CN202012088U - Foundation structure of tower crane - Google Patents
Foundation structure of tower crane Download PDFInfo
- Publication number
- CN202012088U CN202012088U CN2011200913223U CN201120091322U CN202012088U CN 202012088 U CN202012088 U CN 202012088U CN 2011200913223 U CN2011200913223 U CN 2011200913223U CN 201120091322 U CN201120091322 U CN 201120091322U CN 202012088 U CN202012088 U CN 202012088U
- Authority
- CN
- China
- Prior art keywords
- tower crane
- laced
- foundation
- steel bar
- battened compression
- Prior art date
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 52
- 239000010959 steel Substances 0.000 claims abstract description 52
- 239000004567 concrete Substances 0.000 claims abstract description 51
- 238000007906 compression Methods 0.000 claims description 38
- 281000119710 All-Steel companies 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 5
- 239000011150 reinforced concrete Substances 0.000 abstract 4
- 239000000789 fasteners Substances 0.000 description 2
- 230000003014 reinforcing Effects 0.000 description 2
- 238000010586 diagrams Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering processes Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Abstract
Description
Technical field
The utility model belongs to tower crane technical field for building, the foundation structure of refering in particular to a kind of tower crane.
Background technology
At present, the tower crane that uses on the building site substantially all is to be connected with the tower crane main body on the packaged type pedestal, want to make the feeding radius of tower crane big, that the weight of portable pedestal will be done is very big, otherwise when the object of slinging moves to the outermost end of tower crane, the situation that the tower crane overturning will occur takes place, minimizing along with the increasing of population, soil, what building covered is more and more higher, therefore, the height of tower crane is also more and more higher, and the weight of packaged type pedestal is also increasing, its weak point is: the one, and the acquisition expenses of tower crane increases, and makes on the building costs high; The 2nd, bring difficulty to the building site moving tower crane; The 3rd, in case the weight of slinging exceeds standard, the accident of tower crane overturning will take place, dangerous big.
Summary of the invention
The purpose of this utility model provide a kind of safe in utilization, cost is low, without the foundation structure of the tower crane of moving tower crane pedestal.
The purpose of this utility model is achieved in that
A kind of foundation structure of tower crane, be provided with on the top of the steel bar concrete castinplace pile more than three the all-in-one-piece concrete platform is built at the top of all steel bar concrete castinplace piles, be provided with a laced of battened compression member on the top of every steel bar concrete castinplace pile, the bottom of laced of battened compression member is stretched in the root steel bar concrete castinplace pile and is built and is integral, top is stretched out concrete platform and is connected into the steel column supporting component by horizontal batten plate and oblique batten plate, be provided with at the top of every laced of battened compression member all-in-one-piece tower crane cushion cap is built at the top of all laced of battened compression member, in the tower crane cushion cap, be provided with the column connector of tower crane.
Above-mentioned steel bar concrete castinplace pile has four.
Above-mentioned column connector has four, and the bottom all vertically is cast in the tower crane cushion cap.
Above-mentioned steel column supporting component is a main body for four laced of battened compression member on four angles that are arranged on rectangle between concrete platform upper surface and the tower crane cushion cap soffit, every be provided with horizontal batten plate every the diagonal of four laced of battened compression member of 2500-3500mm between the upper and lower, be provided with oblique batten plate between adjacent two laced of battened compression member between the two horizontal batten plates, be provided with the supporter that connects oblique batten plate and horizontal batten plate successively between two parties between adjacent two laced of battened compression member.
The cross section of above-mentioned laced of battened compression member is a rectangle, be respectively arranged with angle angle steel inwardly on four angles of rectangle, be welded with the horizontal support batten plate at a certain distance outside around the angle steel between the upper and lower, the arranged outside between adjacent two angle steel between the levels horizontal support batten plate has the bearing diagonal batten plate; Or described laced of battened compression member is a shaped steel.
Adjacent two length of sides of the laced of battened compression member cross section of above-mentioned rectangular configuration are respectively 420-480mm and 390-450mm.
Above-mentioned steel bar concrete castinplace pile is a circular configuration, and the diameter of steel bar concrete castinplace pile is 600-1000mm, highly is 25000-30000mm that the center to center distance between the adjacent two steel bar concrete castinplace piles is 2000-3000mm.
The thickness of above-mentioned concrete platform is 150-300mm, the thickness of tower crane cushion cap is 800-1000mm, the length that the bottom of laced of battened compression member is stretched in the root steel bar concrete castinplace pile is 2000-3000mm, and the distance between concrete platform upper surface and the tower crane cushion cap soffit is 6000-7000mm.
Above-mentioned tower crane cushion cap is a cube, and its length * wide * height is: 4000mm * 4000mm * 1000mm.
The beneficial effects of the utility model are:
1, tower crane pedestal of the present utility model casts directly over the construction site, and cost is low, need not move large-scale tower crane to new building site with large-scale Move tool again.
2, steel bar concrete castinplace pile of the present utility model about 25-30m, makes being built on the rock of tower crane in the cast degree of depth of below ground, assembles the tower crane main body on the column connector of tower crane, and is safe and reliable.
3, of the present utility model simple in structure, easy construction is applicable to the pedestal use of heavy construction building site as tower crane.
Description of drawings
Fig. 1 is a structure principle chart of the present utility model.
Fig. 2 is that structure of the present utility model is overlooked schematic diagram.
Fig. 3 is the sectional view of tower crane cushion cap of the present utility model.
Fig. 4 is the sectional view of steel column supporting component of the present utility model.
Fig. 5 is the sectional view of laced of battened compression member of the present utility model.
Fig. 6 is the sectional view of steel bar concrete castinplace pile of the present utility model.
Fig. 7 is the side schematic view of laced of battened compression member of the present utility model.
The specific embodiment
The utility model is further described with specific embodiment below in conjunction with accompanying drawing, referring to Fig. 1-8:
A kind of foundation structure of tower crane, be provided with on the top of the steel bar concrete castinplace pile 1 more than three all-in-one-piece concrete platform 2 is built at the top of all steel bar concrete castinplace piles 1, be provided with a laced of battened compression member 31 on the top of every steel bar concrete castinplace pile 1, the bottom of laced of battened compression member 31 is stretched in the root steel bar concrete castinplace pile 1 and is built and is integral, top is stretched out concrete platform 2 and is connected into steel column supporting component 3 by horizontal batten plate 32 and oblique batten plate 33, be provided with at the top of every laced of battened compression member 31 all-in-one-piece tower crane cushion cap 4 is built at the top of all laced of battened compression member 31, in tower crane cushion cap 4, be provided with the column connector 5 of tower crane.
Above-mentioned steel bar concrete castinplace pile 1 has four, forms with reinforcing bar 11, spirality stirrup 12 and concrete 13 cast.
Above-mentioned column connector 5 has four, and the bottom all vertically is cast in the tower crane cushion cap 4.
Above-mentioned steel column supporting component 3 is main body for four laced of battened compression member on four angles that are arranged on rectangle between concrete platform 2 upper surfaces and tower crane cushion cap 4 soffits 31, whenever be provided with horizontal batten plate 33 every the diagonal of 2500-3500mm (for example between the upper and lower every 3000mm), four laced of battened compression member 31 between the upper and lower, be provided with oblique batten plate 32 between adjacent two laced of battened compression member 31 between the two horizontal batten plates 33, be provided with the supporter 34 that connects oblique batten plate 32 and horizontal batten plate 33 successively between two parties between adjacent two laced of battened compression member 31.
The cross section of above-mentioned laced of battened compression member 31 is a rectangle, be respectively arranged with angle angle steel 311 inwardly on four angles of rectangle, be welded with horizontal support batten plate 312 at a certain distance outside around the angle steel 311 between the upper and lower, the arranged outside between adjacent two angle steel 311 between the levels horizontal support batten plate 312 has bearing diagonal batten plate 313; Or described laced of battened compression member is the shaped steel of integral structure.
Adjacent two length of sides of laced of battened compression member 31 cross sections of above-mentioned rectangular configuration are respectively: and L1=420-480mm and L2=390-450mm (present embodiment is got: L1=450mm, L2=420mm).
Above-mentioned steel bar concrete castinplace pile 1 is a circular configuration, the diameter of steel bar concrete castinplace pile 1 is 600-1000mm (present embodiment is got 800mm), highly for H4=25000-30000mm (present embodiment is got 27000mm), the center to center distance L3=2000-3000mm (present embodiment is got 2400mm) between the adjacent two steel bar concrete castinplace piles 1.
The thickness H3=150-300mm (present embodiment is got 200mm) of above-mentioned concrete platform 2, the thickness H1=800-1000mm (present embodiment is got 900mm) of tower crane cushion cap 4, the length that the bottom of laced of battened compression member 31 is stretched in the root steel bar concrete castinplace pile 1 is 2000-3000mm (present embodiment is got 2500mm), the distance H 2=6000-7000mm (present embodiment is got 6500mm) between concrete platform 2 upper surfaces and tower crane cushion cap 4 soffits.
Above-mentioned tower crane cushion cap 4 is a cube, and its length * wide * height is: 4000mm * 4000mm * 1000mm forms with reinforcing bar 41, stirrup 42 and concrete 43 cast.
Use of the present utility model, during manufacturing, the base plate bottom surface of the upper surface of concrete platform 2 of the present utility model and building basement is contour, tower crane cushion cap 4 is built below ground line, top at the column connector 5 of tower crane is fastened into the tower crane main body with body fastener 51 successively from bottom to top with column connector 5 and body, can make tower crane uses, after building is finished, by body fastener 51 all being installed to tower crane main body on the column connector 5 removes to deposit and gets final product the steel bar concrete castinplace pile 1 of making, concrete platform 2 and tower crane cushion cap 4 are stayed the fastness that can strengthen building in the building site.
The foregoing description is preferred embodiment of the present utility model only, is not to limit protection domain of the present utility model according to this, so: all equivalences of doing according to structure of the present utility model, shape, principle change, and all should be covered by within the protection domain of the present utility model.
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011200913223U CN202012088U (en) | 2011-03-30 | 2011-03-30 | Foundation structure of tower crane |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011200913223U CN202012088U (en) | 2011-03-30 | 2011-03-30 | Foundation structure of tower crane |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202012088U true CN202012088U (en) | 2011-10-19 |
Family
ID=44782701
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011200913223U CN202012088U (en) | 2011-03-30 | 2011-03-30 | Foundation structure of tower crane |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202012088U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102433889A (en) * | 2011-10-20 | 2012-05-02 | 中天建设集团有限公司天津分公司 | Method for constructing high-rise pile cap tower footing and high-rise pile cap tower footing structure |
CN103132537A (en) * | 2013-02-04 | 2013-06-05 | 中天建设集团有限公司 | Steel latticed column homocentric-square-shaped concrete bearing platform combination type tower crane base structure and construction method |
CN103498482A (en) * | 2013-09-30 | 2014-01-08 | 上海建工七建集团有限公司 | Three-pile lattice type combined tower crane foundation structure |
CN103510534A (en) * | 2013-10-15 | 2014-01-15 | 广州电力设计院 | Tower pile foundation exposure lifting structure and construction method |
CN106759442A (en) * | 2017-01-05 | 2017-05-31 | 中建三局第二建设工程有限责任公司 | A kind of single-pile elevated bearing-platform and anchor cable tower-crane foundation structure and its construction method |
CN106758814A (en) * | 2016-12-14 | 2017-05-31 | 中交公局第三工程有限公司 | For the platform and its construction method of king-tower |
-
2011
- 2011-03-30 CN CN2011200913223U patent/CN202012088U/en not_active IP Right Cessation
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102433889A (en) * | 2011-10-20 | 2012-05-02 | 中天建设集团有限公司天津分公司 | Method for constructing high-rise pile cap tower footing and high-rise pile cap tower footing structure |
CN103132537A (en) * | 2013-02-04 | 2013-06-05 | 中天建设集团有限公司 | Steel latticed column homocentric-square-shaped concrete bearing platform combination type tower crane base structure and construction method |
CN103498482A (en) * | 2013-09-30 | 2014-01-08 | 上海建工七建集团有限公司 | Three-pile lattice type combined tower crane foundation structure |
CN103510534A (en) * | 2013-10-15 | 2014-01-15 | 广州电力设计院 | Tower pile foundation exposure lifting structure and construction method |
CN103510534B (en) * | 2013-10-15 | 2014-11-19 | 广州电力设计院 | Tower pile foundation exposure lifting structure and construction method |
CN106758814A (en) * | 2016-12-14 | 2017-05-31 | 中交公局第三工程有限公司 | For the platform and its construction method of king-tower |
CN106759442A (en) * | 2017-01-05 | 2017-05-31 | 中建三局第二建设工程有限责任公司 | A kind of single-pile elevated bearing-platform and anchor cable tower-crane foundation structure and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101418573B (en) | Caisson structure and method for smoothly and accurately sinking caisson structure into earth surface | |
CN201972268U (en) | Combined shear wall of steel pipe concrete columns and double steel plates | |
CN102535845A (en) | Construction method of bearing frame of corridor structure | |
CN102839678B (en) | Structure for improving rigidity and stability of foundation pit steel support | |
CN203403422U (en) | Long-span reinforced concrete inner support structure of rectangular deep foundation pit | |
CN102251525A (en) | Framework prestress anchor rod-reinforced supporting structure for gravity type retaining wall and construction method thereof | |
CN201826325U (en) | Foundation structure of tower crane | |
CN204282199U (en) | Pile-column concrete hollow pile bridge pier structure | |
CN102330432A (en) | Panel-type framework prestressed anchor rod flexible support structure and construction method thereof | |
CN203145038U (en) | Latticed column type tower crane foundation | |
CN204753813U (en) | Steel construction conversion truss | |
CN203113352U (en) | Pre-stressed beam for retaining and protection of foundation pit | |
CN101240550A (en) | Construction method for lattice type steel column tower crane pedestal | |
CN103437460B (en) | Embedded steel frame concrete blast wall | |
CN202718135U (en) | Prestress baffle type assembly prefabricated reinforced concrete tower crane foundation | |
CN101701485A (en) | Hollow steel pipe-reinforced concrete superimposed member | |
CN201762717U (en) | Structure for connecting prestressed pipe pile and cushion cap | |
CN201433512Y (en) | Special-shaped steel pipe concrete column stiffened through combination of steel plates and reinforcing steel bars | |
CN203270461U (en) | Bailey beam support without buttress in soft foundation | |
CN202519697U (en) | Steel hoop truss high pile-cap tower crane basic structure | |
CN203487803U (en) | Safety protection structure for elevator shaft construction | |
CN101457548A (en) | Node for connecting round steel tube concrete column with reinforced concrete floor and method for making same | |
CN102704593B (en) | Steel tube reinforced concrete composite column-steel beam-lattice steel support shear wall and manufacturing method | |
CN102061742B (en) | Shockproof reinforced concrete pseudo-classic building structural system | |
CN202755370U (en) | Structure for improving rigidity and stability of foundation pit steel support |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
C14 | Grant of patent or utility model | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20111019 Termination date: 20140330 |
|
C17 | Cessation of patent right |