CN202850027U - Reverse building method pile foundation construction steel column location verticality adjustment device - Google Patents
Reverse building method pile foundation construction steel column location verticality adjustment device Download PDFInfo
- Publication number
- CN202850027U CN202850027U CN 201220442459 CN201220442459U CN202850027U CN 202850027 U CN202850027 U CN 202850027U CN 201220442459 CN201220442459 CN 201220442459 CN 201220442459 U CN201220442459 U CN 201220442459U CN 202850027 U CN202850027 U CN 202850027U
- Authority
- CN
- China
- Prior art keywords
- vertical adjustment
- pile foundation
- verticality
- foundation construction
- steel post
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Foundations (AREA)
Abstract
The utility model relates to the construction field of building foundations, in particular to a reverse building method pile foundation construction steel column location verticality adjustment device which is characterized by comprising a verticality adjustment frame wholly of a cuboid frame structure. An upper verticality adjustment bolt set for locating steel columns and adjusting the verticality of the steel columns is positioned at the upper portion of the verticality adjustment frame, and a lower verticality adjustment bolt set for locating the steel columns and adjusting the verticality of the steel columns is positioned at the upper portion of the verticality adjustment frame. The reverse building method pile foundation construction steel column location verticality adjustment device can accurately locate the reverse method pile foundation construction steel columns and adjust verticality of the reverse method pile foundation construction steel columns.
Description
Technical field
The utility model relates to the construction foundation working field, particularly a kind of contrary sequence method pile foundation construction steel post positioning and plumbing device.
Background technology
The conventional order of architecture construction is first excavation pit, then from the basis, and successively upwards construction, the supporting that excavation of foundation pit is required belongs to the measure of construction, and each is irrelevant with the underground structure of building.Contrary sequence method is for the conventional order of architecture construction, basement top-down method construction is that the building cover structure, beam, plate, post and the external wall structure that utilize basement is as the braced structures of foundation pit enclosure structure and foundation construction, the hole in horizontal struts system with go along with sb. to guard him the construction that system is from top to bottom carried out basement structure, meanwhile can carry out the construction of superstructure.In the reverse construction stage, when the basis end and vertical structure not yet formed, all structural loads of top were born by steel post in the stake and diaphragm wall, so the positioning and plumbing of steel post is of crucial importance.
Summary of the invention
The purpose of this utility model is to overcome the shortcoming of prior art, and a kind of contrary sequence method pile foundation construction steel post positioning and plumbing device is provided, and can position and vertical adjustment contrary sequence method pile foundation construction steel post effectively accurately.
For solving above technical problem, the technical solution of the utility model is: contrary sequence method pile foundation construction steel post positioning and plumbing device, its difference is: it comprises that integral body is the vertical adjustment frame of cuboid frame construction, the top of described vertical adjustment frame is provided with for the upper vertical adjustment bolt group that steel post is positioned vertical adjustment, and the bottom of described vertical adjustment frame is provided with for the lower vertical adjustment bolt group that steel post is positioned vertical adjustment.
[0005]By above scheme, the bolt quantity of described upper vertical adjustment bolt group, lower vertical adjustment bolt group is four, and described upper vertical adjustment bolt group, lower vertical adjustment bolt group all circumferentially are crossing distribution around steel post.
The contrast prior art, beneficial features of the present utility model is: this contrary sequence method pile foundation construction steel post positioning and plumbing device can position and vertical adjustment contrary sequence method pile foundation construction steel post effectively accurately.
Description of drawings
Fig. 1 is the utility model embodiment structural representation under the use state in the construction of pile foundation steel post;
Fig. 2 is the plan structure schematic diagram of the utility model embodiment;
Wherein: vertical adjustment bolt group, 3-vertical adjustment frame, 4-steel post, 5-stake hole under the upper vertical adjustment bolt of 1-group, the 2-.
The specific embodiment
By reference to the accompanying drawings the utility model is described in further detail below by the specific embodiment.
Please refer to Fig. 1 and Fig. 2, the utility model embodiment contrary sequence method pile foundation construction steel post positioning and plumbing device, it comprises that integral body is the vertical adjustment frame 3 of cuboid frame construction, the top of described vertical adjustment frame 3 is provided with for the upper vertical adjustment bolt group 1 that steel post 4 is positioned vertical adjustment, and the bottom of described vertical adjustment frame 3 is provided with for the lower vertical adjustment bolt group 2 that steel post 4 is positioned vertical adjustment.
Preferably, the bolt quantity of upper vertical adjustment bolt group 1, lower vertical adjustment bolt group 2 is four, and upper vertical adjustment bolt group 1, lower vertical adjustment bolt group 2 all circumferentially are crossing distribution around steel post 4.
The using method of the utility model contrary sequence method pile foundation construction steel post positioning and plumbing device is: after the complete and reinforcing cage of pile hole construction is transferred and put in place, with crane vertical adjustment frame 3 is lifted into 5 tops, a hole, and fix, again with upper vertical adjustment bolt group 1 and lower vertical adjustment bolt group 2 middle hang to stake hole 5 of steel post 4 from vertical adjustment frame 3, then screw up and down total eight bolts from four direction, fix steel post 4.Utilize two transits that the steel post 4 in the vertical adjustment frame 3 is carried out the measurement of position and verticality, after finding deviation, by screwing or unscrew the up-down adjustment bolt, steel post 4 is positioned adjusting, make its verticality and steel post 4 centre coordinates reach design and code requirement.
Upper vertical adjustment bolt group 1 and lower vertical adjustment bolt group 2 have formed the up and down structure of two-layer bolt group, and four bolts of every group are in the same level face and around steel post 4 and circumferentially are crossing distribution; Vertical adjustment frame 3 uses jointly with upper vertical adjustment bolt group 1, lower vertical adjustment bolt group 2 during use.Vertical adjustment frame 3 is according to the dimensions of steel post 4, and length and width are generally 3.0m * 3.0m, high 4.0m; Upper vertical adjustment bolt group 1 is positioned at the position apart from about the vertical adjustment frame 3 top 0.5m, and lower vertical adjustment bolt group 2 is positioned at the position apart from about the bottom 0.5m of vertical adjustment frame 3.
Above content is in conjunction with concrete embodiment further detailed description of the utility model, can not assert that implementation of the present utility model is confined to these explanations.For the utility model person of an ordinary skill in the technical field, without departing from the concept of the premise utility, can also make some simple deduction or replace, all should be considered as belonging to protection domain of the present utility model.
Claims (2)
1. contrary sequence method pile foundation construction steel post positioning and plumbing device, it is characterized in that: it comprises that integral body is the vertical adjustment frame of cuboid frame construction, the top of described vertical adjustment frame is provided with for the upper vertical adjustment bolt group that steel post is positioned vertical adjustment, and the bottom of described vertical adjustment frame is provided with for the lower vertical adjustment bolt group that steel post is positioned vertical adjustment.
2. contrary sequence method pile foundation construction steel post positioning and plumbing device as claimed in claim 1, it is characterized in that: the bolt quantity of described upper vertical adjustment bolt group, lower vertical adjustment bolt group is four, and described upper vertical adjustment bolt group, lower vertical adjustment bolt group all circumferentially are crossing distribution around steel post.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220442459 CN202850027U (en) | 2012-09-03 | 2012-09-03 | Reverse building method pile foundation construction steel column location verticality adjustment device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220442459 CN202850027U (en) | 2012-09-03 | 2012-09-03 | Reverse building method pile foundation construction steel column location verticality adjustment device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202850027U true CN202850027U (en) | 2013-04-03 |
Family
ID=47981243
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220442459 Expired - Fee Related CN202850027U (en) | 2012-09-03 | 2012-09-03 | Reverse building method pile foundation construction steel column location verticality adjustment device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202850027U (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104532843A (en) * | 2014-12-26 | 2015-04-22 | 中国一冶集团有限公司 | Method for positioning and straightening steel stand column of stand column pile |
CN104762969A (en) * | 2015-04-02 | 2015-07-08 | 浙江鼎业基础工程有限公司 | Verticality adjusting device for pile pulling guide rod |
CN105951747A (en) * | 2016-05-10 | 2016-09-21 | 温州市建设监理有限公司 | Construction method for embedding latticed column through reverse building method |
CN107675889A (en) * | 2017-08-04 | 2018-02-09 | 上海建工建集团有限公司 | Contrary sequence method steel pipe column vertical adjustment mould and vertical adjustment method |
CN108570989A (en) * | 2018-05-07 | 2018-09-25 | 广西建工集团第二建筑工程有限责任公司 | The suspension vertical adjustment system placed in the middle and construction method of pile foundation steel lattice column |
CN110031173A (en) * | 2018-07-16 | 2019-07-19 | 中建六局土木工程有限公司 | A kind of high-precision heavy track embedded part construction method |
CN111622222A (en) * | 2020-06-22 | 2020-09-04 | 上海市机械施工集团有限公司 | Verticality adjusting device |
CN112761186A (en) * | 2021-03-08 | 2021-05-07 | 中国建筑第七工程局有限公司 | Perpendicularity adjusting device for one-pile two-column construction and using method |
-
2012
- 2012-09-03 CN CN 201220442459 patent/CN202850027U/en not_active Expired - Fee Related
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104532843A (en) * | 2014-12-26 | 2015-04-22 | 中国一冶集团有限公司 | Method for positioning and straightening steel stand column of stand column pile |
CN104532843B (en) * | 2014-12-26 | 2016-08-24 | 中国一冶集团有限公司 | A kind of steel column location straightening method of stand column pile |
CN104762969A (en) * | 2015-04-02 | 2015-07-08 | 浙江鼎业基础工程有限公司 | Verticality adjusting device for pile pulling guide rod |
CN105951747A (en) * | 2016-05-10 | 2016-09-21 | 温州市建设监理有限公司 | Construction method for embedding latticed column through reverse building method |
CN107675889A (en) * | 2017-08-04 | 2018-02-09 | 上海建工建集团有限公司 | Contrary sequence method steel pipe column vertical adjustment mould and vertical adjustment method |
CN108570989A (en) * | 2018-05-07 | 2018-09-25 | 广西建工集团第二建筑工程有限责任公司 | The suspension vertical adjustment system placed in the middle and construction method of pile foundation steel lattice column |
CN110031173A (en) * | 2018-07-16 | 2019-07-19 | 中建六局土木工程有限公司 | A kind of high-precision heavy track embedded part construction method |
CN110031173B (en) * | 2018-07-16 | 2020-09-15 | 中建六局土木工程有限公司 | High-precision heavy rail embedded part construction method |
CN111622222A (en) * | 2020-06-22 | 2020-09-04 | 上海市机械施工集团有限公司 | Verticality adjusting device |
CN112761186A (en) * | 2021-03-08 | 2021-05-07 | 中国建筑第七工程局有限公司 | Perpendicularity adjusting device for one-pile two-column construction and using method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202850027U (en) | Reverse building method pile foundation construction steel column location verticality adjustment device | |
CN202658909U (en) | Steel column positioning rack based on reverse-building method | |
CN205134327U (en) | Concrete diclinic props row -pile support system | |
CN202012088U (en) | Foundation structure of tower crane | |
CN203795458U (en) | Bearing-platform-free lattice-type tower crane foundation device capable of traversing basement | |
CN102828469B (en) | Positioning mounting construction method for triangular steel constructed pillar of inclined-leg steel box | |
CN203270461U (en) | Bailey beam support without buttress in soft foundation | |
CN203626055U (en) | Super-high-rise large-section half-embedded type intensive anchor bar steel column base locating support | |
CN104878786B (en) | Tiltedly orthogonal is for group's Pile-soil-structure Interaction experimental model | |
CN202850507U (en) | Locating verticality adjusting device for top-down method pile foundation construction steel upright | |
CN201665992U (en) | Whole lifting platform of large steel net frame | |
CN202125061U (en) | Scaffold of large-space concrete structure | |
CN204753656U (en) | A clump of piles - soil - structure interact experimental model directly replaces to one side | |
CN202595758U (en) | Batter post foundation structure for overhead transmission line | |
CN204298830U (en) | Based on lattice column plane in subterranean excavation and elevation regulation device | |
CN205591587U (en) | Steel structure box type board room | |
CN107237515B (en) | Support device of circular steel truss structure and use method thereof | |
CN201554033U (en) | Tower crane foundation for deep foundation ditch | |
CN201169781Y (en) | Cap digging pit structure | |
CN203256744U (en) | Device for correcting perpendicularity of concrete-filled steel tubular column through reverse construction method | |
CN203320543U (en) | Basic structure of construction elevator | |
CN113373971A (en) | Prestressed framework type steel pipe wind power tower positioning tool and inclined foundation structure system | |
CN203531413U (en) | Auxiliary structure hoisting whole steel structure wire frame | |
CN204023600U (en) | Pillar crane composite base structure | |
CN204919565U (en) | Steel platform of use is demolishd in shoring of trench |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130403 Termination date: 20170903 |