CN203270461U - Bailey beam support without buttress in soft foundation - Google Patents

Bailey beam support without buttress in soft foundation Download PDF

Info

Publication number
CN203270461U
CN203270461U CN 201320221198 CN201320221198U CN203270461U CN 203270461 U CN203270461 U CN 203270461U CN 201320221198 CN201320221198 CN 201320221198 CN 201320221198 U CN201320221198 U CN 201320221198U CN 203270461 U CN203270461 U CN 203270461U
Authority
CN
China
Prior art keywords
buttress
bailey beam
cushion cap
steel pipe
bailey
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320221198
Other languages
Chinese (zh)
Inventor
张书良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN 201320221198 priority Critical patent/CN203270461U/en
Application granted granted Critical
Publication of CN203270461U publication Critical patent/CN203270461U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a Bailey beam support without a buttress in a soft foundation. The Bailey beam support comprises a cushion cap with a pier body, steel pipes are arranged on the pier body, the bottoms of the steel pipes are connected with the cushion cap, a first beam and a second beam parallel to each other are arranged at the end portions of the steel pipes, the steel pipes are connected with the cushion cap through cushion cap embedded parts, the steel pipes are connected with the pier body through pier body embedded parts, supporting frames are arranged between the steel pipes, Bailey beams are arranged between the first beam and the second beam, and a jack and a formwork are sequentially arranged on the second beam. The Bailey beam support without the buttress in the soft foundation reduces production cost, shortens a construction period, is convenient to construct, and ensures safe production.

Description

In a kind of soft base without the Bailey beam support of buttress
Technical field
The utility model relates to the construction equipment of building bridge, relate in particular to bridge in soft base to the Bailey beam support of in-situ beam casting employing without buttress.
Background technology
Along with modern economy development at a high speed, the construction of rail transport is extremely urgent.In the construction of rail transport, cast-in-situ box girder is often adopted in the construction of bridge.Wherein, part simple supported box beam and continuous beam adopt full framing and steel pipe Bailey beam support to build.In prior art, disclose as 2011205160386 patents and utilize steel pipe Bailey beam rack construction in soft base, this Technology Need builds the steel pipe buttress by castinplace pile, steel pipe pile, has increased cost of production, has extended the duration, has strengthened difficulty of construction.Simultaneously, the Bailey beam in this technology is single layer structure, and when employing was constructed without the buttress technology, its bearing capacity can't meet the demands.
Summary of the invention
For problems of the prior art, the utility model provide a kind of in soft base to the double-deck Bailey beam support of in-situ beam casting employing without buttress, this Techniques For Reducing cost of production, shortened the duration, constructability guarantees safety in production.
In order to solve the deficiencies in the prior art, the technical solution adopted in the utility model is:
In a kind of soft base without the Bailey beam support of buttress, comprise the cushion cap with pier shaft, be provided with the steel pipe that the bottom is connected with described cushion cap on described pier shaft, the end of described steel pipe is provided with first crossbeam and the second cross beam that is parallel to each other, described steel pipe is connected with described cushion cap by the cushion cap built-in fitting, described steel pipe is by pier shaft built-in fitting and described pier shaft, be provided with bracing frame between described steel pipe, be provided with Bailey beam between described first crossbeam and second cross beam, be disposed with jack and template on described second cross beam.
Described Bailey beam is double-decker.
More than described Bailey beam at least 15 groups.
Support frame as described above is that the parallel and drift angle in two bases is to the triangular structure on top.
The spacing of each described cushion cap built-in fitting is a few shape reinforcing bars of 80-100mm.
The spacing of each described pier shaft built-in fitting is a few shape reinforcing bars of 80-100mm.
Described jack is more than at least 6.
Distance between each described jack is 1.0m.
The beneficial effects of the utility model are: first, the utility model has adopted to be installed built-in fitting and is connected with steel pipe on cushion cap, pier shaft, utilizing original cushion cap, pier shaft and steel pipe to form complete integral body has replaced needing in prior art to build buttress, reconstruct ground, save production cost, the duration shortens.The second, the utility model has been set up bracing frame between steel pipe, guaranteed between steel pipe stressed evenly, strengthened the stability of cast-in-place box beam bracket.The 3rd, the double-deck Bailey beam in the utility model can be decomposed the gravity that the jack of face from it applies, and the gravity of having avoided steel pipe can't bear template causes cast-in-situ box girder to cave in, and guarantees safety in production.
Description of drawings
Fig. 1 is the utility model structural representation.
Fig. 2 is side view of the present utility model.
Fig. 3 is the structural representation of cushion cap built-in fitting or pier shaft built-in fitting in the utility model.
Reference numeral
1-cushion cap, 2-pier shaft, 3-cushion cap built-in fitting, 4-steel pipe, 5-pier shaft built-in fitting, 6-bracing frame
7-first crossbeam, 8-second cross beam, 9-Bailey beam, 10-jack, 11-template.
The specific embodiment
The utility model is described in further detail below in conjunction with accompanying drawing:
As Fig. 1, as shown in Figure 2, the utility model provides in a kind of soft base the Bailey beam support without buttress, comprise the cushion cap 1 that is provided with pier shaft 2, be provided with the steel pipe 4 that the bottom is connected with described cushion cap 1 on described pier shaft 2, the end of described steel pipe 4 is provided with the first crossbeam 7 and second cross beam 8 that is parallel to each other, described steel pipe 4 is connected with described cushion cap 1 by cushion cap built-in fitting 3, described steel pipe 4 is connected by pier shaft built-in fitting 5 connections with pier shaft, steel pipe 4 adopts the spiral steel plates and is equally distributed on that on cushion cap 1, cushion cap built-in fitting 3 welds usually; Between cushion cap built-in fitting 3, distance is between 2~3m, and built-in fitting 3 can adopt a few shape reinforcing bars of weld spacing 80~100mm on steel plate as shown in Figure 3.Be provided with bracing frame 6 between described steel pipe 4, support frame as described above 6 is that the parallel and drift angle in two bases is to the triangular structure on top.Can guarantee that like this steel pipe 4 is firm and stressed evenly.In manufacturing process, bracing frame 6 is channel-section steel and is welded into bridging.Be vertically arranged with 15 groups of above Bailey beams 9 between described first crossbeam 7 and second cross beam 8, described Bailey beam 9 is double-decker.It is equidistantly the two limb channel-section steels in 0.5~1 meter left and right that described first crossbeam 7 adopts i iron crossbeam, second cross beam 8 to adopt.Simultaneously, the spacing of the double-deck Bailey beam 9 of single group, quantity are determined by the weight of template and beam body.More firm for the structure that makes Bailey beam 9, can adopt the top-bottom chord of Bailey beam 9 to increase and strengthen chord member, brace and the local mode of strengthening of montant are constructed.Laterally set gradually the jack 10 more than at least 6 on described second cross beam 8.The position of jack 10 is mutually corresponding with the position of template 11 cross members.In reality, jack 10 is preferably selected the jackscrew of 16 tons.Placing box girder steel formwork 11 on jack 10 is adjusted the absolute altitude of template 11 by the height of adjusting jack 10, can reduce jack 10 so that the demoulding when needing form removal after concreting is completed.For the construction of Cast-in-situ Beam, use the mode of template 11 many, such as steel form, wooden form and plywood form are arranged, also have typified form and assembling combination template etc.The utility model has well solved the technical barrier at geological conditions defective sector cast-in-situ box girder beam type rack constructions such as mud, cross a river ditches, has saved cost.Its technology novel point is that direct of support stands on bridge bearing platform 1, does not need the independent support ground that carries out to process.A kind of job practices of novelty is provided for beam type rack construction Cast-in-situ Beam, has had good generalization.
Above embodiment is described preferred embodiment of the present utility model; be not that scope of the present utility model is carried out limit; under the prerequisite that does not break away from the utility model design spirit; various distortion and transformation that those of ordinary skills make the utility model all should fall into the protection domain that claims of the present utility model are determined.

Claims (8)

  1. In a soft base without the Bailey beam support of buttress, comprise the cushion cap with pier shaft, it is characterized in that: be provided with the steel pipe that the bottom is connected with described cushion cap on described pier shaft, the end of described steel pipe is provided with first crossbeam and the second cross beam that is parallel to each other, described steel pipe is connected with described cushion cap by the cushion cap built-in fitting, described steel pipe is by pier shaft built-in fitting and described pier shaft, be provided with bracing frame between described steel pipe, be provided with Bailey beam between described first crossbeam and second cross beam, be disposed with jack and template on described second cross beam.
  2. According to claim 1 in soft base without the Bailey beam support of buttress, it is characterized in that: described Bailey beam is double-decker.
  3. According to claim 1 and 2 in described soft base without the Bailey beam support of buttress, it is characterized in that: more than described Bailey beam at least 15 groups.
  4. According to claim 3 in soft base without the Bailey beam support of buttress, it is characterized in that: support frame as described above is that the parallel and drift angle in two bases is to the triangular structure on top.
  5. According to claim 4 in soft base without the Bailey beam support of buttress, it is characterized in that: the spacing of described cushion cap built-in fitting is a few shape reinforcing bars of 80-100mm.
  6. According to claim 5 in soft base without the Bailey beam support of buttress, it is characterized in that: the spacing of described pier shaft built-in fitting is a few shape reinforcing bars of 80-100mm.
  7. According to claim 6 in soft base without the Bailey beam support of buttress, it is characterized in that: described jack is more than at least 6.
  8. According to claim 7 in soft base without the Bailey beam support of buttress, it is characterized in that: the distance between each described jack is 1.0m.
CN 201320221198 2013-04-27 2013-04-27 Bailey beam support without buttress in soft foundation Expired - Fee Related CN203270461U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320221198 CN203270461U (en) 2013-04-27 2013-04-27 Bailey beam support without buttress in soft foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320221198 CN203270461U (en) 2013-04-27 2013-04-27 Bailey beam support without buttress in soft foundation

Publications (1)

Publication Number Publication Date
CN203270461U true CN203270461U (en) 2013-11-06

Family

ID=49500902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320221198 Expired - Fee Related CN203270461U (en) 2013-04-27 2013-04-27 Bailey beam support without buttress in soft foundation

Country Status (1)

Country Link
CN (1) CN203270461U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103233426A (en) * 2013-04-27 2013-08-07 中国建筑第六工程局有限公司 Bailey beam support free of buttress in soft foundation and supporting method thereof
CN103669226A (en) * 2013-12-25 2014-03-26 中建六局土木工程有限公司 River-crossing prestressed concrete continuous beam bridge box girder 0# block support construction method
CN103850183A (en) * 2014-03-12 2014-06-11 中交二航局第四工程有限公司 Support structure for realizing no-cushion cap approach viaduct concrete box girder less-support cast-in-place
CN103866696A (en) * 2014-03-26 2014-06-18 中铁二十四局集团安徽工程有限公司 Cast-in-situ support of long-cantilever zero segment of short-pylon cable-stayed bridge
CN105484164A (en) * 2015-12-30 2016-04-13 中交第二航务工程局有限公司 Spanning type bailey beam bracket and construction method thereof
CN107190986A (en) * 2017-05-02 2017-09-22 郑楚英 A kind of construction method of concrete structure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103233426A (en) * 2013-04-27 2013-08-07 中国建筑第六工程局有限公司 Bailey beam support free of buttress in soft foundation and supporting method thereof
CN103669226A (en) * 2013-12-25 2014-03-26 中建六局土木工程有限公司 River-crossing prestressed concrete continuous beam bridge box girder 0# block support construction method
CN103850183A (en) * 2014-03-12 2014-06-11 中交二航局第四工程有限公司 Support structure for realizing no-cushion cap approach viaduct concrete box girder less-support cast-in-place
CN103866696A (en) * 2014-03-26 2014-06-18 中铁二十四局集团安徽工程有限公司 Cast-in-situ support of long-cantilever zero segment of short-pylon cable-stayed bridge
CN105484164A (en) * 2015-12-30 2016-04-13 中交第二航务工程局有限公司 Spanning type bailey beam bracket and construction method thereof
CN105484164B (en) * 2015-12-30 2017-05-17 中交第二航务工程局有限公司 Spanning type bailey beam bracket and construction method thereof
CN107190986A (en) * 2017-05-02 2017-09-22 郑楚英 A kind of construction method of concrete structure

Similar Documents

Publication Publication Date Title
CN203270461U (en) Bailey beam support without buttress in soft foundation
CN101824800B (en) Method for construction of bridge cast-in-situ pre-stressed concrete continuous beam
CN201648977U (en) Slant legged rigid frame bracket system of cast-in-place prestressed concrete continuous beam at bridge site
CN102888815B (en) The pouring construction method of a kind of wide-angle V-type pier and 0# block case beam
CN103321151B (en) Long span continuous box girder spanning existing railway stand construction method
CN105568854B (en) Shaped form fish-bellied type cast-in-situ steel reinforced concrete box girder construction method waterborne
CN202954299U (en) Template support structure for large-angle V-shaped pier and No.0 block of continuous rigid framework bridge
CN103669226A (en) River-crossing prestressed concrete continuous beam bridge box girder 0# block support construction method
CN202347446U (en) Supporting structure for construction of zero block of reinforced concrete continuous beam
CN103410102A (en) H-shaped double column pier wide-bridge-surface cantilever temporary consolidation structure and construction method thereof
CN103362069B (en) Steel and concrete combined box girder concrete wing plate formwork and construction method
CN203223003U (en) Detachable triangular jig frame for steel truss assembling
CN102733307B (en) Method for constructing cast-in-place beam falsework
CN104047234A (en) Self load bearing side span closure construction method for corrugated steel web plate continuous rigid frame bridge
CN102777050B (en) Assembly type jig frame for longspan pipe truss roof girder
CN201648978U (en) Tied arch support of bridge location cast-in-situ prestressed concrete continuous beam
CN103233426A (en) Bailey beam support free of buttress in soft foundation and supporting method thereof
CN203475310U (en) Formwork for concrete slabs of composite steel-concrete box girders
CN204212058U (en) For the steel truss girder assembling support in the construction of steel concrete composite truss beam
CN209584813U (en) Frame bridge system
CN204780635U (en) Super wide nonprismatic continuous beam 0# piece concreties and relieves construction structures
CN203821248U (en) Steel pipe arch main arch assembling supporting system
CN202689585U (en) Ground fitting up assembly mould of large steel truss
CN206233115U (en) A kind of supporting bracket of bridge construction
CN205804178U (en) Scalable without holder device for the liftable of bridge coping construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131106

Termination date: 20190427