- CN103457200A CN103457200A CN2013103053716A CN201310305371A CN103457200A CN 103457200 A CN103457200 A CN 103457200A CN 2013103053716 A CN2013103053716 A CN 2013103053716A CN 201310305371 A CN201310305371 A CN 201310305371A CN 103457200 A CN103457200 A CN 103457200A
- Authority
- CN
- China
- Prior art keywords
- insulator string
- tool set
- bottle
- ratchet lever
- strain insulator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Electric Cable Installation (AREA)
- Insulators (AREA)
Abstract
The invention discloses a tool set for replacing a strain insulator string of a substation framework. The tool set is provided with an insulator cradle, wherein the insulator string is placed on the insulator cradle, the two ends of the insulator cradle are provided with a movable clamp (2) and a fixed clamp (3) respectively, the two sides, arranged at one end of the fixed clamp (3), of the insulator cradle are respectively provided with a ratchet lever pulley block (4), the two ratchet lever pulley blocks (4) are connected with the movable clamp (2) through a tightening rope (5), and the two ratchet lever pulley blocks (4) drive the movable clamp (2) to move through the tightening rope (5). According to the tool set, the power outage time can be greatly shortened, the labor intensity can be reduced, and the labor efficiency is improved.
Description
Technical field
The present invention relates to a kind of for changing the tool set of electric substation's framework strain insulator string.
Background technology
The old common insulator that most of 35KV and above electric substation use all needs to be replaced by pollution proof insulator, but the workload of this replacing is large, and the equipment interruption duration is short in the process of changing, higher to quality and safe requirement in construction, but due to the construction site complexity of electric substation, charging equipment is many, working range is less, and not only increased labour intensity while adopting at present the one chip jig, reduce operating efficiency, and needed when mounted time of having a power failure long.
Summary of the invention
The invention provides a kind ofly for changing the tool set of electric substation's framework strain insulator string, it not only can shorten interruption duration greatly, and can reduce labour intensity, raises labour efficiency.
The present invention has adopted following technical scheme: a kind of for changing the tool set of electric substation's framework strain insulator string, it is provided with bottle-holding rack, insulator string is placed on bottle-holding rack, be respectively equipped with movable fixture and holding clamp at the two ends of bottle-holding rack, the both sides that are positioned at holding clamp one end at bottle-holding rack are respectively equipped with the ratchet lever hoist, two ratchet lever hoists are connected with movable fixture by hauling, and two ratchet lever hoists drive the movable fixture motion by hauling.
The both sides of described bottle-holding rack are fixed metal support, are provided with some cross bars and vertical pole between two metallic supports, and cross bar and vertical pole are the insulating epoxy pipe, after cross bar is connected with metallic support with vertical pole, form the stretcher shape.Described ratchet lever hoist is 3T ratchet lever hoist.Described movable fixture is angle bar.Described holding clamp is galvanized steel bar.Described bottle-holding rack side is provided with the lifting lever, and an end of lifting lever is connected with holder, and the other end is connected with lifting tackle, is wound with insulation ropes on lifting tackle.
The present invention has following beneficial effect: the present invention adopts bottle-holding rack and ratchet lever hoist, tighten up insulator string by the ratchet lever hoist, after not stressing, insulator string more renews insulator string, so not only can change easily insulator string, reduce labour intensity, well improve the effect of efficiency of construction and fail safe, and save the workmen, can greatly shorten interruption duration simultaneously.
The accompanying drawing explanation
Fig. 1 is structural representation of the present invention.
Embodiment
In Fig. 1, the present invention is a kind of for changing the tool set of electric substation's framework strain insulator string, it is provided with bottle-holding rack, the both sides of bottle-holding rack are fixed metal support 6, be provided with some cross bars 7 and vertical pole 8 between two metallic supports 6, cross bar 7 and vertical pole 8 are the insulating epoxy pipe, after being connected with metallic support 6 with vertical pole 8, cross bar 7 forms the stretcher shape, insulator string is placed on bottle-holding rack, be respectively equipped with movable fixture 2 and holding clamp 3 at the two ends of bottle-holding rack, movable fixture 2 is angle bar, holding clamp 3 is galvanized steel bar, the both sides that are positioned at holding clamp 3 one ends at bottle-holding rack are respectively equipped with ratchet lever hoist 4, ratchet lever hoist 4 is 3T ratchet lever hoist, two ratchet lever hoists 45 are connected with movable fixture 2 by hauling, two ratchet lever hoists 4 are by 5 drive movable fixture 2 motions of hauling, be provided with lifting lever 9 on the bottle-holding rack side, one end of lifting lever 9 is connected with holder 10, the other end is connected with lifting tackle 11, be wound with insulation ropes 1 on lifting tackle 11.The present invention on insulator string, installs ratchet lever hoist 4 by the bottle-holding rack colligation, tightens up ratchet lever hoist 4, and insulator string is not stressed, and promotes insulator string by the lifting tackle 11 on lifting lever 9 and goes out the insulator string more renewed after bottle-holding rack.
Claims (6)
1. one kind for changing the tool set of electric substation's framework strain insulator string, it is characterized in that it is provided with bottle-holding rack, insulator string is placed on bottle-holding rack, be respectively equipped with movable fixture (2) and holding clamp (3) at the two ends of bottle-holding rack, the both sides that are positioned at holding clamp (3) one ends at bottle-holding rack are respectively equipped with ratchet lever hoist (4), two ratchet lever hoists (4) are connected with movable fixture (2) by haul (5), and two ratchet lever hoists (4) drive movable fixture (2) motion by haul (5).
2. according to claim 1 for changing the tool set of electric substation's framework strain insulator string, the both sides that it is characterized in that described bottle-holding rack are fixed metal support (6), be provided with some cross bars (7) and vertical pole (8) between two metallic supports (6), cross bar (7) and vertical pole (8) are the insulating epoxy pipe, after cross bar (7) is connected with metallic support (6) with vertical pole (8), form the stretcher shape.
3. according to claim 1 for changing the tool set of electric substation's framework strain insulator string, it is characterized in that described ratchet lever hoist (4) is 3T ratchet lever hoist.
4. according to claim 1 for changing the tool set of electric substation's framework strain insulator string, it is characterized in that described movable fixture (2) is angle bar.
5. according to claim 1 for changing the tool set of electric substation's framework strain insulator string, it is characterized in that described holding clamp (3) is galvanized steel bar.
6. according to claim 1 for changing the tool set of electric substation's framework strain insulator string, it is characterized in that the bottle-holding rack side is provided with lifting lever (9), one end of lifting lever (9) is connected with holder (10), the other end is connected with lifting tackle (11), is wound with insulation ropes (1) on lifting tackle (11).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310305371.6A CN103457200B (en) | 2013-07-22 | A kind of tool set for changing substation framework strain insulator string |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310305371.6A CN103457200B (en) | 2013-07-22 | A kind of tool set for changing substation framework strain insulator string |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103457200A true CN103457200A (en) | 2013-12-18 |
CN103457200B CN103457200B (en) | 2016-11-30 |
Family
ID=
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104283146A (en) * | 2014-07-07 | 2015-01-14 | 中国南方电网有限责任公司超高压输电公司南宁局 | Device and method for replacing insulator string |
CN105098655A (en) * | 2015-08-25 | 2015-11-25 | 广东电网有限责任公司惠州供电局 | Strain insulator exchange tool |
CN105186360A (en) * | 2015-08-27 | 2015-12-23 | 国网上海市电力公司 | Presettable arched insulator cradle for insulators |
CN106169715A (en) * | 2016-08-09 | 2016-11-30 | 国网上海市电力公司 | A kind of UHV transmission line cross-arm side whole string strain insulator departs from and restoration methods |
CN106207855A (en) * | 2016-08-09 | 2016-12-07 | 国网上海市电力公司 | A kind of UHV transmission line whole string strain insulator exchange method |
CN106253132A (en) * | 2016-08-09 | 2016-12-21 | 国网上海市电力公司 | A kind of whole string strain insulator handling scalable pole and application thereof |
CN106410660A (en) * | 2016-08-09 | 2017-02-15 | 国网上海市电力公司 | Whole string tension insulator separation and recovery device at cross arm side of ultra-high voltage transmission line |
CN106410661A (en) * | 2016-08-09 | 2017-02-15 | 国网上海市电力公司 | Whole string tension insulator exchange device of ultra-high voltage transmission line |
CN110854736A (en) * | 2019-11-22 | 2020-02-28 | 云南电网有限责任公司红河供电局 | Method for assisting electric field feeding by adopting insulating bottle supporting frame |
CN113809683A (en) * | 2021-10-25 | 2021-12-17 | 国网四川省电力公司成都供电公司 | Method and system for replacing insulator string |
CN114188872A (en) * | 2021-11-01 | 2022-03-15 | 广西电网有限责任公司玉林供电局 | 500kV line strain insulator rod type insulator fixture |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06153343A (en) * | 1991-03-19 | 1994-05-31 | Tokyo Electric Power Co Inc:The | Lifting temporary arm |
JP3140486U (en) * | 2008-01-15 | 2008-03-27 | 関西電力株式会社 | Overhead wire lifting device |
CN201336531Y (en) * | 2009-01-13 | 2009-10-28 | 福建省三明电业局 | Clamping tool for replacing charged insulators of pre-stranded hardware fittings |
CN201887387U (en) * | 2010-12-14 | 2011-06-29 | 江西景德镇供电公司 | Universal-type telescopic insulator cradle |
CN203445523U (en) * | 2013-07-22 | 2014-02-19 | 国家电网公司 | Tool set for replacing dead-end insulator chain of substation framework |
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06153343A (en) * | 1991-03-19 | 1994-05-31 | Tokyo Electric Power Co Inc:The | Lifting temporary arm |
JP3140486U (en) * | 2008-01-15 | 2008-03-27 | 関西電力株式会社 | Overhead wire lifting device |
CN201336531Y (en) * | 2009-01-13 | 2009-10-28 | 福建省三明电业局 | Clamping tool for replacing charged insulators of pre-stranded hardware fittings |
CN201887387U (en) * | 2010-12-14 | 2011-06-29 | 江西景德镇供电公司 | Universal-type telescopic insulator cradle |
CN203445523U (en) * | 2013-07-22 | 2014-02-19 | 国家电网公司 | Tool set for replacing dead-end insulator chain of substation framework |
Non-Patent Citations (1)
Title |
---|
刘春田等: "500kV线路整串更换耐张绝缘子的施工工艺", 《电力建设》, vol. 25, no. 2, 29 February 2004 (2004-02-29) * |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104283146B (en) * | 2014-07-07 | 2017-01-04 | 中国南方电网有限责任公司超高压输电公司南宁局 | A kind of device and method changing insulator chain |
CN104283146A (en) * | 2014-07-07 | 2015-01-14 | 中国南方电网有限责任公司超高压输电公司南宁局 | Device and method for replacing insulator string |
CN105098655A (en) * | 2015-08-25 | 2015-11-25 | 广东电网有限责任公司惠州供电局 | Strain insulator exchange tool |
CN105186360B (en) * | 2015-08-27 | 2017-07-14 | 国网上海市电力公司 | A kind of insulator bottle-holding rack of predeterminable arch |
CN105186360A (en) * | 2015-08-27 | 2015-12-23 | 国网上海市电力公司 | Presettable arched insulator cradle for insulators |
CN106207855A (en) * | 2016-08-09 | 2016-12-07 | 国网上海市电力公司 | A kind of UHV transmission line whole string strain insulator exchange method |
CN106253132A (en) * | 2016-08-09 | 2016-12-21 | 国网上海市电力公司 | A kind of whole string strain insulator handling scalable pole and application thereof |
CN106169715A (en) * | 2016-08-09 | 2016-11-30 | 国网上海市电力公司 | A kind of UHV transmission line cross-arm side whole string strain insulator departs from and restoration methods |
CN106410660A (en) * | 2016-08-09 | 2017-02-15 | 国网上海市电力公司 | Whole string tension insulator separation and recovery device at cross arm side of ultra-high voltage transmission line |
CN106410661A (en) * | 2016-08-09 | 2017-02-15 | 国网上海市电力公司 | Whole string tension insulator exchange device of ultra-high voltage transmission line |
CN110854736A (en) * | 2019-11-22 | 2020-02-28 | 云南电网有限责任公司红河供电局 | Method for assisting electric field feeding by adopting insulating bottle supporting frame |
CN113809683A (en) * | 2021-10-25 | 2021-12-17 | 国网四川省电力公司成都供电公司 | Method and system for replacing insulator string |
CN114188872A (en) * | 2021-11-01 | 2022-03-15 | 广西电网有限责任公司玉林供电局 | 500kV line strain insulator rod type insulator fixture |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104143782A (en) | Electrified replacement tool and method for +/-800 kV circuit strain insulator string | |
CN201766314U (en) | Insulator replacing tool | |
CN101814707B (en) | Tool for live replacement of 220kV line 'V' string insulator and method | |
WO2012100595A1 (en) | Tool for replacing ceramic rod type insulator | |
CN202333602U (en) | Double-connection board wire tightening clamp | |
CN203282420U (en) | Double conductor tension indicating wire grip | |
CN202197048U (en) | Double angle steel hanging point lifting and connecting tool for tower use | |
CN203278097U (en) | Electric pole cross arm erecting device | |
CN202978103U (en) | Insulator fixture | |
CN202488034U (en) | Lifting device for electric transmission line of angle iron tower | |
CN201932878U (en) | Detachable distribution transform core lifting device | |
CN203445523U (en) | Tool set for replacing dead-end insulator chain of substation framework | |
CN204103345U (en) | A kind of novel conductors on quad bundled strain insulator string side of wire link plate clamping tool | |
CN203813330U (en) | Tool for live-line replacement of 500 kV strain insulator strings | |
CN103500961B (en) | Tool special for electrified replacement of strain insulator string | |
CN202586222U (en) | Elevating gear for enclosing bus installation | |
CN103457200A (en) | Tool set for replacing strain insulator string of substation framework | |
CN202978098U (en) | Overhead ground wire lifter | |
CN103457200B (en) | A kind of tool set for changing substation framework strain insulator string | |
CN201584701U (en) | Tool for replacing 'V' string insulator of 220kV line in live state | |
CN104253394A (en) | Tension insulator string replacement tool | |
CN203787859U (en) | Portable derrick applied to transmission line overhauling | |
CN202488035U (en) | Hoisting device for maintenance of power transmission line above concrete poles | |
CN203119388U (en) | Multifunctional mounting rack for changing tension-resistant crossarm | |
CN202930836U (en) | Tension insulator replacement tool |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |