CN202865855U - Stabilizing plate type anchoring pile retaining structure - Google Patents

Stabilizing plate type anchoring pile retaining structure Download PDF

Info

Publication number
CN202865855U
CN202865855U CN 201220496656 CN201220496656U CN202865855U CN 202865855 U CN202865855 U CN 202865855U CN 201220496656 CN201220496656 CN 201220496656 CN 201220496656 U CN201220496656 U CN 201220496656U CN 202865855 U CN202865855 U CN 202865855U
Authority
CN
China
Prior art keywords
anchor pile
retaining structure
anchoring pile
stabilizing plate
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220496656
Other languages
Chinese (zh)
Inventor
陈云
庞应刚
杨静梅
陈永
纪小彬
任华锋
张洪文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN 201220496656 priority Critical patent/CN202865855U/en
Application granted granted Critical
Publication of CN202865855U publication Critical patent/CN202865855U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a stabilizing plate type anchoring pile retaining structure. The stabilizing plate type anchoring pile retaining structure resolves the problems of a large cantilever, large soil pressure, or landslide thrust, and large deformation of soil layer anchoring pile ground in a conventional design. The section of each anchoring pile is optimized, the safety of the retaining structure is improved, and construction cost is lowered. The stabilizing plate type anchoring pile retaining structure comprises anchoring piles (10) which are arranged at intervals, wherein the lower portion of each anchoring pile (10) is embedded in an anchoring rock-oil mass (B), a vertical panel (12) and a horizontal stabilizing plate (13) are arranged at the top of each anchoring pile (10), each vertical panel (12) and each horizontal stabilizing plate (13) are fixedly connected with the top of each anchoring pile (10), and each horizontal stabilizing plate (13) inwards extends into a fill side slope filling (C) or a slide slope slip mass (D) in the horizontal direction.

Description

Stablize board-like anchor pile retaining structure
Technical field
The utility model relates to the retaining structure of geotechnical engineering, particularly applies to the anchor pile retaining structure of long cantilever section in high embankment closing slope or the landslide control, large soil pressure (or Thrust of Landslide).
Background technology
Along with the development of society, a lot of high embankment side slopes has appearred, simultaneously because the restriction of engineering specifications, much engine requests employing retaining structure closing slopes in the engineering.On the other hand, some stable Rock And Soil of occurring in nature along with the variation of the external conditions such as geology, the hydrology, becomes understable, unstable.Under aforementioned engineering specifications, can relate to and use the long anchor pile of cantilever segment, effect soil pressure or Thrust of Landslide thereon is also larger, and this has proposed very high requirement to anchor pile.Yet the cantilevered anchor pile is as a kind of cantilever structure, and is stressed and deformation performance is relatively poor.Especially anchor pile is when the soil layer anchoring, be difficult to reach " horizontal movement of place, ground stake should not greater than 10mm " of code requirement, if surpass, just conventional coefficient of subgrade reaction can not adopt, must carry out reduction, coefficient of subgrade reaction diminishes after the reduction, and it is larger to draw pile deformation, forms vicious circle, control the stake horizontal movement of place, ground so usually adopt increase stake cross section or increasing buried depth, final economic effect is not good, and the buried depth of stake is excessive, constructional difficulties.At present, the gear measure in high embankment closing slope or the landslide control mainly contains following several:
The stake board wall is developed by anchor pile, when the embankment side slope adopts the cantilevered anchor pile to prop up gear, between the stake breast boards is set, in order to the soil body behind the protected apron.The embankment, the cutting that can be used for general area, soaking district and earthquake zone prop up gear, also can be used for a landslide gear protection.Early 1970s takes the lead in being applied in the trunk railways such as a Liu Tielu, Line of Nankun Railway.
Prestressed anchor pull-type (anchor cable) stake board wall is that the cantilever segment at anchor pile applies prestressing force, with the engineering measure of the gear protection that solves high slope.It is a kind of structure of drawing facility to be combined as a whole on stake board wall and anchor.Typical engineering has Line of Nankun Railway stone stockaded village prestressed anchor sheet-pile retaining wall engineering.
Pile foundation joist retaining wall is the combining form of retaining wall and stake, is connected by joist.Be mainly used in solving the lower problem of bearing capacity, retaining wall is generally weight formula or gravity, and pile foundation is anchor pile.In the geotechnical engineering field, this gear form is widely used.
The anchor pile of said structure under certain engineering boundary condition, can relate to that cantilever segment is long, soil pressure or Thrust of Landslide is large, do not have stable anchor to draw the engineering specifications such as rock mass after the stake.Inevitably calculate the stake of heavy in section, long anchoring section, its result is very uneconomical, and difficulty of construction is also very large.
The utility model content
Technical problem to be solved in the utility model provides a kind of board-like anchor pile retaining structure of stablizing, and is out of shape the difficult problems such as excessive with the long cantilever that runs in the solution conventional design, large soil pressure or Thrust of Landslide, place, soil layer anchor pile ground.Optimize the anchor pile cross section, improve the safety of retaining structure, reduce construction costs.
The technical scheme that its technical problem that solves the utility model adopts is as follows:
Of the present utility modelly stablize board-like anchor pile retaining structure, comprise the anchor pile that the interval arranges, the bottom of anchor pile is embedded in the anchoring Rock And Soil, it is characterized in that: the stake top of described anchor pile is provided with the with it fixed setting panel that is integrated and horizontal stable plate, and steadying plate laterally inwardly extends into the embankment side slope and bankets or come down in the gliding mass.
The beneficial effects of the utility model are: effectively solve the difficult problems such as the long cantilever that runs in the conventional design, large soil pressure or Thrust of Landslide, the distortion of place, soil layer anchor pile ground be excessive, optimize the anchor pile cross section, improve the safety of retaining structure, reduce construction costs; The retaining structure system is simple, stressed clear, and exploitativeness is strong.
Description of drawings
This manual comprises following six width of cloth accompanying drawings:
Fig. 1 is that the utility model is stablized the generalized section that board-like anchor pile retaining structure applies to the embankment side slope;
Fig. 2 is that the utility model is stablized the front schematic view that board-like anchor pile retaining structure applies to the embankment side slope;
Fig. 3 is that the utility model is stablized the soil pressure distribution schematic diagram that board-like anchor pile retaining structure applies to the embankment side slope;
Fig. 4 is that the utility model is stablized load action type and the position view that board-like anchor pile retaining structure applies to the embankment side slope;
Fig. 5 is that the utility model is stablized the structural representation that board-like anchor pile retaining structure applies to landslide control.
Fig. 6 is that the utility model is stablized the perspective view that board-like anchor pile retaining structure applies to landslide control.
Mark among the figure: slide surface A, anchoring Rock And Soil B, the C that bankets, gliding mass D, soil pressure distribution E, soil pressure distribution F, soil pressure Ea1, soil pressure Ea2, banket and ground load G1, stablize beam slab gravity load G2, top gliding mass load G3, anchor pile 10, panel 12, steadying plate 13, edge of a wing structure 14, breast boards 20.
The specific embodiment
Below in conjunction with drawings and Examples the utility model is further specified.
With reference to Fig. 1 and Fig. 4, of the present utility modelly stablize board-like anchor pile retaining structure, comprise the anchor pile 10 that the interval arranges, the bottom of anchor pile 10 is embedded in anchoring Rock And Soil B.The stake top of described anchor pile 10 is provided with it fixed setting panel 12 and horizontal stable plate 13, and steadying plate 13 laterally inwardly extends into the embankment side slope and bankets in C or the landslide gliding mass D.See figures.1.and.2, when applying to the embankment slope supporting, anchor pile 10 sidewalls have edge of a wing structure 14, hang breast boards 20 by edge of a wing structure 14 between adjacent anchor pile 10.With reference to Fig. 5 and Fig. 6, when applying to landslide control, can not hang breast boards 20 between the adjacent anchor pile 10.
With reference to Fig. 3, soil pressure distribution E is the stressing conditions of anchor pile 10, and soil pressure distribution F is the stressing conditions of panel 12.With reference to Fig. 4 and Fig. 5, banket on soil pressure Ea1, the steadying plate 13 and ground load G1 or top gliding mass load G3, steadying plate gravity load G2.This shows, the setting of steadying plate 13 can increase the stabilizing moment of anchor pile 10, to reduce or negative function overturning moment on anchor pile 10, reduces the load on anchor pile 10, the force and deformation of control anchor pile 10, the especially horizontal movement of place, soil layer anchor pile ground stake.By above 3 points, optimize dexterously the anchor pile fringe conditions, effectively solved a Practical Project difficult problem.
Of the present utility model stablizing in the board-like anchor pile retaining structure, anchor pile 10, steadying plate 13, panel 12, breast boards 20 composition systems finish the closing slope of high embankment stage by stage.Its construction sequence is as follows:
(1) adopt manually digging hole or boring, construction anchor pile 10, the stake top embeds steadying plate 13;
When (2) treating that pile strength reaches requirement, the limit hangs breast boards 20 limit placements in layers and bankets and grinding compacting;
When (3) filling to steadying plate 13 bottom surface, build the thick plain concrete cushion layer of one deck 0.1m, colligation steadying plate 13 and panel 12 reinforcing bars, concreting;
When (4) treating that concrete strength reaches requirement, fill steadying plate banketing more than 13.
The above the utility model that just explains through diagrams is stablized some principles and the embodiment of board-like anchor pile retaining structure, be not be the utility model to be confined to shown in and in described concrete structure and the scope of application, so every corresponding modify that might be utilized and equivalent all belong to the claim that the utility model is applied for.

Claims (2)

1. stablize board-like anchor pile retaining structure, comprise the anchor pile (10) that the interval arranges, the bottom of anchor pile (10) is embedded in anchoring Rock And Soil (B), it is characterized in that: the stake top of described anchor pile (10) is provided with the with it fixed setting panel (12) that is integrated and horizontal stable plate (13), and steadying plate (13) laterally inwardly extends into the embankment side slope and bankets (C) or come down in the gliding mass (D).
2. as claimed in claim 1ly stablize board-like anchor pile retaining structure, it is characterized in that: described anchor pile (10) sidewall has edge of a wing structure (14), hangs breast boards (20) by edge of a wing structure (14) between adjacent anchor pile (10).
CN 201220496656 2012-09-26 2012-09-26 Stabilizing plate type anchoring pile retaining structure Expired - Lifetime CN202865855U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220496656 CN202865855U (en) 2012-09-26 2012-09-26 Stabilizing plate type anchoring pile retaining structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220496656 CN202865855U (en) 2012-09-26 2012-09-26 Stabilizing plate type anchoring pile retaining structure

Publications (1)

Publication Number Publication Date
CN202865855U true CN202865855U (en) 2013-04-10

Family

ID=48032586

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220496656 Expired - Lifetime CN202865855U (en) 2012-09-26 2012-09-26 Stabilizing plate type anchoring pile retaining structure

Country Status (1)

Country Link
CN (1) CN202865855U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102839686A (en) * 2012-09-26 2012-12-26 中铁二院工程集团有限责任公司 Stabilizing plate type anchor pile retaining structure
CN104018496A (en) * 2014-05-13 2014-09-03 中冶集团武汉勘察研究院有限公司 Round-section slide-resistant pile with pile body provided with horizontal haunched beam and construction method of round-section slide-resistant pile
WO2015023812A1 (en) * 2013-08-14 2015-02-19 Geopier Foundation Company, Inc. Method and apparatus for stabilizing slopes and embankments with soil load transfer plates
CN104805850A (en) * 2015-05-08 2015-07-29 中铁工程设计咨询集团有限公司 Vertex-aligning buttress balancing plate type cutting supporting block device
CN104878769A (en) * 2015-06-19 2015-09-02 中国电建集团成都勘测设计研究院有限公司 Debris flow protecting system
CN111005389A (en) * 2019-12-27 2020-04-14 深圳市工勘岩土集团有限公司 Construction method of unloading plate type supporting structure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102839686A (en) * 2012-09-26 2012-12-26 中铁二院工程集团有限责任公司 Stabilizing plate type anchor pile retaining structure
WO2015023812A1 (en) * 2013-08-14 2015-02-19 Geopier Foundation Company, Inc. Method and apparatus for stabilizing slopes and embankments with soil load transfer plates
US10094087B2 (en) 2013-08-14 2018-10-09 Geopier Foundation Company, Inc. Method and apparatus for stabilizing slopes and embankments with soil load transfer plates
CN104018496A (en) * 2014-05-13 2014-09-03 中冶集团武汉勘察研究院有限公司 Round-section slide-resistant pile with pile body provided with horizontal haunched beam and construction method of round-section slide-resistant pile
CN104805850A (en) * 2015-05-08 2015-07-29 中铁工程设计咨询集团有限公司 Vertex-aligning buttress balancing plate type cutting supporting block device
CN104878769A (en) * 2015-06-19 2015-09-02 中国电建集团成都勘测设计研究院有限公司 Debris flow protecting system
CN111005389A (en) * 2019-12-27 2020-04-14 深圳市工勘岩土集团有限公司 Construction method of unloading plate type supporting structure

Similar Documents

Publication Publication Date Title
CN202865855U (en) Stabilizing plate type anchoring pile retaining structure
CN103967031B (en) A kind of caisson of consolidated subsoil and stake combination foundation and construction method thereof
CN103510531B (en) A kind of split type open caisson staking Compound Anchorage basis and construction method thereof
CN106522270B (en) A kind of the pile foundation barricade antidetonation retaining structure and construction method of the buffer layer containing EPS
CN102839686A (en) Stabilizing plate type anchor pile retaining structure
CN102561132B (en) Plate supporting type embankment structure for post-construction settlement controlling of deep soft soil foundation on high-grade highway
CN203213136U (en) Caisson and pile combined foundation of consolidated subsoil
CN111021376A (en) Three-dimensional frame pile body structure for deep landslide treatment and construction process thereof
CN104790429A (en) Integral prestress reinforced earth retaining wall construction method
CN202430681U (en) Bank protection structure
CN109056790A (en) Stake three layers of retaining wall structure of support and construction method
CN207525567U (en) A kind of pile plate composite structure suitable for Steep Slope Embankment
CN101967786A (en) Airfield pavement structure with box-type shock-isolation foundation
CN206902734U (en) A kind of earth construction of soft foundation zone
CN201801843U (en) Overwater gravity type earth-retaining structure with anchoring structure
CN103306295A (en) Rigid frame pile supporting and blocking structure
CN108487234B (en) Construction method of cast-in-situ pile plate type platform wall
CN206844132U (en) Superelevation light supporting structure
CN212077974U (en) T-shaped slide-resistant pile structure for filling side slope
CN203284795U (en) Buttressed retaining wall with anchor board
CN218813764U (en) Stress-maintaining type faces combination continuous pile wall supporting construction forever
CN111945657A (en) Wharf upgrading and reconstruction structure and wharf upgrading and reconstruction construction method
CN209669613U (en) A kind of road structure with pile foundation bent cap
CN204456182U (en) Vertical anchorage pile retaining wall
CN203639929U (en) Split open caisson and pile composite anchor foundation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20130410

CX01 Expiry of patent term