CN103939875B - A kind of vertical exhaust-heat boiler module hoisting construction method - Google Patents

A kind of vertical exhaust-heat boiler module hoisting construction method Download PDF

Info

Publication number
CN103939875B
CN103939875B CN201410220758.6A CN201410220758A CN103939875B CN 103939875 B CN103939875 B CN 103939875B CN 201410220758 A CN201410220758 A CN 201410220758A CN 103939875 B CN103939875 B CN 103939875B
Authority
CN
China
Prior art keywords
module
lifting
row
head base
lifting device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410220758.6A
Other languages
Chinese (zh)
Other versions
CN103939875A (en
Inventor
吴廷森
曲武
刘伟
李国栋
张晶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Power Construction Third Engineering Co Ltd
Original Assignee
Shangdong Electric Power Construction No3 Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shangdong Electric Power Construction No3 Engineering Co filed Critical Shangdong Electric Power Construction No3 Engineering Co
Priority to CN201410220758.6A priority Critical patent/CN103939875B/en
Publication of CN103939875A publication Critical patent/CN103939875A/en
Application granted granted Critical
Publication of CN103939875B publication Critical patent/CN103939875B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of vertical exhaust-heat boiler module hoisting construction method, the method is for completing more than two row, being often classified as the lifting construction of 1-4 waste heat boiler, and step is: preparation of construction; Lifting device is installed; The lifting of I-1 module; Remove I-1 module packing material; I-1 module is connected with lower anchor head base; The lifting of I-1 module; II-2 module and the docking of I-1 module, promote II-2 module; Repeat above-mentioned steps, complete the lifting of the 1st all the other modules of row; Lifting device changes row, repeats above-mentioned steps, completes the lifting of all the other row modules; Remove lifting device and clear up job site.Beneficial effect of the present invention is: 1) adopt and traditional hanging method difference apportion, block-by-block hanging method, save hanging device Meteorological; 2) Lao Xinge hydraulic lifting system is adopted to promote and in place, safe and reliable; 3) single-row hoisting module is adopted, easy to operate.

Description

A kind of vertical exhaust-heat boiler module hoisting construction method
Technical field
The present invention relates to Construction Technology field, especially relate to a kind of construction method of vertical exhaust-heat boiler module hoisting.
Background technology
As the waste heat boiler of vertical, three-pressure reheat, Natural Circulation, this boiler for generation of high, medium and low voltage steam and reheated steam, outdoor layout.The heating surface of waste heat boiler is adopted the modular design supply of material by supplier, the heating surface module of every platform boiler is divided into three row totally 12 modules, often row are 1-4 module vertical cartel and form, often row module gross weight is 563800kg, waste heat boiler physical dimension is 41.5m × 17m, and HP steam drum center line absolute altitude is about 39.2m.Chimney top absolute altitude is 65m, and diameter 5.91m, is arranged in furnace roof.Boiler steel frame is formed by H profile steel and Plate Welding, and both sides are totally 28 root posts (containing stair and elevator support).If hanging method conventionally completes the lifting construction of this module, long in time limit, cost is high.
Summary of the invention
The object of the invention is to change traditional hanging method, adopt single-row lifting, often arranged after change the hanging method that row mode instead of conventional multiple row Synchronous lifting, cost 70% is saved than traditional hanging method, the technical scheme adopted is: a kind of vertical exhaust-heat boiler module hoisting construction method, the method is for completing more than two row, being often classified as the lifting construction of 1-4 module, and step is:
I) preparation of construction;
II) lifting device is installed;
III) lifting of I-1 module:
III 1) I-1 module packing material is removed;
III 2) I-1 module is connected with lower anchor head base;
III 3) lifting of I-1 module;
IV) I-2 module and the docking of I-1 module, promote I-2 module;
V) step III is repeated) and IV), complete the lifting of the 1st all the other modules of row;
VI) lifting device changes row, repeats step III) and IV), complete the lifting of all the other row modules;
VII) remove lifting device and clear up job site.
Technical characteristic of the present invention also has: the step of described II) installing lifting device comprises:
II 1) line setting: the center line of releasing 8 suspension centres, surveys the sideline in place of marking bearing support according to the structural parameters of the bearing support of lifting device and the position of center line of suspension centre;
II 2) according to designing requirement, hydraulic lifting apparatus is in place, and ensures the suspension centre conllinear of lifting device, and the cable wire center of each suspension centre is by predetermined position, design centre; In advance by the leader height adjustment that casts anchor of lifting device to the height that can possess installation module suspension rod;
II 3) realize the connection of suspension rod and lower anchor head base by means of fork truck or lower anchor head base dropped to connection ground realizing suspension rod and lower anchor head base;
II 4) lifting device is used the least significant end of module suspension rod to be risen to 5m height.
Technical characteristic of the present invention also has: the step that described III 2) I-1 module is connected with lower anchor head base comprises:
I-1 module packing material is removed and cleaned out, and commander's transport vehicle enters Hoisting Position according to predetermined route, realizes docking of suspension rod and module boatswain chair by the lifting chassis and manipulation hydraulic lifting apparatus adjusting transport vehicle, and locking cable wire bus one by one;
Dismounting I-1 module is fixedly connected with part with bottom support frame;
I-1 module is connected with lower anchor head base.
Technical characteristic of the present invention also has: described III 3) step of the lifting of I-1 module comprises:
Node is all connected and rearward, one by one the cable wire of hydraulic jack can be tightened and reach synchronous condition;
The jack line of header before and after suspention permutation module and bottle gouard moved by hands are hung up properly;
One by one the dividing plate gap of module is tightened up with chain block, and spot welding is fixed;
Connection hanger between adjacent block is installed;
By module raises to about 5m.
Technical characteristic of the present invention also has: described IV) I-2 module and the docking of I-1 module, and the step promoting I-2 module comprises:
IV 1) transport vehicle is entered into Hoisting Position according to the route preset, realize I-2 module and the docking of I-1 module by the lifting chassis and manipulation hydraulic lifting apparatus adjusting transport vehicle;
IV 2) with the bottle gouard moved by hands stocked in advance and jack line, the front and back header bolt of I-2 module is tight and tighten up and mention;
IV 3) that removes I-2 module and bottom support frame is fixedly connected with part.
Technical characteristic of the present invention also has: the step that described VI) lifting device changes row comprises:
VI 1) elevator system translation gliding device is laid;
VI 2) adopt crawler crane and be in place according to the elevator system of designing requirement by a row module, ensure the suspension centre conllinear of all lifting devices, and S1 is departed from the cable wire center of each suspension centre and position, design centre, by the leader height adjustment that casts anchor to the height that can possess installation module suspension rod;
VI 3) realize the connection of suspension rod and lower anchor head base by means of fork truck, or lower anchor head base is dropped to connection ground realizing suspension rod and lower anchor head base;
VI 4) elevator system promotes, and makes the least significant end of module suspension rod reach about 5m.
Technical characteristic of the present invention also has: described columns is 3 row, often row 4 modules.
Technical characteristic of the present invention also has: the support of elevator system is four column truss structures.
Beneficial effect of the present invention is: 1) adopt and traditional hanging method difference apportion, block-by-block hanging method, save hanging device Meteorological; 2) Lao Xinge hydraulic lifting system is adopted to promote and in place, safe and reliable; 3) single-row hoisting module is adopted, easy to operate.
Accompanying drawing explanation
Accompanying drawing 1 is that the present invention lifts operational flowchart, and accompanying drawing 2 is that schematic diagram arranged by lifting device, and wherein 1 is hot beam, and 2 is pass crossbeam, and 3 is mast-ups, and 4 is modules, and 5 is hydraulic lifting apparatus.
Detailed description of the invention
Below in conjunction with accompanying drawing, the specific embodiment of the present invention is described.This construction method for hanging adopts apportion, block-by-block hanging method carries out, and is provided with the lifting work that two covers (eight groups 100 tons) hydraulic lifting apparatus implements often row module altogether.Often row module is taked from top to bottom, block-by-block docking, upside-down mounting adult, disposable mode in place come; Ith row lift by crane in situ, IIth row are after the heart is lifted to height in place to the position of a stove left side (the 3rd row) direction displacement s1 wherein, it is in place to implement translation again, time in place, the absolute altitude of base is improved compensation rate h1, the upper gap principles and requirements between the dividing plate of the Ith row module and the IIth row module controls to arrange the IIth to exceed a than the Ith row; IIIth row are after the heart is lifted to height in place to the position of stove left direction displacement s2 wherein, it is in place to implement translation again, time in place, the absolute altitude of base are improved compensation rate h2; Every four groups of hydraulic lifting apparatus are combined into a translation unit, adopt two respectively and are not less than the hydraulic jack of 25 tons and are moved by translational stiffness beam carrying out horizontal, require that four jack synchronously carry out during translation.Displacement s1, s2 are that the clear space amount must arranged according to modular structure calculates, and compensation rate h1, h2, a calculate according to the configuration state parameter of hot beam and module.
This lifting mode construction technology step comprises:
I) preparation of construction:
I 1) module is installed and should be carried out after boiler steel frame installs acceptance(check), and carries out the examination of the level Four before module hoisting visa.
I 2) according to erecting by overhang layout drawing, hot beam should be numbered, be rule before installing, and on the hot beam of furnace roof, mark the numbering of centre of location line and corresponding mounting rail, to ensure that the installation site of suspension rod conforms to drawing requirement.
I 3) approach axis (transport vehicle is poured into) of transport vehicle is determined according to the physical condition at scene, to ensure that module enters smoothly and docks; Before the entrucking of heating surface module, the position should installed according to the requirement of traffic program and module, determines direction before entrucking.
I 4) approach course of module transportation vehicle and the checking of handling capacity.Do to implement the eve slinger, the route that must be marched into the arena by transport vehicle in advance and handling capacity are investigated, repair, are verified.Road conditions need meet following requirement:
Can not have barrier, pipe trench, basis etc. around transport routes, road surface should be backfilling and compacted;
Whole piece transport routes straightway width of roadway is not less than 8m, and inside turnaround section, radius of turn is not less than 15m;
Transport routes and pedrail crane Active workings need smooth solid, and the average bearing capacity of transport routes is greater than 105N/m 2, the average bearing capacity of pedrail crane Active workings is greater than 105N/m 2;
Furnace bottom module hoisting transport channel is laid two row thickness 12mm steel plates;
IIth row fill with the stove left half of the hot joist support seat at the IIIth row module suspension centre place is slow, install after module translation puts in place again;
Before module hoisting, in advance the backplate of boiler both sides to be hung to precalculated position temporarily, and by locking device, backplate is tightly locked on grate steel column; Carry out the rainproof safeguard measure of backplate;
The horizontal absolute altitude of 24 sling points is found accurately, and by adjusting parallels leveling, carrying out mark, accomplishes a little and parallels one_to_one corresponding; On the horizontal plane of finding accurately in advance, unification improves the parallels height of 2mm again.
II) lifting device is installed;
II 1) line setting: the center line of releasing 8 suspension centres, surveys the sideline in place of marking bearing support according to the structural parameters of the bearing support of lifting device and the position of center line of suspension centre;
II 2) according to designing requirement, hydraulic lifting apparatus is in place, and ensures the suspension centre conllinear of lifting device, and the cable wire center of each suspension centre is by predetermined position, design centre; In advance by the leader height adjustment that casts anchor of lifting device to the height that can possess installation module suspension rod;
II 3) realize the connection of suspension rod and lower anchor head base by means of fork truck or lower anchor head base dropped to connection ground realizing suspension rod and lower anchor head base;
II 4) lifting device is used the least significant end of module suspension rod to be risen to 5m height.
III) lifting of I-1 module:
III 1) I-1 module packing material is removed;
III 2) I-1 module is connected with lower anchor head base;
I-1 module packing material is removed and is cleaned out rear (fixing with iron wire between the three-ply board at top and module), commander's transport vehicle enters Hoisting Position according to predetermined route, docking of suspension rod and module boatswain chair is realized by the lifting chassis and manipulation hydraulic lifting apparatus that adjust transport vehicle, and lock according to the bus correspondence position of the feature cable wire controlled in advance one by one, to ensure that every root cable wire is all common bus in whole process hoists process;
Dismounting I-1 module is fixedly connected with part with bottom support frame.
III 2) step that I-1 module is connected with lower anchor head base comprises:
I-1 module packing material is removed and cleaned out, and commander's transport vehicle enters Hoisting Position according to predetermined route, realizes docking of suspension rod and module boatswain chair by the lifting chassis and manipulation hydraulic lifting apparatus adjusting transport vehicle, and locking cable wire bus one by one;
Dismounting I-1 module is fixedly connected with part with bottom support frame;
I-1 module is connected with lower anchor head base.
III 3) lifting of I-1 module;
III 3) step of the lifting of I-1 module comprises:
Node is all connected and rearward, one by one the cable wire of hydraulic jack can be tightened and reach synchronous condition;
The jack line of header before and after suspention permutation module and bottle gouard moved by hands are hung up properly;
One by one the dividing plate gap of module is tightened up with chain block, and spot welding is fixed;
Connection hanger between adjacent block is installed;
By module raises to about 5m.
IV) II-2 module and the docking of I-1 module, promote II-2 module;
First packing material is removed before docking;
IV 1) transport vehicle is entered into Hoisting Position according to the route preset, realize II-2 module and the docking of I-1 module by the lifting chassis and manipulation hydraulic lifting apparatus adjusting transport vehicle;
IV 2) with the bottle gouard moved by hands stocked in advance and jack line, the front and back header bolt of II-2 module is tight and tighten up and mention;
IV 3) that removes II-2 module and bottom support frame is fixedly connected with part.
V) step III is repeated) and IV), complete the lifting of the 1st all the other modules of row;
VI) lifting device changes row, repeats step III) and IV), complete the lifting of all the other row modules;
VI) step that lifting device changes row comprises:
VI 1) elevator system translation gliding device is laid;
VI 2) adopt crawler crane and be in place according to the elevator system of designing requirement by a row module, ensure the suspension centre conllinear of all lifting devices, and S1 is departed from the cable wire center of each suspension centre and position, design centre, by the leader height adjustment that casts anchor to the height that can possess installation module suspension rod;
VI 3) realize the connection of suspension rod and lower anchor head base by means of fork truck, or lower anchor head base is dropped to connection ground realizing suspension rod and lower anchor head base;
VI 4) elevator system promotes, and makes the least significant end of module suspension rod reach about 5m.
VII) remove lifting device and clear up job site.
In the present invention, the columns of embodiment is 3 row, often row 4 modules.

Claims (7)

1. a vertical exhaust-heat boiler module hoisting construction method, the method is for completing more than two row, being often classified as the lifting construction of 1-4 module, and step is:
I) preparation of construction;
II) lifting device is installed;
III) lifting of I-1 module:
III 1) I-1 module packing material is removed;
III 2) I-1 module is connected with lower anchor head base;
III 3) lifting of I-1 module;
IV) I-2 module and the docking of I-1 module, promote I-2 module;
V) step III is repeated) and IV), complete the lifting of the 1st all the other modules of row;
VI) lifting device changes row, repeats step III) and IV), complete the lifting of all the other row modules;
VII) remove lifting device and clear up job site;
Described II) step of installing lifting device comprises:
II 1) line setting: the center line of releasing 8 suspension centres, surveys the sideline in place of marking bearing support according to the structural parameters of the bearing support of lifting device and the position of center line of suspension centre;
II 2) according to designing requirement, hydraulic lifting apparatus is in place, and ensures the suspension centre conllinear of lifting device, and the cable wire center of each suspension centre is by predetermined position, design centre; In advance by the leader height adjustment that casts anchor of lifting device to the height that can possess installation module suspension rod;
II 3) realize the connection of suspension rod and lower anchor head base by means of fork truck or lower anchor head base dropped to connection ground realizing suspension rod and lower anchor head base;
II 4) lifting device is used the least significant end of module suspension rod to be risen to 5m height.
2. according to vertical exhaust-heat boiler module hoisting construction method according to claim 1, it is characterized in that: the step that described III 2) I-1 module is connected with lower anchor head base comprises:
I-1 module packing material is removed and cleaned out, and commander's transport vehicle enters Hoisting Position according to predetermined route, realizes docking of suspension rod and module boatswain chair by the lifting chassis and manipulation hydraulic lifting apparatus adjusting transport vehicle, and locking cable wire bus one by one;
Dismounting I-1 module is fixedly connected with part with bottom support frame;
I-1 module is connected with lower anchor head base.
3. according to vertical exhaust-heat boiler module hoisting construction method according to claim 1, it is characterized in that: described III 3) step of the lifting of I-1 module comprises:
Node is all connected and rearward, one by one the cable wire of hydraulic jack can be tightened and reach synchronous condition;
The jack line of header before and after suspention permutation module and bottle gouard moved by hands are hung up properly;
One by one the dividing plate gap of module is tightened up with chain block, and spot welding is fixed;
Connection hanger between adjacent block is installed;
By module raises to about 5m.
4. according to vertical exhaust-heat boiler module hoisting construction method according to claim 1, it is characterized in that: described IV) I-2 module and the docking of I-1 module, the step promoting I-2 module comprises:
IV 1) transport vehicle is entered into Hoisting Position according to the route preset, realize I-2 module and the docking of I-1 module by the lifting chassis and manipulation hydraulic lifting apparatus adjusting transport vehicle;
IV 2) with the bottle gouard moved by hands stocked in advance and jack line, the front and back header bolt of I-2 module is tight and tighten up and mention;
IV 3) that removes I-2 module and bottom support frame is fixedly connected with part.
5. according to vertical exhaust-heat boiler module hoisting construction method according to claim 1, it is characterized in that: the step that described VI) lifting device changes row comprises:
VI 1) elevator system translation gliding device is laid;
VI 2) adopt crawler crane and be in place according to the elevator system of designing requirement by a row module, ensure the suspension centre conllinear of all lifting devices, and S1 is departed from the cable wire center of each suspension centre and position, design centre, by the leader height adjustment that casts anchor to the height that can possess installation module suspension rod;
VI 3) realize the connection of suspension rod and lower anchor head base by means of fork truck, or lower anchor head base is dropped to connection ground realizing suspension rod and lower anchor head base;
VI 4) elevator system promotes, and makes the least significant end of module suspension rod reach about 5m.
6. according to vertical exhaust-heat boiler module hoisting construction method according to claim 1, it is characterized in that: described columns is 3 row, often row 4 modules.
7. according to vertical exhaust-heat boiler module hoisting construction method according to claim 1, it is characterized in that: the support of elevator system is four column truss structures.
CN201410220758.6A 2014-05-23 2014-05-23 A kind of vertical exhaust-heat boiler module hoisting construction method Active CN103939875B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410220758.6A CN103939875B (en) 2014-05-23 2014-05-23 A kind of vertical exhaust-heat boiler module hoisting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410220758.6A CN103939875B (en) 2014-05-23 2014-05-23 A kind of vertical exhaust-heat boiler module hoisting construction method

Publications (2)

Publication Number Publication Date
CN103939875A CN103939875A (en) 2014-07-23
CN103939875B true CN103939875B (en) 2016-02-24

Family

ID=51187656

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410220758.6A Active CN103939875B (en) 2014-05-23 2014-05-23 A kind of vertical exhaust-heat boiler module hoisting construction method

Country Status (1)

Country Link
CN (1) CN103939875B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105314537B (en) * 2015-08-19 2017-01-25 中国能源建设集团天津电力建设有限公司 Lifting alignment in-place method for boiler water storing tank
CN106322345A (en) * 2016-08-17 2017-01-11 中国能源建设集团天津电力建设有限公司 Installation technology of Pi-type boiler economizer pipe panels
CN109237457A (en) * 2018-08-17 2019-01-18 上海二十冶建设有限公司 A kind of segmentation installation method of waste heat boiler pure water tank
CN110817723A (en) * 2019-11-15 2020-02-21 上海东鼎钢结构有限公司 Method and device for installing heat exchanger of automobile test wind tunnel
CN111853736B (en) * 2020-07-18 2021-06-04 四川华川基业建设集团有限公司 Construction process for alkali furnace installation project

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10253001A (en) * 1997-03-14 1998-09-25 Babcock Hitachi Kk Waste heat recovery boiler
CN201842567U (en) * 2010-04-22 2011-05-25 东方日立锅炉有限公司 Lifting frame for modular tube panel of waste heat boiler
CN103253591A (en) * 2013-05-31 2013-08-21 无锡海源重工股份有限公司 Hoisting tool for heating surface module tube panel components of combined cycle waste heat boiler

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10253001A (en) * 1997-03-14 1998-09-25 Babcock Hitachi Kk Waste heat recovery boiler
CN201842567U (en) * 2010-04-22 2011-05-25 东方日立锅炉有限公司 Lifting frame for modular tube panel of waste heat boiler
CN103253591A (en) * 2013-05-31 2013-08-21 无锡海源重工股份有限公司 Hoisting tool for heating surface module tube panel components of combined cycle waste heat boiler

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
北京天然气热电联产工程大件吊装;程建棠等;《工程机械与维修》;20140131(第1期);105-109 *
半山燃机机组余热锅炉受热面吊装工艺;金欣;《电力建设》;20090430;第30卷(第04期);104-105 *

Also Published As

Publication number Publication date
CN103939875A (en) 2014-07-23

Similar Documents

Publication Publication Date Title
CN103939875B (en) A kind of vertical exhaust-heat boiler module hoisting construction method
CN101435276B (en) Cabin top steel beam hydraulic hoisting and positioning apparatus of cylinder cabin structure building and construction method thereof
CN204940312U (en) A kind of integral lifting lowering system of steel cofferdam
CN102094106A (en) Quick installation method for large four-point suspended type converter
CN103882813B (en) For calf support platform and the building method thereof of bridge pier and straining beam synchronous construction
CN202810173U (en) Mounting and construction platform for steel lining bracket and circular crane track girder of nuclear power plant
CN103541744A (en) Tire walking full-hydraulic lining trolley
CN203007849U (en) Movable construction device for cast-in-place concrete crash barriers with hanging eaves
CN107013038A (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN206616184U (en) Coke oven loss flue dust dust gathering arrester supporting construction
CN204626411U (en) A kind of pile foundation steel bar cage erecting device
CN205662832U (en) Under hold formula beiLei beam steel suspension bridge
CN111675111A (en) Boiler hoisting sling in closed plant area and construction method
CN203878979U (en) Bolt opposite-pulling type track sliding formwork
JP3110985B2 (en) Construction method of column capital of overhang girder bridge
CN211472207U (en) Suspension beam system for hoisting prefabricated section box girder
CN205369229U (en) But walking hoisting frame suitable for manual hole digging pile steel reinforcement cage is laid
CN107587885A (en) Two lining trolley structures and assembling method in a kind of standard cross-section of tunnel
CN104234447A (en) Tool-type suspension staircase for deep foundation pit
CN109368519B (en) Lifting method for emergency diesel generator of nuclear power station
CN202099311U (en) Backing ring assembling platform for four-point suspension type mammoth converter
CN203129581U (en) Slip form system
CN108951430A (en) A kind of road and bridge in-site installation structure, method and loop wheel machine
CN215107098U (en) Theatre main stage truck crane hoisting platform
CN103754791A (en) Method for lifting water-tower 1000m<3> water tank by utilizing prestressed strands

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 266100 No. 882-1 Tong'an Road, Laoshan District, Qingdao City, Shandong Province

Patentee after: Shandong Power Construction Third Engineering Co., Ltd.

Address before: 266100 No. 882-1 Tong'an Road, Laoshan District, Qingdao City, Shandong Province

Patentee before: Shangdong Electric Power Construction No.3 Engineering Co.

CP01 Change in the name or title of a patent holder