CN201554033U - Tower crane foundation for deep foundation ditch - Google Patents

Tower crane foundation for deep foundation ditch Download PDF

Info

Publication number
CN201554033U
CN201554033U CN2009202129149U CN200920212914U CN201554033U CN 201554033 U CN201554033 U CN 201554033U CN 2009202129149 U CN2009202129149 U CN 2009202129149U CN 200920212914 U CN200920212914 U CN 200920212914U CN 201554033 U CN201554033 U CN 201554033U
Authority
CN
China
Prior art keywords
foundation
tower crane
concrete
basis
deep
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009202129149U
Other languages
Chinese (zh)
Inventor
章晓鹏
汪敏刚
李仲凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai No2 Building Co Ltd
Original Assignee
Shanghai No2 Building Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai No2 Building Co Ltd filed Critical Shanghai No2 Building Co Ltd
Priority to CN2009202129149U priority Critical patent/CN201554033U/en
Application granted granted Critical
Publication of CN201554033U publication Critical patent/CN201554033U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model discloses a tower crane foundation for a deep foundation ditch, which comprises a concrete foundation, a ground anchor and a base section, wherein the concrete foundation is arranged on an underground continuous wall, the ground anchor is arranged on the concrete foundation, and the base section is fixedly arranged on an upper plane of the ground anchor. In the tower crane foundation, the concrete foundation of a crane is arranged on the underground continuous wall, and an underground structure bracing system is used as the vertical supporting body system of the foundation. The foundation form overcomes the defects that the multiple existing foundation forms further need construction foundations, pile foundations and other aspects. The enclosure wall of the foundation ditch is used as the foundation, thus saving construction cost and construction field, and being more suitable for the deep foundation ditch engineering of the underground continuous wall bracing system. The bracing wall system does not need to arrange a tower crane foundation, thus reducing construction cost and ensuring safety of a tower crane.

Description

A kind of tower crane basis that is used for deep foundation ditch
Technical field
The utility model relates to technical field of building construction, relates to a kind of tower crane basis, is specifically related to a kind of tower crane basis that is used for deep foundation ditch.
Background technology
Present existing tower crane form often has following several form: forms such as independent cushion cap, pile cap, steel structure platform.But along with further pushing ahead of Chinese Urbanization's process, urban land day is becoming tight, especially higher relatively in the bustling location of down town development cost, the developer adopts the highrise building of deep foundation ditch more to the building of its exploitation, all there is the deep foundation ditch basement in most engineerings, the construction plant is comparatively narrow, does not have the construction plant, and traditional tower crane form often can not be suitable for.
Summary of the invention
Technical problem to be solved in the utility model provides a kind of tower crane basis that can satisfy deep foundation ditch basement construction site requirements, to overcome the above-mentioned defective that prior art exists.
The technical scheme of the utility model technical solution problem is as follows:
A kind of tower crane basis that is used for deep foundation ditch, it comprises concrete basis, earth anchor and base section, it is characterized in that, and described concrete basis instrument is on diaphragm wall, and described earth anchor is provided with on the concrete basis, and described base section is fixedly installed on the earth anchor on the plane.
By above disclosed technical scheme as can be known, the utility model passes through loop wheel machine concrete basis instrument to utilize underground structure to go along with sb. to guard him the vertical supporter system of system as the basis on diaphragm wall.This base form has overcome existing multiple base form needs the deficiency of each side such as construction basis, pile foundation separately.Utilize the bracing of foundation pit wall as the basis, saved construction cost, saved the construction plant, relatively be fit to the deep-foundation pit engineering that diaphragm wall is gone along with sb. to guard him system.Owing to utilize the enclosure wall system, need not to be provided with separately tower crane, reduced construction cost, guaranteed safety of tower crane.
Description of drawings
Fig. 1 is the utility model tower crane foundation structure schematic diagram.
Fig. 2 is the A-A section structure schematic diagram of Fig. 1.
Reference numeral is as follows:
1, diaphragm wall 2, concrete basis
3, earth anchor 4, base section
The specific embodiment
Below in conjunction with drawings and Examples the utility model is described further.
As shown in Figure 1, 2, the utility model is used for the tower crane basis of deep foundation ditch, it comprises concrete basis 2, earth anchor 3 and base section 4, described concrete basis 2 is arranged on the diaphragm wall 1, described concrete basis is a square, described earth anchor 3 has four, uniform being arranged on the concrete basis 2, and tower crane base section 4 is fixedly installed on the earth anchor on the plane.
The above is a better embodiment of the present utility model only, is not to be used for limiting protection domain of the present utility model, and every equal conversion of being done according to the utility model claim is all within protection domain of the present utility model.

Claims (2)

1. tower crane basis that is used for deep foundation ditch, it comprises concrete basis, earth anchor and base section, it is characterized in that, and described concrete basis instrument is on diaphragm wall, and described earth anchor is provided with on the concrete basis, and described base section is fixedly installed on the earth anchor on the plane.
2. the tower crane basis that is used for deep foundation ditch according to claim 1 is characterized in that, described concrete basis is a square, and described earth anchor has four, uniform being arranged on the concrete basis.
CN2009202129149U 2009-12-10 2009-12-10 Tower crane foundation for deep foundation ditch Expired - Fee Related CN201554033U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009202129149U CN201554033U (en) 2009-12-10 2009-12-10 Tower crane foundation for deep foundation ditch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009202129149U CN201554033U (en) 2009-12-10 2009-12-10 Tower crane foundation for deep foundation ditch

Publications (1)

Publication Number Publication Date
CN201554033U true CN201554033U (en) 2010-08-18

Family

ID=42613710

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009202129149U Expired - Fee Related CN201554033U (en) 2009-12-10 2009-12-10 Tower crane foundation for deep foundation ditch

Country Status (1)

Country Link
CN (1) CN201554033U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102359118A (en) * 2011-08-02 2012-02-22 北京健安诚岩土工程有限公司 Annular foundation of underground continuous wall and construction method thereof
CN102535505A (en) * 2011-12-09 2012-07-04 中国建筑第二工程局有限公司 Tower crane foundation formed by using external walls of basement and supporting piles of foundation pit
CN105887918A (en) * 2015-12-31 2016-08-24 上海建工七建集团有限公司 Tower crane foundation and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102359118A (en) * 2011-08-02 2012-02-22 北京健安诚岩土工程有限公司 Annular foundation of underground continuous wall and construction method thereof
CN102359118B (en) * 2011-08-02 2013-12-04 北京健安诚岩土工程有限公司 Annular foundation of underground continuous wall and construction method thereof
CN102535505A (en) * 2011-12-09 2012-07-04 中国建筑第二工程局有限公司 Tower crane foundation formed by using external walls of basement and supporting piles of foundation pit
CN105887918A (en) * 2015-12-31 2016-08-24 上海建工七建集团有限公司 Tower crane foundation and construction method thereof
CN105887918B (en) * 2015-12-31 2018-06-22 上海建工七建集团有限公司 A kind of tower crane and its construction method

Similar Documents

Publication Publication Date Title
CN202644541U (en) Steel support structure for ultra-deep foundation pit construction in narrow field
CN201546227U (en) Steel support beam for supporting foundation pit bracing piling wall and basement structure outer wall
CN201891123U (en) Single-wall steel hanging box with concrete bottom plate
CN201554033U (en) Tower crane foundation for deep foundation ditch
CN201474361U (en) Ground self-supporting steel surge tower
CN204212177U (en) A kind of double doing in the hole of stand column pile cheats diaphragm wall structure
CN203626055U (en) Super-high-rise large-section half-embedded type intensive anchor bar steel column base locating support
CN202090352U (en) Deep foundation pit bracing system with steel pipe piles-self-drilling type pre-stress anchor rods
CN202416324U (en) Beam and slab structure superposed through top-down beam and down-top slab construction of foundation pit project
CN202745063U (en) Deep foundation pit steel plate pile and anchor cable shoring system construction structure
CN202595758U (en) Batter post foundation structure for overhead transmission line
CN204753656U (en) A clump of piles - soil - structure interact experimental model directly replaces to one side
CN204125935U (en) A kind of micropore castinplace pile being applicable to solar photovoltaic bracket basis
CN201169781Y (en) Cap digging pit structure
CN203411988U (en) Independent medium-sized pile foundation
CN202866002U (en) Steel reinforced concrete non-embedded type pillar base
CN203007965U (en) Steel hanging box system for underwater high-rise pile cap construction
CN104453336B (en) Base structure of high-pressure steel pipe pole
CN203514325U (en) Foundation pit stair support system with gravity type cement cob wall in combination with single rank of piles
CN103215965A (en) Laminate type high-rise platform pile tower crane foundation and construction method
CN202706053U (en) Offshore fan foundation combined with spider negative-pressure pile barrel
CN202440824U (en) Three-line-pile super-deep foundation-pit support structure
CN203213140U (en) Laminate-type high pile cap tower crane foundation structure
CN202017494U (en) Large-diameter jacking pipe structure for power tunnel engineering
CN202208929U (en) Support strengthening device capable of enabling underground pipeline to occupy support structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100818

Termination date: 20171210