CN203621666U - Feed mechanism for manufacturing water meter copper connectors - Google Patents

Feed mechanism for manufacturing water meter copper connectors Download PDF

Info

Publication number
CN203621666U
CN203621666U CN201320859677.1U CN201320859677U CN203621666U CN 203621666 U CN203621666 U CN 203621666U CN 201320859677 U CN201320859677 U CN 201320859677U CN 203621666 U CN203621666 U CN 203621666U
Authority
CN
China
Prior art keywords
water meter
meter copper
copper sleeve
feed mechanism
passage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320859677.1U
Other languages
Chinese (zh)
Inventor
潘建浩
潘建能
潘建波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Tianci Brothers Water Meter & Sanitaryware Co Ltd
Original Assignee
Ningbo Tianci Brothers Water Meter & Sanitaryware Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Tianci Brothers Water Meter & Sanitaryware Co Ltd filed Critical Ningbo Tianci Brothers Water Meter & Sanitaryware Co Ltd
Priority to CN201320859677.1U priority Critical patent/CN203621666U/en
Application granted granted Critical
Publication of CN203621666U publication Critical patent/CN203621666U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a feed mechanism for manufacturing water meter copper connectors. The feed mechanism is characterized in that the feed mechanism comprises a climbing device, a sorting device and an order ranking device; the climbing device is used for sequentially selecting out the water meter copper connector semi-finished products from a storage box and transferring the water meter copper connector semi-finished products; the tail end of the climbing device is connected with an inlet of the sorting device through a conveying mechanism and used for sorting out the water meter copper connector semi-finished products with unqualified heights and transferring the water meter copper connector semi-finished products with qualified heights to the order ranking device; an inlet of the order ranking device is connected with an outlet of the sorting device and an outlet of the order ranking device is connected with an external water meter copper connector machining lathe. All the devices complete orderly conveying, automatic sorting and real-time before-output arrangement conditions monitoring of the water meter copper connector semi-finished products respectively, the overall work progress of the feed mechanism is adjusted, overall mechanization and automation of the feed mechanism are realized, and the working efficiency is improved.

Description

A kind of feed mechanism of making water meter copper sleeve
Technical field
The present invention relates to a kind of feeding structure, be specifically related to a kind of feeding structure of making water meter copper sleeve.
Background technology
Water meter copper sleeve is the connecting elements of indispensability when resident's water meter is installed, in machining tool, its one end is processed into screw-like and can obtains the water meter copper sleeve for installing by water meter copper sleeve semi-finished product are sent into, install at water meter two ends respectively and connect water meter copper sleeve and to realize, water meter is arranged on water supply line.Water meter whether be closely connected with water supply line and install after the use state of water meter all closely related with the quality of water meter copper sleeve that water meter is installed, the water meter copper sleeve of manufacturing specification coupling is one of critical process.All generally to adopt streamline to carry out production and processing for this class workpiece of water meter copper sleeve, workpiece to be processed is generally successively through feed zone, transmission range, select materials district and material discharge region, finally enter processing district, workpiece only has successively through above-mentioned each region and just can complete and finally be processed into qualified product.In water meter copper sleeve feeding process in the past, mostly adopt the mode of artificial feeding, this feeding style has increased staff's labour intensity, and feeding frequency is unstable.Adopt the mode feeding of conveyer belt to enhance productivity, reduce staff's labour intensity by the automatization level that improves production line, Chinese invention patent " automatic feeding " (publication No. CN102807078A) discloses a kind of automatic feeding that comprises conveying mechanism, this conveying mechanism comprises support, motor, the feeding delivery mechanism (being equivalent to conveyer mechanism) being tilted to and be arranged on the multiple work supporting blocks on feeding delivery mechanism, this device employing conveyer mechanism and the work supporting block distributing on it transmit material in an orderly manner, accurate positioning, effectively enhance productivity.But, said apparatus is preferably applied in the transmission to powder, need like this workpiece of single transmission for water meter copper sleeve semi-finished product, in feeding process, but there is the problem of workpiece adhesion, exist on a work supporting block and be accompanied with plural water meter copper sleeve semi-finished product, cannot really realize the object that workpiece is transmitted in order.
In addition, the water meter copper sleeve of producing in order to ensure each machining tool can both meet product standard, possess corresponding product specification, need to carry out prescreen to water meter copper sleeve semi-finished product to be processed, pick out that those are underproof as with water meter copper sleeve semi-finished product jagged, that size height is not inconsistent.And in actual mechanical process, this sorting operation relies on manual work to complete often, not only spend a large amount of manpowers and time, and adopt manpower sorting also to have larger error.Further, adopt aforementioned streamline to carry out feeding to water meter copper sleeve semi-finished product, cooperation between each functional region is the key that guarantees the flow work efficiency, and in actual production process, once do mechanization operation is all realized in each region, to be difficult to ensure that each other card coordinates flexibly, from main regulation job schedule, although can be by interlock belt, the feeding transmission speed of the equipment control feed zones such as belt pulley and transmission range, but for the more difficult realization of district and material discharge region of selecting materials, especially in material discharge region, when the speed that enters material discharge region when water meter copper sleeve semi-finished product to be processed exceedes it and exports the speed of machining tool to from material discharge region, water meter copper sleeve semi-finished product will be trapped in material discharge region until affect whole feed mechanism operation, cause the confusion of flow process.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of feeding structure of making water meter copper sleeve for above-mentioned prior art, completes the half-finished orderly transmission of water meter copper sleeve, arranges to the water meter copper sleeve semi-finished product automatic sorting not highly being inconsistent and to exporting front water meter copper sleeve semi-finished product.
The technical scheme in the invention for solving the above technical problem is: a kind of feed mechanism of making water meter copper sleeve, is characterized in that: comprise
For the climbing device that water meter copper sleeve semi-finished product are selected successively and transferred from material storing box;
Material choosing apparatus, the end of climbing device is connected with the entrance of material choosing apparatus by connecting gear, for water meter copper sleeve semi-finished product highly against regulation are screened, and the water meter copper sleeve semi-finished product that highly conform with the regulations is transferred to collator;
Collator, the entrance of collator is connected with the outlet of material choosing apparatus, and the outlet of collator is connected with external water meter copper sleeve machining tool.
As improvement, described climbing device comprises for depositing the half-finished material storing box of water meter copper sleeve, vertically or the conveyer belt being obliquely installed, accept with material storing box, and the first driving mechanism of driving conveyer belt transmission, on described conveyer belt, be provided with the parts of accepting from accepting water meter copper sleeve in material storing box, the side that parts are accepted in described conveyer belt setting is provided with the brush roll being driven by the second driving mechanism, thus the setting position of this brush roll with accept the corresponding assurance of parts brush roll and can clean the improper water meter copper sleeve of accepting on parts that is undertaken on.This structure, guarantees only to carry water meter copper sleeve semi-finished product on a work supporting block and can really realize the object that water meter copper sleeve semi-finished product are transmitted in order.
As preferably, described in accept the bracket that parts are pair of opposing, between this pair of bracket, be formed with and accept the half-finished container cavity of water meter copper sleeve.Climb in process, bracket moves and realizes transmission in container cavity and with conveyer belt from accepting water meter copper sleeve semi-finished product in material storing box.
Further, the side that parts are accepted in described conveyer belt setting is also provided with gear and removes the half-finished backstopping assembly of unnecessary water meter copper sleeve on described bracket.Described backstopping assembly comprises the holder being connected with conveyer belt, on described holder, offer Connection Block hole, and be through in this Connection Block hole can easy on and off activity block axis, the bottom of described block axis can prop up described container cavity edge under Gravitative Loads.Meanwhile, the upper end of described block axis is provided with and prevents the locating part of block axis from dropping in Connection Block hole.Concrete process is to accept the half-finished bracket of water meter copper sleeve along with conveyer belt moves upward, after contacting with the bottom of block axis, by block axis jack-up, in the process of contact jack-up, the unnecessary water meter copper sleeve semi-finished product that may exist on bracket are blocked axle bumper, further guarantee that a pair of bracket only carries water meter copper sleeve semi-finished product, is fallen under the effect of self gravitation again by the block axis of jack-up afterwards.
Preferably, described backstopping assembly is arranged on the top of brush roll, further carry out backstop removing to accepting water meter copper sleeve semi-finished product unnecessary on parts in brush roll to accepting after parts complete first cleaning, guarantee that each parts of accepting only carry water meter copper sleeve semi-finished product.
Described making water meter copper sleeve is provided with the connecting gear porch of feed mechanism and accepts the container cavity bottom of parts described in stretching into, for accepting the half-finished guide plate of water meter copper sleeve, realize water meter copper sleeve semi-finished product and enter more swimmingly connecting gear from climbing device.
Described material choosing apparatus comprises the passage of selecting materials that guiding water meter copper sleeve semi-finished product pass through, described in the select materials top of passage be provided with limit for height lid; The both sides of the described passage of selecting materials are relatively set with the first correlation sensor, the first correlation sensor comprises the first emission sensor and first receiving sensor of the work of cooperatively interacting, correspondingly, passage and/or the limit for height of selecting materials described in covers to have and makes the transmitting through the through hole of the passage of selecting materials of the first emission sensor; The bottom of the described passage of selecting materials is provided with the door of being closed by driving mechanisms control, the first receiving sensor of described the first correlation sensor is connected with described driving mechanism, thereby door is opened these water meter copper sleeve semi-finished product is dropped in the passage of selecting materials in the time having water meter copper sleeve semi-finished product to be stuck in to cause in the passage of selecting materials receiving sensor can not receive the signal that the first emission sensor sends, described in described driving mechanisms control, realize the half-finished sorting of water meter copper sleeve with this, highly underproof workpiece is rejected in feed mechanism.
Preferably, described in limit for height lid described in above-mentioned material choosing apparatus is arranged on by fixture, select materials on passage, and limit for height lid and the height of selecting materials between passage can regulate by described fixture, so just can adapt to the water meter copper sleeve of different size.
Described collator comprises the sequence passage that holds the orderly accumulation of water meter copper sleeve, and be arranged on the second correlation sensor of described sequence passage both sides, the second correlation sensor comprises the second emission sensor and second receiving sensor of the work of cooperatively interacting, described the second receiving sensor is connected with the first driving mechanism, while causing the second receiving sensor not receive transmitting of the second emission sensor after the water meter copper sleeve of sequence in passage is aligned to the second correlation sensor institute correspondence position, described the first driving mechanism quits work.By the second correlation sensor to sequence in-channel water table copper sleeve half-finished Real-Time Monitoring, and the second receiving sensor is connected with the first driving mechanism, just can regulate the overall work process of feed mechanism, make climbing device, material choosing apparatus and the co-ordination of collator energy, realize mechanization, the automation of feed mechanism entirety, improved complete machine operating efficiency.
Compared with prior art, the utility model has the advantage of: the feed mechanism that adopts the utility model to provide, can better complete the half-finished orderly transmission of water meter copper sleeve, can also carry out automatic sorting to the water meter copper sleeve semi-finished product that are not highly inconsistent, can also effectively arrange exporting front water meter copper sleeve semi-finished product simultaneously, total automaticity is higher, without artificial participation, has improved feeding efficiency.
The climbing device particularly providing in the further technical scheme of the utility model is by vertically or on the conveyer belt being obliquely installed installing brush roll, brush roll is cleaned accepting parts, sweep off the improper water meter copper sleeve semi-finished product of accepting on parts that are undertaken on, guarantee that water meter copper sleeve semi-finished product are transmitted in an orderly manner, avoided work piece delivery confusion.In addition, the bracket being arranged on conveyer belt is to design according to the true form of water meter copper sleeve, is conducive to accept this water meter copper sleeve and reduces overloading; And be arranged in addition on conveyer belt for gear and remove to accept the half-finished backstopping assembly of unnecessary water meter copper sleeve on parts, further guarantee that a pair of bracket of accepting only carries water meter copper sleeve semi-finished product, has really realized to the half-finished orderly transmission of water meter copper sleeve the climbing device of this feed mechanism.
In the further technical scheme of the utility model, material choosing apparatus is designed to the channel design of selecting materials that guides water meter copper sleeve semi-finished product to pass through, limit for height lid is set above the passage of selecting materials, described limit for height lid and the distance of selecting materials between passage are adjustable, and be oppositely arranged correlation sensor in the both sides of the passage of selecting materials, realize the automatic sorting to water meter copper sleeve semi-finished product height, replace operating personnel's heavy and monotonous labour, realize mechanization and the automation of the operation of selecting materials.
In the further technical scheme of the utility model, collator is designed to hold the sequence channel design of water meter copper sleeve semi-finished product ordered arrangement, and at this sequence passage both sides relative position, correlation sensor is installed, realize Real-Time Monitoring the operation of energy flexible modulation feed mechanism of water meter copper sleeve semi-finished product to be exported in collator being arranged to situation, guaranteed the normal operation of whole feeding program.
Accompanying drawing explanation
Fig. 1 is the overall schematic of feed mechanism in the utility model embodiment;
Fig. 2 is the structural representation of climbing device bracket in the utility model embodiment;
Fig. 3 is the structural representation of climbing device backstopping assembly in the utility model embodiment;
Fig. 4 is the overall schematic at another visual angle of feed mechanism in the utility model embodiment;
Fig. 5 is the partial structurtes schematic diagram of the material choosing apparatus of B portion shown in Fig. 4.
The specific embodiment
Below in conjunction with accompanying drawing, embodiment is described in further detail the utility model.
Making water meter copper sleeve in the present embodiment mainly comprises climbing device, connecting gear, material choosing apparatus and the collator with material storing box with feed mechanism, and described climbing device, connecting gear, material choosing apparatus and collator join successively.Water meter copper sleeve semi-finished product in material storing box are transmitted in order through climbing device, entering material choosing apparatus through connecting gear sorts, reject highly underproof water meter copper sleeve semi-finished product, finally wait for that by sort qualified water meter copper sleeve semi-finished product introducing collator through material choosing apparatus being delivered to external machining tool completes last processing.
As shown in Figure 1, the climbing device of this feed mechanism comprises for depositing the half-finished material storing box 1 of water meter copper sleeve, vertically or the conveyer belt 2 being obliquely installed, accept with material storing box 1, on described conveyer belt 2, be provided with in material storing box 1 and accept the half-finished parts 4 of accepting of water meter copper sleeve, described conveyer belt 2 arranges a side of accepting parts and is provided with brush roll 5, thus the setting position of this brush roll 5 with accept the corresponding assurance of parts 4 brush roll 5 and can clean the improper water meter copper sleeve semi-finished product of accepting on parts that are undertaken on.
In the present embodiment, the rotating shaft of described brush roll 5 and conveyer belt 2 be arranged in parallel, are more conducive to brush roll 5 and clean loading on the unnecessary water meter copper sleeve semi-finished product of accepting on parts 4.
As shown in Figure 2, described in accept the bracket 41 that parts 4 are pair of opposing, between this pair of bracket 41, be formed with and accept the half-finished container cavity A of water meter copper sleeve.Climb in process, bracket 41 moves and realizes transmission in container cavity A and with conveyer belt 2 from accepting water meter copper sleeve semi-finished product in material storing box 1.
On described bracket 41, be also provided with installing hole 42, fixture is arranged on bracket 41 on described conveyer belt 2 through this installing hole 42.
As shown in Figure 1,3, the side that parts 4 are accepted in described conveyer belt 2 settings is also provided with gear and removes the half-finished backstopping assembly 6 of unnecessary water meter copper sleeve on described bracket 41.Described backstopping assembly 6 comprises the holder 61 being connected with conveyer belt 2, on described holder 61, offer Connection Block hole 610, and be through in this Connection Block hole 610 can easy on and off activity block axis 62, the bottom of described block axis 62 can prop up described container cavity A edge under Gravitative Loads.Meanwhile, the upper end of described block axis 62 is provided with and prevents the locating part 620 of block axis 62 from dropping in Connection Block hole 610.Concrete process is to accept the half-finished bracket of water meter copper sleeve along with conveyer belt moves upward, after contacting with the bottom of block axis, by block axis jack-up, in the process of contact jack-up, the unnecessary water meter copper sleeve semi-finished product that may exist on bracket are blocked axle bumper, are again fallen afterwards by the block axis of jack-up under the effect of self gravitation.
In the present embodiment, described backstopping assembly 6 is arranged on the top of brush roll 5, further carry out backstop removing to accepting water meter copper sleeve semi-finished product unnecessary on parts in brush roll to accepting after parts complete first cleaning, guaranteed to accept parts and once only carried water meter copper sleeve semi-finished product.
The half-finished climbing device of this transmission water meter copper sleeve also comprises the first driving mechanism that drives conveyer belt transmission, the second driving mechanism that drives brush roll to rotate, the first driving mechanism and the second driving mechanism are same driving mechanism, driving mechanism can adopt motor or hydraulic drive mechanism, the present embodiment adopts motor, and motor is arranged on the inside of frame 3.
Described making water meter copper sleeve is provided with the connecting gear porch of feed mechanism and accepts the container cavity A bottom of parts 4 described in stretching into, for accepting the half-finished guide plate (not shown) of water meter copper sleeve; realize water meter copper sleeve semi-finished product and enter connecting gear from climbing device, the first transport unit 14 and horizontally disposed the second transport unit 15 under connecting gear protection is tilted to.
As shown in Figure 4,5, the material choosing apparatus in the present embodiment comprises the passage 8 of selecting materials that guiding water meter copper sleeve semi-finished product pass through, described in the select materials top of passage be provided with limit for height lid 9; Described both sides of selecting materials passage 8 are relatively set with the first correlation sensor, the first correlation sensor comprises the first emission sensor 11-1 and the first receiving sensor 11-2 of the work of cooperatively interacting, correspondingly, described in, select materials to have on passage 8 and limit for height lid 9 and make the transmitting through the through hole 90 of the passage 8 of selecting materials of the first emission sensor; Described bottom of selecting materials passage 8 is provided with by driving mechanism 7 and controls the door (not shown) of closing, the receiving sensor of described the first correlation sensor is connected with described driving mechanism 7, thereby when the through hole 90 that blocks signal transmission when having water meter copper sleeve semi-finished product to be stuck in to select materials in passage 8 causes the first receiving sensor can not receive the signal that emission sensor sends, described driving mechanism 7 controls described door and open these water meter copper sleeve semi-finished product are dropped in the passage 8 of selecting materials.
Described limit for height lid 9 is selected materials on passage 8 described in being arranged on by fixture 10, and limit for height lid 9 and the height of selecting materials between passage 8 can regulate by described fixture 10.
In the present embodiment, described the first correlation sensor is infrared emission sensor, comprises infrared emission sensor and infrared receiving sensor.Block the through hole 90 that signal transmits during when having water meter copper sleeve semi-finished product to be trapped in to select materials in passage 8, infrared receiving sensor does not receive signal, and the driving mechanism 7 being attached thereto is opened the door of the channel bottom of selecting materials, and these water meter copper sleeve semi-finished product are dropped automatically.
The described passage 8 of selecting materials is obliquely installed, so that guiding water meter copper sleeve workpiece passes through.
As shown in Figure 4, collator in the present embodiment is arranged on the end of making water meter copper sleeve feed mechanism, and be connected with the entrance of water meter copper sleeve machining tool, comprise and hold the sequence passage 12 that water meter copper sleeve semi-finished product are piled up in order, and be arranged on the second correlation sensor of described sequence passage both sides, the second correlation sensor comprises the second emission sensor 13-1 and the second receiving sensor 13-2 of the work of cooperatively interacting, described receiving sensor is connected with the driving mechanism of controlling feed mechanism action, while causing the second receiving sensor not receive transmitting of the second emission sensor after the water meter copper sleeve semi-finished product in sequence passage are aligned to the second correlation sensor institute correspondence position, described driving mechanism quits work.
Described sequence passage 12 is obliquely installed, and water meter copper sleeve semi-finished product will, in the interior closely arrangement in an orderly manner of sequence passage 1, make sequence and output more smooth and easy under Action of Gravity Field like this.
Described in the present embodiment, the second correlation sensor is infrared emission sensor, comprises infrared emission sensor and infrared receiving sensor.When in sequence passage in the time that the water meter copper sleeve semi-finished product of exporting are stacked into enough height and block the transmitting and receiving of infrared signal, drive the driving mechanism of feed mechanism operation automatically to close down; When water meter copper sleeve semi-finished product in the passage that sorts are reduced to infrared receiving sensor and again receive the infrared signal of infrared emission sensor emission, described driving mechanism restarts, so realize the monitoring to sequence in-channel water table copper sleeve semi-finished product sequence situation, and control flexibly feed mechanism operation.
Climbing device, material choosing apparatus and the collator of said structure completed respectively the water meter copper sleeve semi-finished product in material storing box transmitted in order, also automatically regulates feed mechanism operation to the water meter copper sleeve semi-finished product automatic sorting highly differing and to water meter copper sleeve semi-finished product at the sequence situation Real-Time Monitoring in sequence district, make whole feed mechanism realize mechanization, automation, effectively improved operating efficiency.
The foregoing is only the preferred embodiment of the present invention, for a person skilled in the art, do not departing under principle of the present invention, can also make multiple improvement to each portion structure of feed mechanism, for example be formed with inside hole slot according to the two ends of water meter copper sleeve self, for the ease of accept water meter copper sleeve semi-finished product in material storing box, the described parts of accepting can be designed as the post of accepting being vertically set on described conveyer belt, accept interior also this water meter copper sleeve half product of jack-up of hole slot that post stretches into any one end of water meter copper sleeve semi-finished product, realize the step of accepting feeding from material storing box, the distortion of this class formation also all should be considered as in protection scope of the present invention.

Claims (10)

1. a feed mechanism of making water meter copper sleeve, is characterized in that: comprise
For the climbing device that water meter copper sleeve semi-finished product are selected successively and transferred from material storing box;
Material choosing apparatus, the end of climbing device is connected with the entrance of material choosing apparatus by connecting gear, for water meter copper sleeve semi-finished product highly against regulation are screened, and the water meter copper sleeve semi-finished product that highly conform with the regulations is transferred to collator;
Collator, the entrance of collator is connected with the outlet of material choosing apparatus, and the outlet of collator is connected with external water meter copper sleeve machining tool.
2. feed mechanism according to claim 1, it is characterized in that: described climbing device comprises for depositing the half-finished material storing box of water meter copper sleeve, vertically or be obliquely installed, the conveyer belt of accepting with material storing box, and the first driving mechanism of driving conveyer belt transmission, on described conveyer belt, be provided with the parts of accepting from accepting water meter copper sleeve in material storing box, the side that parts are accepted in described conveyer belt setting is provided with the brush roll being driven by the second driving mechanism, thereby the setting position of this brush roll with accept the corresponding assurance of parts brush roll and can clean the improper water meter copper sleeve of accepting on parts that is undertaken on.
3. feed mechanism according to claim 2, is characterized in that: described in accept the bracket that parts are pair of opposing, between this pair of bracket, be formed with the container cavity of accepting water meter copper sleeve.
4. feed mechanism according to claim 3, it is characterized in that: the side that parts are accepted in described conveyer belt setting is also provided with gear removes the backstopping assembly of unnecessary water meter copper sleeve on described bracket, described backstopping assembly comprises the holder being connected with conveyer belt, on described holder, offer Connection Block hole, and be through in this Connection Block hole can easy on and off activity block axis, the bottom of described block axis can prop up described container cavity edge under Gravitative Loads, and the upper end of described block axis is provided with and prevents the locating part of block axis from dropping in Connection Block hole.
5. feed mechanism according to claim 4, is characterized in that: described backstopping assembly is arranged on the top of brush roll.
6. feed mechanism according to claim 3, is characterized in that: described connecting gear porch be provided with can stretch into accept the container cavity bottom of parts, for accepting the half-finished guide plate of water meter copper sleeve.
7. feed mechanism according to claim 2, is characterized in that: rotating shaft and the conveyer belt of described brush roll be arranged in parallel.
8. feed mechanism according to claim 1, is characterized in that: described material choosing apparatus comprises the passage of selecting materials that a guiding water meter copper sleeve passes through, described in the select materials top of passage be provided with limit for height lid; The both sides of the described passage of selecting materials are relatively set with the first correlation sensor, the first correlation sensor comprises the first emission sensor and first receiving sensor of the work of cooperatively interacting, correspondingly, passage and/or the limit for height of selecting materials described in covers and has the through hole that makes the transmitting number of the first emission sensor pass the passage of selecting materials; The bottom of the described passage of selecting materials is provided with the door that driving mechanisms control is closed, the first receiving sensor of described the first correlation sensor is connected with described driving mechanism, thereby door is opened this water meter copper sleeve is dropped in the passage of selecting materials when having water meter copper sleeve to be stuck in to select materials while causing the first receiving sensor can not receive the signal that the first emission sensor sends in passage, described in described driving mechanisms control.
9. feed mechanism according to claim 8, is characterized in that: described in described limit for height lid is arranged on by fixture, select materials on passage, and limit for height lid and the height of selecting materials between passage can regulate by described fixture.
10. feed mechanism according to claim 2, it is characterized in that: described collator comprises the sequence passage that holds the orderly accumulation of water meter copper sleeve, and be arranged on the second correlation sensor of described sequence passage both sides, the second correlation sensor comprises the second emission sensor and second receiving sensor of the work of cooperatively interacting, described the second receiving sensor is connected with the first driving mechanism, while causing the second receiving sensor not receive transmitting of the second emission sensor after the water meter copper sleeve in sequence passage is aligned to the second correlation sensor institute correspondence position, described the first driving mechanism quits work.
CN201320859677.1U 2013-12-24 2013-12-24 Feed mechanism for manufacturing water meter copper connectors Expired - Fee Related CN203621666U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320859677.1U CN203621666U (en) 2013-12-24 2013-12-24 Feed mechanism for manufacturing water meter copper connectors

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320859677.1U CN203621666U (en) 2013-12-24 2013-12-24 Feed mechanism for manufacturing water meter copper connectors

Publications (1)

Publication Number Publication Date
CN203621666U true CN203621666U (en) 2014-06-04

Family

ID=50808184

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320859677.1U Expired - Fee Related CN203621666U (en) 2013-12-24 2013-12-24 Feed mechanism for manufacturing water meter copper connectors

Country Status (1)

Country Link
CN (1) CN203621666U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103692032A (en) * 2013-12-24 2014-04-02 宁波天赐兄弟水表水暖有限公司 Feeding mechanism for manufacturing water meter copper connector

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103692032A (en) * 2013-12-24 2014-04-02 宁波天赐兄弟水表水暖有限公司 Feeding mechanism for manufacturing water meter copper connector
CN103692032B (en) * 2013-12-24 2016-05-11 宁波天赐兄弟水表水暖有限公司 A kind of feed mechanism of making water meter copper sleeve

Similar Documents

Publication Publication Date Title
CN207954349U (en) A kind of automatic sticky stick system of silicon rod
CN104150206A (en) Blood collection tube labeling and assembling automatic connecting device
CN110124988A (en) A kind of automatic sorting device based on car li grade
CN103692276A (en) Sequencing device of feeding mechanism for manufacturing water meter copper connector
CN206543726U (en) Fruit switching mechanism and its fruit sorter
CN203599964U (en) Material selecting device of feeding mechanism for manufacture water meter copper connectors
CN203621666U (en) Feed mechanism for manufacturing water meter copper connectors
CN205764181U (en) Pipe Cutting blanking device in full-automatic loading and unloading one pipe cutting machine
CN203611052U (en) Arranging system of feeding mechanism for production of copper water meter connectors
CN103692032B (en) A kind of feed mechanism of making water meter copper sleeve
CN203599961U (en) Climbing device of feeding mechanism for manufacturing water meter copper connectors
CN206827582U (en) Pinaculum of badminton automatic feeding
CN210711841U (en) Down feather sorting and filtering device
CN105562346B (en) A kind of sheet material sorting unit
CN205324520U (en) Spinning -lathe is with treating processing material workbin structure
CN109482510B (en) A kind of full-automatic hardness detection sorter
CN106622993A (en) Fruit turning mechanism and fruit classifying device thereof
CN203959289U (en) Heparin tube labeling and assembling automatic junction device
CN206425290U (en) The automatic Wafer Cleaning mechanism for returning basket
CN110155679A (en) A kind of automatic discharging equipment in placement simple grain dried fruit on food
CN103692278A (en) Sorting device of feeding mechanism for manufacturing water meter copper connector
CN103659428B (en) A kind of climbing device of making water meter copper sleeve feed mechanism
CN208361506U (en) Carton production line automatic counting feeding-distribution device
CN207642639U (en) A kind of painting pen full automatic assembly machine
CN209668017U (en) A kind of automatic cleaning product line feeding device of bearing finished products

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140604

Termination date: 20141224

EXPY Termination of patent right or utility model