Laminate-type high pile cap tower crane foundation structure Download PDFInfo
- Publication number
- CN203213140U CN203213140U CN 201320175505 CN201320175505U CN203213140U CN 203213140 U CN203213140 U CN 203213140U CN 201320175505 CN201320175505 CN 201320175505 CN 201320175505 U CN201320175505 U CN 201320175505U CN 203213140 U CN203213140 U CN 203213140U
- Authority
- CN
- China
- Prior art keywords
- tower crane
- cast
- place concrete
- foundation
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model provides a laminate-type high pile cap tower crane foundation structure which comprises four cast-in-place concrete piles arranged in a foundation pit. The cast-in-place concrete piles penetrate through a foundation mat, a reinforced concrete pile cap is fixedly arranged on pile tops of the cast-in-place concrete piles, a tower crane foundation joint is fixedly arranged in the reinforced concrete pile cap, a plurality of concrete laminate structures are formed on the cast-in-place concrete piles located above the foundation mat, and the cast-in-place concrete piles are arranged in the concrete laminate structures in a penetrating mode. The laminate-type high pile cap tower crane foundation structure well solves the problems that a tower crane is utilized to carry out vertical transportation in the whole process of the construction process of the foundation pit and the tower crane is poor in performance, the tower crane can be installed in advance for operating before engineering piles are constructed or before foundation pit earth excavation, foundation pit excavation time is effectively shortened, work efficiency of foundation pit construction is improved, the foundation pit construction period can be greatly shortened, and advantages for smooth proceeding of follow-up working procedures are provided.
Description
Technical field
The utility model relates to a kind of tower crane structure, particularly relates to a kind of laminated board type highrise pile cap tower crane structure.
Background technology
At present, the comparatively common a kind of mode of large-scale construction method of deep foundation ditch is: before soil excavation, four concrete filled steel tube castinplace piles of elder generation's construction or cast-in-place concrete pile, stake top mark height is located at below the tower crane cushion cap, after treating that tower crane installs, carry out soil excavation again, the castinplace pile of support tower crane successively exposes with the intensification of the soil excavation degree of depth, form destabilizing factor, for addressing this problem, need between four steel tube concrete piles or concrete pile, to form bridging with the steel pipe welding, increase the resistance to overturning of high stake part.Though this method has increased the stability of tower crane, increase welding sequence, increased a large amount of other operations such as steel work welding engineering amount, make tower crane be subjected to certain limitation service time.
Summary of the invention
In view of the existing technical problem that exists, the utility model provide a kind of Stability Analysis of Structures, firmly, the efficiency of construction in the safety, raising foundation ditch, and easy construction, laminated board type highrise pile cap tower crane structure with low cost.
Laminated board type highrise pile cap tower crane structure of the present utility model, comprise four cast-in-place concrete piles that are arranged in the foundation ditch, described cast-in-place concrete pile runs through sole plate, the stake top of described cast-in-place concrete pile is installed with a steel concrete cushion cap, be installed with tower crane joint in the described steel concrete cushion cap, be on the cast-in-place concrete pile of described sole plate top and be formed with plural layer of concrete plated construction, and described cast-in-place concrete pile is arranged in the described layer of concrete plated construction.
The length that described cast-in-place concrete pile is positioned at the following anchoring section of sole plate is not less than 2 with the length ratio that exposes to the revealed section of foundation ditch.
Described layer of concrete plated construction comprises the reinforced mesh of double-layer double-direction.
The utility model makes its beneficial effect that has be owing to adopt above technical scheme:
Behind construction and mounted castinplace pile and concrete bearing platform, earth excavation is built then and is formed the plural layer veneer structure downwards, finishes the installation of tower crane.The utility model is by being arranged on each plated construction layer by layer on four castinplace piles, make tower crane Stability Analysis of Structures of the present utility model, firmly, safe, compare other highrise pile cap easy constructions, with low cost, preferably resolving in the foundation pit construction process overall process uses tower crane to carry out vertical transport, the difficult problem of tower crane poor stability, the engineering stake do not construct or pit earthwork excavation before just can install tower crane in advance and turn round, effectively shortened the excavation of foundation pit time, improved the operating efficiency of foundation pit construction, can shorten the foundation pit construction duration in a large number, carrying out smoothly for subsequent handling provides advantage.
Description of drawings
Fig. 1 is the utility model tower crane structure elevation;
Fig. 2 is the utility model tower crane structural laminate plate structural plan figure.
The specific embodiment
For the benefit of to the understanding of structure of the present utility model, describe below in conjunction with drawings and Examples.
In conjunction with Fig. 1 and shown in Figure 2, laminated board type highrise pile cap tower crane structure of the present utility model, comprise four cast-in-place concrete piles 1 that are arranged in the foundation ditch, become the four directions to arrange, a stake top mark high position is near ground surface, castinplace pile 1 wears in the sole plate 2, the length that every castinplace pile 1 is positioned at sole plate 2 following anchoring sections 11 is not less than 2 with the length ratio that exposes to the revealed section 12 of foundation ditch, guaranteed the stability of castinplace pile 1, and a steel concrete cushion cap 3 has been built in the stake top casting, pre-buried tower crane joint 4 in the concrete bearing platform 3, can make body of the tower and foundation structure is affixed is integral by tower crane joint 4, be on the castinplace pile 1 of sole plate 2 tops and be formed with plural layer of concrete plated construction 5, castinplace pile 1 is arranged in the veneer structure 5, and adjacent layer plated construction 5 is between the upper and lower every being not more than 2m, the every limit of planar dimension exceeds castinplace pile 1 and is not less than 0.5m, thick 250mm, configuration reinforcement diameter are not less than 25mm@150mm double-layer double-direction reinforced mesh, and the strength grade of concrete of veneer structure 5 is not less than C35.
Before the pit earthwork excavation, four cast-in-place concrete piles 1 of elder generation's construction, make castinplace pile 1 through sole plate 2, steel concrete cushion cap 3 is built in stake top casting at four castinplace piles 1, earlier pre-buried tower crane joint 4 is built then before concrete bearing platform 3 is built, and finishes the installation of tower crane, then excavation 500mm is dark downwards earlier around concrete bearing platform, substantially after smooth, lay common composite board, assembling reinforcement net sheet, template around installing then, build and form first floor veneer structure 5, the excavation pit earthwork then is in digging process, whenever dig 2m downwards, according to the identical step plated construction 5 from level to level of constructing, thereby finish the construction of tower crane structure, increased the resistance to overturning of high stake part, by tower crane joint 4 body of the tower is installed on the tower crane structure then, lifts hauling operation.
The utility model is by being arranged on each the layer concrete veneer structure 5 on four cast-in-place concrete piles 1, make tower crane Stability Analysis of Structures of the present utility model, firmly, safe, compare other highrise pile cap easy constructions, with low cost, preferably resolving in the foundation pit construction process overall process uses tower crane to carry out vertical transport, the difficult problem of tower crane poor stability, the engineering stake do not construct or pit earthwork excavation before just can install tower crane in advance and turn round, effectively shortened the excavation of foundation pit time, improved the operating efficiency of foundation pit construction, can shorten the foundation pit construction duration in a large number, carrying out smoothly for subsequent handling provides advantage.
Claims (3)
1. laminated board type highrise pile cap tower crane structure, comprise four cast-in-place concrete piles that are arranged in the foundation ditch, described cast-in-place concrete pile runs through sole plate, the stake top of described cast-in-place concrete pile is installed with a steel concrete cushion cap, be installed with tower crane joint in the described steel concrete cushion cap, it is characterized in that: be on the cast-in-place concrete pile of described sole plate top and be formed with plural layer of concrete plated construction, and described cast-in-place concrete pile is arranged in the described layer of concrete plated construction.
2. tower crane structure according to claim 1 is characterized in that: the length that described cast-in-place concrete pile is positioned at the following anchoring section of sole plate is not less than 2 with the length ratio that exposes to the revealed section of foundation ditch.
3. tower crane structure according to claim 1, it is characterized in that: described layer of concrete plated construction comprises the reinforced mesh of double-layer double-direction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201320175505 CN203213140U (en) | 2013-04-10 | 2013-04-10 | Laminate-type high pile cap tower crane foundation structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201320175505 CN203213140U (en) | 2013-04-10 | 2013-04-10 | Laminate-type high pile cap tower crane foundation structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203213140U true CN203213140U (en) | 2013-09-25 |
Family
ID=49202688
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201320175505 Expired - Fee Related CN203213140U (en) | 2013-04-10 | 2013-04-10 | Laminate-type high pile cap tower crane foundation structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203213140U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103215965A (en) * | 2013-04-10 | 2013-07-24 | 中国建筑第八工程局有限公司 | Laminate type high-rise platform pile tower crane foundation and construction method |
CN103924611A (en) * | 2014-05-06 | 2014-07-16 | 同济大学建筑设计研究院(集团)有限公司 | Prefabricated prestressed concrete frame inserting and connecting integrated high pile bearing platform foundation |
-
2013
- 2013-04-10 CN CN 201320175505 patent/CN203213140U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103215965A (en) * | 2013-04-10 | 2013-07-24 | 中国建筑第八工程局有限公司 | Laminate type high-rise platform pile tower crane foundation and construction method |
CN103924611A (en) * | 2014-05-06 | 2014-07-16 | 同济大学建筑设计研究院(集团)有限公司 | Prefabricated prestressed concrete frame inserting and connecting integrated high pile bearing platform foundation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103437567B (en) | Method for supporting existing building underground added storey through original pile foundations | |
CN104453274B (en) | Utilize supporting and protection structure and underpinning structure to support existing building underground and increase layer method | |
US9359741B2 (en) | Wind turbine generator foundation with pressure-dispersive high strength pre-stressed anchors | |
CN102191777B (en) | Steel sheet pile coefferdam structure and topdown construction method thereof | |
CN107299643A (en) | Steel lattice column combined type tower crane foundation structure in foundation pit and construction method | |
CN201132960Y (en) | Composite batardeau of steel light structure | |
CN103225304B (en) | A kind of marine foundation supporting structure and construction method thereof | |
CN110374111B (en) | Slope releasing and steel pipe pile anchor cooperative supporting system | |
CN101240550A (en) | Construction method for lattice type steel column tower crane pedestal | |
CN102561384A (en) | Steel hoop truss type elevated pile cap tower crane foundation construction method and structure | |
CN102434717A (en) | Construction method of joist steel pipe-jacking work pit | |
CN103938634A (en) | Deep foundation pit supporting structure and construction method | |
CN103556651A (en) | Precast concrete jacket type offshore wind turbine foundation | |
CN205024712U (en) | Modular tower crane basis | |
CN202519697U (en) | Steel hoop truss high pile-cap tower crane basic structure | |
CN203429648U (en) | Large steel cylinder cofferdam structure | |
CN101498133B (en) | Method and supporting construction for enlarging basement top-down method earth excavation space | |
CN203213140U (en) | Laminate-type high pile cap tower crane foundation structure | |
CN204590059U (en) | A kind of combined type tower-crane foundation structure | |
CN103215965A (en) | Laminate type high-rise platform pile tower crane foundation and construction method | |
CN202745063U (en) | Deep foundation pit steel plate pile and anchor cable shoring system construction structure | |
CN106400814A (en) | Foundation pit supporting method | |
CN203821399U (en) | Deep foundation pit supporting structure | |
CN201722700U (en) | Infrastructure of tower crane | |
CN205205848U (en) | Cavity gravity type marine wind power basis |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130925 Termination date: 20190410 |