CN204754945U - Mine method tunnel preliminary bracing lining cutting grid steel support make - Google Patents

Mine method tunnel preliminary bracing lining cutting grid steel support make Download PDF

Info

Publication number
CN204754945U
CN204754945U CN201520431049.2U CN201520431049U CN204754945U CN 204754945 U CN204754945 U CN 204754945U CN 201520431049 U CN201520431049 U CN 201520431049U CN 204754945 U CN204754945 U CN 204754945U
Authority
CN
China
Prior art keywords
main reinforcement
chord
reinforcement chord
steel frame
grid steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201520431049.2U
Other languages
Chinese (zh)
Inventor
史宣陶
林刚
罗世陪
李学军
喻波
张建祥
徐剑旋
李辉
罗生
徐亮
徐搴
段劲夫
彭健海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201520431049.2U priority Critical patent/CN204754945U/en
Application granted granted Critical
Publication of CN204754945U publication Critical patent/CN204754945U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

矿山法隧道初期支护衬砌格栅钢架构造,在满足结构安全和构造要求的前提下,能有效降低构造钢筋比例,降低格栅钢架单延米重量,减小工程投资。包括在横截面上呈三角形布设的第一主筋弦杆、第二主筋弦杆和第三主筋弦杆,第一主筋弦杆与第二主筋弦杆、第一主筋弦杆与第三主筋弦杆、第二主筋弦杆与第三主筋弦杆之间搭接焊接斜杆钢筋形成竖向延伸的格栅钢架。

Under the premise of meeting the structural safety and structural requirements, the initial support lining grid steel frame structure of the mining method tunnel can effectively reduce the proportion of structural steel bars, reduce the weight per linear meter of the grid steel frame, and reduce project investment. Including the first main reinforcement chord, the second main reinforcement chord and the third main reinforcement chord arranged in a triangle on the cross section, the first main reinforcement chord and the second main reinforcement chord, the first main reinforcement chord and the third main reinforcement chord , The second main reinforcement chord and the third main reinforcement chord are overlapped to form a vertically extending grid steel frame.

Description

矿山法隧道初期支护衬砌格栅钢架构造Primary support lining grid steel frame structure of mining method tunnel

技术领域technical field

本实用新型涉及隧道工程,特别涉及一种适用于矿山法隧道初期支护衬砌的格栅钢架。The utility model relates to tunnel engineering, in particular to a grid steel frame suitable for the initial support lining of mine tunnels.

背景技术Background technique

目前,矿山法施工工法在高速公路、铁路、地铁隧道中使用相当广泛,其一般采用复合式衬砌结构,即由开挖后立即施作的初期支护和后期模筑的二次衬砌组成。At present, the mining method construction method is widely used in expressways, railways, and subway tunnels. It generally adopts a composite lining structure, which is composed of primary support immediately after excavation and secondary lining in the later stage.

矿山法初期支护作为施工阶段的主要承载结构,在防止围岩坍塌、抑制围岩变形、承受施工期间围岩荷载及增强结构耐久性等方面起着重要作用。目前初期支护一般由型钢钢架或钢筋格栅钢架与喷射混凝土组成;在地质条件较好的地段通常采用钢筋格栅钢架,格栅钢架为四弦杆式,主杆间设斜杆,组合焊接成格栅形式。由于四弦杆式格栅钢架构造钢筋比例较高,因此在满足结构安全和构造要求的前提下,可对传统的四弦杆式格栅钢架进行研究和优化。As the main load-bearing structure in the construction stage, the primary support of mining method plays an important role in preventing the collapse of surrounding rock, restraining the deformation of surrounding rock, bearing the load of surrounding rock during construction and enhancing the durability of the structure. At present, the initial support is generally composed of section steel frame or steel grid steel frame and shotcrete; in areas with good geological conditions, steel grid steel frame is usually used. Rods, welded in combination into a grid form. Due to the relatively high proportion of steel bars in the structure of the four-chord grid steel frame, the traditional four-chord grid steel frame can be studied and optimized under the premise of meeting the structural safety and construction requirements.

实用新型内容Utility model content

本实用新型所要解决的技术问题是提供一种矿山法隧道初期支护衬砌格栅钢架构造,在满足结构安全和构造要求的前提下,能有效降低构造钢筋比例,降低格栅钢架单延米重量,减小工程投资。The technical problem to be solved by the utility model is to provide a mine tunnel initial support lining grid steel frame structure, which can effectively reduce the proportion of structural steel bars and reduce the single extension of the grid steel frame on the premise of meeting the structural safety and structural requirements. meter weight, reducing engineering investment.

本实用新型解决其技术问题所采用的技术方案如下:The technical solution adopted by the utility model to solve its technical problems is as follows:

本实用新型矿山法隧道初期支护衬砌格栅钢架构造,其特征是:包括在横截面上呈三角形布设的第一主筋弦杆、第二主筋弦杆和第三主筋弦杆,第一主筋弦杆与第二主筋弦杆、第一主筋弦杆与第三主筋弦杆、第二主筋弦杆与第三主筋弦杆之间搭接焊接斜杆钢筋形成竖向延伸的格栅钢架。The utility model mine tunnel primary support lining grid steel frame structure is characterized in that it includes the first main reinforcement chord, the second main reinforcement chord and the third main reinforcement chord arranged in a triangle on the cross section, the first main reinforcement The vertically extending grid steel frame is formed by overlapping welded oblique bar steel bars between the chord bar and the second main bar chord bar, the first main bar chord bar and the third main bar chord bar, and the second main bar chord bar and the third main bar chord bar.

本实用新型的有益效果是,将主筋弦杆由传统的4根调整为3根,能有效降低构造钢筋比例,降低格栅钢架单延米重量,减小工程投资。The beneficial effect of the utility model is that the main reinforcement chords are adjusted from four traditional ones to three, which can effectively reduce the proportion of structural steel bars, reduce the weight per linear meter of the grid steel frame, and reduce engineering investment.

附图说明Description of drawings

本说明书包括如下六幅附图:This manual includes the following six drawings:

图1是本实用新型矿山法隧道初期支护衬砌格栅钢架构造的横截面图Figure 1 is a cross-sectional view of the initial support lining grid steel frame structure of the utility model mine tunnel

图2是本实用新型矿山法隧道初期支护衬砌格栅钢架构造的左视图;Fig. 2 is the left view of the initial support lining grid steel frame structure of the utility model mine tunnel;

图3是本实用新型矿山法隧道初期支护衬砌格栅钢架构造的右视图;Fig. 3 is the right view of the initial support lining grid steel frame structure of the utility model mine tunnel;

图4是本实用新型矿山法隧道初期支护衬砌格栅钢架构造中斜杆钢筋的大样图;Fig. 4 is a large sample diagram of the oblique bar reinforcement in the initial support lining grid steel frame structure of the utility model mine tunnel;

图5是本实用新型矿山法隧道初期支护衬砌格栅钢架构造中箍筋的大样图;Fig. 5 is a large sample diagram of the stirrup in the initial support lining grid steel frame structure of the utility model mine tunnel;

图6是本实用新型矿山法隧道初期支护衬砌格栅钢架构造中接头的示意图。Fig. 6 is a schematic diagram of the joints in the initial support lining grid steel frame structure of the mine tunnel of the utility model.

图中示出构件名称及所对应的标记:第一主筋弦杆11a、第二主筋弦杆11b、第三主筋弦杆12、斜杆钢筋13、箍筋14、接头钢板15。The figure shows component names and corresponding marks: the first main reinforcement chord 11a, the second main reinforcement chord 11b, the third main reinforcement chord 12, the inclined bar reinforcement 13, the stirrup 14, and the joint steel plate 15.

具体实施方式Detailed ways

下面结合附图和具体的实施方式对本实用新型作进一步详细说明。The utility model will be described in further detail below in conjunction with the accompanying drawings and specific embodiments.

参照图1、图2和图3,本实用新型矿山法隧道初期支护衬砌格栅钢架构造,包括在横截面上呈三角形布设的第一主筋弦杆11a、第二主筋弦杆11b和第三主筋弦杆12,第一主筋弦杆11a与第二主筋弦杆11b、第一主筋弦杆11a与第三主筋弦杆12、第二主筋弦杆11b与第三主筋弦杆12之间搭接焊接斜杆钢筋13形成竖向延伸的格栅钢架。即主筋弦杆及连接主筋弦杆的斜杆从传统的4根调整为3根,能有效降低构造钢筋比例,降低格栅钢架单延米重量,减小工程投资。Referring to Fig. 1, Fig. 2 and Fig. 3, the primary support lining grid steel frame structure of the mining method tunnel of the present invention includes the first main reinforcement chord 11a, the second main reinforcement chord 11b and the first main reinforcement chord 11b arranged in a triangle on the cross section. Three main reinforcement chords 12, the first main reinforcement chord 11a and the second main reinforcement chord 11b, the first main reinforcement chord 11a and the third main reinforcement chord 12, the second main reinforcement chord 11b and the third main reinforcement chord 12 The grid steel frame extending vertically is formed by welding the oblique bar reinforcing bar 13. That is to say, the main reinforcement chord and the oblique rods connecting the main reinforcement chord are adjusted from the traditional 4 to 3, which can effectively reduce the proportion of structural reinforcement, reduce the weight per linear meter of the grid steel frame, and reduce the project investment.

参照图1、图2、图3、图4和图5,所述格栅钢架上竖向间隔设置箍筋14,各箍筋14位于第一主筋弦杆11a、第二主筋弦杆11b和第三主筋弦杆12的外侧且与之固定连接。参照图6,所述格栅钢架的竖向端设置有接头钢板15,该接头钢板15与第一主筋弦杆11a、第二主筋弦杆11b和第三主筋弦杆12的纵向端穿孔塞焊连接,接头钢板15上间隔布设螺栓连接孔,格栅钢架节与节之间通过螺栓连接。Referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4 and Fig. 5, stirrups 14 are vertically spaced on the grid steel frame, and each stirrup 14 is located at the first main reinforcement chord 11a, the second main reinforcement chord 11b and The outer side of the third main rib chord 12 is fixedly connected with it. Referring to Fig. 6, the vertical end of the grid steel frame is provided with a joint steel plate 15, and the joint steel plate 15 is connected with the longitudinal end of the first main reinforcement chord 11a, the second main reinforcement chord 11b and the third main reinforcement chord 12. Welding connection, bolt connection holes are arranged at intervals on the joint steel plate 15, and the grid steel frame sections are connected by bolts.

以上所述只是用图解说明实用新型矿山法隧道初期支护衬砌格栅钢架构造的一些原理,并非是要将本实用新型局限在所示和所述的具体结构和适用范围内,故凡是所有可能被利用的相应修改以及等同物,均属于本实用新型所申请的专利范围。The above description is just to illustrate some principles of the initial support lining grid steel frame structure of the utility model mine method tunnel, not to limit the utility model to the specific structure and scope of application shown and described, so all Corresponding modifications and equivalents that may be utilized all belong to the patent scope of the utility model application.

Claims (3)

1.矿山法隧道初期支护衬砌格栅钢架构造,其特征是:包括在横截面上呈三角形布设的第一主筋弦杆(11a)、第二主筋弦杆(11b)和第三主筋弦杆(12),第一主筋弦杆(11a)与第二主筋弦杆(11b)、第一主筋弦杆(11a)与第三主筋弦杆(12)、第二主筋弦杆(11b)与第三主筋弦杆(12)之间搭接焊接斜杆钢筋(13)形成竖向延伸的格栅钢架。1. The primary support lining grid steel frame structure of the mine method tunnel, which is characterized by: including the first main reinforcement chord (11a), the second main reinforcement chord (11b) and the third main reinforcement chord arranged in a triangle on the cross section Rod (12), the first main reinforcement chord (11a) and the second main reinforcement chord (11b), the first main reinforcement chord (11a) and the third main reinforcement chord (12), the second main reinforcement chord (11b) and The third main reinforcement chords (12) are overlapped with welded inclined bar steel bars (13) to form a vertically extending grid steel frame. 2.如权利要求1所述的矿山法隧道初期支护衬砌格栅钢架构造,其特征是:所述格栅钢架上竖向间隔设置箍筋(14),各箍筋(14)位于第一主筋弦杆(11a)、第二主筋弦杆(11b)和第三主筋弦杆(12)的外侧且与之固定连接。2. The initial support lining grid steel frame structure of mine tunnel as claimed in claim 1, characterized in that: vertically spaced stirrups (14) are arranged on the grid steel frame, and each stirrup (14) is located at The outer sides of the first main reinforcement chord (11a), the second main reinforcement chord (11b) and the third main reinforcement chord (12) are fixedly connected thereto. 3.如权利要求1所述的矿山法隧道初期支护衬砌格栅钢架构造,其特征是:所述格栅钢架的竖向端设置有接头钢板(15),该接头钢板(15)与第一主筋弦杆(11a)、第二主筋弦杆(11b)和第三主筋弦杆(12)的纵向端穿孔塞焊连接,接头钢板(15)上间隔布设螺栓连接孔。3. The mine method tunnel primary support lining grid steel frame structure as claimed in claim 1, characterized in that: the vertical end of the grid steel frame is provided with a joint steel plate (15), and the joint steel plate (15) It is connected with the longitudinal ends of the first main reinforcement chord (11a), the second main reinforcement chord (11b) and the third main reinforcement chord (12) through hole plug welding, and bolt connection holes are arranged at intervals on the joint steel plate (15).
CN201520431049.2U 2015-06-23 2015-06-23 Mine method tunnel preliminary bracing lining cutting grid steel support make Expired - Lifetime CN204754945U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520431049.2U CN204754945U (en) 2015-06-23 2015-06-23 Mine method tunnel preliminary bracing lining cutting grid steel support make

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520431049.2U CN204754945U (en) 2015-06-23 2015-06-23 Mine method tunnel preliminary bracing lining cutting grid steel support make

Publications (1)

Publication Number Publication Date
CN204754945U true CN204754945U (en) 2015-11-11

Family

ID=54469664

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520431049.2U Expired - Lifetime CN204754945U (en) 2015-06-23 2015-06-23 Mine method tunnel preliminary bracing lining cutting grid steel support make

Country Status (1)

Country Link
CN (1) CN204754945U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105781593A (en) * 2016-05-13 2016-07-20 中铁四局集团第三建设有限公司 Steel grating assisted diversion tunnel preliminary bracing structure and method
CN109372554A (en) * 2018-12-25 2019-02-22 中铁二院工程集团有限责任公司 The method and device of steelframe connecting plate screw is protected in a kind of constructing tunnel
CN112727493A (en) * 2020-12-30 2021-04-30 中铁十八局集团第三工程有限公司 Lining structure for reinforcing steel bars of facing of karst tunnel secondary lining plain concrete section

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105781593A (en) * 2016-05-13 2016-07-20 中铁四局集团第三建设有限公司 Steel grating assisted diversion tunnel preliminary bracing structure and method
CN109372554A (en) * 2018-12-25 2019-02-22 中铁二院工程集团有限责任公司 The method and device of steelframe connecting plate screw is protected in a kind of constructing tunnel
CN112727493A (en) * 2020-12-30 2021-04-30 中铁十八局集团第三工程有限公司 Lining structure for reinforcing steel bars of facing of karst tunnel secondary lining plain concrete section

Similar Documents

Publication Publication Date Title
CN205189893U (en) Be used for a lane coal column to wearing reinforced (rfd) supporting construction
CN106894523A (en) A kind of connecting node of rectangular steel-tube concrete column and girder with rolled steel section en cased in concrete
CN103572839B (en) Mixed shear connector
CN102953739A (en) Bidirectional punching method for underground excavation of subway station
CN106567499B (en) Prefabricated steel-concrete combined column structure and its implementation method
CN206092004U (en) Loess tunnel initial stage supporting device that is under construction
CN104790970A (en) Method for utilizing combined structure to conduct shield tunnel strengthening
CN106050240A (en) Stability control method for mountainous area weak surrounding rock small-distance tunnel mid-adjacent rock
CN113738422B (en) Determination method of soft rock roadway floor heave amount calculation, control and control method
CN103953361A (en) Clearance strengthening system for serious cracks of existing tunnel arch lining
CN204877493U (en) Soft rock tunnel supporting construction
CN204754945U (en) Mine method tunnel preliminary bracing lining cutting grid steel support make
CN103953362A (en) Clearance-free strengthening system for serious cracks of existing tunnel arch lining
CN203531922U (en) High-toughness nodular cast iron and reinforced concrete combined tunnel wall plate
CN104196152B (en) Connecting structure for steel coupling beam and concrete wall
CN206942196U (en) The structure of attached assembling type node power consumption frame strengthening outside a kind of existing framework
CN106437758B (en) Upper and lower integral type shield tunnel segment lining structure
CN204253052U (en) A kind of lattice steel reinforced concrete antiarch support
CN205532716U (en) Block structure of ore bin bottom
CN203878779U (en) Rectangular concrete-filled steel tube column and I-steel beam rebar penetrating type joint
CN206942780U (en) A kind of tunnel cross mouth advance support structure
CN205154191U (en) Tunnel preliminary bracing steel pipe concrete steelframe
CN204783112U (en) Mining novel air door wall body
CN204001280U (en) A kind of fabricated shear wall of novel embedded i iron
CN212177164U (en) Section steel and shotcrete combined stiff structure tunnel supporting system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20151111