CN204940312U - A kind of integral lifting lowering system of steel cofferdam - Google Patents
A kind of integral lifting lowering system of steel cofferdam Download PDFInfo
- Publication number
- CN204940312U CN204940312U CN201520693849.1U CN201520693849U CN204940312U CN 204940312 U CN204940312 U CN 204940312U CN 201520693849 U CN201520693849 U CN 201520693849U CN 204940312 U CN204940312 U CN 204940312U
- Authority
- CN
- China
- Prior art keywords
- steel
- lowering system
- steel cofferdam
- lifting
- cofferdam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
本实用新型公开了一种钢围堰的整体起吊下放系统,其特征在于所述整体起吊下放系统包括至少两道支撑架以及安装于所述支撑架顶部两端的起吊机构,每道所述支撑架包括两根桩基钢护筒、位于所述桩基钢护筒上的接高立柱以及水平架设于两根所述接高立柱顶部的贝雷梁。本实用新型的优点是,整体起吊下放系统组成简单,通过接长桩基钢护筒并架设贝雷梁以构成用于起吊的支撑架,实现就地对钢围堰的起吊下放就位,克服了常规采用岸上整体拼装、下水、整体浮运就位的缺点,可降低工程造价。
The utility model discloses an integral hoisting and lowering system for a steel cofferdam, which is characterized in that the overall hoisting and lowering system includes at least two support frames and lifting mechanisms installed at both ends of the top of the support frame, each of the support frames It includes two pile foundation steel casings, a high-connection column located on the pile foundation steel casing, and a Bailey beam horizontally erected on the top of the two high-connection columns. The utility model has the advantage that the overall lifting and lowering system is simple in composition, and the supporting frame for lifting is formed by connecting the steel casing of the pile foundation and erecting the Bailey beam to realize the lifting and lowering of the steel cofferdam on the spot. It eliminates the disadvantages of conventional shore-based overall assembly, launching, and overall floating in place, and can reduce project costs.
Description
技术领域 technical field
本实用新型涉及桥梁工程技术领域,具体涉及一种钢围堰的整体起吊下放系统。 The utility model relates to the technical field of bridge engineering, in particular to an integral hoisting and lowering system of a steel cofferdam.
背景技术 Background technique
随着跨江大跨度桥梁的飞速发展,大体量深水基础工程越来越多。如南昌朝阳大桥基础的施工,采用了桥梁深水浅覆盖层基础(覆盖层最浅处仅有1m左右)施工专用新设备:大吨位(400t)单-双壁结合钢围堰。该钢围堰采用两端圆弧+中间矩形结构,主要由围堰拼装胎架系统、围堰下放导向系统、围堰底节(带刃脚)、围堰顶节、加固围檩等组成,一套钢围堰分为2节,1个双壁钢围堰底节和1个单壁钢围堰顶节,底节钢围堰共分为22个单元块,其中圆弧部分分成12块,直线部分分成10块(直线部分侧板和竖向主梁均单独作为一个分块),顶节分为6个单元块。 With the rapid development of long-span bridges across the river, there are more and more large-scale deep-water foundation projects. For example, in the foundation construction of Chaoyang Bridge in Nanchang, new special equipment for the construction of the deep-water and shallow overburden foundation of the bridge (the shallowest part of the overburden is only about 1m) was adopted: large-tonnage (400t) single-double-wall combined steel cofferdam. The steel cofferdam adopts a circular arc at both ends + a rectangular structure in the middle, and is mainly composed of a cofferdam assembly frame system, a cofferdam lowering guide system, a cofferdam bottom section (with edge feet), a cofferdam top section, and a reinforced cofferdam purlin. A set of steel cofferdam is divided into 2 sections, 1 double-wall steel cofferdam bottom section and 1 single-wall steel cofferdam top section, the bottom section steel cofferdam is divided into 22 unit blocks, of which the arc part is divided into 12 blocks , the straight line part is divided into 10 pieces (the side plate and the vertical main beam of the straight line part are separately regarded as a block), and the top section is divided into 6 unit blocks.
针对钢围堰的吊装,传统方法是将钢围堰在工厂制作成整体,现场借助大型浮吊就位后整体下沉,需要大型浮云吊装设备,对施工空间和水深有要求,且不能拆除重复利用。 For the hoisting of steel cofferdams, the traditional method is to manufacture the steel cofferdams as a whole in the factory, and then use large-scale floating cranes to place them in place and then sink as a whole. Large-scale floating cloud hoisting equipment is required, which requires construction space and water depth, and cannot be dismantled and repeated. use.
发明内容 Contents of the invention
本实用新型的目的是根据上述现有技术的不足之处,提供一种钢围堰的整体起吊下放系统,该整体起吊下放系统通过接长桩基钢护筒并架设贝雷梁以构成用于起吊的支撑架,实现对钢围堰的起吊下放就位。 The purpose of this utility model is to provide an integral hoisting and lowering system for steel cofferdams according to the deficiencies of the above-mentioned prior art. The hoisting support frame realizes the hoisting and lowering of the steel cofferdam.
本实用新型目的实现由以下技术方案完成: The utility model goal is realized by the following technical solutions:
一种钢围堰的整体起吊下放系统,其特征在于所述整体起吊下放系统包括至少两道支撑架以及安装于所述支撑架顶部两端的起吊机构,每道所述支撑架包括两根桩基钢护筒、位于所述桩基钢护筒上的接高立柱以及水平架设于两根所述接高立柱顶部的贝雷梁。 An integral hoisting and lowering system for a steel cofferdam, characterized in that the overall hoisting and lowering system includes at least two supporting frames and lifting mechanisms installed at both ends of the top of the supporting frames, and each of the supporting frames includes two pile foundations The steel casing, the high-connecting columns on the steel casing of the pile foundation, and the Bailey beams horizontally erected on the top of the two high-connecting columns.
所述接高立柱顶部与所述贝雷梁之间布置有垫梁,所述垫梁为横桥向布置的双拼H型钢。 A pad beam is arranged between the top of the high-connecting column and the Bailey beam, and the pad beam is a double-assembled H-shaped steel arranged in the direction of the bridge.
所述起吊机构包括下放分配梁、穿心千斤顶以及吊杆,所述下放分配梁和所述穿心千斤顶布置于所述贝雷梁两端,所述吊杆竖向连接于所述穿心千斤顶下端。 The lifting mechanism includes a lowered distribution beam, a through-hole jack and a boom, the lowered distribution beam and the through-hole jack are arranged at both ends of the Bailey beam, and the boom is vertically connected to the through-hole jack lower end.
本实用新型的优点是,整体起吊下放系统组成简单,通过接长桩基钢护筒并架设贝雷梁以构成用于起吊的支撑架,实现就地对钢围堰的起吊下放就位,克服了常规采用岸上整体拼装、下水、整体浮运就位的缺点,可降低工程造价。 The utility model has the advantage that the overall lifting and lowering system is simple in composition, and the supporting frame for lifting is formed by connecting the steel casing of the pile foundation and erecting the Bailey beam to realize the lifting and lowering of the steel cofferdam on the spot. It eliminates the disadvantages of conventional shore-based overall assembly, launching, and overall floating in place, and can reduce the project cost.
附图说明 Description of drawings
图1为本实用新型中钢围堰的整体起吊下放系统平面布置示意图; Fig. 1 is a schematic plan layout diagram of the overall hoisting and lowering system of the steel cofferdam of the utility model;
图2为本实用新型中钢围堰的整体起吊下放系统立面示意图。 Fig. 2 is a schematic diagram of the elevation of the overall hoisting and lowering system of the steel cofferdam of the utility model.
具体实施方式 detailed description
以下结合附图通过实施例对本实用新型的特征及其它相关特征作进一步详细说明,以便于同行业技术人员的理解: The features of the present utility model and other relevant features are further described in detail below in conjunction with the accompanying drawings through the embodiments, so as to facilitate the understanding of those skilled in the art:
如图1-2,图中标记1-11分别为:钢围堰1、起吊机构2、垫梁3、桩基钢护筒4、贝雷梁5、导向架6、垫梁7、接高立柱8、穿心千斤顶9、下放分配梁10、吊杆11。 As shown in Figure 1-2, the marks 1-11 in the figure are: steel cofferdam 1, lifting mechanism 2, pad beam 3, pile foundation steel casing 4, Bailey beam 5, guide frame 6, pad beam 7, height connection Upright column 8, through jack 9, drop distribution beam 10, boom 11.
实施例:如图1、2所示,本实施例具体涉及一种钢围堰的整体起吊下放系统,用于起吊下放两端呈圆弧、中间呈矩形的钢围堰,且该钢围堰是在现场桩基施工平台上拼装成整体的。 Embodiment: As shown in Figures 1 and 2, this embodiment specifically relates to an overall lifting and lowering system for a steel cofferdam, which is used for lifting and lowering a steel cofferdam with circular arcs at both ends and a rectangular center in the middle, and the steel cofferdam It is assembled into a whole on the site pile foundation construction platform.
如图1、2所示,本实施例中的整体起吊下放系统由两道支撑架以及设置于支撑架顶部的起吊机构所组成。 As shown in Figures 1 and 2, the overall lifting and lowering system in this embodiment consists of two support frames and a lifting mechanism arranged on the top of the support frames.
支撑架呈“∏”型,包括桩基钢护筒4、接高立柱8以及贝雷梁5,每道支撑架选定两根桩基钢护筒4,并通过接高立柱8将各桩基钢护筒4接长至超出施工平台面以上14m,在接高立柱8的顶部设置有一小段横向的垫梁3,垫梁3具体为双拼H型钢;每两个接高立柱8顶部的垫梁3上纵向放置有贝雷梁5以将两个接高立柱8连接为一整体,需要说明的是,贝雷梁5与钢围堰上的吊点按相对应的位置进行设置。 The support frame is "∏" type, including pile foundation steel casing 4, high-connected column 8 and Bailey beam 5, two pile-foundation steel casings 4 are selected for each support frame, and each pile is connected by high-connection column 8 The base steel casing 4 is extended to exceed 14m above the construction platform surface, and a small section of horizontal pad beam 3 is arranged on the top of the high column 8, and the pad beam 3 is specifically a pair of H-shaped steel; every two high column 8 tops A Bailey beam 5 is vertically placed on the pad beam 3 to connect the two high-connecting columns 8 into a whole. It should be noted that the Bailey beam 5 and the lifting points on the steel cofferdam are set at corresponding positions.
起吊机构包括下放分配梁10、穿心千斤顶9以及吊杆11,其中下放分配梁10以及穿心千斤顶对称设置于贝雷梁5的两端部,吊杆11竖向设置,其上端连接穿心千斤顶9,下端用于同待起吊下放的钢围堰1连接。 The lifting mechanism includes a lowering distribution beam 10, a through-hole jack 9 and a boom 11, wherein the lowering distribution beam 10 and the through-hole jack are symmetrically arranged at both ends of the Bailey beam 5, and the boom 11 is vertically arranged, and its upper end is connected to the through-hole Jack 9, the lower end is used to be connected with the steel cofferdam 1 that is to be hoisted and lowered.
此外,本实施例中的整体起吊下放系统还包括设置于各桩基钢护筒4外围的导向架6用于对在下放过程中的钢围堰1起到导向定位作用,导向架6的尺寸略小于钢围堰1的尺寸,但两者的形状相对应,导向架6与钢围堰1之间的空隙为5cm。 In addition, the overall lifting and lowering system in this embodiment also includes a guide frame 6 arranged on the periphery of each pile foundation steel casing 4 for guiding and positioning the steel cofferdam 1 during the lowering process. The size of the guide frame 6 Slightly smaller than the size of the steel cofferdam 1, but the shapes of the two are corresponding, and the gap between the guide frame 6 and the steel cofferdam 1 is 5cm.
如图1、2所示,本实施例中的钢围堰整体起吊下放系统的安装方法及其工作原理如下: As shown in Figures 1 and 2, the installation method and working principle of the steel cofferdam integral hoisting and lowering system in this embodiment are as follows:
(1)利用钢管桩施作桩基施工平台,在该施工平台上完成钢围堰1的整体拼装,其中,钢围堰1为双壁钢套箱围堰,长、宽、高分别为34m、21.4m、13m,采用两端圆弧中间矩形的构造,重400吨,双壁围堰壁之间的间距为1.6m,底部刃脚高3m; (1) Steel pipe piles are used as the pile foundation construction platform, and the overall assembly of the steel cofferdam 1 is completed on the construction platform. Among them, the steel cofferdam 1 is a double-wall steel casing cofferdam, and the length, width and height are respectively 34m, 21.4m, 13m, using a rectangular structure with circular arcs at both ends, weighing 400 tons, the distance between the double-walled cofferdam walls is 1.6m, and the height of the bottom edge is 3m;
(2)利用钢围堰1四个角点处的桩基钢护筒4做反力架支撑,待该四根桩基钢护筒4施工结束后,在桩基钢护筒4外围设置导向架6;将四根桩基钢护筒4通过接高立柱8接长至超出施工平台面以上14m,之后在接高立柱上设置一段长4m的横向双拼H型钢作为垫梁3;垫梁3上纵向布置21m长的贝雷梁5以将两根桩基钢护筒4连成整体;将贝雷梁5在垫梁3上进行横向微调以使贝雷梁5与钢围堰1上的吊点位置构成对应; (2) Utilize the pile foundation steel casing 4 at the four corners of the steel cofferdam 1 as the support of the reaction force frame, and after the construction of the four pile foundation steel casing 4 is completed, set guides around the pile foundation steel casing 4 frame 6; the four pile foundation steel casings 4 are extended to 14m above the construction platform surface through the high-connecting column 8, and then a section of 4m-long horizontal double-jointed H-shaped steel is set on the high-connecting column as the pad beam 3; the pad beam 3, a 21m long Bailey beam 5 is longitudinally arranged to connect the two pile foundation steel casings 4 into a whole; The position of the lifting point constitutes a correspondence;
在各道贝雷梁5的两端设置起吊机构,即,在贝雷梁5的两端部安装下放分配梁10,然后安装精轧螺纹钢吊杆11并同钢围堰1连接,再安装穿心千斤顶9;需要说明的是,四个起吊下放点,每一个吊点部位配备两根φ50精轧螺纹钢吊杆11和两个250t穿心千斤顶9,通过精轧螺纹钢吊杆11与下放分配梁10,贝雷梁5与穿心千斤顶9相连; Set hoisting mechanisms at the two ends of each Bailey beam 5, that is, install and lower the distribution beam 10 at the two ends of the Bailey beam 5, then install the finish-rolled rebar suspender rod 11 and connect it with the steel cofferdam 1, and then install Through-hole jack 9; it should be noted that, for the four lifting and lowering points, each lifting point is equipped with two φ50 fine-rolled rebar suspenders 11 and two 250t through-the-heart jacks 9, through the finish-rolled rebar suspender 11 and The distribution beam 10 is lowered, and the Bailey beam 5 is connected with the through jack 9;
(3)待整体起吊下放系统安装完成后,进行试吊,启动穿心千斤顶9,将钢围堰1整体起吊约10cm,消除各点连接间隙和塑性变形,同时检查系统的工作稳定性及结构安全性; (3) After the installation of the overall lifting and lowering system is completed, carry out trial lifting, start the through-hole jack 9, lift the steel cofferdam 1 as a whole by about 10cm, eliminate the connection gap and plastic deformation of each point, and check the working stability and structure of the system at the same time safety;
(4)试吊完成后,将下放分配梁10上吊杆11螺帽松开至一定高度,穿心千斤顶9收回油缸,钢围堰1下放,最后钢围堰1的重量通过螺帽转换至下放分配梁10上。 (4) After the test hoisting is completed, loosen the nuts on the upper boom 11 of the lowering distribution beam 10 to a certain height, retract the oil cylinder through the core jack 9, lower the steel cofferdam 1, and finally transfer the weight of the steel cofferdam 1 to the lowering through the nuts. distribution beam 10.
本实施例中的整体起吊下放系统组成简单,受力支撑结构稳定,通过接长桩基钢护筒并架设贝雷梁以构成用于起吊的支撑架,实现就地对钢围堰的起吊下放就位,克服了常规采用岸上整体拼装、下水、整体浮运就位的缺点,可降低工程造价。 The overall hoisting and lowering system in this embodiment has a simple composition and a stable supporting structure. The supporting frame for hoisting is formed by connecting the steel casing of the pile foundation and erecting the Bailey beam to realize the hoisting and lowering of the steel cofferdam on the spot. In place, it overcomes the shortcomings of conventional shore-based overall assembly, launching, and overall floating in place, and can reduce project costs.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520693849.1U CN204940312U (en) | 2015-09-09 | 2015-09-09 | A kind of integral lifting lowering system of steel cofferdam |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520693849.1U CN204940312U (en) | 2015-09-09 | 2015-09-09 | A kind of integral lifting lowering system of steel cofferdam |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204940312U true CN204940312U (en) | 2016-01-06 |
Family
ID=55007754
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520693849.1U Expired - Lifetime CN204940312U (en) | 2015-09-09 | 2015-09-09 | A kind of integral lifting lowering system of steel cofferdam |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204940312U (en) |
Cited By (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107869144A (en) * | 2017-11-17 | 2018-04-03 | 中铁二十二局集团第四工程有限公司 | A kind of pre- slotting ring seal Double-Wall Steel Boxed Cofferdam deep water foundation comprehensive construction method |
| CN106284081B (en) * | 2016-08-12 | 2018-07-13 | 中建三局基础设施建设投资有限公司 | A kind of blast cofferdam is as cast-in-place box beam bracket foundation construction method |
| CN109374193A (en) * | 2018-11-21 | 2019-02-22 | 中铁大桥科学研究院有限公司 | A device and method for measuring wave buoyancy force of steel hanging box cofferdam of cross-sea bridge |
| CN109972846A (en) * | 2018-08-19 | 2019-07-05 | 中建六局安装工程有限公司 | A kind of moulding bed and its construction method for steel cylinder upside-down mounting jack-up construction |
| CN110606430A (en) * | 2019-08-28 | 2019-12-24 | 中铁大桥局集团有限公司 | A cofferdam hanging system and method |
| CN110644363A (en) * | 2019-06-24 | 2020-01-03 | 高军 | Construction method of underwater main tower of cross-river cable-stayed bridge of high-speed railway |
| CN110777826A (en) * | 2019-11-07 | 2020-02-11 | 孟北方 | Cofferdam hoisting and lowering construction device and cofferdam hoisting and lowering construction method |
| CN112267481A (en) * | 2020-10-22 | 2021-01-26 | 郑州大学 | Steel Cofferdam Lowering Construction Method |
| CN113982005A (en) * | 2021-11-12 | 2022-01-28 | 中铁大桥局集团有限公司 | A kind of cofferdam guide structure and its construction method |
| CN114319400A (en) * | 2022-02-17 | 2022-04-12 | 中交第三航务工程局有限公司 | Assembling and lowering technology of steel cofferdam for underwater bearing platform construction |
-
2015
- 2015-09-09 CN CN201520693849.1U patent/CN204940312U/en not_active Expired - Lifetime
Cited By (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106284081B (en) * | 2016-08-12 | 2018-07-13 | 中建三局基础设施建设投资有限公司 | A kind of blast cofferdam is as cast-in-place box beam bracket foundation construction method |
| CN107869144A (en) * | 2017-11-17 | 2018-04-03 | 中铁二十二局集团第四工程有限公司 | A kind of pre- slotting ring seal Double-Wall Steel Boxed Cofferdam deep water foundation comprehensive construction method |
| CN109972846A (en) * | 2018-08-19 | 2019-07-05 | 中建六局安装工程有限公司 | A kind of moulding bed and its construction method for steel cylinder upside-down mounting jack-up construction |
| CN109374193A (en) * | 2018-11-21 | 2019-02-22 | 中铁大桥科学研究院有限公司 | A device and method for measuring wave buoyancy force of steel hanging box cofferdam of cross-sea bridge |
| CN110644363A (en) * | 2019-06-24 | 2020-01-03 | 高军 | Construction method of underwater main tower of cross-river cable-stayed bridge of high-speed railway |
| CN110606430B (en) * | 2019-08-28 | 2020-12-01 | 中铁大桥局集团有限公司 | A cofferdam hanging system and method |
| CN110606430A (en) * | 2019-08-28 | 2019-12-24 | 中铁大桥局集团有限公司 | A cofferdam hanging system and method |
| CN110777826A (en) * | 2019-11-07 | 2020-02-11 | 孟北方 | Cofferdam hoisting and lowering construction device and cofferdam hoisting and lowering construction method |
| CN110777826B (en) * | 2019-11-07 | 2021-06-18 | 孟北方 | Cofferdam hoisting and lowering construction device and cofferdam hoisting and lowering construction method |
| CN112267481A (en) * | 2020-10-22 | 2021-01-26 | 郑州大学 | Steel Cofferdam Lowering Construction Method |
| CN112267481B (en) * | 2020-10-22 | 2022-02-18 | 郑州大学 | Steel cofferdam lowering construction method |
| CN113982005A (en) * | 2021-11-12 | 2022-01-28 | 中铁大桥局集团有限公司 | A kind of cofferdam guide structure and its construction method |
| CN114319400A (en) * | 2022-02-17 | 2022-04-12 | 中交第三航务工程局有限公司 | Assembling and lowering technology of steel cofferdam for underwater bearing platform construction |
| CN114319400B (en) * | 2022-02-17 | 2023-12-29 | 中交第三航务工程局有限公司 | Assembling and lowering process of steel cofferdam for underwater bearing platform construction |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN204940312U (en) | A kind of integral lifting lowering system of steel cofferdam | |
| CN104727236B (en) | A kind of whole bridge beam based on ground supports transfers the construction method of dismounting system | |
| CN101289862B (en) | Construction method of purlin support in foundation pit above water | |
| CN114606870A (en) | Integral dismantling method for hoop-method bent cap supporting system | |
| CN106088120B (en) | A kind of cofferdam decentralization construction method | |
| CN206986743U (en) | A kind of fixed trestle navigable vertical lift device | |
| CN204455856U (en) | A kind of pressure mechanism in place of prefabricated pier | |
| CN208009277U (en) | A kind of short sliding installation system of land-based area large-tonnage steel box beam | |
| CN203613467U (en) | Steel pipe bracket for construction of arch tower in oblique arch tower double-cable plane pre-stressed concrete cable-stayed bridge | |
| CN207812523U (en) | Anchor jacked pile constructing device | |
| CN216304646U (en) | Double-wall steel suspension box cofferdam positioning device | |
| CN113802478B (en) | An arch bridge deck structure dismantling device based on arch rib support | |
| CN115961549A (en) | Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge | |
| CN214939311U (en) | Integrated bridge erection machine for prefabricated bridge piers and beams | |
| CN110172922A (en) | A kind of environmentally friendly downlink Self-propelled steel trestle work structure construction method | |
| CN207392053U (en) | A kind of alignment control device suitable for steel construction abnormity tower | |
| CN106149732B (en) | A kind of deep basal pit faces side large scale hoisting machinery construction method for hanging | |
| CN108625292A (en) | A kind of template assembly platform of prefabricated stand column | |
| CN112610754A (en) | Bailey frame supporting and protecting structure for shallow underground pipeline | |
| CN209323381U (en) | A kind of high-speed railway assembled segment pier shaft hoisting bracket | |
| CN207862964U (en) | A kind of land bearing platform construction system | |
| CN214994007U (en) | Bridge steel protects a section of thick bamboo and steel reinforcement cage and is connected locating rack | |
| CN116043893A (en) | Anti-burst sinking device for open caisson | |
| CN212000656U (en) | Construction device for river-crossing special-shaped steel bridge | |
| CN216074755U (en) | Pin-connected panel supports frock suitable for bridge construction usefulness |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CX01 | Expiry of patent term | ||
| CX01 | Expiry of patent term |
Granted publication date: 20160106 |