CN201065505Y CNU200720072310XU CN200720072310U CN201065505Y CN 201065505 Y CN201065505 Y CN 201065505Y CN U200720072310X U CNU200720072310X U CN U200720072310XU CN 200720072310 U CN200720072310 U CN 200720072310U CN 201065505 Y CN201065505 Y CN 201065505Y
Authority
CN
China
Prior art keywords
box culvert
correcting device
deviation correcting
back beam
oil top
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU200720072310XU
Other languages
Chinese (zh)
Inventor
庄国强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hongrun Construction Group Co Ltd
Original Assignee
Hongrun Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hongrun Construction Group Co Ltd filed Critical Hongrun Construction Group Co Ltd
Priority to CNU200720072310XU priority Critical patent/CN201065505Y/en
Application granted granted Critical
Publication of CN201065505Y publication Critical patent/CN201065505Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model provides a deviation-rectifying device for box culverts, comprising a first Larsen pile, a back beam, a plurality of oil ejectors and at least one first shim, wherein, the first Larsen pile is arranged in parallel on the first side of the box culvert far from the designed center surface; a predetermined distance is kept between the first Larsen pile and the first side; the back beam, which is parallel with the first side of the box culvert, is clung to the first Larsen pile and is fixed on the ground; the oil ejectors are arranged in parallel based on the back beam and can be extended and retracted to the first side of the box culvert; at least one first shim is clung tightly to the first side of the box culvert. When in moving, the box culvert is moved from the existing center surface to the designed center surface due to the oil ejectors extending to the first shim. The utility model is used for moving the box culvert from an existing central surface to a designed central surface when the existing surface deviates from the designing surface.

Description

The box culvert deviation correcting device
Technical field
The utility model relates to a kind of box culvert deviation correcting device.
Background technology
Box culvert occurs under following several situations in off normal: a, the prefabricated process of box culvert easily because the artificial origin has caused off normal; After b, box culvert concrete pouring finished, box culvert two lateral earth pressure imbalances had caused off normal; C, existing box culvert median plane and design road-center face off normal are too big.One of ordinary skill in the art runs into these situations or is to cut existing box culvert by modes such as blasts, or must not be the decline of the caused workmanship of receiving pit culvert off normal then.
The utility model content
The purpose of this utility model is to provide a kind of box culvert deviation correcting device, and this device is by to the correction of existing box culvert, to avoid off normal because of box culvert that box culvert is cut or degradation problem under the workmanship to occur.
In order to realize described purpose, the utility model provides a kind of box culvert deviation correcting device, when the existing median plane off-design median plane of box culvert, be used for box culvert is passed to described design centre face from described existing median plane, be characterized in, comprise: the first Larsen stake, back beam, a plurality of oil top and at least one first pad.The first Larsen stake be arranged on abreast described box culvert away from first side of described design centre face and with described first side at a distance of predetermined distance; The back beam is parallel to first side of described box culvert and is close to the first Larsen stake and bottom surface regularly; A plurality of oil top is arranged in parallel based on described back beam, can be flexible to first side of described box culvert; At least one first pad is close to first side of described box culvert; Wherein, when described box culvert was passed, a plurality of described oil top was stretched to described first pad and described box culvert is passed to described design centre face from described existing median plane.
Described box culvert deviation correcting device, its further characteristics are that described back beam is formed by concrete pouring.
Described box culvert deviation correcting device, its further characteristics are to be provided with asphaltic felt between described back beam and the described first Larsen stake.
Described box culvert deviation correcting device, its further characteristics are to be provided with a plurality of second pads between described back beam and the described oil top, each corresponding described second pad in described oil top.
Described box culvert deviation correcting device, its further characteristics be, is provided with one second pad between described back beam and the described oil top, and described second pad is parallel to described first side.
Described box culvert deviation correcting device, its further characteristics are to be provided with a carrier bar between described back beam and the described oil top.
Described box culvert deviation correcting device, its further characteristics are that described carrier bar is a steel I-beam.
Described box culvert deviation correcting device, its further characteristics are to be provided with parallels between described carrier bar and the described oil top.
Described box culvert deviation correcting device, its further characteristics be, also is provided with the second Larsen stake in second side of the described design centre of the vicinity of described box culvert face, and described second Larsen stake and described second side are at a distance of default distance.
Box culvert deviation correcting device of the present utility model has such advantage at least: box culvert deviation correcting device of the present utility model is passed box culvert to the design centre face from existing median plane by a plurality of oil top; thereby realized the correction when off normal appears in box culvert; do not need to cut existing box culvert; and the problem of having avoided the caused workmanship of box culvert off normal to descend; save construction costs; reduce construction cost; protected environment; reduction of erection time, solved those skilled in the art for a long time and thirsted for the technical problem that solves and fail to solve.
For further specifying above-mentioned purpose of the present utility model, design feature and effect, the utility model is described in detail below with reference to accompanying drawing.
Description of drawings
Fig. 1 is the cross-sectional view strength of first embodiment of box culvert deviation correcting device of the present utility model;
Fig. 2 is the vertical view of the box culvert deviation correcting device among Fig. 1;
Fig. 3 is the cross-sectional view strength of second embodiment of box culvert deviation correcting device of the present utility model.
The specific embodiment
To describe preferred embodiment of the present utility model in detail now, although the employed term in back is to select from public term, but some term then is the applicant to be judged by it and selects, and its detailed meanings should be understood according to the spirit that the application's desire discloses.
As depicted in figs. 1 and 2, the existing median plane 901 off-design median planes 902 of box culvert 90, box culvert deviation correcting device 1 among first embodiment of the present utility model is used for box culvert 90 is passed to design centre face 902 from existing median plane 901, and it comprises the first Larsen stake 10, back beam 20, a plurality of oil top 50, at least one first pad 40.The first Larsen stake 10 be arranged on box culvert 90 away from first side of design centre face 902 and with first side at a distance of predetermined distance.Back beam 20 is parallel to first side 910 of box culvert 90 and is close to the first Larsen stake 10, and is fixed in the bottom surface, ground.A plurality of oil top 50 is a brace foundation with back beam 20 all, can be flexible to first side 910 of box culvert 90.First pad 40 is close to first side 910 of box culvert 90.When box culvert was passed, a plurality of oil top 50 was stretched to first pad 40 and box culvert 90 is passed to design centre face 902 from existing median plane 901.
When finding box culvert 90 off normals, the first Larsen stake 10 is inserted earlier and is beaten near first side 910 of box culvert 90, excavate the earthwork between the box culvert 90 and the first Larsen stake 10 then, other component and fitting of the last space mounting box culvert deviation correcting device 1 that forms in the earthwork back of excavating, the first Larsen stake 10 both can be the stake of original bracing of foundation pit Larsen, also can be to insert the Larsen steel sheet pile of beating again.
Back beam 20 mainly is the brace foundation as oil top 50, back beam 20 can be to be formed by concrete pouring, it also can be the beam body that other material forms, after the Deviation Correction Construction of finishing box culvert 90, for the ease of the dismounting of back beam 20, between back beam 20 and Larsen stake 10, be provided with the asphaltic felt (not shown).Also comprise a steel I-beam 30 at box culvert deviation correcting device 1 shown in Figure 1, steel I-beam 30 is arranged between oil top 50 and the back beam 20, after thereby the effect counter-force of oil top 50 box culverts that are subjected to 90 is delivered to steel I-beam 30 earlier, be delivered to back beam 20 again, steel I-beam 30 is to be delivered to back beam 20 after the concentrated force that oil top 50 applies is disperseed, to avoid interaction force between back beam 20 and the Larsen stake 10 excessive and Larsen stake 10 is damaged, the damage of Larsen stake 10 will directly have influence on the building on the ground surface 110.Steel I-beam 30 also can substitute with other beam body.
Change example as one of present embodiment, box culvert deviation correcting device 1 can not comprise steel I-beam 30, but back beam 20 should be enough thick.At this moment, for oil top 50 more abundant with contacting of back beam 20, can oil push up 50 and back beam 20 between second pad is set, each oil top 50 corresponding one second pad, perhaps all second microscler pads of oil top 50 correspondences.
As shown in Figure 2, all oil tops 50 are arranged in parallel based on steel I-beam 30 and are controlled by same hydraulic cabinet 51, and in the present embodiment, hydraulic cabinet 51 is by all oil tops 50 of oil pipe line 501 controls.Each oil top 50 corresponding one first pad 40, in fact, first pad, 40, the first pads 40 that a plurality of first pads 40 in Fig. 2 can be merged into a strip can be the thick steel plates of 10mm.
Protect the building on the ground surface of second side of box culvert 90 if desired, second Larsen stake 10 ', the second Larsen stake 10 ' and second side 911 can also be set in second side 911 of the contiguous design centre of box culvert 90 face 902 at a distance of default distance.
Fig. 3 shows second embodiment of box culvert deviation correcting device of the present utility model, maximum different being included between oil top 50 and the back beam 20 of box culvert deviation correcting device 2 and box culvert deviation correcting device 1 is provided with a plurality of parallels 60, the situation when the top journey that box culvert deviation correcting device 2 is mainly used in oil top 50 is not enough to finish the correction of box culvert 90.
Going on to say the mounting means of a kind of above-mentioned box culvert deviation correcting device 1 and/or 2 below, but it should be noted that, is in order to make those skilled in the art understand the utility model rather than in order to limit the utility model to the explanation of this mounting means.
At first, insert in first side 910 of box culvert 90 and to play the first Larsen stake 10 (or utilizing the stake of original bracing of foundation pit Larsen), if necessary, also should be simultaneously play the second Larsen stake 10 ' in that second side 911 is slotting.
Then, excavate the earthwork between box culvert 90 and Larsen stake 10 or 10 ', at Larsen stake 10 limit fluid concrete back beams 20 or other beam body is installed, separate with asphaltic felt between back beam 20 and the Larsen stake 10.
Secondly, oil top 50 and operation panel 51 are installed, are laid steel I-beam 30 (if necessary) between oil top 50 and back beam 20, lay steel plate (first pad 40) between oil top 50 and box culvert 90, oil top 50 all is arranged in parallel.
At last, start oil top 50, push up the correction that 50 1 top journeys are not enough to finish box culvert 90 as oil, behind 50 retractions of oil top, push up 50 behind top iron 60 at oil, the oil top 50 that reruns arrives design attitude until box culvert 90.
Though the utility model discloses as above with preferred embodiment; yet it is not in order to limit the utility model; anyly be familiar with one of ordinary skill in the art; in not breaking away from spirit and scope of the present utility model; therefore should make the variation or the replacement of all equivalences, protection domain of the present utility model is when looking accompanying being as the criterion that the application's claim scope defined.

Claims (9)

1. box culvert deviation correcting device when the existing median plane off-design median plane of box culvert, is used for box culvert is passed to described design centre face from described existing median plane, it is characterized in that, comprising:
The first Larsen stake, be arranged on abreast described box culvert away from first side of described design centre face and with described first side at a distance of predetermined distance;
The back beam is parallel to first side of described box culvert and is close to the first Larsen stake and bottom surface regularly;
A plurality of oil top is arranged in parallel based on described back beam, can be flexible to first side of described box culvert;
At least one first pad is close to first side of described box culvert;
Wherein, when described box culvert was passed, a plurality of described oil top was stretched to described first pad and described box culvert is passed to described design centre face from described existing median plane.
2. box culvert deviation correcting device as claimed in claim 1 is characterized in that, described back beam is formed by concrete pouring.
3. box culvert deviation correcting device as claimed in claim 2 is characterized in that, is provided with asphaltic felt between described back beam and the described first Larsen stake.
4. box culvert deviation correcting device as claimed in claim 1 is characterized in that, is provided with a plurality of second pads between described back beam and the described oil top, each corresponding described second pad in described oil top.
5. box culvert deviation correcting device as claimed in claim 1 is characterized in that, is provided with one second pad between described back beam and the described oil top, and described second pad is parallel to described first side.
6. box culvert deviation correcting device as claimed in claim 1 is characterized in that, is provided with a carrier bar between described back beam and the described oil top.
7. box culvert deviation correcting device as claimed in claim 6 is characterized in that described carrier bar is a steel I-beam.
8. box culvert deviation correcting device as claimed in claim 6 is characterized in that, is provided with parallels between described carrier bar and the described oil top.
9. box culvert deviation correcting device as claimed in claim 1 is characterized in that, also is provided with the second Larsen stake in second side of the described design centre of the vicinity of described box culvert face, and described second Larsen stake and described second side are at a distance of default distance.
CNU200720072310XU 2007-07-10 2007-07-10 Box culvert error-correcting device Expired - Lifetime CN201065505Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU200720072310XU CN201065505Y (en) 2007-07-10 2007-07-10 Box culvert error-correcting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU200720072310XU CN201065505Y (en) 2007-07-10 2007-07-10 Box culvert error-correcting device

Publications (1)

Publication Number Publication Date
CN201065505Y true CN201065505Y (en) 2008-05-28

Family

ID=39482675

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU200720072310XU Expired - Lifetime CN201065505Y (en) 2007-07-10 2007-07-10 Box culvert error-correcting device

Country Status (1)

Country Link
CN (1) CN201065505Y (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926394A (en) * 2010-06-05 2013-02-13 朱虹 Method for using lime piles to rectify deviation of open caisson
CN101749024B (en) * 2008-12-22 2013-05-29 上海广联建设发展有限公司 Pipe-pulling construction method of underground buried box culvert
CN101749028B (en) * 2008-12-16 2013-05-29 上海广联建设发展有限公司 Cross-pulling construction method for soft soil zone with high ground water level
CN109610493A (en) * 2018-12-29 2019-04-12 中铁大桥局集团第四工程有限公司 Correct the construction method of open caisson center deviation
CN110804919A (en) * 2019-11-19 2020-02-18 兰州交通大学 Novel roadbed structure for crossing active fault
CN113638276A (en) * 2021-08-16 2021-11-12 内蒙古大学 Road pile foundation, self-feeding type deviation rectifying method and device and pile foundation system

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101749028B (en) * 2008-12-16 2013-05-29 上海广联建设发展有限公司 Cross-pulling construction method for soft soil zone with high ground water level
CN101749024B (en) * 2008-12-22 2013-05-29 上海广联建设发展有限公司 Pipe-pulling construction method of underground buried box culvert
CN102926394A (en) * 2010-06-05 2013-02-13 朱虹 Method for using lime piles to rectify deviation of open caisson
CN102926394B (en) * 2010-06-05 2015-03-25 朱虹 Method for using lime piles to rectify deviation of open caisson
CN109610493A (en) * 2018-12-29 2019-04-12 中铁大桥局集团第四工程有限公司 Correct the construction method of open caisson center deviation
CN110804919A (en) * 2019-11-19 2020-02-18 兰州交通大学 Novel roadbed structure for crossing active fault
CN113638276A (en) * 2021-08-16 2021-11-12 内蒙古大学 Road pile foundation, self-feeding type deviation rectifying method and device and pile foundation system

Similar Documents

Publication Publication Date Title
CN201065505Y (en) Box culvert error-correcting device
CN105887587A (en) Turnout zone and non-turnout zone transition section structure for medium and low-speed magnetic levitation low implantation line
CN101725357A (en) Construction method for lower section of underground tunnel
CN106253190B (en) Cable duct structure, cabling arrangements and cable laying method
CN202416263U (en) Concrete faced rockfill dam compounded with gravity dam
CN202865855U (en) Stabilizing plate type anchoring pile retaining structure
CN204780933U (en) Shoring of trench landing stage system
CN204455801U (en) A kind of bridge abutment structure
CN102839686A (en) Stabilizing plate type anchor pile retaining structure
CN207109812U (en) A kind of reinforced anchor rod support system
CN102226345A (en) Method for carrying out advanced water shut-off on post-cast strips in underground engineering and advanced water shut-off steel plate structure
CN208981282U (en) A kind of high earthquake territory concrete face rockfill dam dam crest structure
CN206784393U (en) T-piece and underground pipe gallery foundation pit support system
CN206157792U (en) Complementary rectification reinforced structure of stake raft
CN101565940A (en) Coupling structure of gravity dam and unfavorable geological bank slope and the construction method thereof
CN108487302B (en) Composite retaining pile wall for supporting piles, retaining wall and pile foundation and construction method
CN100507164C (en) Water proof method of open trench tunnel suitable for large value stratun ununiform settling or diastrophism
CN107940102B (en) Underground raw water pipeline protection construction method
US20220325492A1 (en) Prefabricated, modular hydropower foundation system for soil conditions
CN104047273B (en) Power station dissipation and scouring wall and construction method thereof
CN203795435U (en) Diagonal bracing reinforcing structure
KR20120073623A (en) Connecting structure of steel pipe sheet pile
CN201406678Y (en) Linkage structure of gravity dam and unfavorable geological bank slope
CN212405217U (en) Pile foundation underpins structure
CN205617160U (en) Low distributed switch foundation structure of circuit rib post that puts of moderate -low speed magnetic levitation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20080528