CN102277968A - Concrete pump pipe fixing structure for ultra-high rise building construction - Google Patents

Concrete pump pipe fixing structure for ultra-high rise building construction Download PDF

Info

Publication number
CN102277968A
CN102277968A CN2011101133026A CN201110113302A CN102277968A CN 102277968 A CN102277968 A CN 102277968A CN 2011101133026 A CN2011101133026 A CN 2011101133026A CN 201110113302 A CN201110113302 A CN 201110113302A CN 102277968 A CN102277968 A CN 102277968A
Authority
CN
China
Prior art keywords
body frame
pump pipe
concrete pump
building construction
ultra
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011101133026A
Other languages
Chinese (zh)
Inventor
羊成效
皮朝阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN2011101133026A priority Critical patent/CN102277968A/en
Publication of CN102277968A publication Critical patent/CN102277968A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Structures Of Non-Positive Displacement Pumps (AREA)

Abstract

The invention discloses a concrete pump pipe fixing structure for ultra-high rise building construction, which comprises a horizontally-arranged rectangular body frame, wherein one end of the body frame is fixedly connected with a building, the other end of the body frame is provided with a square frame, a pump pipe is sleeved in the square frame and fixed on the square frame through a hoop, support legs are respectively aslant connected to two sides of the body frame, and tail ends of the support legs are fixedly connected with the building. The invention has the advantages of being capable of realizing safe and effective fixation of the concrete pump pipe during the ultra-high rise building construction, ensuring safe operation and management of concrete pumping during the ultra-high rise building construction, and improving safe management level and comprehensive benefits of the ultra-high rise building construction from the main points of the concrete pump pipe fixing structure. The concrete pump pipe fixing structure for the ultra-high rise building construction has the advantages of firmness, reliability, low cost and applicability, flexibility and convenience, can be repeatedly used in a plurality of projects and is convenient for wide popularization and application in building construction enterprises.

Description

A kind of construction of super highrise building concrete pump pipe fixation structure
Technical field
The present invention relates to a kind of concrete pump pipe fixation structure, more specifically say, it relates to a kind of construction of super highrise building concrete pump pipe fixation structure.
Background technology
At present construction of super highrise building concrete pump line is fixing all is to adopt steelframe and the scaffold material as the fixed pump pipe holder by rule of thumb, in construction of super highrise building, the construction of core tube vertical structure is constructed prior to horizontal structure, can only bear by the vertical structure of finishing of constructing the fixing of concrete pump line, give vertical structure by the special delivery of pump line fixed mount the power that produces in the transmission and concrete transmission.Present construction of super highrise building is fixed by rule of thumb pump line, in the transmission and concrete transmission process because all multifactor uncertainties, have bigger security risk, construction enterprises do not form the fixing systems approach of concrete pump line, have bigger potential safety hazard in the construction of superelevation layer concrete.
Summary of the invention
The objective of the invention is to overcome deficiency of the prior art, provide a kind of rational in infrastructure, cost is low, and safety and firmness effectively reduces the construction of super highrise building concrete pump pipe fixation structure of security risk.
This construction of super highrise building concrete pump pipe fixation structure, the body frame that comprises rectangular horizontal positioned, one end of body frame is fixedlyed connected with building, the other end of body frame is provided with square frame, be arranged with pump line in the square frame, pump line is fixed on the square frame by hoop, each oblique supporting leg that is connected with of the dual-side of body frame, and the end of described supporting leg is fixedlyed connected with building.
As preferably: described hoop and square frame are fixed by double nut.
As preferably: assisting between described hoop and pump line has rubber for tire.
As preferably: described midleg also is provided with lacing and is connected with body frame.
As preferably: the end that described body frame is fixedlyed connected with building is provided with the body frame steel plate, and the body frame steel plate is fixedlyed connected with building by split bolt.
As preferably: the end that described supporting leg is fixedlyed connected with building is provided with the supporting leg steel plate, and the supporting leg steel plate is fixedlyed connected with building by split bolt.
The invention has the beneficial effects as follows: by above patent main points exploitation, can realize in the construction of super highrise building concrete pump line being carried out safe and effective fixing, guarantee the safe operation and the management of construction of super highrise building concrete pumping, improve the safety management level and the comprehensive benefit of construction of super highrise building.This construction of super highrise building concrete pump pipe fixing method is solid and reliable, economic and practical, flexible, can have enough to meet the need use in a plurality of engineerings, is convenient to enterprise in charge of construction and applies widely.
Description of drawings
Fig. 1 is master's TV structure schematic diagram of the present invention;
Fig. 2 is a plan structure schematic diagram of the present invention;
Fig. 3 is the present invention left side TV structure schematic diagram;
Reference numeral: body frame 1; Supporting leg 2; Lacing 3; Pump line 4; Hoop 5; Body frame steel plate 6; Supporting leg steel plate 7; Split bolt 8; Double nut 9; Square frame 10.
The specific embodiment
Below in conjunction with drawings and Examples the present invention is described further.Though the present invention will be described in conjunction with preferred embodiment, should know, do not represent to limit the invention among the described embodiment.On the contrary, the present invention will be contained alternative, modified and the equivalent in the scope of the present invention that can be included in attached claims qualification.
Extremely shown in Figure 3 referring to Fig. 1, construction of super highrise building concrete pump pipe fixation structure of the present invention, the body frame 1 that comprises rectangular horizontal positioned, one end of body frame 1 is fixedlyed connected with building, the other end of body frame 1 is provided with square frame 10, is arranged with pump line 4 in the square frame 10, and pump line 4 is fixed on the square frame 10 by hoop 5, each oblique supporting leg 2 that is connected with of the dual-side of body frame 1, the end of described supporting leg 2 is fixedlyed connected with building.Described hoop 5 is fixing by double nut 9 with square frame 10.4 of described hoop 5 and pump lines are assisted rubber for tire are arranged.Described supporting leg 2 middle parts also are provided with lacing 3 and are connected with body frame 1.The end that described body frame 1 is fixedlyed connected with building is provided with body frame steel plate 6, and body frame steel plate 6 is fixedlyed connected with building by split bolt 8.The end that described supporting leg 2 is fixedlyed connected with building is provided with supporting leg steel plate 7, and supporting leg steel plate 7 is fixedlyed connected with building by split bolt 8.
Size according to the concrete pump line, the equal leg angle of employing 80 * 80 is welded as the long 1240mm that is, wide is the body frame 1 of 350mm, 80 * 80 equal leg angle and body frame 1 welding are adopted in body frame 1 one end tops and middle part, mill the bolt hole of Φ 14 apart from end 138mm, 303mm, 438mm, 603mm place, adopt external application double nuts 9 in the hoop 5 of Φ 12,5 of pump line 4 and hoops assist rubber for tire to carry out pump line 4 to fix.Equal leg angle apart from 520mm place, body frame 1 end employing 80 * 80 becomes 27 degree welding support supporting legs 2 with two side skeletons, length is 994mm, the supporting leg steel plate 7 of the thick 200mm * 240mm of supporting leg 2 ends welding 10mm, supporting leg steel plate 7 mills 4 bolts hole of Φ 22, supporting leg 2 welds 50 * 50 equal leg angle lacing 3 with body frame 1, the body frame steel plate 6 of the thick 200mm * 500mm of body frame 1 end welding 10mm, body frame steel plate 6 mills 6 bolts hole of Φ 22, and body frame steel plate 6 adopts the split bolt 8 of Φ 20 to fixedly connected with the building structure vertical member.

Claims (6)

1. construction of super highrise building concrete pump pipe fixation structure, it is characterized in that: the body frame (1) that comprises rectangular horizontal positioned, one end of body frame (1) is fixedlyed connected with building, the other end of body frame (1) is provided with square frame (10), be arranged with pump line (4) in the square frame (10), pump line (4) is fixed on the square frame (10) by hoop (5), each oblique supporting leg (2) that is connected with of the dual-side of body frame (1), and the end of described supporting leg (2) is fixedlyed connected with building.
2. construction of super highrise building concrete pump pipe fixation structure according to claim 1 is characterized in that: described hoop (5) is fixing by double nut (9) with square frame (10).
3. construction of super highrise building concrete pump pipe fixation structure according to claim 1 is characterized in that: assisting between described hoop (5) and pump line (4) has rubber for tire.
4. construction of super highrise building concrete pump pipe fixation structure according to claim 1 is characterized in that: described supporting leg (2) middle part also is provided with lacing (3) and is connected with body frame (1).
5. construction of super highrise building concrete pump pipe fixation structure according to claim 1, it is characterized in that: the end that described body frame (1) is fixedlyed connected with building is provided with body frame steel plate (6), and body frame steel plate (6) is fixedlyed connected with building by split bolt (8).
6. construction of super highrise building concrete pump pipe fixation structure according to claim 1, it is characterized in that: the end that described supporting leg (2) is fixedlyed connected with building is provided with supporting leg steel plate (7), and supporting leg steel plate (7) is fixedlyed connected with building by split bolt (8).
CN2011101133026A 2011-04-27 2011-04-27 Concrete pump pipe fixing structure for ultra-high rise building construction Pending CN102277968A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101133026A CN102277968A (en) 2011-04-27 2011-04-27 Concrete pump pipe fixing structure for ultra-high rise building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101133026A CN102277968A (en) 2011-04-27 2011-04-27 Concrete pump pipe fixing structure for ultra-high rise building construction

Publications (1)

Publication Number Publication Date
CN102277968A true CN102277968A (en) 2011-12-14

Family

ID=45103665

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101133026A Pending CN102277968A (en) 2011-04-27 2011-04-27 Concrete pump pipe fixing structure for ultra-high rise building construction

Country Status (1)

Country Link
CN (1) CN102277968A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103541551A (en) * 2012-07-11 2014-01-29 上海建工五建集团有限公司 Construction structure suitable for super high-rise concrete-filled steel tubes and side throwing vibration-free method
CN103628685A (en) * 2013-12-12 2014-03-12 深圳市鹏城建筑集团有限公司 Method for preventing concrete lateral displacement of concrete pump pipe and concrete pump pipe strengthening device
CN106353031A (en) * 2016-08-26 2017-01-25 北京建工新型建材有限责任公司 Horizontal coil system and method for monitoring super high-rise pumping pressure of large flowing concrete

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201344316Y (en) * 2008-12-17 2009-11-11 李奇超 Supporting fixing device of pipeline system
CN201358588Y (en) * 2008-12-30 2009-12-09 三一重工股份有限公司 Concrete transportation pipe fixing device capable of absorbing shock and reducing noise
CN201568641U (en) * 2010-01-04 2010-09-01 山东电力研究院 Apparatus for limiting horizontal pipe displacement
CN201606575U (en) * 2009-12-30 2010-10-13 中建一局集团第二建筑有限公司 Copper pipe bearing support for super high-rise building
CN201795174U (en) * 2010-07-30 2011-04-13 北京城建设计研究总院有限责任公司 Fixing support for erecting and laying ductile iron pipes
CN202039606U (en) * 2011-04-27 2011-11-16 中天建设集团有限公司 Concrete pump pipe fixing structure of super high rise building construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201344316Y (en) * 2008-12-17 2009-11-11 李奇超 Supporting fixing device of pipeline system
CN201358588Y (en) * 2008-12-30 2009-12-09 三一重工股份有限公司 Concrete transportation pipe fixing device capable of absorbing shock and reducing noise
CN201606575U (en) * 2009-12-30 2010-10-13 中建一局集团第二建筑有限公司 Copper pipe bearing support for super high-rise building
CN201568641U (en) * 2010-01-04 2010-09-01 山东电力研究院 Apparatus for limiting horizontal pipe displacement
CN201795174U (en) * 2010-07-30 2011-04-13 北京城建设计研究总院有限责任公司 Fixing support for erecting and laying ductile iron pipes
CN202039606U (en) * 2011-04-27 2011-11-16 中天建设集团有限公司 Concrete pump pipe fixing structure of super high rise building construction

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103541551A (en) * 2012-07-11 2014-01-29 上海建工五建集团有限公司 Construction structure suitable for super high-rise concrete-filled steel tubes and side throwing vibration-free method
CN103541551B (en) * 2012-07-11 2015-06-24 上海建工五建集团有限公司 Construction structure suitable for super high-rise concrete-filled steel tubes and side throwing vibration-free method
CN103628685A (en) * 2013-12-12 2014-03-12 深圳市鹏城建筑集团有限公司 Method for preventing concrete lateral displacement of concrete pump pipe and concrete pump pipe strengthening device
CN103628685B (en) * 2013-12-12 2015-11-18 深圳市鹏城建筑集团有限公司 A kind of method and concrete pump pipe bracing means preventing concrete pump pipe lateral displacement
CN106353031A (en) * 2016-08-26 2017-01-25 北京建工新型建材有限责任公司 Horizontal coil system and method for monitoring super high-rise pumping pressure of large flowing concrete

Similar Documents

Publication Publication Date Title
CN103075020B (en) A kind of steel tray supports actuating system
CN204098918U (en) Dimensional parameters multiple degrees of freedom is adjustable uses shield launching bracket repeatedly
CN202039606U (en) Concrete pump pipe fixing structure of super high rise building construction
CN105484514A (en) Method for strengthening circular reinforced concrete pier column
CN102277968A (en) Concrete pump pipe fixing structure for ultra-high rise building construction
CN202954557U (en) Scaffold wall connection part
CN205207907U (en) Novel pipeline bracket of tape base plinth
CN206738723U (en) A kind of U-shaped hydraulic pipeline support
CN202936996U (en) Wall connecting piece for scaffold
CN101881029A (en) Detachable tower foundation
CN204024084U (en) Easy unloading type triangular pipe truss just spells moulding bed
CN204552111U (en) Material distributing machine
CN203907010U (en) Flexible connection device for pipe jacking construction in soft soil layer
CN204040494U (en) The assembled moulding bed of easy unloading type triangular pipe truss
CN206015628U (en) Combination type for pressure penstock installation in hole is unloaded arc bracket assembly from jacking
CN202248255U (en) Inclined single-end steel support
CN202577162U (en) Combined-type steel pipe bracket
CN105569368A (en) Annular steel plate strengthening device for reinforced concrete column with circular cross section
CN205575471U (en) Reducing jar body hoisting device on power station desulfurization absorption tower
CN204728149U (en) Be applicable to the quick lap joint track of geological hazard control engineering rolling topography
CN203878779U (en) Rectangular concrete-filled steel tube column and I-steel beam rebar penetrating type joint
CN203475867U (en) Lattice type supporting system
CN203411908U (en) Temporary tensioned prestress anchoring device
CN207582985U (en) A kind of fixing bracket for transporting prefabricated panel
CN206397109U (en) The connecting elements of external scaffolding wall connecting rod part and shear wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20111214