CN202954557U - Scaffold wall connection part - Google Patents

Scaffold wall connection part Download PDF

Info

Publication number
CN202954557U
CN202954557U CN 201220634132 CN201220634132U CN202954557U CN 202954557 U CN202954557 U CN 202954557U CN 201220634132 CN201220634132 CN 201220634132 CN 201220634132 U CN201220634132 U CN 201220634132U CN 202954557 U CN202954557 U CN 202954557U
Authority
CN
China
Prior art keywords
steel plate
bolt hole
wall
scaffold
cross bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220634132
Other languages
Chinese (zh)
Inventor
刘剑锋
徐国金
钟丽华
曾庞春
孔圣翔
马霞
李法富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG SENTUO CONSTRUCTION ENGINEERING Co Ltd
ZHEJIANG HENGSHENG CONSTRUCTION GROUP CO Ltd
Original Assignee
ZHEJIANG SENTUO CONSTRUCTION ENGINEERING Co Ltd
ZHEJIANG HENGSHENG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG SENTUO CONSTRUCTION ENGINEERING Co Ltd, ZHEJIANG HENGSHENG CONSTRUCTION GROUP CO Ltd filed Critical ZHEJIANG SENTUO CONSTRUCTION ENGINEERING Co Ltd
Priority to CN 201220634132 priority Critical patent/CN202954557U/en
Application granted granted Critical
Publication of CN202954557U publication Critical patent/CN202954557U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model belongs to the technical field of building engineering and in particular relates to a scaffold wall connection part which comprises an embedded sleeve which is previously embedded in a wall body or a concrete beam and penetrates through the wall body or the concrete beam, a steel plate and a horizontal rod. Bolts are arranged in the embedded sleeve, a bolt hole and an arc slide groove with the bolt hole as the circle center are arranged on the steel plate, the horizontal rod is arranged on the steel plate between the bolt hole and the arc slide groove, the axis of the horizontal rod is perpendicular to the steel plate, the bolt hole and the arc slide groove correspond to the embedded sleeve in a one-to-one mode, and the bolts penetrate through the bolt hole and the arc slide groove which are arranged on the steel plate to fix the steel plate on the wall body or the concrete beam. By means of the arc slide groove, the position of the horizontal rod can be adjusted according to the position of a scaffold vertical rod. The wall connection part uses the two bolts to connect so as to be large in bearing capacity. Thus, the number of the wall connection parts can be reduced to save cost. The bolts, the steel plate and the horizontal rod can be recycled so as to save resources and reduce construction cost. The scaffold wall connection part is suitable for building site occasions.

Description

Wall-connecting piece for scaffold
Technical field:
The utility model belongs to construction engineering technical field, refers in particular to a kind of reusable wall-connecting piece for scaffold.
Background technology:
Scaffold refers to the various supports that job site is vertical for the operating personnel solves and horizontal transport is set up, and is building while building, and scaffold need to be fixed by wall-connecting piece and body of wall or concrete beam.Wall-connecting piece is the important component part of scaffold, and scaffold generation transverse integral unstability is played to effect of contraction, and scaffold is played to firm effect, prevents that scaffold from toppling over or rocking.The Scaffold Collapse Accident occurred both at home and abroad is substantially all to cause because wall-connecting piece arranges after deficiency or wall-connecting piece are removed to mend to establish in time.
Summary of the invention:
The purpose of this utility model is to provide a kind of convenient transportation, reusable, the wall-connecting piece for scaffold that reduces construction cost.
The utility model is achieved in that
Wall-connecting piece for scaffold, comprise the service sleeve that is embedded in body of wall or concrete beam, runs through body of wall or concrete beam, steel plate and cross bar, be provided with bolt in described service sleeve, be provided with bolt hole on described steel plate and take the arc chute that bolt hole is the center of circle, cross bar is arranged on the steel plate between bolt hole and arc chute, the axis of cross bar is perpendicular to steel plate, described bolt hole and arc chute are corresponding one by one with service sleeve, and bolt is fixed on steel plate on body of wall or concrete beam by bolt hole and the arc chute through on steel plate.
Above-mentioned bolt is stud, and an end of stud is through bolt hole and arc chute on steel plate and be bolted with nut, the other end is bolted with nut through the bolt hole on cushion block steel plate is fixed on body of wall or concrete beam.
Above-mentioned cross bar is welded to connect on steel plate, and the center of circle of the point of the axis of cross bar on steel plate, bolt hole and the mid point of arc chute are on same straight line.
Above-mentioned cross bar is steel pipe or round steel.
Above-mentioned service sleeve is the PVC service sleeve.
The utility model outstanding advantage compared to existing technology is:
1, PVC service sleeve of the present utility model can make the bolt recycling;
2, be provided with on steel plate of the present utility model and take the arc chute that bolt hole is the center of circle, can guarantee that cross bar can adjust its position according to the position of scaffold upright rod, reach exactly and connect;
3, two bolts that the utility model arranges connect, and make the wall-connecting piece bearing capacity larger, are mainly to bear larger pulling force, therefore can reduce the quantity that wall-connecting piece arranges, and have saved cost;
4, all recyclable recyclings such as bolt of the present utility model, steel plate, cross bar, economize on resources, and reduces construction cost, improves corporate profit margin;
5, the utility model is applicable to the building operations occasion.
The accompanying drawing explanation:
Fig. 1 is use state generalized section of the present utility model;
Fig. 2 is that cross bar of the present utility model is welded on the schematic perspective view on steel plate;
Fig. 3 is that the master that cross bar of the present utility model is welded on steel plate looks schematic diagram;
Fig. 4 is the use state diagram be connected with scaffold of the present utility model.
The specific embodiment:
Below with specific embodiment, the utility model is further described, referring to Fig. 1-4:
Wall-connecting piece for scaffold, comprise and being embedded in body of wall or concrete beam 10, the service sleeve 20 that runs through body of wall or concrete beam 10, steel plate 30 and cross bar 40, be provided with bolt 50 in described service sleeve 20, be provided with the arc chute 302 that bolt hole 301 and the bolt hole 301 of take are the center of circle on described steel plate 30, cross bar 40 is arranged on the steel plate 30 between bolt hole 301 and arc chute 302, the axis of cross bar 40 is perpendicular to steel plate 30, described bolt hole 301 and arc chute 302 are corresponding one by one with service sleeve 20, bolt 50 is fixed on steel plate 30 on body of wall or concrete beam 10 by bolt hole 301 and the arc chute 302 through on steel plate 30.
Above-mentioned bolt 50 is stud, and an end of stud is through bolt hole 301 and arc chute 302 on steel plate 30 and be bolted with nut 60, the other end is bolted with nut 60 through the bolt hole on cushion block 70 steel plate 30 is fixed on body of wall or concrete beam 10.
Above-mentioned cross bar 40 is welded to connect on steel plate 30, be provided with cross bar hole on steel plate 30, one end of cross bar 40 is arranged in cross bar hole, and be weldingly fixed on steel plate 30, be formed with weld seam 80 between steel plate 30 and cross bar 40, the mid point of the point at the axis of cross bar 40 on steel plate 30, the center of circle of bolt hole 301 and arc chute 302 is on same straight line.Can also adopt other connected mode between cross bar 40 and steel plate 30: as be threaded.
Above-mentioned cross bar 40 is steel pipe or round steel.
Above-mentioned service sleeve 20 is PVC service sleeves.
Using method of the present utility model:
Two ends that stretch out the stud of body of wall or concrete beam 10 wall faces pass respectively bolt hole 301 and the arc chute 302 on steel plate 30, extremely best according to the position of position adjustments cross bar 40 in arc chute 302 of scaffold upright rod 90, stud stretches out an end of body of wall or concrete beam 10 interior metopes through two bolts hole on cushion block 70, the two ends of stud are bolted with respectively nut 60 steel plate 30 are fixed on body of wall or concrete beam 10, between steel plate 30 and nut 60, be provided with pad 100 between cushion block 70 and nut 60, cross bar 40 is connected with scaffold upright rod 90 by rotary buckle 110.
Above-described embodiment is only one of preferred embodiment of the present utility model; not with this, limit practical range of the present utility model; therefore: all equivalences of doing according to shape of the present utility model, structure, principle change, within all should being covered by protection domain of the present utility model.

Claims (5)

1. for the wall-connecting piece of scaffold, it is characterized in that: comprise and being embedded in body of wall or concrete beam, the service sleeve that runs through body of wall or concrete beam, steel plate and cross bar, be provided with bolt in described service sleeve, be provided with bolt hole on described steel plate and take the arc chute that bolt hole is the center of circle, cross bar is arranged on the steel plate between bolt hole and arc chute, the axis of cross bar is perpendicular to steel plate, described bolt hole and arc chute are corresponding one by one with service sleeve, bolt is fixed on steel plate on body of wall or concrete beam by bolt hole and the arc chute through on steel plate.
2. the wall-connecting piece for scaffold according to claim 1, it is characterized in that: described bolt is stud, and an end of stud is through bolt hole and arc chute on steel plate and be bolted with nut, the other end is bolted with nut through the bolt hole on cushion block steel plate is fixed on body of wall or concrete beam.
3. the wall-connecting piece for scaffold according to claim 1, it is characterized in that: described cross bar is welded to connect on steel plate, and the center of circle of the point of the axis of cross bar on steel plate, bolt hole and the mid point of arc chute are on same straight line.
4. according to the described wall-connecting piece for scaffold of claim 1 or 3, it is characterized in that: described cross bar is steel pipe or round steel.
5. the wall-connecting piece for scaffold according to claim 1, it is characterized in that: described service sleeve is the PVC service sleeve.
CN 201220634132 2012-11-26 2012-11-26 Scaffold wall connection part Expired - Fee Related CN202954557U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220634132 CN202954557U (en) 2012-11-26 2012-11-26 Scaffold wall connection part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220634132 CN202954557U (en) 2012-11-26 2012-11-26 Scaffold wall connection part

Publications (1)

Publication Number Publication Date
CN202954557U true CN202954557U (en) 2013-05-29

Family

ID=48460136

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220634132 Expired - Fee Related CN202954557U (en) 2012-11-26 2012-11-26 Scaffold wall connection part

Country Status (1)

Country Link
CN (1) CN202954557U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107152160A (en) * 2017-06-22 2017-09-12 中国五冶集团有限公司 A kind of shuttering supporting builder's jack operation platform erection method
CN108005375A (en) * 2017-12-28 2018-05-08 上海建工二建集团有限公司 Scaffold wall connecting assembly and construction method thereof
CN108149917A (en) * 2017-12-28 2018-06-12 上海建工二建集团有限公司 Adjustable scaffold wall connecting assembly and construction method thereof
CN111576843A (en) * 2020-04-28 2020-08-25 云南建投第十一建设有限公司 Reusable wall connecting piece pulling device and using method thereof
CN113550562A (en) * 2021-06-02 2021-10-26 中国五冶集团有限公司 Large-span large-storey high-wall-connecting piece setting method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107152160A (en) * 2017-06-22 2017-09-12 中国五冶集团有限公司 A kind of shuttering supporting builder's jack operation platform erection method
CN108005375A (en) * 2017-12-28 2018-05-08 上海建工二建集团有限公司 Scaffold wall connecting assembly and construction method thereof
CN108149917A (en) * 2017-12-28 2018-06-12 上海建工二建集团有限公司 Adjustable scaffold wall connecting assembly and construction method thereof
CN111576843A (en) * 2020-04-28 2020-08-25 云南建投第十一建设有限公司 Reusable wall connecting piece pulling device and using method thereof
CN113550562A (en) * 2021-06-02 2021-10-26 中国五冶集团有限公司 Large-span large-storey high-wall-connecting piece setting method

Similar Documents

Publication Publication Date Title
CN202954557U (en) Scaffold wall connection part
CN204252286U (en) A kind of rectangular steel-tube concrete column-steel beam connecting joint
CN204097882U (en) For the assembling combined steel pipe mounting system of bridge engineering
CN202936996U (en) Wall connecting piece for scaffold
CN203809870U (en) Supporting and fixing tool for level pump pipe on concrete floor
CN201817814U (en) Adjustable fixed support of vertical surface sheet steel form
CN203307937U (en) Concrete column and steel beam rigidity node construction
CN203412292U (en) Detachable discharging platform
CN203654710U (en) Instrumental connecting tube for external wall scaffold shearing wall portion
CN103821234A (en) Joint construction for steel-reinforced concrete column and reinforced concrete beam
CN103628569B (en) A kind of draw-in groove assembly concrete-filled steel tube post-steel beam connecting joint
CN203247717U (en) Connecting node of concrete column and steel beam
CN202611223U (en) Recyclable bolt type scaffold wall connection piece
CN202039606U (en) Concrete pump pipe fixing structure of super high rise building construction
CN207633226U (en) Easy-to-mount high stability supporting bridge fixed frame
CN204754945U (en) Mine method tunnel preliminary bracing lining cutting grid steel support make
CN203603253U (en) Detachable steel corbel structure on reinforced concrete column
CN204401628U (en) Large-span steel supports multidirectional connector
CN203559432U (en) Underground powerhouse vault
CN205000653U (en) Concrete pump pipe fixing device
CN204059589U (en) A kind of shaped steel combination formula supporting and the cantilevered structure of going along with sb. to guard him
CN202866310U (en) Sleeve type protective railing fastening part for edge hole of floor
CN202090616U (en) Protective device for stairs during construction
CN102277968A (en) Concrete pump pipe fixing structure for ultra-high rise building construction
CN202728873U (en) An adjustable support for conveying cylinders

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130529

Termination date: 20161126

CF01 Termination of patent right due to non-payment of annual fee