flat link rods are usually made of steel pipes. When the cable tower is implemented specifically, the center distance between the two bases 3 is equal to the center distance between the two opposite flat connecting rods 7 of the cable tower, and the arc diameter of the arc-shaped clamping groove 5 is equal to the outer diameter of the flat connecting rods. When the cable tower is installed, a crane is adopted to hoist the cable tower to a preset height, the clamping grooves at the bottoms of the two bases 3 are respectively clamped on the two opposite flat connecting rods 7 and are welded with the flat connecting rods. In order to enhance the strength and the bearing capacity of the flat link rod, concrete 8 can be poured into the flat link rod 7 of the utility model which is preset to be installed when the cable tower is installed in a flat manner.

Claims (4)

1. The utility model provides an arch rib detains cable anchor roof beam for tower lock unification which characterized in that: the device comprises a cross beam, wherein an anchoring seat is welded on the top surface of each of two ends of the cross beam, a base is installed on the bottom surface of each of two ends of the cross beam, the top of each base is fixedly connected with the cross beam through a bolt, and an arc-shaped clamping groove is formed in the bottom of each base.
2. A rib and tendon anchoring beam for a tower fastener according to claim 1, characterized in that: the anchoring seat comprises two bearing plates vertically welded on the top surface of the cross beam, a certain distance is reserved between the two bearing plates, one end of each bearing plate is welded with an anchor backing plate, and each bearing plate, each anchor backing plate and the top surface of the cross beam are welded with a plurality of reinforcing plates.
3. A rib and tendon anchoring beam for a tower fastener according to claim 1, characterized in that: the base comprises a top plate, the top plate is connected with the cross beam through a bolt, two vertical plates perpendicular to the top plate are welded to the bottom surface of the top plate, a certain distance is reserved between the two vertical plates, the clamping grooves are formed in the bottom edges of the two vertical plates, and a plurality of stiffening plates are welded between the two sides of each vertical plate and the top plate.
4. A rib and tendon anchoring beam for a tower fastener according to claim 1, characterized in that: a plurality of strip-shaped through holes are formed in the beam along the longitudinal direction.
CN202121838400.1U 2021-08-06 2021-08-06 Arch rib buckle cable anchoring beam for tower buckle integration Active CN215925647U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121838400.1U CN215925647U (en) 2021-08-06 2021-08-06 Arch rib buckle cable anchoring beam for tower buckle integration

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121838400.1U CN215925647U (en) 2021-08-06 2021-08-06 Arch rib buckle cable anchoring beam for tower buckle integration

Publications (1)

Publication Number Publication Date
CN215925647U true CN215925647U (en) 2022-03-01

Family

ID=80400007

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121838400.1U Active CN215925647U (en) 2021-08-06 2021-08-06 Arch rib buckle cable anchoring beam for tower buckle integration

Country Status (1)

Country Link
CN (1) CN215925647U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115948986A (en) * 2023-02-02 2023-04-11 广西路桥工程集团有限公司 Universal cable saddle buckling device and universal cable saddle buckling system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115948986A (en) * 2023-02-02 2023-04-11 广西路桥工程集团有限公司 Universal cable saddle buckling device and universal cable saddle buckling system
CN115948986B (en) * 2023-02-02 2023-07-04 广西路桥工程集团有限公司 General cable saddle device and general cable saddle system of detaining

Similar Documents

Publication Publication Date Title
CN100543235C (en) The method and system of erecting steel trusses by stay cable auxiliary complete cantilever
CN207032041U (en) Variable Section Steel box beam pushing tow combines the unit
CN201106155Y (en) Inclined guy cable auxiliary full cantaliver crane trussed steel beam device
CN104005338A (en) Three-directional temporary tower and girder consolidation structure of large-span cable-stayed bridge
CN215925647U (en) Arch rib buckle cable anchoring beam for tower buckle integration
CN108999088A (en) A kind of construction method of cable-stayed bridge
CN109440724B (en) Installation method of cast-in-place beam template suspension support system of high-pile wharf
CN110700119A (en) Upper traveling system of assembled Bailey beam hanging basket and design method thereof
CN113699884A (en) Rectangular concrete-filled steel tube cable tower adopting prefabricated web plates
CN203866711U (en) Large span cable-stayed bridge tower beam three-way temporary consolidation structure
CN103806373B (en) Oblique pull assembly type steel bridge on highway suspension cable anchor system
CN210439301U (en) Foundation section steel concrete waist rail supporting structure
CN210395127U (en) Assembled Bailey beam hanging basket upper walking system
CN213740636U (en) Cast-in-place construction auxiliary device of continuous case roof beam cantilever of variable cross section
CN212077660U (en) Large-span wide width bridge girder rhombus hanging basket construction structure
CN111254827B (en) Stay cable and bridge tower anchoring structure and manufacturing method
CN211312214U (en) Cable crane system installation system
CN210712562U (en) Tower crane system for construction of cast-in-situ tower column of cable-stayed bridge
CN108867548B (en) Construction platform and construction platform erection method for on-site watering high pile wharf
CN113235389A (en) Ground anchor type suspension bridge structure suitable for special terrain
CN202245789U (en) Special typhoon prevention device for gantry crane
CN111236049A (en) External prestress steering structure
CN218757578U (en) Auxiliary stabilizing structure for building foundation pit rock cracks
CN216712768U (en) Temporary sliding and storing device for steel box girder of suspension bridge
CN216918390U (en) Auxiliary roof dismantling structure for small tower crane of internal climbing tower crane

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant