CN206015628U CN201620811714.5U CN201620811714U CN206015628U CN 206015628 U CN206015628 U CN 206015628U CN 201620811714 U CN201620811714 U CN 201620811714U CN 206015628 U CN206015628 U CN 206015628U
Authority
CN
China
Prior art keywords
jacking
hole
bracket assembly
combination type
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620811714.5U
Other languages
Chinese (zh)
Inventor
陈群运
卫学识
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Mechanical and Electrical Construction Co Ltd
Original Assignee
China Gezhouba Group Mechanical and Electrical Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Mechanical and Electrical Construction Co Ltd filed Critical China Gezhouba Group Mechanical and Electrical Construction Co Ltd
Priority to CN201620811714.5U priority Critical patent/CN206015628U/en
Application granted granted Critical
Publication of CN206015628U publication Critical patent/CN206015628U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

A kind of combination type for pressure penstock installation in hole is unloaded arc bracket assembly from jacking, including two supporting legs, two supporting leg one end are fixedly connected by bolt with transport trolley, the two supporting leg other ends are connected to form an entirety with arc joist by top board and bolt, jack is positioned in the cavity between two supporting legs, and the top board hole that the jacking end of jack is opened up from top board is stretched out and is engaged with arc joist bottom surface of support saddle.The combination type for pressure penstock installation in hole that this utility model is provided is unloaded arc bracket assembly from jacking, can solve the problems, such as that costly, efficiency is low, both reduce cost, improve efficiency, and safe and reliable, easy to operate.

Description

Combination type for pressure penstock installation in hole is unloaded arc bracket assembly from jacking
Technical field
This utility model is related to a kind of bracket assembly, and especially a kind of combination type for pressure penstock installation in hole is from top Rise arc bracket assembly of unloading.
Background technology
At present, penstock installation unit entrucking transport is arrived by work using transport trolley bearing mode in hydroelectric project tunnel Behind position, it is typically employed in erection jack between transport trolley left and right sides crag and steel pipe and is unloaded, as which requires peace Dress unit is in the special supporting leg of unloading of maker welding equipment while the tunnel wall of very heavy top/bottom part is cambered surface normally cannot support, it is necessary to Carry out local chipping process or pour concrete buttress of unloading.Therefore, using which is costly, efficiency is low, very heavy top bottom surface flat Whole property is larger to jacking security implication, particularly when installation unit only have one stiffening ring when, unload jacking when security risk Larger.
Content of the invention
Technical problem to be solved in the utility model is to provide a kind of combination type for pressure penstock installation in hole certainly Jacking is unloaded arc bracket assembly, can solve the problems, such as that costly, efficiency is low, both reduce cost, improve efficiency, pacifies again Entirely reliable, easy to operate.
For solving above-mentioned technical problem, the technical scheme adopted by this utility model is:One kind is for penstock in hole The combination type of installation is unloaded arc bracket assembly from jacking, and including two supporting legs, two supporting leg one end are with transport trolley by positioning spiral shell Bolt is fixedly connected, and the two supporting leg other ends are connected to form an entirety with arc joist by top board and bolt, and jack is positioned over In cavity between two supporting legs, top board hole that the jacking end of jack is opened up from top board stretch out and with arc joist bearing bottom Face is engaged.
Bolt is flange bolt.
The combination type for pressure penstock installation in hole that this utility model is provided is unloaded arc bracket assembly from jacking, adopts Carry out the entrucking of penstock installation unit to support and unload construction from jacking with transport trolley bearing mode, take full advantage of transport Chassis, rail supporting body system, it is to avoid routine techniquess need to arrange the supporting leg need in supporting leg correspondence position of unloading to tunnel arc of unloading The drawbacks of face crag is processed, low cost, efficiency high, safe and reliable, easy to use, can meet in tunnel and adopt transport trolley Bearing mode carries out the entrucking of penstock installation unit and supports and unload construction from jacking.Super-large diameter, super large can especially be met The situation of weight, tunnel and penstock outer wall narrow space.
Description of the drawings
The utility model is described in further detail with reference to the accompanying drawings and examples:
Fig. 1 is structural representation of the present utility model;
Fig. 2 is schematic diagram of this utility model on penstock installation unit.
Specific embodiment
As shown in figure 1, a kind of combination type for pressure penstock installation in hole is unloaded arc bracket assembly from jacking, including Two supporting legs 2, two supporting legs, 2 one end are fixedly connected by bolt 5 with the chassis beam 8 of transport trolley 7, and two supporting legs, 2 other end leads to Cross top board 6 and bolt 3 and be connected one entirety of formation with arc joist 1, jack 4 is positioned in the cavity between two supporting legs 2, thousand The top board hole that the jacking end on jin top 4 is opened up from top board 6 is stretched out and is engaged with 1 bottom surface of support saddle of arc joist.
Bolt 3 is flange bolt.
Schematic diagram of this utility model on penstock installation unit 9 is as shown in Fig. 2 first by supporting leg 2 when using It is connected by bolt 5 with the chassis beam 8 of transport trolley 7, then arc joist 1 is connected by flange bolt 3 with supporting leg 2 It is integrated;Then jack 4 is inserted in its cavity from 2 left and right banks direction open-mouth of supporting leg, and is stretched by 2 top board hole of supporting leg Go out and held out against with 1 bottom surface of support saddle of arc joist in advance.After 9 entrucking of penstock installation unit transport in place, arc joist 1 and supporting leg 2 Flange bolt 3 between faying face is unlocked, operates 4 jacking of jack;Installation unit jacking is in place, in transport trolley both sides, steel pipe adds Between strength ring and tunnel crag, after welding equipment bracing members, jack 4 falls to withdrawing from and complete to unload.
9 entrucking of penstock installation unit is carried out using transport trolley bearing mode to support and unload construction from jacking, is filled Point make use of transport trolley 7, rail supporting body system 10, it is to avoid routine techniquess need to arrange the supporting leg need to be in supporting leg of unloading of unloading The drawbacks of correspondence position is processed to tunnel cambered surface crag, low cost, efficiency high, safe and reliable, easy to use, tunnel can be met The entrucking of penstock installation unit is carried out using transport trolley bearing mode in hole to support and unload construction from jacking.Especially can be full The situation of sufficient super-large diameter, super large weight, tunnel and penstock outer wall narrow space.

Claims (2)

1. a kind of combination type for pressure penstock installation in hole is unloaded arc bracket assembly from jacking, it is characterised in that:Including Two supporting legs(2), two supporting legs(2)One end and transport trolley(7)By bolt(5)It is fixedly connected, two supporting legs(2)The other end leads to Cross top board(6)And bolt(3)With arc joist(1)Connection forms an entirety, jack(4)It is positioned over two supporting legs(2)Between Cavity in, jack(4)Jacking end from top board(6)On the top board hole that opens up stretch out and with arc joist(1)Bearing bottom Face is engaged.
2. the combination type for pressure penstock installation in hole according to claim 1 is unloaded arc bracket assembly from jacking, It is characterized in that:Bolt(3)For flange bolt.
CN201620811714.5U 2016-07-29 2016-07-29 Combination type for pressure penstock installation in hole is unloaded arc bracket assembly from jacking Expired - Fee Related CN206015628U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620811714.5U CN206015628U (en) 2016-07-29 2016-07-29 Combination type for pressure penstock installation in hole is unloaded arc bracket assembly from jacking

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620811714.5U CN206015628U (en) 2016-07-29 2016-07-29 Combination type for pressure penstock installation in hole is unloaded arc bracket assembly from jacking

Publications (1)

Publication Number Publication Date
CN206015628U true CN206015628U (en) 2017-03-15

Family

ID=58245734

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620811714.5U Expired - Fee Related CN206015628U (en) 2016-07-29 2016-07-29 Combination type for pressure penstock installation in hole is unloaded arc bracket assembly from jacking

Country Status (1)

Country Link
CN (1) CN206015628U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107010567A (en) * 2017-06-02 2017-08-04 中国水利水电第七工程局有限公司 Self-unloading Mobile hydraulic elevating equipment in a kind of penstock hole
CN109017533A (en) * 2018-07-25 2018-12-18 中国葛洲坝集团机械船舶有限公司 A kind of special transportation vehicle and method for large-scale steel pipe transport installation

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107010567A (en) * 2017-06-02 2017-08-04 中国水利水电第七工程局有限公司 Self-unloading Mobile hydraulic elevating equipment in a kind of penstock hole
CN109017533A (en) * 2018-07-25 2018-12-18 中国葛洲坝集团机械船舶有限公司 A kind of special transportation vehicle and method for large-scale steel pipe transport installation

Similar Documents

Publication Publication Date Title
CN203639005U (en) Reinforcing device of tower crane
CN103572763B (en) Large-span steel supports pattern foundation pit supporting structure Demolition Construction method
CN206015628U (en) Combination type for pressure penstock installation in hole is unloaded arc bracket assembly from jacking
CN205134271U (en) Artifical dam body of groundwater reservoir
CN202039606U (en) Concrete pump pipe fixing structure of super high rise building construction
CN104476055B (en) A kind of spud leg manufacture method of meter of font stay tube
CN105019405A (en) Offshore wind turbine foundation docking member with easy assembly and disassembly
CN204686330U (en) Adjustable support structure frock
CN204040494U (en) The assembled moulding bed of easy unloading type triangular pipe truss
CN203959007U (en) Rotational moulding transfer cask
CN105883605A (en) Web reinforcing device for crane
CN207452955U (en) A kind of measurement in a closed series Tower System
CN206488246U (en) The draw bail of street lamp steel pipe lamp stand and pedestal
CN205329739U (en) Wind -powered electricity generation field aerogenerator tower section of thick bamboo basis reinforcing apparatus
CN204662997U (en) A kind of pump line elbow bracing reinforcement component
CN102277968A (en) Concrete pump pipe fixing structure for ultra-high rise building construction
CN203920973U (en) A kind of Multi-functional transporting chassis for large-scale penstock installation in tunnel
CN201512354U (en) Connecting structure of floor beam and support leg of crane
CN106760568A (en) A kind of construction servicing unit
CN202557542U (en) Arc trolley used for horizontally transporting penstock in hole
CN205061241U (en) Elevator load -bearing device structure
CN205172606U (en) I -steel canopy
CN204264661U (en) A kind of carriage/storage device of large cylindrical parts
CN204690760U (en) A kind of inner supporting structure drawing lagging pile for supporting anchor in basement construction
CN207111099U (en) A kind of detachable vehicle frame for supporting trailer after rock tunnel(ling) machine

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170315

Termination date: 20180729

CF01 Termination of patent right due to non-payment of annual fee