CN203445523U - Tool set for replacing dead-end insulator chain of substation framework - Google Patents

Tool set for replacing dead-end insulator chain of substation framework Download PDF

Info

Publication number
CN203445523U
CN203445523U CN201320432759.8U CN201320432759U CN203445523U CN 203445523 U CN203445523 U CN 203445523U CN 201320432759 U CN201320432759 U CN 201320432759U CN 203445523 U CN203445523 U CN 203445523U
Authority
CN
China
Prior art keywords
tool set
bottle
insulator string
changing
electric substation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320432759.8U
Other languages
Chinese (zh)
Inventor
瞿梁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JINGJIANG POWER SUPPLY CO Ltd JIANGSU ELECTRIC POWER Co
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Taizhou Power Supply Co of Jiangsu Electric Power Co
Original Assignee
JINGJIANG POWER SUPPLY CO Ltd JIANGSU ELECTRIC POWER Co
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Taizhou Power Supply Co of Jiangsu Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JINGJIANG POWER SUPPLY CO Ltd JIANGSU ELECTRIC POWER Co, State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Taizhou Power Supply Co of Jiangsu Electric Power Co filed Critical JINGJIANG POWER SUPPLY CO Ltd JIANGSU ELECTRIC POWER Co
Priority to CN201320432759.8U priority Critical patent/CN203445523U/en
Application granted granted Critical
Publication of CN203445523U publication Critical patent/CN203445523U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a tool set for replacing a dead-end insulator chain of a substation framework. The tool set comprises an insulator cradle, the insulator chain is placed on the insulator cradle, a movable clamping device (2) and a fixed clamping device (3) are respectively arranged at the two ends of the insulator cradle, and two ratchet palm gourds (4) are respectively arranged at the two sides of the end, where the fixed clamping device (3) is placed, of the insulator cradle, are connected with the movable clamping device (2) via fastening ropes (5), and drive the movable clamping device (2) to move via the fastening ropes (5). The tool set for replacing the dead-end insulator chain of the substation framework can greatly shorten power failure time, reduces labor intensity and improves working efficiency.

Description

A kind of for changing the tool set of electric substation's framework strain insulator string
Technical field
The utility model relates to a kind of for changing the tool set of electric substation's framework strain insulator string.
Background technology
The old common insulator that most of 35KV and above electric substation use all needs to be replaced by pollution proof insulator, but the workload of this replacing is large, and equipment interruption duration is short in the process of changing, higher to quality and safe requirement in construction, but because the construction site of electric substation is complicated, charging equipment is many, working range is less, and not only increased labour intensity while adopting at present one chip jig, reduce operating efficiency, and needed when mounted time of having a power failure long.
Summary of the invention
It is a kind of for changing the tool set of electric substation's framework strain insulator string that the utility model provides, and it not only can shorten interruption duration greatly, and can reduce labour intensity, raises labour efficiency.
The utility model has adopted following technical scheme: a kind of for changing the tool set of electric substation's framework strain insulator string, it is provided with bottle-holding rack, insulator string is placed on bottle-holding rack, at the two ends of bottle-holding rack, be respectively equipped with movable fixture and holding clamp, the both sides that are positioned at holding clamp one end at bottle-holding rack are respectively equipped with ratchet lever hoist, two ratchet lever hoists are connected with movable fixture by hauling, and two ratchet lever hoists drive movable fixture to move by hauling.
The both sides of described bottle-holding rack are fixed metal support, are provided with some cross bars and vertical pole between two metallic supports, and cross bar and vertical pole are insulating epoxy pipe, after cross bar is connected with metallic support with vertical pole, form stretcher shape.Described ratchet lever hoist is 3T ratchet lever hoist.Described movable fixture is angle bar.Described holding clamp is galvanized steel bar.Described bottle-holding rack side is provided with lifting lever, and one end of lifting lever is connected with holder, and the other end is connected with lifting tackle, is wound with insulation ropes on lifting tackle.
The utlity model has following beneficial effect: the utility model adopts bottle-holding rack and ratchet lever hoist, by ratchet lever hoist, tighten up insulator string, after not stressing, insulator string more renews insulator string, so not only can change easily insulator string, reduce labour intensity, well improve the effect of efficiency of construction and fail safe, and save workmen, can greatly shorten interruption duration simultaneously.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Embodiment
In Fig. 1, the utility model is a kind of for changing the tool set of electric substation's framework strain insulator string, it is provided with bottle-holding rack, the both sides of bottle-holding rack are fixed metal support 6, between two metallic supports 6, be provided with some cross bars 7 and vertical pole 8, cross bar 7 and vertical pole 8 are insulating epoxy pipe, after being connected with metallic support 6 with vertical pole 8, cross bar 7 forms stretcher shape, insulator string is placed on bottle-holding rack, at the two ends of bottle-holding rack, be respectively equipped with movable fixture 2 and holding clamp 3, movable fixture 2 is angle bar, holding clamp 3 is galvanized steel bar, the both sides that are positioned at holding clamp 3 one end at bottle-holding rack are respectively equipped with ratchet lever hoist 4, ratchet lever hoist 4 is 3T ratchet lever hoist, two ratchet lever hoists 45 are connected with movable fixture 2 by hauling, two ratchet lever hoists 4 are by 5 drive movable fixture 2 motions of hauling, on bottle-holding rack side, be provided with lifting lever 9, one end of lifting lever 9 is connected with holder 10, the other end is connected with lifting tackle 11, on lifting tackle 11, be wound with insulation ropes 1.The utility model on insulator string, installs ratchet lever hoist 4 by bottle-holding rack colligation, tightens up ratchet lever hoist 4, and insulator string is not stressed, and promotes insulator string go out the insulator string more renewing after bottle-holding rack by the lifting tackle 11 on lifting lever 9.

Claims (6)

1. one kind for changing the tool set of electric substation's framework strain insulator string, it is characterized in that it is provided with bottle-holding rack, insulator string is placed on bottle-holding rack, at the two ends of bottle-holding rack, be respectively equipped with movable fixture (2) and holding clamp (3), the both sides that are positioned at holding clamp (3) one end at bottle-holding rack are respectively equipped with ratchet lever hoist (4), two ratchet lever hoists (4) are connected with movable fixture (2) by haul (5), and two ratchet lever hoists (4) drive movable fixture (2) motion by haul (5).
2. according to claim 1 for changing the tool set of electric substation's framework strain insulator string, the both sides that it is characterized in that described bottle-holding rack are fixed metal support (6), between two metallic supports (6), be provided with some cross bars (7) and vertical pole (8), cross bar (7) and vertical pole (8) are insulating epoxy pipe, after cross bar (7) is connected with metallic support (6) with vertical pole (8), form stretcher shape.
3. according to claim 1 for changing the tool set of electric substation's framework strain insulator string, it is characterized in that described ratchet lever hoist (4) is 3T ratchet lever hoist.
4. according to claim 1 for changing the tool set of electric substation's framework strain insulator string, it is characterized in that described movable fixture (2) is angle bar.
5. according to claim 1 for changing the tool set of electric substation's framework strain insulator string, it is characterized in that described holding clamp (3) is galvanized steel bar.
6. according to claim 1 for changing the tool set of electric substation's framework strain insulator string, it is characterized in that bottle-holding rack side is provided with lifting lever (9), one end of lifting lever (9) is connected with holder (10), the other end is connected with lifting tackle (11), is wound with insulation ropes (1) on lifting tackle (11).
CN201320432759.8U 2013-07-22 2013-07-22 Tool set for replacing dead-end insulator chain of substation framework Expired - Fee Related CN203445523U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320432759.8U CN203445523U (en) 2013-07-22 2013-07-22 Tool set for replacing dead-end insulator chain of substation framework

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320432759.8U CN203445523U (en) 2013-07-22 2013-07-22 Tool set for replacing dead-end insulator chain of substation framework

Publications (1)

Publication Number Publication Date
CN203445523U true CN203445523U (en) 2014-02-19

Family

ID=50096542

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320432759.8U Expired - Fee Related CN203445523U (en) 2013-07-22 2013-07-22 Tool set for replacing dead-end insulator chain of substation framework

Country Status (1)

Country Link
CN (1) CN203445523U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103457200A (en) * 2013-07-22 2013-12-18 国家电网公司 Tool set for replacing strain insulator string of substation framework
CN103457200B (en) * 2013-07-22 2016-11-30 国家电网公司 A kind of tool set for changing substation framework strain insulator string

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103457200A (en) * 2013-07-22 2013-12-18 国家电网公司 Tool set for replacing strain insulator string of substation framework
CN103457200B (en) * 2013-07-22 2016-11-30 国家电网公司 A kind of tool set for changing substation framework strain insulator string

Similar Documents

Publication Publication Date Title
CN203522074U (en) Bundling fixing device for tail wire and main wire of stay wire of power transmission line poles
CN201766314U (en) Insulator replacing tool
CN202804150U (en) Rotary grapping lifting manipulator mechanism
CN201838934U (en) Novel portable adjustable rod upper platform
CN203946776U (en) Head tower bearing plate turnover hoisting fixture
CN101814707B (en) Tool for live replacement of 220kV line 'V' string insulator and method
CN202333602U (en) Double-connection board wire tightening clamp
CN203282420U (en) Double conductor tension indicating wire grip
CN202197048U (en) Double angle steel hanging point lifting and connecting tool for tower use
CN201932878U (en) Detachable distribution transform core lifting device
CN202488034U (en) Lifting device for electric transmission line of angle iron tower
CN203445523U (en) Tool set for replacing dead-end insulator chain of substation framework
CN203813330U (en) Tool for live-line replacement of 500 kV strain insulator strings
CN203193189U (en) Portable overhead ground wire lifting device
CN103500961B (en) Tool special for electrified replacement of strain insulator string
CN202978098U (en) Overhead ground wire lifter
CN202586222U (en) Elevating gear for enclosing bus installation
CN103457200A (en) Tool set for replacing strain insulator string of substation framework
CN103457200B (en) A kind of tool set for changing substation framework strain insulator string
CN104253394A (en) Tension insulator string replacement tool
CN204057687U (en) Steel embryo fetches and delivers fixture
CN203787859U (en) Portable derrick applied to transmission line overhauling
CN202488035U (en) Hoisting device for maintenance of power transmission line above concrete poles
CN202930836U (en) Tension insulator replacement tool
CN202199643U (en) Multifunctional pipe bender

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140219

Termination date: 20190722