CN201842567U - Lifting frame for modular tube panel of waste heat boiler - Google Patents
Lifting frame for modular tube panel of waste heat boiler Download PDFInfo
- Publication number
- CN201842567U CN201842567U CN2010201664473U CN201020166447U CN201842567U CN 201842567 U CN201842567 U CN 201842567U CN 2010201664473 U CN2010201664473 U CN 2010201664473U CN 201020166447 U CN201020166447 U CN 201020166447U CN 201842567 U CN201842567 U CN 201842567U
- Authority
- CN
- China
- Prior art keywords
- lifting
- crossbeam
- beams
- tube panel
- panel
- Prior art date
Links
- 239000002918 waste heat Substances 0.000 title claims abstract description 19
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 26
- 239000010959 steel Substances 0.000 claims abstract description 26
- 239000002965 ropes Substances 0.000 claims abstract description 25
- 239000000725 suspensions Substances 0.000 claims description 22
- 230000000875 corresponding Effects 0.000 claims description 6
- 210000001503 Joints Anatomy 0.000 description 4
- 239000003344 environmental pollutants Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000203 mixtures Substances 0.000 description 1
- 231100000719 pollutant Toxicity 0.000 description 1
- 239000007787 solids Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Abstract
Description
Technical field
The utility model relates to a kind of upending frame, especially relates to a kind of waste heat boiler module upending frame of, poor rigidity object heavier than length and width degree broad, weight by lifting thing length.
Background technology
Since entering this century, China has built the modern large-scale 9F level power station waste heat boiler of large quantities of high efficiencys, low pollutant emission, for huge contribution has been made in the development that improves energy utilization rate, reduction atmospheric contamination and China's electric utility.
Yet, nearly 25 meters of 9F level waste heat boiler module tube panel length, about 4 meters of width, nearly 25 tons of weight, and at length, Width rigidity extreme difference, conventional lifting method is as 4 points, 6 points, 8 lifting modes etc., it is very big to produce horizontal component of force in length, Width, this product of can't slinging; Promptly enable lifting, also can have potential safety hazard owing to too poor by lifting thing rigidity.Therefore, how to solve the lifting problem of waste heat boiler module, become each cauldron producer and Installation in Plant company exigence, have realistic meanings and practical value.
Summary of the invention
The utility model mainly is to solve the difficult technical matters of existing in prior technology 9F level waste heat boiler module tube panel lifting, and a kind of upending frame that can effectively solve, poor rigidity object lifting problem heavier than length and width degree broad, weight by lifting thing length and have safety is provided.
Above-mentioned technical matters of the present utility model is mainly solved by following technical proposals: the utility model comprises two crossbeams, some lifting beams, the connecting panel of captiveing joint with lifting beam, the lifting beam anchor fitting, limiting stopper captiveing joint with crossbeam in the two ends of crossbeam is suspended on the steel rope on the lifting beam, is fixed on the suspension hook on the steel rope, the hanger of captiveing joint with crossbeam, crossbeam is by connecting panel and lifting beam sliding block joint.
As preferably, lifting beam is the 4-9 root, and 2 hangers are set on every crossbeam, and the quantity of steel rope is the 4-9 root.
As preferably, the lifting beam anchor fitting comprises nuts and bolt, and nut is captiveed joint with lifting beam, and bolt passes on the lifting beam and withstands on the crossbeam with the corresponding hole of bolt.
As preferably, connecting panel is that L shaped, L shaped minor face is captiveed joint with lifting beam, and L shaped long side suspension is on crossbeam.
Therefore, the utlity model has characteristics, especially length direction such as rational in infrastructure, easy to use and be provided with 4-9 shelves lifting beam, and on lifting beam, arrange 4-9 suspension hook 8, make module tube panel stress point mostly be 81 most at crossbeam 1.Dress weldering sliding block joint steel plate makes it be connected with crossbeam on lifting beam, this structure makes the position of lifting beam scalable at the stress point of length direction, make upending frame can be suitable for the lifting of the waste heat boiler module tube panel of different model, and make maximum 81 stress points for vertically upward object not being produced horizontal component of force, solved by lifting thing poor rigidity, the difficult problem that conventional lifting method can't lift by crane.Device nut, bolt decide in the dress solid welding on lifting beam, are used to prevent the slide relative between crossbeam and the lifting beam, guarantee to lift by crane safety.At crossbeam two ends dress weldering limiting stopper, be used to prevent that lifting beam from skidding off crossbeam.Hanger is housed on lifting beam, is used for weight-lifting equipment and links to each other with upending frame (for 4 conventional liftings), so the utility model has solved by lifting thing length effectively than length and width degree broad, the difficult problem of weight lifting heavier, the poor rigidity object.
Description of drawings
Accompanying drawing 1 is a structural representation of the present utility model;
Accompanying drawing 2 is A-A views.
The specific embodiment
Below by embodiment, and in conjunction with the accompanying drawings, the technical solution of the utility model is described in further detail.
Embodiment 1: the utility model comprises two crossbeams 1,4 lifting beams 2, the L shaped connecting panel 3 of captiveing joint with lifting beam 2, nut 4 and bolt 5, the limiting stopper 6 of captiveing joint with crossbeam 1 at the two ends of crossbeam 1, be suspended on 4 steel ropes 7 on the lifting beam 2, be fixed on the suspension hook 8 on the steel rope 7, be fixedly connected with two hangers 9 on the every crossbeam 1, crossbeam 1 is by connecting panel 3 and lifting beam 2 sliding block joints, and nut 4 is captiveed joint with lifting beam 2, and bolt 5 passes on the lifting beam 2 and withstands on the crossbeam 1 with bolt 5 corresponding holes, the minor face of L shaped connecting panel 3 is captiveed joint with lifting beam 2, and L shaped long side suspension is on crossbeam 1.(referring to Fig. 1, Fig. 2)
In the present embodiment, when lifting, length according to waste heat boiler module tube panel 10 is provided with 4 lifting beams 2,4 steel ropes 7 are set on the every lifting beam 2, to catch on the fixedly pipe clamp 11 of tube panel with the suspension hook 8 of utility model simultaneously, according to pipe clamp position adjustments lifting beam 2 relative position, make the distance between the lifting beam 2 equate that with distance between the module tube panel pipe clamp assurance object is stressed vertically upward with crossbeam 1; Tighting a bolt 5 prevents that lifting beam from sliding on crossbeam, guarantee lifting safety.Four hangers 9 on the upending frame are linked to each other with weight-lifting equipment by steel rope, 16 suspension hooks 8 are hung over implement lifting on the pipe clamp of module tube panel, making module tube panel stress point by upending frame is 16, make 16 stress points for vertically upward object not being produced horizontal component of force, solved by lifting thing poor rigidity, the difficult problem that conventional lifting method can't lift by crane.At crossbeam two ends dress weldering limiting stopper, be used to prevent that lifting beam from skidding off crossbeam.Because four hangers are housed in the utility model, lifting method still is 4 conventional liftings.
Embodiment 2: the utility model comprises two crossbeams 1,6 lifting beams 2, the L shaped connecting panel 3 of captiveing joint with lifting beam 2, nut 4 and bolt 5, the limiting stopper 6 of captiveing joint with crossbeam 1 at the two ends of crossbeam 1, be suspended on 6 steel ropes 7 on the lifting beam 2, be fixed on the suspension hook 8 on the steel rope 7, be fixedly connected with two hangers 9 on the every crossbeam 1, crossbeam 1 is by connecting panel 3 and lifting beam 2 sliding block joints, and nut 4 is captiveed joint with lifting beam 2, and bolt 5 passes on the lifting beam 2 and withstands on the crossbeam 1 with bolt 5 corresponding holes, the minor face of L shaped connecting panel 3 is captiveed joint with lifting beam 2, and L shaped long side suspension is on crossbeam 1.(referring to Fig. 1, Fig. 2)
In the present embodiment, when lifting, length according to waste heat boiler module tube panel 10 is provided with 6 lifting beams 2,6 steel ropes 7 are set on the every lifting beam 2, to catch on the fixedly pipe clamp 11 of tube panel with the suspension hook 8 of utility model simultaneously, according to pipe clamp position adjustments lifting beam 2 relative position, make the distance between the lifting beam 2 equate that with distance between the module tube panel pipe clamp assurance object is stressed vertically upward with crossbeam 1; Tighting a bolt 5 prevents that lifting beam from sliding on crossbeam, guarantee lifting safety.Four hangers 9 on the upending frame are linked to each other with weight-lifting equipment by steel rope, 36 suspension hooks 8 are hung over implement lifting on the pipe clamp of module tube panel, making module tube panel stress point by upending frame is 36, make 36 stress points for vertically upward object not being produced horizontal component of force, solved by lifting thing poor rigidity, the difficult problem that conventional lifting method can't lift by crane.At crossbeam two ends dress weldering limiting stopper, be used to prevent that lifting beam from skidding off crossbeam.Because four hangers are housed in the utility model, lifting method still is 4 conventional liftings.
Embodiment 3: the utility model comprises two crossbeams 1,9 lifting beams 2, the L shaped connecting panel 3 of captiveing joint with lifting beam 2, nut 4 and bolt 5, the limiting stopper 6 of captiveing joint with crossbeam 1 at the two ends of crossbeam 1, be suspended on 9 steel ropes 7 on the lifting beam 2, be fixed on the suspension hook 8 on the steel rope 7, be fixedly connected with two hangers 9 on the every crossbeam 1, crossbeam 1 is by connecting panel 3 and lifting beam 2 sliding block joints, and nut 4 is captiveed joint with lifting beam 2, and bolt 5 passes on the lifting beam 2 and withstands on the crossbeam 1 with bolt 5 corresponding holes, the minor face of L shaped connecting panel 3 is captiveed joint with lifting beam 2, and L shaped long side suspension is on crossbeam 1.(referring to Fig. 1, Fig. 2)
In the present embodiment, when lifting, length according to waste heat boiler module tube panel 10 is provided with 9 lifting beams 2,9 steel ropes 7 are set on the every lifting beam 2, to catch on the fixedly pipe clamp 11 of tube panel with the suspension hook 8 of utility model simultaneously, according to pipe clamp position adjustments lifting beam 2 relative position, make the distance between the lifting beam 2 equate that with distance between the module tube panel pipe clamp assurance object is stressed vertically upward with crossbeam 1; Tighting a bolt 5 prevents that lifting beam from sliding on crossbeam, guarantee lifting safety.Four hangers 9 on the upending frame are linked to each other with weight-lifting equipment by steel rope, 81 suspension hooks 8 are hung over implement lifting on the pipe clamp of module tube panel, making module tube panel stress point by upending frame is 81, make 81 stress points for vertically upward object not being produced horizontal component of force, solved by lifting thing poor rigidity, the difficult problem that conventional lifting method can't lift by crane.At crossbeam two ends dress weldering limiting stopper, be used to prevent that lifting beam from skidding off crossbeam.Because four hangers are housed in the utility model, lifting method still is 4 conventional liftings.
Embodiment 4: the utility model comprises two crossbeams 1,7 lifting beams 2, the L shaped connecting panel 3 of captiveing joint with lifting beam 2, nut 4 and bolt 5, the limiting stopper 6 of captiveing joint with crossbeam 1 at the two ends of crossbeam 1, be suspended on 5 steel ropes 7 on the lifting beam 2, be fixed on the suspension hook 8 on the steel rope 7, be fixedly connected with two hangers 9 on the every crossbeam 1, crossbeam 1 is by connecting panel 3 and lifting beam 2 sliding block joints, and nut 4 is captiveed joint with lifting beam 2, and bolt 5 passes on the lifting beam 2 and withstands on the crossbeam 1 with bolt 5 corresponding holes, the minor face of L shaped connecting panel 3 is captiveed joint with lifting beam 2, and L shaped long side suspension is on crossbeam 1.(referring to Fig. 1, Fig. 2)
In the present embodiment, when lifting, length according to waste heat boiler module tube panel 10 is provided with 7 lifting beams 2,5 steel ropes 7 are set on the every lifting beam 2, to catch on the fixedly pipe clamp 11 of tube panel with the suspension hook 8 of utility model simultaneously, according to pipe clamp position adjustments lifting beam 2 relative position, make the distance between the lifting beam 2 equate that with distance between the module tube panel pipe clamp assurance object is stressed vertically upward with crossbeam 1; Tighting a bolt 5 prevents that lifting beam from sliding on crossbeam, guarantee lifting safety.Four hangers 9 on the upending frame are linked to each other with weight-lifting equipment by steel rope, 35 suspension hooks 8 are hung over implement lifting on the pipe clamp of module tube panel, making module tube panel stress point by upending frame is 35, make 35 stress points for vertically upward object not being produced horizontal component of force, solved by lifting thing poor rigidity, the difficult problem that conventional lifting method can't lift by crane.At crossbeam two ends dress weldering limiting stopper, be used to prevent that lifting beam from skidding off crossbeam.Because four hangers are housed in the utility model, lifting method still is 4 conventional liftings.
Certainly, the shape of connecting panel 3 is not limited in L shaped, also can be modes such as half elliptic, can use so long as can realize the shape of the sliding block joint between crossbeam 1 and the lifting beam 2; The lifting beam anchor fitting also is not limited in the nuts and bolt structure, as long as effectively the fixed form of fixed cross beam 1 and lifting beam 2 can adopt; The quantity of lifting beam 2 and steel rope 7 also is not limited in the foregoing description simultaneously, so long as the different combination between the 4-9 root can be adopted; Such variation all drops within the protection domain of the present utility model.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010201664473U CN201842567U (en) | 2010-04-22 | 2010-04-22 | Lifting frame for modular tube panel of waste heat boiler |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010201664473U CN201842567U (en) | 2010-04-22 | 2010-04-22 | Lifting frame for modular tube panel of waste heat boiler |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201842567U true CN201842567U (en) | 2011-05-25 |
Family
ID=44037464
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010201664473U CN201842567U (en) | 2010-04-22 | 2010-04-22 | Lifting frame for modular tube panel of waste heat boiler |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201842567U (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103912865A (en) * | 2014-03-28 | 2014-07-09 | 无锡华光锅炉股份有限公司 | Suspender support system of horizontal waste heat boiler module and mounting suspender structure of suspender support system |
CN103939875A (en) * | 2014-05-23 | 2014-07-23 | 山东电力建设第三工程公司 | Vertical type waste heat boiler module hanging construction method |
CN104003291A (en) * | 2014-06-11 | 2014-08-27 | 山东电力建设第一工程公司 | Single-rail walking lifting device for mounting boiler equipment in power plant |
CN104016279A (en) * | 2014-04-02 | 2014-09-03 | 无锡华光锅炉股份有限公司 | Frame for overturning single-piece module of horizontal type heat recovery steam generator |
CN104016220A (en) * | 2014-06-16 | 2014-09-03 | 山东电力建设第一工程公司 | Adjustable loading and unloading hanging bracket of waste heat boiler module |
CN105240619A (en) * | 2015-11-02 | 2016-01-13 | 无锡华光锅炉股份有限公司 | Pipe system hanging device of coal economizer |
CN106016233A (en) * | 2016-06-20 | 2016-10-12 | 中国十五冶金建设集团有限公司 | Boiler roof with long span and fewer welding spots and hoisting method for boiler roof |
CN107010529A (en) * | 2017-06-05 | 2017-08-04 | 上海外高桥造船有限公司 | Derrick branch erects the application method that piece frock hangs code |
CN107043067A (en) * | 2016-12-27 | 2017-08-15 | 四川川锅锅炉有限责任公司 | A kind of S-shaped tube panel boom hoisting |
CN109335962A (en) * | 2018-10-26 | 2019-02-15 | 中国能源建设集团江苏省电力建设第三工程有限公司 | Furnace roof superheater assembly hanging method after a kind of boiler |
CN111170142A (en) * | 2018-11-12 | 2020-05-19 | 青岛腾远设计事务所有限公司 | A but automatically regulated hanging beam for component hoist and mount |
-
2010
- 2010-04-22 CN CN2010201664473U patent/CN201842567U/en not_active IP Right Cessation
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103912865B (en) * | 2014-03-28 | 2016-04-06 | 无锡华光锅炉股份有限公司 | A kind of boom rest system of horizontal type waste heat boiler module and mounting suspension structure thereof |
CN103912865A (en) * | 2014-03-28 | 2014-07-09 | 无锡华光锅炉股份有限公司 | Suspender support system of horizontal waste heat boiler module and mounting suspender structure of suspender support system |
CN104016279A (en) * | 2014-04-02 | 2014-09-03 | 无锡华光锅炉股份有限公司 | Frame for overturning single-piece module of horizontal type heat recovery steam generator |
CN103939875B (en) * | 2014-05-23 | 2016-02-24 | 山东电力建设第三工程公司 | A kind of vertical exhaust-heat boiler module hoisting construction method |
CN103939875A (en) * | 2014-05-23 | 2014-07-23 | 山东电力建设第三工程公司 | Vertical type waste heat boiler module hanging construction method |
CN104003291A (en) * | 2014-06-11 | 2014-08-27 | 山东电力建设第一工程公司 | Single-rail walking lifting device for mounting boiler equipment in power plant |
CN104003291B (en) * | 2014-06-11 | 2015-12-23 | 山东电力建设第一工程公司 | A kind of power plant boiler equipment installation single track is walked suspender |
CN104016220B (en) * | 2014-06-16 | 2016-01-06 | 山东电力建设第一工程公司 | The adjustable handling suspension bracket of waste heat boiler module |
CN104016220A (en) * | 2014-06-16 | 2014-09-03 | 山东电力建设第一工程公司 | Adjustable loading and unloading hanging bracket of waste heat boiler module |
CN105240619A (en) * | 2015-11-02 | 2016-01-13 | 无锡华光锅炉股份有限公司 | Pipe system hanging device of coal economizer |
CN105240619B (en) * | 2015-11-02 | 2018-05-15 | 无锡华光锅炉股份有限公司 | A kind of economizer piping erecting by overhang |
CN106016233A (en) * | 2016-06-20 | 2016-10-12 | 中国十五冶金建设集团有限公司 | Boiler roof with long span and fewer welding spots and hoisting method for boiler roof |
CN107043067A (en) * | 2016-12-27 | 2017-08-15 | 四川川锅锅炉有限责任公司 | A kind of S-shaped tube panel boom hoisting |
CN107043067B (en) * | 2016-12-27 | 2018-09-18 | 四川川锅锅炉有限责任公司 | A kind of S-shaped tube panel boom hoisting |
CN107010529A (en) * | 2017-06-05 | 2017-08-04 | 上海外高桥造船有限公司 | Derrick branch erects the application method that piece frock hangs code |
CN107010529B (en) * | 2017-06-05 | 2018-07-20 | 上海外高桥造船有限公司 | Derrick branch erects the application method of piece tooling hanging code |
CN109335962A (en) * | 2018-10-26 | 2019-02-15 | 中国能源建设集团江苏省电力建设第三工程有限公司 | Furnace roof superheater assembly hanging method after a kind of boiler |
CN111170142A (en) * | 2018-11-12 | 2020-05-19 | 青岛腾远设计事务所有限公司 | A but automatically regulated hanging beam for component hoist and mount |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101672102B (en) | Steel structural overhead ceiling construction platform | |
CN201381166Y (en) | Hanging-point adjustable transverse hanging beam | |
CN102659019A (en) | Special lifting appliance for steel containment cover head in nuclear power station nuclear island and lifting method thereof | |
CN201565749U (en) | Special maintenance platform for isolating switch | |
CN201439475U (en) | Multifunctional balance hanging beam | |
CN202755634U (en) | Suspension type operational platform | |
CN204185120U (en) | Mobile unit dolly in place | |
CN203845712U (en) | Heavy-duty equipment hoisting device | |
CN202785258U (en) | Hoisting device for air overturn of large-sized steel column | |
CN201458590U (en) | Special hoisting tool of power transforming equipment | |
CN201882763U (en) | Special carrying pole type beam of double-machine lifting crane | |
CN202881852U (en) | Suspension bridge cable installation system | |
CN202706503U (en) | Electric lifting discharging platform for main building construction | |
CN202201618U (en) | Multi-level hoisting beam hoisting tool | |
CN202080812U (en) | Dedicated sling system for large-scaled reinforcing cage | |
CN202116219U (en) | Portable small-sized multipurpose portal frame | |
CN203474220U (en) | Spreader system for overturning and hoisting large diameter overweight sealing head | |
CN203128000U (en) | Hoisting device for direct-driven wind power generator set | |
CN104631810A (en) | High-altitude movable hanging basket system and construction method thereof | |
CN201943007U (en) | Constant amplitude frame beam crane capable of being used in combination with movable support frame | |
CN202508791U (en) | Novel tower section lead-in device | |
CN104131519B (en) | A kind of bridging toughening equipment construction method | |
CN201626764U (en) | Coke oven fire door hanger | |
CN202298606U (en) | Descending frame for mounting reinforcement cage of pile foundation | |
CN204342250U (en) | A kind of multi-state hoisting balance beam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
C14 | Grant of patent or utility model | ||
CP01 | Change in the name or title of a patent holder |
Address after: 314050 No. 1572 South City Road, Nanhu District, Zhejiang, Jiaxing Patentee after: MHPS DONGFANG BOILER CO., LTD. Address before: 314050 No. 1572 South City Road, Nanhu District, Zhejiang, Jiaxing Patentee before: Eastern Hitachi boiler Limited Company Address after: 314050 No. 1572 South City Road, Nanhu District, Zhejiang, Jiaxing Patentee after: MHPS DONGFANG BOILER CO., LTD. Address before: 314050 No. 1572 South City Road, Nanhu District, Zhejiang, Jiaxing Patentee before: Eastern Hitachi boiler Limited Company |
|
C56 | Change in the name or address of the patentee |
Owner name: DONGFANG MHPS BOLIER CO., LTD. Free format text: FORMER NAME: DONGFANG RILI BOILER CO., LTD. |
|
CP02 | Change in the address of a patent holder |
Address after: 314036 No. 1267, Chenggong Road, Zhejiang, Jiaxing Patentee after: MHPS DONGFANG BOILER CO., LTD. Address before: 314050 No. 1572 South City Road, Nanhu District, Zhejiang, Jiaxing Patentee before: MHPS DONGFANG BOILER CO., LTD. Address after: 314036 No. 1267, Chenggong Road, Zhejiang, Jiaxing Patentee after: MHPS DONGFANG BOILER CO., LTD. Address before: 314050 No. 1572 South City Road, Nanhu District, Zhejiang, Jiaxing Patentee before: MHPS DONGFANG BOILER CO., LTD. |
|
C56 | Change in the name or address of the patentee | ||
CX01 | Expiry of patent term |
Granted publication date: 20110525 |
|
CX01 | Expiry of patent term |