CN104003291A - Single-rail walking lifting device for mounting boiler equipment in power plant - Google Patents

Single-rail walking lifting device for mounting boiler equipment in power plant Download PDF

Info

Publication number
CN104003291A
CN104003291A CN201410255277.9A CN201410255277A CN104003291A CN 104003291 A CN104003291 A CN 104003291A CN 201410255277 A CN201410255277 A CN 201410255277A CN 104003291 A CN104003291 A CN 104003291A
Authority
CN
China
Prior art keywords
jig arm
walking
lifting
fixed
power plant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410255277.9A
Other languages
Chinese (zh)
Other versions
CN104003291B (en
Inventor
李开
崔文杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SEPCO Electric Power Construction Co Ltd
Original Assignee
SEPCO1 Electric Power Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SEPCO1 Electric Power Construction Co Ltd filed Critical SEPCO1 Electric Power Construction Co Ltd
Priority to CN201410255277.9A priority Critical patent/CN104003291B/en
Publication of CN104003291A publication Critical patent/CN104003291A/en
Application granted granted Critical
Publication of CN104003291B publication Critical patent/CN104003291B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to a single-rail walking lifting device for mounting boiler equipment in a power plant. The lifting device comprises a rail beam, a walking trolley, a beam, an upper lifting lug, a plurality of lower lifting lugs, chain blocks and clamping devices, wherein the walking trolley is arranged on the rail beam; the beam is horizontally arranged below the rail beam, and is spatially perpendicular to the rail beam; the upper lifting lug is arranged above the beam; the lower lifting lugs are arranged below the beam; the chain blocks are fixed on the corresponding lower lifting lugs; the clamping devices are fixed below the chain blocks, are respectively positioned between the corresponding fins, and hook each pipeline on a serpentine pipe screen; the upper lifting lug is fixed below the walking trolley through a lifting ring. According to the device, each clamping device is arranged between the corresponding fins to fix the serpentine pipe screen, so that the condition of damage to the fins in the lifting process can be effectively prevented; during lifting, the chain blocks are used for lifting the serpentine pipe screen, and a plurality of chain blocks are arranged below the beam, so that a plurality of lifting points are formed, and the device is stable and reliable; the serpentine pipe screen can be driven by the walking trolley to longitudinally move to a proper position, so that the efficiency is improved.

Description

A kind of power plant boiler equipment is installed with the single track suspender of walking
Technical field
The present invention relates to suspender technical field, be specifically related to a kind of power plant boiler equipment and install with the single track suspender of walking.
Background technology
In heat power plant boiler equipment, be generally all designed with S-shaped tube panel, this S-shaped tube panel lifting rigidity is poor, after lifting, need translation could arrive installation site, some S-shaped tube panels are designed with ultra-thin heat transfer H type fin, generally adopt at present steel rope binding lifting, the binding angle of steel rope can damage the H type fin of S-shaped tube panel, and original lifting mode efficiency is lower, uses steel rope more.
Summary of the invention
The present invention is in order to overcome the deficiency of above technology, provides a kind of power plant boiler equipment that can not damage S-shaped tube panel H type fin to install with the single track suspender of walking.
The present invention overcomes the technical scheme that its technical matters adopts:
This power plant boiler equipment is installed with the single track suspender of walking, comprise track girder, be installed on walking dolly on track girder, be horizontally placed on track girder below and and the crossbeam of track girder spatial vertical, be installed on crossbeam top upper hanger, be installed on crossbeam below some lower hanger, be fixed on the chain and tackle block on each lower hanger and be fixed on chain and tackle block below between two fins and hook the clamping apparatus of each pipeline on S-shaped tube panel, described upper hanger is fixed on walking dolly below by suspension ring.
Above-mentioned clamping apparatus comprises that thickness is less than the shackle plate of two fin pitch, is arranged at lifting hole(eyelet) on shackle plate, by bearing pin I, rotated and be installed on the connecting panel that shackle plate below and thickness are less than the left jig arm of two fin pitch and right jig arm and are fixed on respectively left jig arm and right jig arm below by bearing pin II, in described left jig arm and right jig arm, be relatively set with some gib heads, when left jig arm and right jig arm turn to while being parallel to each other, left jig arm and right jig arm and each gib head form the cavity volume that some cross-sectional planes are greater than S-shaped tube panel pipeline diameter.
In order once to lift by crane two S-shaped tube panels, above-mentioned crossbeam is two, and two crossbeams are parallel to each other, and described two upper and lower two ends of crossbeam are connected and fixed by some connecting panels respectively.
For the convenient lifting position of adjusting, above-mentioned crossbeam below is provided with slide rail, and described lower hanger is slidably fixed in slide rail.
In order not damage power cable, on above-mentioned track girder, be provided with along its length steel wire bracing wire, the power cable of described walking dolly is slided and is threaded onto in steel wire bracing wire by some links.
The invention has the beneficial effects as follows: by clamping apparatus, be placed between every two fins S-shaped tube panel is fixed, thereby can effectively prevent that the situation that fin damages in lifting process from occurring.During lifting, utilize chain and tackle block that S-shaped tube panel is lifted by crane, because crossbeam below is provided with a plurality of chain and tackle blocks, so Heave Here is many, reliable and stable.Walking dolly can drive S-shaped tube panel to move longitudinally to correct position, has improved efficiency.
Accompanying drawing explanation
Fig. 1 is main TV structure schematic diagram of the present invention;
Fig. 2 is left TV structure schematic diagram of the present invention;
Fig. 3 is clamping apparatus portion structure schematic diagram of the present invention;
In figure, 1. right jig arm 18. gib head 19. connecting panel 20. bearing pin II of 6. times hangers of hanger 5. crossbeam, the 7. chain and tackle block 8. clamping apparatus 9. S-shaped tube panel 10. steel wire bracing wire 11. power cable left jig arm 17. of 12. connecting panel 13. shackle plate 14. lifting hole(eyelet) 15. bearing pin I 16. on track girder 2. walking dolly 3. suspension ring 4..
The specific embodiment
Below in conjunction with accompanying drawing 1, accompanying drawing 2, the present invention will be further described for accompanying drawing 3.
This power plant boiler equipment is installed with the single track suspender of walking, comprise track girder 1, be installed on walking dolly 2 on track girder 1, be horizontally placed on track girder 1 below and and the crossbeam 5 of track girder 1 spatial vertical, be installed on crossbeam 5 tops upper hanger 4, be installed on crossbeam 5 belows some lower hanger 6, be fixed on the chain and tackle block 7 on each lower hanger 6 and be fixed on chain and tackle block 7 belows between two fins and hook the clamping apparatus 8 of each pipeline on S-shaped tube panel 9, upper hanger 4 is fixed on walking dolly 2 belows by suspension ring 3.By clamping apparatus 8, be placed between every two fins S-shaped tube panel 9 is fixed, thereby can effectively prevent that the situation that fin damages in lifting process from occurring.During lifting, utilize chain and tackle block 7 by S-shaped tube panel 9 liftings, because crossbeam 5 belows are provided with a plurality of chain and tackle blocks 7, so Heave Here is many, reliable and stable.Walking dolly 2 can drive S-shaped tube panel 9 to move longitudinally to correct position, has improved efficiency.
Above-mentioned clamping apparatus 8 comprises that thickness is less than the shackle plate 13 of two fin pitch, be arranged at the lifting hole(eyelet) 14 on shackle plate 13, by bearing pin I 15, rotate and be installed on the connecting panel 19 that shackle plate 13 belows and thickness are less than the left jig arm 16 of two fin pitch and right jig arm 17 and are fixed on respectively left jig arm 16 and right jig arm 17 belows by bearing pin II 20, in left jig arm 16 and right jig arm 17, be relatively set with some gib heads 18, when left jig arm 16 and right jig arm 17 turn to while being parallel to each other, left jig arm 16 and right jig arm 17 form with each gib head 18 cavity volume that some cross-sectional planes are greater than S-shaped tube panel 9 pipeline diameters.In the time of need to lifting, bearing pin II 20 is extracted, thereby connecting panel 12 is pulled down, now to both sides, rotate respectively left jig arm 16 and right jig arm 17, thereby make it open mouth, and make left jig arm 16 and right jig arm 17 lay respectively at the both sides of S-shaped tube panel 9, afterwards left jig arm 16 and right jig arm 17 are drawn close to the inside, left jig arm 16 and right jig arm 17 are placed between two fins, and make gib head 18 hook each pipeline in S-shaped tube panel 9, by bearing pin II 20, connecting panel 12 is fixed on to left jig arm 16 and right jig arm 17 belows afterwards, realizes locking.Now can utilize by the hook of chain and tackle block 7 lower ends lifting hole(eyelet) 14 by S-shaped tube panel 9 liftings, convenient disassembly is simple.
Crossbeam 5 can be two, and two crossbeams 5 are parallel to each other, and two crossbeams are connected and fixed by some connecting panels 12 respectively at two ends Shang Xia 5.By two crossbeams 5 are set, can once lift by crane two S-shaped tube panels 9, improve efficiency.
Crossbeam 5 belows can be provided with slide rail, and lower hanger 6 is slidably fixed in slide rail.By movement, descend hanger 6 to make its size according to S-shaped tube panel 9 move to correct position, can conveniently adjust lifting position, improved the convenience using.
On track girder 1, be provided with along its length steel wire bracing wire 10, the power cable 11 of walking dolly 2 is slided and is threaded onto in steel wire bracing wire 10 by some links.When walking dolly 2 is walked along track girder 1, its power cable 11 can be followed walking dolly 2 along steel wire bracing wire 10 by link and be moved, and effectively prevents that the situation of power cable 11 fails in tension from occurring, and has improved the reliability using.

Claims (5)

1. power plant boiler equipment is installed with the single track suspender of walking, it is characterized in that: comprise track girder (1), be installed on the walking dolly (2) on track girder (1), be horizontally placed on track girder (1) below and with the crossbeam (5) of track girder (1) spatial vertical, be installed on the upper hanger (4) of crossbeam (5) top, be installed on the some lower hanger (6) of crossbeam (5) below, be fixed on the chain and tackle block (7) on each lower hanger (6) and be fixed on chain and tackle block (7) below between two fins and hook the clamping apparatus (8) of upper each pipeline of S-shaped tube panel (9), described upper hanger (4) is fixed on walking dolly (2) below by suspension ring (3).
2. power plant boiler according to claim 1 equipment is installed with the single track suspender of walking, it is characterized in that: described clamping apparatus (8) comprises that thickness is less than the shackle plate of two fin pitch (13), be arranged at the lifting hole(eyelet) (14) on shackle plate (13), by bearing pin I (15), rotate and to be installed on shackle plate (13) below and thickness and to be less than the left jig arm (16) of two fin pitch and right jig arm (17) and by bearing pin II (20), to be fixed on the connecting panel (19) below left jig arm (16) and right jig arm (17) respectively, in described left jig arm (16) and right jig arm (17), be relatively set with some gib heads (18), when left jig arm (16) and right jig arm (17) turn to while being parallel to each other, left jig arm (16) and right jig arm (17) form with each gib head (18) cavity volume that some cross-sectional planes are greater than S-shaped tube panel (9) pipeline diameter.
3. power plant boiler according to claim 1 equipment is installed with the single track suspender of walking, it is characterized in that: described crossbeam (5) is two, and two crossbeams (5) are parallel to each other, the upper and lower two ends of described two crossbeams (5) are connected and fixed by some connecting panels (12) respectively.
4. according to the power plant boiler equipment described in claim 1 or 2 or 3, install with the single track suspender of walking, it is characterized in that: described crossbeam (5) below is provided with slide rail, and described lower hanger (6) is slidably fixed in slide rail.
5. power plant boiler according to claim 4 equipment is installed with the single track suspender of walking, it is characterized in that: on described track girder (1), be provided with along its length steel wire bracing wire (10), the power cable (11) of described walking dolly (2) is slided and is threaded onto in steel wire bracing wire (10) by some links.
CN201410255277.9A 2014-06-11 2014-06-11 A kind of power plant boiler equipment installation single track is walked suspender Active CN104003291B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410255277.9A CN104003291B (en) 2014-06-11 2014-06-11 A kind of power plant boiler equipment installation single track is walked suspender

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410255277.9A CN104003291B (en) 2014-06-11 2014-06-11 A kind of power plant boiler equipment installation single track is walked suspender

Publications (2)

Publication Number Publication Date
CN104003291A true CN104003291A (en) 2014-08-27
CN104003291B CN104003291B (en) 2015-12-23

Family

ID=51364238

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410255277.9A Active CN104003291B (en) 2014-06-11 2014-06-11 A kind of power plant boiler equipment installation single track is walked suspender

Country Status (1)

Country Link
CN (1) CN104003291B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106219415A (en) * 2016-08-24 2016-12-14 中铁第四勘察设计院集团有限公司 A kind of balance crane lifting elongated object
CN106629373A (en) * 2017-02-14 2017-05-10 太仓联洲机械设备有限公司 Track lifting mechanism
CN107416690A (en) * 2016-05-23 2017-12-01 五冶集团上海有限公司 A kind of dry quenched coke boiler economizer coiled pipe installs suspender in place and its application method
CN107738986A (en) * 2017-11-23 2018-02-27 国家电网公司 Complete non-maintaining simple and easy hoisting system manually
CN110343798A (en) * 2019-07-01 2019-10-18 中冶宝钢技术服务有限公司 A kind of corrugated pipe disassembling device and assembly and disassembly methods

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2939686A1 (en) * 1979-09-29 1981-04-02 Klöckner-Becorit GmbH, 4620 Castrop-Rauxel LIFTING BARS FOR A RAILWAY RAILWAY
GB2095641A (en) * 1981-04-01 1982-10-06 Neuhauser Kg A hoisting beam for transporting a tiltably suspended transport skip or the like
DE4326563A1 (en) * 1993-08-07 1995-02-09 Rainer F Tracksdorf Conveying apparatus for vehicle bodies
JP2000327259A (en) * 1999-05-19 2000-11-28 Ishikawajima Harima Heavy Ind Co Ltd Heating tube panel block hoisting method for exhaust heat recovery boiler
CN201737594U (en) * 2010-04-22 2011-02-09 东方日立锅炉有限公司 Lifting rack for serpentine tube panels
CN201842567U (en) * 2010-04-22 2011-05-25 东方日立锅炉有限公司 Lifting frame for modular tube panel of waste heat boiler
CN202897838U (en) * 2012-07-26 2013-04-24 常州御发工矿设备有限公司 Lifting beam of coal mine transportation system
CN203903767U (en) * 2014-06-11 2014-10-29 山东电力建设第一工程公司 Single-rail walking sling for installing power plant boiler equipment

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2939686A1 (en) * 1979-09-29 1981-04-02 Klöckner-Becorit GmbH, 4620 Castrop-Rauxel LIFTING BARS FOR A RAILWAY RAILWAY
GB2095641A (en) * 1981-04-01 1982-10-06 Neuhauser Kg A hoisting beam for transporting a tiltably suspended transport skip or the like
DE4326563A1 (en) * 1993-08-07 1995-02-09 Rainer F Tracksdorf Conveying apparatus for vehicle bodies
JP2000327259A (en) * 1999-05-19 2000-11-28 Ishikawajima Harima Heavy Ind Co Ltd Heating tube panel block hoisting method for exhaust heat recovery boiler
CN201737594U (en) * 2010-04-22 2011-02-09 东方日立锅炉有限公司 Lifting rack for serpentine tube panels
CN201842567U (en) * 2010-04-22 2011-05-25 东方日立锅炉有限公司 Lifting frame for modular tube panel of waste heat boiler
CN202897838U (en) * 2012-07-26 2013-04-24 常州御发工矿设备有限公司 Lifting beam of coal mine transportation system
CN203903767U (en) * 2014-06-11 2014-10-29 山东电力建设第一工程公司 Single-rail walking sling for installing power plant boiler equipment

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107416690A (en) * 2016-05-23 2017-12-01 五冶集团上海有限公司 A kind of dry quenched coke boiler economizer coiled pipe installs suspender in place and its application method
CN106219415A (en) * 2016-08-24 2016-12-14 中铁第四勘察设计院集团有限公司 A kind of balance crane lifting elongated object
CN106629373A (en) * 2017-02-14 2017-05-10 太仓联洲机械设备有限公司 Track lifting mechanism
CN107738986A (en) * 2017-11-23 2018-02-27 国家电网公司 Complete non-maintaining simple and easy hoisting system manually
CN107738986B (en) * 2017-11-23 2024-04-05 国家电网公司 Full-manual maintenance-free simple hoisting system
CN110343798A (en) * 2019-07-01 2019-10-18 中冶宝钢技术服务有限公司 A kind of corrugated pipe disassembling device and assembly and disassembly methods

Also Published As

Publication number Publication date
CN104003291B (en) 2015-12-23

Similar Documents

Publication Publication Date Title
CN203903767U (en) Single-rail walking sling for installing power plant boiler equipment
CN104003291B (en) A kind of power plant boiler equipment installation single track is walked suspender
CN202098976U (en) Device capable of freely adjusting sling length and overhead transverse posture of part
CN202429881U (en) Automatic pipe clamping device
CN103993745B (en) A kind of conversion beam integral hoisting device for rapid and hanging method thereof
CN101660295B (en) Hoisting method of arch bridge arch rib or beam body along bridge direction
CN102992203B (en) Simple hoisting device for steel structure bridge installation
CN202197048U (en) Double angle steel hanging point lifting and connecting tool for tower use
CN201436274U (en) Special assembling suspender of long chain for slab rolling mill engineering steel plate conveying device
CN102944408B (en) Push chain device of anchor chain tension tester
CN108999458A (en) The double cross-arm assembly integral installation device and method of electric power
CN203513079U (en) Multi-segment lifting device for large tower device
CN102163824B (en) Operating tool and operation method for electrically replacing T-type mounting point suspending insulator in 110kV line steel pipe rod
CN209554640U (en) A kind of novel pier front rack transporting device
CN201809032U (en) Self-adjusting stay device with combinable hanger
CN101695984B (en) Assembly method and assembly lifting appliance of vertical beam and horizontal beam under arc of midheight deck steel pipe concrete arch bridge
CN104016220B (en) The adjustable handling suspension bracket of waste heat boiler module
CN102237654B (en) Method for replacing jumper string using tool at double angle hanging point
CN103273052A (en) Method and device for rapidly transferring hanging type casting bogie
CN215101506U (en) Hoist device that intelligence building was used
CN202967922U (en) Simple hoisting device for mounting steel structural bridge
CN204490327U (en) Joist steel hoisting clamp
CN101767753B (en) Method for hoisting by lifting belt vertically
CN201138725Y (en) Door type frame for indoor equipment repair
CN201946913U (en) Working tool for electrified replacement of T-shaped hanging point suspension insulator on 110 kV line steel tube rod

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: No.6 building, zone 2, Hanyu financial and business center, hi tech Zone, Jinan City, Shandong Province

Patentee after: POWERCHINA SEPCO1 ELECTRIC POWER CONSTRUCTION Co.,Ltd.

Address before: 250131 No. 244 Industrial North Road, Jinan City, Shandong Province

Patentee before: SEPCO1 ELECTRIC POWER CONSTRUCTION Corp.

CP03 Change of name, title or address
CB03 Change of inventor or designer information

Inventor after: Liu Yongyang

Inventor after: Li Kai

Inventor after: Zhang Chongyang

Inventor after: Zhang Jianping

Inventor after: Cui Wenjie

Inventor before: Li Kai

Inventor before: Cui Wenjie

CB03 Change of inventor or designer information