CN202542732U - Mechanism for replacing auxiliary hoisting wire rope of four-beam four-rail dual-trolley bridge crane - Google Patents

Mechanism for replacing auxiliary hoisting wire rope of four-beam four-rail dual-trolley bridge crane Download PDF

Info

Publication number
CN202542732U
CN202542732U CN2012200424467U CN201220042446U CN202542732U CN 202542732 U CN202542732 U CN 202542732U CN 2012200424467 U CN2012200424467 U CN 2012200424467U CN 201220042446 U CN201220042446 U CN 201220042446U CN 202542732 U CN202542732 U CN 202542732U
Authority
CN
China
Prior art keywords
wire rope
trolley
section steel
hoisting wire
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012200424467U
Other languages
Chinese (zh)
Inventor
陈刚
王振江
顾建文
王亚军
秦强
滕永杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd
Original Assignee
Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd filed Critical Baosteel Group Xinjiang Bayi Iron and Steel Co Ltd
Priority to CN2012200424467U priority Critical patent/CN202542732U/en
Application granted granted Critical
Publication of CN202542732U publication Critical patent/CN202542732U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)

Abstract

The utility model discloses a mechanism for replacing an auxiliary hoisting wire rope of a four-beam four-rail dual-trolley bridge crane. The mechanism comprises a primary trolley mechanism and an auxiliary trolley mechanism which are mounted above and below a horizontal frame; two I-section steel bases are respectively placed on bent inner walls at the two sides of the horizontal frame; a horizontally-arranged I-section steel rail is connected to the top faces of the middle parts of the two I-section steel bases through welding; a winch with travelling wheels is mounted on the I-section steel rail in a hanging manner; and the travelling wheels horizontally run along the I-section steel rail. The mechanism has the advantages that the structure is simple, the auxiliary hoisting wire rope of the crane can be conveniently replaced through the winch, and the use is timesaving and laborsaving.

Description

The secondary hoist rope of four beams, four rail double trolley crane in bridge type is converting mechanism more
Technical field
The utility model relates to more converting mechanism of the secondary hoist rope of a kind of four beams, four rail double trolley crane in bridge type.
Background technology
Metallurgy industry is for the continuous lifting of productive capacity at present, and the ability of plant maintenance is also being continued to optimize.When changing the secondary hoist rope of four beams, four rail double trolley, consider that span is high 30 meters in the past, just must use one of 50t tire wheel crane, and when change steel rope more, need 16m * 9m=144m 2The occupation of land scope of work; Perhaps use hoisting crane maintenance electric winch, it is out of service with adjacent hoisting crane to coordinate production when using electronic elevator.These two kinds of methods are restricted by expense, time, place and manpower all can.It is existing because the metallurgical system rhythm of production is tight; Use the purpose of 50t tire cranemobile and maintenance electric winch just two chicken core riggings of steel wire end to be hung crane in bridge type; The weight altogether of two chicken core riggings also just has only about one ton, so these two kinds of methods are not actv. ways.
Summary of the invention
The purpose of the utility model is to provide more converting mechanism of the secondary hoist rope of a kind of four beams, four rail double trolley crane in bridge type, and it is simple in structure, can change the secondary hoist rope of hoisting crane easily, uses the save trouble and labor.
The purpose of the utility model is to realize like this; The secondary hoist rope of a kind of four beams, four rail double trolley crane in bridge type is converting mechanism more; Comprise the main carriage mechanism and the secondary trolley body that are installed in the horizontal frame upper and lower; On the both sides of horizontal frame bending inwall, placing an I-beam section base respectively; Be welded to connect the i-beam track of a horizontal arrangement on the two I-beam section base middle top surface, hanging on this i-beam track the winch with road wheel is installed, road wheel is along said i-beam track level run.
The utility model is simple in structure, and job procedure is simplified in (1), and the once mounting one would be set for life does not need repeated disassembled and assembled, and is simple to operate, need not employ crane and electric block.(2) save replacing auxiliary hook steel rope replacing time 20%-50%, improved maintenance of equipment work efficient.(3) practice thrift the manpower 50% of changing secondary hoist rope, and reduced labour intensity.(4) reduced the direct influence of plant maintenance to producing.(5) directly reduce each crane usage charges 10,000-1.5 ten thousand.Agency cost is 2000 yuan.Can change the secondary hoist rope of hoisting crane easily through winch, use the save trouble and labor.
Description of drawings
To combine accompanying drawing that the utility model is done further detailed explanation below.
Fig. 1 is the main TV structure scheme drawing of the utility model.
The specific embodiment
The secondary hoist rope of a kind of four beams, four rail double trolley crane in bridge type is converting mechanism more; As shown in Figure 1; Comprise the main carriage mechanism 1 and the secondary trolley body 5 that are installed in horizontal frame 3 upper and lowers; On the both sides of horizontal frame bending inwall, place an I-beam section base 4 respectively, do not having fixed connection structure between I-beam section base 4 and the horizontal frame 3, do not hindering the stressed and Stability Analysis of Structures of horizontal frame.Be welded to connect the i-beam track 2 of a horizontal arrangement on two I-beam section bases, 4 middle top surface, hanging on this i-beam track 2 winch 6 with road wheel 7 is installed, road wheel 7 is along said i-beam track 2 level runs.The utility model is simple in structure, can change the secondary hoist rope of hoisting crane easily through winch 6, uses the save trouble and labor.

Claims (1)

1.一种四梁四轨双小车桥式起重机副起升钢丝绳更换机构,包括安装在水平框架上、下方的主小车机构以及副小车机构,其特征是:在水平框架的两侧折弯内壁上分别放置着一根工字钢底座,两工字钢底座中部顶面上焊接连接着一根水平布置的工字钢轨道,该工字钢轨道上吊挂安装着具有行走轮的卷扬机,行走轮沿着所说的工字钢轨道水平运行。 1. A four-beam four-track double-trolley bridge crane auxiliary lifting wire rope replacement mechanism, including a main trolley mechanism and an auxiliary trolley mechanism installed on and below the horizontal frame. An I-steel base is placed, and a horizontally arranged I-steel track is welded on the top surface of the middle part of the two I-steel bases. The hoist with traveling wheels is hung on the I-steel track. Said I-beam track runs horizontally.
CN2012200424467U 2012-02-10 2012-02-10 Mechanism for replacing auxiliary hoisting wire rope of four-beam four-rail dual-trolley bridge crane Expired - Fee Related CN202542732U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012200424467U CN202542732U (en) 2012-02-10 2012-02-10 Mechanism for replacing auxiliary hoisting wire rope of four-beam four-rail dual-trolley bridge crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012200424467U CN202542732U (en) 2012-02-10 2012-02-10 Mechanism for replacing auxiliary hoisting wire rope of four-beam four-rail dual-trolley bridge crane

Publications (1)

Publication Number Publication Date
CN202542732U true CN202542732U (en) 2012-11-21

Family

ID=47163398

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012200424467U Expired - Fee Related CN202542732U (en) 2012-02-10 2012-02-10 Mechanism for replacing auxiliary hoisting wire rope of four-beam four-rail dual-trolley bridge crane

Country Status (1)

Country Link
CN (1) CN202542732U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105537848A (en) * 2015-12-22 2016-05-04 秦皇岛首秦金属材料有限公司 Online repairing method for collision deformation of auxiliary main girders of four-beam double-trolley crane
CN110436365A (en) * 2019-07-26 2019-11-12 山东钢铁股份有限公司 Crane rope replacing options

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105537848A (en) * 2015-12-22 2016-05-04 秦皇岛首秦金属材料有限公司 Online repairing method for collision deformation of auxiliary main girders of four-beam double-trolley crane
CN105537848B (en) * 2015-12-22 2017-08-25 秦皇岛首秦金属材料有限公司 Four beam double trolley cranes pair girder collides the online restorative procedure of deformation
CN110436365A (en) * 2019-07-26 2019-11-12 山东钢铁股份有限公司 Crane rope replacing options

Similar Documents

Publication Publication Date Title
CN202785364U (en) Movable dual-door-type mast hoisting device
CN201825671U (en) Hoisting trolley for track plate
CN110104564A (en) A bridge crane assembly process
CN102051860A (en) Bridge erecting and track laying machine for railway
CN108639968A (en) Whole lateral moving formula cable crane
CN104973517A (en) Electric gantry platform for installing sintering machine head equipment and application method thereof
CN204754249U (en) A transporting device that is used for indoor big flue to install
CN202542732U (en) Mechanism for replacing auxiliary hoisting wire rope of four-beam four-rail dual-trolley bridge crane
CN201195668Y (en) Movable cable saddle
CN202755300U (en) Hanging basket of main cable working vehicle
CN204661163U (en) A kind of Multifunction transformer sleeve pipe lifting support
CN202864734U (en) Novel double-beam bridge crane
CN202390106U (en) Lifting hook portal crane easy to maintain
CN201265028Y (en) Special-purpose tool for changing fibre roller
CN203330385U (en) Mould-opening hoisting and overturning device for sand-coated casting of steel mould
CN215755931U (en) Large transformer hoisting equipment in factory building
CN207468039U (en) Complete non-maintaining simple and easy hoisting system manually
CN202465098U (en) Single-beam gantry crane with V-shaped support legs
CN202465115U (en) Double main beam gantry crane
CN202465110U (en) Shipbuilding portal crane with rail clamping device
CN202465102U (en) Double-trolley rotary electromagnetic overhead crane with carrier-beam
CN107738986A (en) Complete non-maintaining simple and easy hoisting system manually
CN202390762U (en) Multipurpose box girder lifting hole pitch conversion device
CN205328481U (en) Low height of striding hangs formula driving
CN202465106U (en) Large-size shipbuilding gantry crane

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121121