CN204455801U - A kind of bridge abutment structure - Google Patents
A kind of bridge abutment structure Download PDFInfo
- Publication number
- CN204455801U CN204455801U CN201420836552.1U CN201420836552U CN204455801U CN 204455801 U CN204455801 U CN 204455801U CN 201420836552 U CN201420836552 U CN 201420836552U CN 204455801 U CN204455801 U CN 204455801U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- distribution beam
- pipe piles
- back wall
- row
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Foundations (AREA)
Abstract
本实用新型涉及桥梁工程的钢栈桥技术领域,公开了一种桥台结构,包括:钢管桩;还包括:挡土背墙、横向主分配梁、纵向次分配梁;钢管桩设置于栈桥接线便道边坡上,横向主分配梁沿横桥向设置于钢管桩顶部,纵向次分配梁沿纵桥向设置于横向主分配梁上,挡土背板沿横桥向垂直固定于纵向次分配梁上。本实用新型不受暴雨及水浪对台前护坡的冲刷影响,减少了后期的维护保养投入,并且利用钢栈桥结构自身的受力特点平衡台背填土便道的土压力和重力,起到将填土便道与钢栈桥可靠平稳连接的作用。易于安装、拆除,型钢均可回收再次利用,从而避免了圬工结构对环境的污染,提高了材料的周转利用率。
The utility model relates to the technical field of steel trestles in bridge engineering, and discloses an abutment structure, which includes: steel pipe piles; also includes: a retaining back wall, a horizontal main distribution beam, and a longitudinal secondary distribution beam; the steel pipe piles are arranged on the trestle On the side slope of the junction access road, the horizontal main distribution beam is arranged on the top of the steel pipe pile along the transverse bridge direction, the longitudinal secondary distribution beam is arranged on the horizontal main distribution beam along the longitudinal bridge direction, and the retaining back plate is vertically fixed on the longitudinal secondary distribution beam. The utility model is not affected by the erosion of the slope protection in front of the platform by heavy rain and water waves, reduces the maintenance investment in the later period, and uses the force characteristics of the steel trestle structure itself to balance the soil pressure and gravity of the soil filling path at the back of the platform, so as to reduce the The role of the reliable and stable connection between the filling access road and the steel trestle bridge. It is easy to install and dismantle, and the section steel can be recycled and reused, thereby avoiding the environmental pollution of the masonry structure and improving the turnover rate of materials.
Description
技术领域 technical field
本实用新型涉及桥梁工程钢栈桥技术领域。 The utility model relates to the technical field of bridge engineering steel trestle bridges.
背景技术 Background technique
在现代桥梁施工过程中,钢栈桥已经成为一种施工过程中必不可少的辅助工具,以满足人、材、机等各类施工资源的转运需求。在钢栈桥使用过程中,受栈桥通行的施工荷载、暴雨及水浪冲刷等因素的影响,基础容易发生沉降而造成“桥头跳车”的现象,影响栈桥的正常使用。 In the process of modern bridge construction, steel trestle has become an indispensable auxiliary tool in the construction process to meet the transfer needs of various construction resources such as people, materials, and machines. During the use of the steel trestle bridge, affected by factors such as the construction load of the trestle bridge, heavy rain and water wave erosion, the foundation is prone to subsidence and cause the phenomenon of "jumping at the bridge head", which affects the normal use of the trestle bridge.
在传统的钢栈桥施工过程中,两岸接线便道填土为柔性基础,桥台基础位于便道护坡范围,栈桥桥台结构施工前必须对基础进行强度处理,处理方案多为以下两种类型:方案一是在护坡范围内抛填块石进行碾压,将软弱基础进行换填,然后浇筑混凝土桥台基础;方案二是采用管桩基础,在管桩上浇筑混凝土系梁作为栈桥桥台基础。 In the traditional steel trestle construction process, the filling soil of the cross-strait access road is a flexible foundation, and the abutment foundation is located in the slope protection range of the access road. Before the construction of the trestle abutment structure, the strength of the foundation must be treated. Most of the treatment options are the following two types: Scheme 1 The method is to throw and fill the rocks within the scope of slope protection for rolling, replace the weak foundation, and then pour the concrete abutment foundation; the second option is to use the pipe pile foundation, and pour concrete tie beams on the pipe piles as the foundation of the trestle abutment.
现有技术在实际应用中存在的缺点为:方案一虽然克服了暴雨或湖水冲刷对护坡的影响,但是基础沉降的发生不可避免。方案二虽然解决了基础沉降问题,但是混凝土桥台结构施工投入也比较大,受暴雨或水浪冲刷便道桥台迎水面边坡基础容易垮塌,需要投入边坡防护措施。如果将方案一与方案二结合使用,施工投入又比较大,后期还需对桥台结构进行进行维护保养,工程经济性性也不高。 The disadvantages of the existing technology in practical application are: Although the first solution overcomes the influence of heavy rain or lake water scouring on the slope protection, the occurrence of foundation settlement is inevitable. Although Option 2 solves the foundation settlement problem, the investment in the construction of the concrete abutment structure is also relatively large, and the side slope foundation of the access road abutment facing the water is prone to collapse due to heavy rain or water waves, and slope protection measures need to be invested. If plan 1 and plan 2 are used in combination, the construction investment will be relatively large, and the abutment structure will need to be maintained in the later stage, and the economic efficiency of the project will not be high.
实用新型内容 Utility model content
本实用新型所要解决的技术问题是提供一种桥台结构,它具有利用钢管桩基础克服台背填土便道基础的沉降问题,采用挡土背墙结构,避免暴雨和水浪对护坡的冲刷影响,减少施工投入的特点。 The technical problem to be solved by the utility model is to provide an abutment structure, which has the ability to use the steel pipe pile foundation to overcome the settlement problem of the backfill access road foundation, and adopts the retaining back wall structure to avoid the erosion of the slope protection by heavy rain and water waves impact and reduce construction investment.
为解决上述技术问题,本实用新型提供了一种桥台结构,包括:钢管桩;还包括:挡土背墙、横向主分配梁、纵向次分配梁;所述钢管桩设置于栈桥接线便道边坡上,所述横向主分配梁沿横桥向设置于钢管桩顶部,所述纵向次分配梁沿纵桥向设置于所述横向主分配梁上,所述挡土背板沿横桥向垂直固定于纵向次分配梁上。 In order to solve the above technical problems, the utility model provides an abutment structure, including: steel pipe piles; also includes: retaining back wall, horizontal main distribution beam, vertical secondary distribution beam; On the side slope of the sidewalk, the horizontal main distribution beam is arranged on the top of the steel pipe pile along the horizontal bridge direction, the longitudinal secondary distribution beam is arranged on the horizontal main distribution beam along the longitudinal bridge direction, and the soil retaining back plate is arranged along the horizontal bridge direction. The bridge is vertically fixed on the longitudinal secondary distribution beam.
对上述基础结构进行改进的方案为,还包括:撑杆;所述撑杆设置于所述挡土背 墙与所述纵向次分配梁之间,撑杆、挡土背墙与横向纵向配梁之间为三角形结构。 The scheme for improving the above basic structure is to further include: braces; the braces are arranged between the retaining back wall and the longitudinal sub-distributing beam, Between them is a triangular structure.
对上述方案进行优选的技术方案为,所述钢管桩包括:第一排钢管桩、第二排钢管桩;所述第一排钢管桩设置于靠近栈桥接线便道的一侧,所述第二排钢管桩设置于桥身一侧,各个钢管桩之间通过横向连接系4、纵向连接系3连接固定; The preferred technical solution for the above scheme is that the steel pipe piles include: a first row of steel pipe piles and a second row of steel pipe piles; The second row of steel pipe piles is arranged on one side of the bridge body, and each steel pipe pile is connected and fixed by a horizontal connection system 4 and a vertical connection system 3;
所述横向主分配梁包括:第一横向主分配梁、第二横向主分配梁;所述第一横向主分配梁设置于第一排钢管桩顶部,所述第二横向主分配梁设置于第二排钢管桩顶部,第一横向主分配梁与第二横向主分配梁的顶部均与所述纵向次分配梁固定连接; The transverse main distribution beam includes: a first transverse main distribution beam and a second transverse main distribution beam; the first transverse main distribution beam is arranged on the top of the first row of steel pipe piles, and the second transverse main distribution beam is arranged on At the top of the second row of steel pipe piles, the tops of the first transverse main distribution beam and the second transverse main distribution beam are fixedly connected with the longitudinal secondary distribution beam;
所述挡土背墙固定于第一排钢管桩顶部的纵向次分配梁上。 The retaining back wall is fixed on the longitudinal secondary distribution beam at the top of the first row of steel pipe piles.
对上述方案作出进一步改进的技术方案为,还包括:横梁骨架; The technical solution for further improving the above-mentioned solution is to include: beam skeleton;
所述挡土背墙包括:钢板、横向骨架、竖向骨架;所述横向骨架固定于所述钢板的一侧,所述竖向骨架固定于所述横向骨架上,竖向骨架与所述纵向次分配梁对应并且垂直于纵向次分配梁; The retaining back wall includes: a steel plate, a transverse framework, and a vertical framework; the transverse framework is fixed on one side of the steel plate, the vertical framework is fixed on the transverse framework, and the vertical framework and the longitudinal The secondary distribution beam corresponds to and is perpendicular to the longitudinal secondary distribution beam;
所述撑杆的一端固定于所述纵向次分配梁上,撑杆另一端通过所述横梁骨架与挡土背墙的竖向骨架固定。 One end of the strut is fixed on the longitudinal secondary distribution beam, and the other end of the strut is fixed to the vertical skeleton of the retaining back wall through the beam skeleton.
进一步优选的技术方案为,挡土背墙的宽度等于栈桥设计宽度加上挡土背墙设计高度。 A further preferred technical solution is that the width of the retaining back wall is equal to the design width of the trestle plus the design height of the retaining back wall.
更进一步改进的技术方案为,还包括:贝雷片、门型定位卡;所述贝雷片的竖杆与所述横梁骨架顶紧后,通过所述门型定位卡固定在所述第二横向主分配梁上。 A further improved technical solution is to further include: a Bailey sheet and a door-shaped positioning card ; after the vertical rod of the Bailey sheet is pressed against the beam skeleton, it is fixed on the second frame through the door-shaped positioning card. on the transverse main distribution beam.
更加优选的技术方案为,每一排钢管桩的宽度与栈桥宽度相当,第一排钢管桩与第二排钢管桩之间的间距大于所述挡土背墙的高度。 A more preferred technical solution is that the width of each row of steel pipe piles is equivalent to the width of the trestle, and the distance between the first row of steel pipe piles and the second row of steel pipe piles is greater than the height of the retaining back wall.
本实用新型的优点在于: The utility model has the advantages of:
1.本实用新型利用钢管桩基础,克服了台背填土便道基础的沉降问题,采用挡土背墙结构,避免了暴雨和水浪对护坡的冲刷影响,减少了施工投入。 1. The utility model uses the steel pipe pile foundation to overcome the settlement problem of the backfill access road foundation, adopts the retaining back wall structure, avoids the impact of heavy rain and water waves on slope protection, and reduces construction investment.
2.利用撑杆将台背荷载传递至钢管桩基础上,合理的利用了钢栈桥结构自身的受力特点,平衡了台背土压力和重力,避免了因填土便道沉降发生“桥头跳车”的问题。 2. Utilize the struts to transmit the load of the abutment back to the steel pipe pile foundation, rationally utilize the force characteristics of the steel trestle structure itself, balance the soil pressure and gravity of the abutment back, and avoid the occurrence of "bridge head jumping" due to the settlement of the filling access road car" problem.
3.将本实用新型的挡土背墙宽度设计成等于栈桥设计宽度加上背墙设计高度时,即能够满足填土便道放坡的要求,避免台背受水浪的冲刷而垮塌,也不会使防护范围过大,是一个比较合适、合理的宽度选定。 3. When the width of the retaining back wall of the utility model is designed to be equal to the design width of the trestle bridge plus the design height of the back wall, it can meet the requirements of the slope of the filling access road, avoid the back of the platform from collapsing due to the erosion of water waves, and not It will make the protection range too large, which is a more suitable and reasonable width selection.
本实用新型所提供的桥台结构为钢桥台结构,不但施工安全、快捷,不受暴雨及 水浪对台前护坡的冲刷影响,而且减少了后期的维护保养投入,并且利用钢栈桥结构自身的受力特点平衡台背填土便道的土压力和重力,起到将填土便道与钢栈桥可靠平稳连接的作用。本实用新型也易于拆除,型钢均可回收再次利用,从而避免了圬工结构对环境的污染,提高了材料的周转利用率。 The abutment structure provided by the utility model is a steel abutment structure, which is not only safe and fast in construction, is not affected by the erosion of the slope protection in front of the abutment by heavy rain and water waves, but also reduces the maintenance investment in the later period, and utilizes the steel trestle structure itself The force characteristics balance the earth pressure and gravity of the backfill access road on the back of the platform, and play the role of reliable and stable connection between the fill access road and the steel trestle bridge. The utility model is also easy to dismantle, and the section steel can be recycled and reused, thereby avoiding the pollution of the masonry structure to the environment and improving the turnover utilization rate of materials.
附图说明 Description of drawings
图1为本实用新型实施例的纵桥向结构示意图。 Fig. 1 is a schematic diagram of the longitudinal bridge structure of the embodiment of the utility model.
图2为本实用新型实施例的横桥向结构示意图。 Fig. 2 is a schematic structural diagram of the horizontal bridge of the embodiment of the utility model.
其中,1A-第一排钢管桩,1B-第二排钢管桩,2A-第一排横向主分配梁,2B-第二排横向主分配梁,3-桩间纵向连接系,4-桩间横向连接系,5-纵向次分配梁,6-背墙面板,7-背墙横向骨架,8-背墙竖向骨架,9-撑杆,10-横梁骨架,11-贝雷片,12-伸缩钢板,13-接线填土便道,14-门型定位卡,15-加劲板,16-栈桥桥面结构。 Among them, 1A-the first row of steel pipe piles, 1B-the second row of steel pipe piles, 2A-the first row of horizontal main distribution beams, 2B-the second row of horizontal main distribution beams, 3-the longitudinal connection system between piles, 4- Horizontal connection system between piles, 5-longitudinal sub-distribution beam, 6-back wall panel, 7-back wall horizontal skeleton, 8-back wall vertical skeleton, 9-strut, 10-beam skeleton, 11-Berry sheet, 12-telescopic steel plate, 13-junction filling soil access, 14-door positioning card, 15-stiffening plate, 16-deck structure of trestle bridge.
具体实施方式 Detailed ways
为进一步阐述本实用新型为达成预定发明目的所采取的技术手段及功效,以下结合附图及较佳实施例,对依据本实用新型提出的桥台结构的具体实施方式及工作原理进行详细说明。 In order to further explain the technical means and effects of the utility model to achieve the intended invention purpose, the specific implementation and working principle of the abutment structure proposed by the utility model will be described in detail below in conjunction with the accompanying drawings and preferred embodiments.
如图1、图2所示,本实用新型所提供的桥台结构主要包括:钢管桩、挡土背墙、横向主分配梁、纵向次分配梁5。钢管桩设置于栈桥接线便道边坡上,横向主分配梁沿横桥向设置于钢管桩顶部,纵向次分配梁5沿纵桥向设置于横向主分配梁上,挡土背板沿横桥向垂直固定于纵向次分配梁5上。 As shown in Figures 1 and 2, the abutment structure provided by the utility model mainly includes: steel pipe piles, retaining back walls, horizontal main distribution beams, and longitudinal secondary distribution beams 5 . The steel pipe piles are arranged on the side slope of the trestle junction access road, the horizontal main distribution beam is arranged on the top of the steel pipe pile along the horizontal bridge direction, the longitudinal secondary distribution beam 5 is arranged on the horizontal main distribution beam along the longitudinal bridge direction, and the soil retaining back plate The bridge is vertically fixed on the longitudinal secondary distribution beam 5 .
对于挡土背板沿横桥与纵向次分配梁5之间的固定方式,优选的,在挡土背墙与纵向次分配梁5之间设置撑杆9,通过撑杆9将挡土背墙、纵向次分配梁5与撑杆9之间形成稳定的三角形结构。对于挡土背墙的具体结构,优选的,采用:背墙面板6、背墙横向骨架7、背墙竖向骨架8构成。为确保挡土背墙骨架结构均匀受力,在撑杆9与挡土背板之间增加横梁骨架10与挡土背墙的背墙竖向骨架8固定。 For the fixing method between the retaining back plate along the transverse bridge and the longitudinal sub-distribution beam 5, preferably, a brace 9 is set between the retaining back wall and the longitudinal sub-distribution beam 5, and the retaining back wall is fixed by the brace 9 1. A stable triangular structure is formed between the longitudinal secondary distribution beam 5 and the struts 9 . As for the specific structure of the retaining back wall, preferably, it is composed of: a back wall panel 6 , a back wall transverse skeleton 7 , and a back wall vertical skeleton 8 . In order to ensure that the skeleton structure of the retaining back wall is evenly stressed, a beam skeleton 10 is added between the struts 9 and the retaining back plate to fix it with the vertical skeleton 8 of the back wall of the retaining back wall.
对于钢管桩的设置,优选的,钢管桩包括:第一排钢管桩1A、第二排钢管桩1B,本实施例中采用的钢管桩为双排设计。如图1所示,第一排钢管桩1A设置于靠近栈桥接线填土便道13的一侧,第二排钢管桩1B设置于桥身一侧,各个钢管桩之间通过桩 间横向连接系4、桩间纵向连接系3连接固定。每一排钢管桩的宽度与栈桥宽度相当,第一排钢管桩1A与第二排钢管桩1B之间的间距大于挡土背墙的高度。此时,横向主分配梁的数量与钢管桩排数相等,包括:第一排横向主分配梁2A、第二排横向主分配梁2B。第一排横向主分配梁2A设置于第一排钢管桩1A顶部,第二排横向主分配梁2B设置于第二排钢管桩1B顶部,第一排横向主分配梁2A与第二排横向主分配梁2B的顶部均与纵向次分配梁5固定连接,挡土背墙固定于第一排钢管桩1A顶部的纵向次分配梁5上。 For the arrangement of steel pipe piles, preferably, the steel pipe piles include: a first row of steel pipe piles 1A, a second row of steel pipe piles 1B, and the steel pipe piles used in this embodiment are designed in double rows. As shown in Figure 1, the first row of steel pipe piles 1A is arranged on the side close to the filling path 13 of the trestle bridge line, and the second row of steel pipe piles 1B is arranged on the side of the bridge body. The connection system 4 and the longitudinal connection system 3 between the piles are connected and fixed. The width of each row of steel pipe piles is equivalent to the width of the trestle bridge, and the distance between the first row of steel pipe piles 1A and the second row of steel pipe piles 1B is greater than the height of the retaining back wall. At this time, the number of transverse main distribution beams is equal to the number of rows of steel pipe piles, including: the first row of transverse main distribution beams 2A, and the second row of transverse main distribution beams 2B. The first row of transverse main distribution beams 2A is set on the top of the first row of steel pipe piles 1A, the second row of transverse main distribution beams 2B is set on the top of the second row of steel pipe piles 1B, the first row of transverse main distribution beams 2A and the second row of steel pipe piles The tops of the transverse main distribution beams 2B are fixedly connected with the longitudinal sub-distribution beams 5, and the retaining back wall is fixed on the longitudinal sub-distribution beams 5 at the top of the first row of steel pipe piles 1A.
本实用新型的具体施工过程如下:利用打桩设备完成钢栈桥桥台基础钢管桩的施工,依次安装桩间纵向连接系3和桩间横向连接系4,然后安装横向主分配梁,并利用加劲板15将横向主分配梁和钢管桩之间焊接牢固,最后在横向主分配梁上安装纵向分配梁5,并使其与横向分配梁之间焊接牢固。 The specific construction process of the utility model is as follows: use piling equipment to complete the construction of the steel pipe piles of the foundation of the steel trestle abutment, install the longitudinal connection system 3 between the piles and the horizontal connection system 4 between the piles in sequence, then install the transverse main distribution beam, and use the stiffening The plate 15 welds firmly the transverse main distribution beam and the steel pipe pile, and finally installs the longitudinal distribution beam 5 on the transverse main distribution beam, and welds it firmly with the transverse distribution beam.
挡土背墙结构采用钢板和型钢加工制作,挡土背墙的宽度等于栈桥设计宽度加上背墙设计高度,是因为在实际施工过程中,挡土背墙的宽度要大于填土便道的宽度,原因有两点,(1)栈桥两侧接线填土便道13放坡的要求;(2)避免桥台台背受水浪的冲刷而垮塌,但是宽度具体要大多少,在没有实践经验的时候,则无法准确确定。 The structure of the retaining back wall is made of steel plates and section steel. The width of the retaining back wall is equal to the design width of the trestle plus the design height of the back wall, because in the actual construction process, the width of the retaining back wall is greater than the width of the filling path , there are two reasons, (1) the requirement for the grading of the earth filling access road 13 on both sides of the trestle bridge; (2) to prevent the back of the abutment and abutment from collapsing due to the erosion of water waves, but how much wider the width should be, in the absence of practical experience time, it cannot be determined exactly.
为什么要是栈桥设计宽度加上背墙设计高度,因为背墙的设计高度等于贝雷片11的高度加上栈桥桥面结构16的高度来确定,因此如果背墙设计越高,那么填土便道填筑越高,边坡越大,需要防护的锥坡范围就越大,反之则同理,根据现有施工发现,背墙的设计宽度等于栈桥设计宽度加上背墙的设计高度,即能够满足填土便道放坡的要求,避免台背受水浪的冲刷而垮塌,也不会使防护范围过大,是一个比较合适、合理的宽度选定。挡土背墙可先在钢结构加工区加工完成后运至桥台处进行现场安装,挡土背墙型钢骨架的设计强度要满足抵抗台背土压力而不发生较大变形。背墙面板6采用普通A3钢板,在背墙面板6一侧焊接背墙横向骨架7,然后焊接背墙竖向骨架8,背墙竖向骨架8的设置与纵向分配梁5相对应,加工完成后的挡土背墙安装于第一排钢管桩1A位的纵向次分配梁5上,将挡土背墙底端的背墙横向骨架7与纵向分配梁5接触的部位焊接牢固,完成挡土背墙的安装。 Why is the design width of the trestle bridge plus the design height of the back wall, because the design height of the back wall is equal to the height of the Bailey sheet 11 plus the height of the trestle deck structure 16? The higher the building, the larger the slope, and the larger the scope of the cone slope to be protected, and vice versa. According to the existing construction findings, the design width of the back wall is equal to the design width of the trestle bridge plus the design height of the back wall, which can meet the It is a more appropriate and reasonable width selection for the grading requirement of the earth filling access road to avoid the back of the platform from collapsing due to the erosion of water waves, and not to make the protection range too large. The retaining back wall can be processed in the steel structure processing area first, and then transported to the abutment for on-site installation. The design strength of the steel frame of the retaining back wall must meet the resistance to the soil pressure on the back of the abutment without major deformation. The back wall panel 6 is made of ordinary A3 steel plate, and the back wall horizontal frame 7 is welded on one side of the back wall panel 6, and then the back wall vertical frame 8 is welded. The setting of the back wall vertical frame 8 corresponds to the longitudinal distribution beam 5, and the processing is completed. The rear retaining back wall is installed on the longitudinal secondary distribution beam 5 at position 1A of the first row of steel pipe piles, and the part where the back wall transverse skeleton 7 at the bottom of the retaining back wall contacts the longitudinal distribution beam 5 is welded firmly to complete the soil retaining Installation of the back wall.
撑杆9设置于挡土背墙与纵向次分配梁5之间,起到将栈桥台背接线填土便道13侧压力传递给钢管桩基础的作用,撑杆9、挡土背墙与横向纵向次配梁5之间为三角形结构。为确保挡土背墙骨架结构均匀受力,在撑杆9与挡土背墙竖向骨架8之间安 装一道横梁骨架10,同时撑杆9的强度要满足挡土背墙结构承受的土压力,此时,撑杆9的底端与纵向次分配梁5焊接牢固,顶端安装横梁骨架10并与挡土背墙竖向骨架8之间顶紧焊接。为便于施工,将撑杆9、横梁骨架10、挡土背墙、纵向次分配梁5之间按上述方式固定后,再将纵向次分配梁5焊接固定在在横向主分配梁上。 The strut 9 is arranged between the retaining back wall and the longitudinal sub-distributing beam 5, and plays the role of transferring the side pressure of the back filling path 13 of the trestle abutment to the steel pipe pile foundation. The strut 9, the retaining back wall and the lateral Between the longitudinal secondary distribution beams 5 is a triangular structure. In order to ensure that the skeleton structure of the retaining back wall is evenly stressed, a crossbeam skeleton 10 is installed between the strut 9 and the vertical skeleton 8 of the retaining back wall, and the strength of the brace 9 must meet the soil load borne by the retaining back wall structure. Pressure, at this moment, the bottom of strut 9 is welded firmly with longitudinal sub-distributing beam 5, and crossbeam skeleton 10 is installed on the top and welded tightly between vertical skeleton 8 of retaining wall. For the convenience of construction, after the struts 9, beam skeleton 10, retaining back wall, and longitudinal secondary distribution beam 5 are fixed in the above-mentioned manner, the longitudinal secondary distribution beam 5 is welded and fixed on the horizontal main distribution beam.
接下来,安装栈桥施工结构,在安装第一排钢管桩1A与第二排钢管桩1B顶部贝雷片11时,将贝雷片11的竖杆与撑杆9顶端的横梁骨架10之间顶紧,并利用门型定位卡14将贝雷片11与第二排钢管桩1B顶部的第二排横向主分配梁2B之间固定牢固,安装栈桥桥面结构16。 Next, install the construction structure of the trestle bridge. When installing the first row of steel pipe piles 1A and the top Bailey sheet 11 of the second row of steel pipe piles 1B, connect the vertical bar of the Bailey sheet 11 to the beam skeleton 10 at the top of the strut 9. Tighten the space between them, and use the door-type positioning card 14 to fix the Bailey sheet 11 and the second row of transverse main distribution beams 2B on the top of the second row of steel pipe piles 1B firmly, and install the trestle bridge deck structure 16.
最后完成台背接线填土便道13的回填,并进行硬化处理,在接线填土便道13和栈桥桥面结构16之间铺设伸缩钢板12,起到将接线填土便道13和栈桥桥面结构16之间平稳连接的作用。 Finally finish the backfilling of the backfilling access road 13 of the platform back, and carry out hardening treatment, lay telescopic steel plate 12 between the wiring filling access road 13 and the trestle deck structure 16, play the connection filling access road 13 and the trestle bridge deck structure 16 The role of smooth connection between.
应说明的是,以上具体实施方式仅用以说明本实用新型的技术方案而非限制,尽管参照实例对本实用新型进行了详细说明,本领域的普通技术人员应当理解,可以对本实用新型的技术方案进行修改或者等同替换,而不脱离本实用新型技术方案的精神和范围,其均应涵盖在本实用新型的权利要求范围当中。 It should be noted that the above specific embodiments are only used to illustrate the technical solution of the utility model without limitation. Although the utility model has been described in detail with reference to examples, those of ordinary skill in the art should understand that the technical solution of the utility model can be Modifications or equivalent replacements without departing from the spirit and scope of the technical solution of the utility model shall be covered by the claims of the utility model.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420836552.1U CN204455801U (en) | 2014-12-25 | 2014-12-25 | A kind of bridge abutment structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420836552.1U CN204455801U (en) | 2014-12-25 | 2014-12-25 | A kind of bridge abutment structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204455801U true CN204455801U (en) | 2015-07-08 |
Family
ID=53662710
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201420836552.1U Expired - Lifetime CN204455801U (en) | 2014-12-25 | 2014-12-25 | A kind of bridge abutment structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204455801U (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110847020A (en) * | 2019-11-28 | 2020-02-28 | 湖北省路桥集团有限公司 | Steel pipe pile steel trestle end and construction method |
| CN111254918A (en) * | 2020-03-19 | 2020-06-09 | 浙江省大成建设集团有限公司 | Steel trestle steel pipe pile anchoring method reinforced by pile bottom anchor rod |
| CN111576197A (en) * | 2020-05-08 | 2020-08-25 | 中冶南方城市建设工程技术有限公司 | Assembled bridge abutment capable of relieving bumping at bridge head and construction method thereof |
| CN112482202A (en) * | 2020-10-27 | 2021-03-12 | 中建三局基础设施建设投资有限公司 | Pull rod type multipurpose steel trestle bridge abutment and construction method thereof |
| CN112663478A (en) * | 2020-12-14 | 2021-04-16 | 中铁二十局集团第三工程有限公司 | Temporary steel trestle of sea is striden to nearly font |
| CN116043688A (en) * | 2022-09-09 | 2023-05-02 | 中国建筑土木建设有限公司 | Temporary Construction Method of Steel Convenience Bridge |
-
2014
- 2014-12-25 CN CN201420836552.1U patent/CN204455801U/en not_active Expired - Lifetime
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110847020A (en) * | 2019-11-28 | 2020-02-28 | 湖北省路桥集团有限公司 | Steel pipe pile steel trestle end and construction method |
| CN111254918A (en) * | 2020-03-19 | 2020-06-09 | 浙江省大成建设集团有限公司 | Steel trestle steel pipe pile anchoring method reinforced by pile bottom anchor rod |
| CN111576197A (en) * | 2020-05-08 | 2020-08-25 | 中冶南方城市建设工程技术有限公司 | Assembled bridge abutment capable of relieving bumping at bridge head and construction method thereof |
| CN111576197B (en) * | 2020-05-08 | 2021-12-07 | 中冶南方城市建设工程技术有限公司 | Assembled bridge abutment capable of relieving bumping at bridge head and construction method thereof |
| CN112482202A (en) * | 2020-10-27 | 2021-03-12 | 中建三局基础设施建设投资有限公司 | Pull rod type multipurpose steel trestle bridge abutment and construction method thereof |
| CN112663478A (en) * | 2020-12-14 | 2021-04-16 | 中铁二十局集团第三工程有限公司 | Temporary steel trestle of sea is striden to nearly font |
| CN112663478B (en) * | 2020-12-14 | 2022-11-01 | 中铁二十局集团第三工程有限公司 | Temporary steel trestle of sea is striden to nearly font |
| CN116043688A (en) * | 2022-09-09 | 2023-05-02 | 中国建筑土木建设有限公司 | Temporary Construction Method of Steel Convenience Bridge |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN204455801U (en) | A kind of bridge abutment structure | |
| CN208293405U (en) | A kind of abutment of linking deck type suspension bridge and the sidewalk that bankets | |
| CN110565676B (en) | A cantilever tower crane foundation structure and construction method thereof | |
| CN205024690U (en) | Additional strengthening is propped in tearing open of supporting in deep basal pit | |
| CN203229874U (en) | Repeatedly used cast-in-place support system for simply-supported beam | |
| CN102747736A (en) | A combined tool-type internal support replacement method | |
| CN203222738U (en) | Steel pipe latticed column temporary buttress supporting device | |
| CN204662455U (en) | Foundation pit support device reinforced by a kind of adjustable diagonal brace | |
| CN203270461U (en) | Bailey beam support without buttress in soft foundation | |
| CN105240018A (en) | Vertical shaft construction device and method | |
| CN204716257U (en) | Guarantee that shield whole starts and the variable door opening cribbing of station main body synchronous construction | |
| CN103290851A (en) | Prestressed steel support used for controlling internal and external differential displacement of foundation pit enclosure wall and construction method | |
| CN103243638B (en) | Bridge space radioactive concrete-filled steel tube bridge pier and construction method thereof | |
| CN102535525B (en) | Structure and method utilizing anti-floating anchor rods to support underground raft plates | |
| CN103952979A (en) | Bracket-free construction device and construction method for steel-concrete superposed beam top plate | |
| CN205116030U (en) | No. 0 three angle brackets of piece of box girder bridge have just been constructed in succession | |
| CN214459731U (en) | A concrete support structure for preventing settlement and cracking | |
| CN206418464U (en) | A kind of Bailey bracket support system | |
| CN203846512U (en) | Supporting device for long edges of strip-shaped and rectangular foundation pit | |
| CN203846505U (en) | Supporting structure used for long edges of strip-shaped and rectangular foundation pit | |
| CN204311457U (en) | A kind of Metro station excavation excavation construction composite retaining structure system | |
| CN209873811U (en) | Subway major structure medium plate also serves as temporary supporting structure | |
| CN203361163U (en) | Prestress steel support used for controlling differential displacement inside and outside foundation ditch enclosure wall | |
| CN206538769U (en) | Combined support system for foundation pit support structure | |
| CN218373902U (en) | Building foundation ditch angle brace device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| C41 | Transfer of patent application or patent right or utility model | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20160825 Address after: 430100 new agricultural industrial zone, iron industry village, Caidian District, Hubei, Wuhan Patentee after: The 6th Engineering Co.,Ltd. MBEC Address before: 430100 new agricultural industrial zone, iron industry village, Caidian District, Hubei, Wuhan Patentee before: The 6th Engineering Co.,Ltd. MBEC Patentee before: CHINA RAILWAY MAJOR BRIDGE ENGINEERING GROUP Co.,Ltd. |
|
| CX01 | Expiry of patent term |
Granted publication date: 20150708 |
|
| CX01 | Expiry of patent term |